preparing incurred cost submissions: government …€¦ · the final indirect cost rates and...

63
BDO USA, LLP, a Delaware limited liability partnership, is the U.S. member of BDO International Limited, a UK company limited by guarantee, and forms part of the international BDO network of independent member firms. PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT CONTRACTOR’S OVERVIEW 06/01/2020

Upload: others

Post on 17-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

BDO USA, LLP, a Delaware limited liability partnership, is the U.S. member of BDO International Limited, a UK company limited by guarantee, and forms part of the international BDO network of independent member firms.

PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT CONTRACTOR’S OVERVIEW

06/01/2020

Page 2: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

2 DCAA ICS Audits and How to Leverage Costpoint for Success

DARLENE MIHALYSenior Manager, ERP Practice

[email protected]: +703-770-9045Mobile: +937-572-4580

JONATHAN REYNOLDSManaging Director, ERP Industry Specialty Services

[email protected]: +703-336-1674Mobile: +571-205-5757

Introductions

ANNETTE GROTZProduct Marketing Manager, Deltek

[email protected]

Page 3: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

3 DCAA ICS Audits and How to Leverage Costpoint for Success

Agenda

BDO INTRODUCTION AND ERP SERVICES

BACKGROUND ON ICS

TIMELINE AND SUBMISSION

PREPARATION TECHNIQUES AND BEST PRACTICES

WHAT ELSE CAN YOU DO TO PREPARE?

HOW CAN COSTPOINT HELP?

AUDIT TRENDS

HOW CAN BDO HELP?

Page 4: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

BDO INTRODUCTION AND ERP SERVICES

Page 5: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

5 DCAA ICS Audits and How to Leverage Costpoint for Success

Our Core ServicesAt BDO, we know that client service is paramount to building strong, long-term client relationships. As such, we offer a breadth of services, combined with our world-class resources and exceptional client service, tailored to meet every business and financial advisory need.

ADVISORY BDO Digital Business Services and

Outsourcing Corporate Finance Corporate Real Estate

Advisory Services Forensic Investigation

and Litigation Support Healthcare Advisory

Services Risk Advisory Services

BDO CAPITAL ADVISORS, LLC Investment Banking

ASSURANCE Accounting and

Auditing Accounting Reporting

and Advisory Services Audit Data Analytics Employee Benefit Plan

Audits Financial Statement

Audit IFRS Information Systems

Assurance IPO Services SEC Reporting Third-Party

Attestation/SOC

TAX Cost Segregation Federal Tax Matters Global Employer

Services Income Tax Accounting International Tax

Services Nonprofit Tax Services Private Client Services Research and

Development Tax Credit

State & Local Tax Tax Performance

Engineering Tax Transaction

Advisory Services Transfer Pricing

Page 6: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

6 DCAA ICS Audits and How to Leverage Costpoint for Success

ERP Locations

Page 7: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

7 DCAA ICS Audits and How to Leverage Costpoint for Success

BDO’s ERP Services

The BDO implementation team is comprised of seasoned veterans (average 20 years experience) who come from leadership positions within the Industry with a range of credentials such CPA, MBA, PMP, CMA, etc.

Client timelines and priorities are highly important to BDO, therefore, BDO effectively communicates the expectations and level of involvement needed from clients to ensure the implementation is completed timely and with quality.

BDO implementer skillsets extend beyond system integrations. We offer suggestions and solutions to clients including but not limited to reorganization, account/project setup, cost pool design, reporting/business intelligence, and process/procedure best practices.

Existing ERP Health Check

Project Management

Training & Adoption