Content

SEJARAH RU II

PROFIL RU II

DISTRIBUSI PRODUK

PROSES PRODUKSI

UTILITIES & OFFSITE FACILITIES

PENUTUP

Page 3: Presentasi Umum RU II Dumai

3

Kilang Dumai

Kilang SPK

Area P.Brandan

Title

Measure

1993

1995

2006

2008

2009

Pembangunan LPG Plant

Produksi pertama

Operasi dihentikan

Salamander menemukan sumber gas alam

26 Mei 2009, produksi perdana LPG

LPG Plant — 200 T/D

CDU

PL-I/II

HVU

DCU

HCU

— 120 MBSD

— 15 MBSD

— 106 MBSD

— 35.2 MBSD

— 63 MBSD

Pembangunan CDU 100 MBSD

1st development : Penambahan Naphtha

Rerun Unit, Hydrobon-Platforming, and

Mogas blending facilities

2nd development : Penambahan

Hydrocracking Complex (HCC) and Heavy

Oil Complex (peresmian tahun 1984)

Pemasangan APH in CDU’s & menaikkan

kapasitas dari 100 to 120 MBSD

Start-up unit LBO Plant, HCU Revamp (naik

113%) & HVU Revamp (naik 114%).

1971

1972

1981

1992

2007

CDU SPK — 50 MBSD

Pembangunan CDU oleh Refican (25 MBSD)

Penyerahan ke Pertamina

Menaikkan kapasitas 35 MBSD (revamp Heater)

Menaikkan kapasitas 50 MBSD (revamp Kolom)

1969

1974

1977

1979

1. SEJARAH REFINERY UNIT II

Page 4: Presentasi Umum RU II Dumai

Content

SEJARAH RU II

PROFIL RU II

DISTRIBUSI PRODUK

PROSES PRODUKSI

UTILITIES & OFFSITE FACILITIES

PENUTUP

Page 5: Presentasi Umum RU II Dumai

Kilang Dumai ( UP-II)

Kilang Musi ( UP-III )

Kilang Cilacap (UP-IV)

Kilang Balikpapan (UP-V)

Kilang Balongan (UP-VI)

Kilang Kasim (UP-VII)

RU IV 29,98 %

RU II 17,89 % RU VI 17,33 %

RU V 23,17 %

RU VII 0,45 %

RU III 11,18 %

Kontribusi Kilang RU – II Dari Total Produksi Nasional

2. PROFIL RU II

Page 6: Presentasi Umum RU II Dumai

US average 128

Japan average 152

UK average 170

Taiwan average 305

South Korea average 430

170

260

340

RU II Pkl. Brandan

RU II Dumai

RU VI Balongan

130

RU V Balikpapan

10 RU VII Kasim

RU III Plaju / Musi

RU IV Cilacap

5

125

10.7

7.7

9.0

5.9

5.0

5.7

3.6

4.3

2.1

3.3

1.0

9.3

Capacity : k bpcd Nelson Complexity Index* Catatan

Konfigurasi disain relatif sederhana, banyak memproduksi “low value products” dan kurang handal.

Skala :

1 = sangat sederhana

10 = kompleksitas tinggi

• Tidak merefleksikan marjin / profitabilitias, hal-hal lain seperti tantangan logistik juga mempengaruhi profil ekonomi kilang dan tidak direfleksikan oleh indeks Nelson.

Sumber: FACTS; US Ebassy Jakarta Petroleum Report 2005; analisa McKinsey

Refinery :

PROFIL KOMPLEKSITAS KILANG RU II

Page 7: Presentasi Umum RU II Dumai

Content

SEJARAH RU II

PROFIL RU II

DISTRIBUSI PRODUK

PROSES PRODUKSI

UTILITIES & OFFSITE FACILITIES

PENUTUP

Page 8: Presentasi Umum RU II Dumai

Lokasi Produk

NAD BBM

Sumut

BBM

Avtur

LPG

Riau

BBM

Avtur

LPG

Sumbar

BBM

Avtur

LPG

DKI Avtur

Ekspor LSWR

Green Coke

3. DISTRIBUSI PRODUK

Page 9: Presentasi Umum RU II Dumai

KILANG DUMAI &

S. PAKNING

JAKARTA (AVTUR)

TANGKI PERTAMINA PPDN - BK. BATREM

DERMAGA DUMAI &

SPK

Dalam Satuan Juta Liter / Bulan

*) LPG : Ribu Ton

P. BARU, LABUAN BATU,

ASAHAN, KAMPAR & DUMAI

(RIAU)

KIJANG, TELUK KABUNG,

BATAM,

P. SAMBU, T. UBAN, BELAWAN,

NAD, SIAK PEKANBARU

PEKANBARU P. BENGKALIS &

S.PAKNING, DUMAI (RIAU),

PADANG

REFINERY UNIT II UNIT PEMASARAN KERO : 71.11

PREMIUM : 70.13

SOLAR : 203.36

LPG : 6.18

AVTUR : 28.61

KERO : 5.61

PREMIUM : 32.83

SOLAR : 74.12

LPG : 3.42* AVTUR : 3.61

DISTRIBUSI BBM DARI KILANG DUMAI & S.PAKNING

Page 10: Presentasi Umum RU II Dumai

Content

SEJARAH RU II

PROFIL RU II

DISTRIBUSI PRODUK

PROSES PRODUKSI

UTILITIES & OFFSITE FACILITIES

PENUTUP

Page 11: Presentasi Umum RU II Dumai

4. PROSES PRODUKSI

RENCANA

DISTRIBUSI

KANTOR

PUSAT

RENCANA

DISTRIBUSI

UPMS I

PENYALURAN PRODUK

• PIPA / MOBIL

• KAPAL ALOKASI UPMS I

• KAPAL ALOKASI KANTOR

PUSAT

PROGRAM PELAYANAN

TRANFER / PEMUATAN KILANG

RU II DMI / S.PK

RAPAT ALOKASI

MM & INTERMEDIA

ANTAR RU &

KANTOR PUSAT

PERENCANAAN

PRODUKSI

BULANAN

PROSES

PRODUKSI

Page 12: Presentasi Umum RU II Dumai

*) TON / DAY **) MMSCF /DAY

@ Saat ini unit tidak beroperasi (Idle)

UNIT PRODUKSI MBSD

KAP. DESIGN KAP. EFEKTIF

CDU DUMAI 120,0 127,0

CDU S. PAKNING 50,0 49,0

NAPTHA RERUN UNIT 9,0 9,0

HYDROBON & PLATFORMER 6,2 6,9

HIGH VACUUM UNIT 106,0 106,0

HYDROCRACKER 211 31,5 31,5

HYDROCRACKER 212 31,5 31,5

NAPTHA HYDROTREATER 10,1 10,1

CCR PLATFORMER 8,8 8,8

DISTILLATE HYDROTREATER 12,7 13,3

DELAYED COOKER 35,2 35,2

CALCINER @ 1.063,0 *) 1.063,0

LPG RECOVERY 174,0 *) 174,0

HYDROGEN PLANT 701 39,2**) 39,2

HYDROGEN PLANT 702 39,2**) 39,2

KAPASITAS REFINERY UNIT – II DUMAI

Page 13: Presentasi Umum RU II Dumai

6,66

MBCD

Typical Product Th 2011

16,67

MBSD

13.12

MBCD

60.13

MBCD

11.95

MBCD

7.10

MBCD

8.98

MBCD

4.08

MBCD

Page 14: Presentasi Umum RU II Dumai

Content

SEJARAH RU II

PROFIL RU II

DISTRIBUSI PRODUK

PROSES PRODUKSI

UTILITIES & OFFSITE FACILITIES

PENUTUP

Page 15: Presentasi Umum RU II Dumai

UTILITIES

POWER UTILITIES

OTHER

5. UTILITIES & OFFSITE FACILITIES

• Steam Generator

– HP Steam : 350 Ton/jam

– MP Steam : 200 Ton/jam

– LP Steam : 170 Ton/jam

• Power Plant

– Power generate : 45 MW

• Cooling Water System

• Fuel System

• Instrument - Plant Air System

• Air Baku

Sumber air baku dari Sei Rokan jarak dari

Dumai + 43 km.

• WTP Bukit Datuk

Kapasitas produksi 1100 - 1200 m3/jam.

• Udara Kempa.

Kompresor udara kempa + 10700 NM3/Jam

Page 16: Presentasi Umum RU II Dumai

OFFSITE

FASILITAS

PENGOLAH LIMBAH

TANK & JETTY

5. UTILITIES & OFFSITE FACILITIES

• SEPARATOR dilengkapi dengan Biotreatment.

• FLARE sebagai pembakar gas sisa.

• SOUR WATER STRIPPER sebagai pengolah air

proses sebelum dibuang.

• FIRE GAS DETECTOR SYSTEM.

• CEMS (Continous Emision Monitoring System).

• Tanki Timbun

– Tanki Crude : 208.000 m3

– Tanki Produk : 1.160.000 m3

• Dermaga Pertamina (DP)

– Loading BBM : DP–1, 2, 3 & 5

– Loading LPG : DP–6

– Loading Coke : DP–4

• Sweet Flare, 2 (dua) buah di Existing dan New

Plant.

Page 17: Presentasi Umum RU II Dumai

Content

SEJARAH RU II

PROFIL RU II

DISTRIBUSI PRODUK

PROSES PRODUKSI

UTILITIES & OFFSITE FACILITIES

PENUTUP

Page 18: Presentasi Umum RU II Dumai

PT PERTAMINA (PERSERO) REFINERY UNIT II DUMAI

Page 19: Presentasi Umum RU II Dumai

1. Penerapan Quality Management system (QMS) dalam wadah Sistem Manajemen Mutu Pertamina

Sertifikasi ISO-14001, ISO-17025 dan ISO-9000

Manajemen Keselamatan Proses (MKP)

Implementasi Enterprise Resource Planning (ERP) SAP R/3

Kebijakan PROPER Biru

Pengukuran Kinerja dengan menggunakan kriteria MBNQA

(early improvement)

2. Penerapan Good Corporate Governance (GCG)

Implementasi e-Auction untuk proses pelelangan

Penandatanganan Pakta Integritas oleh Tim Manajemen

SISTEM MANAJEMEN

PT PERTAMINA (PERSERO) RU - II

3. Program transformasi

OPI (Operational Performance Improvement)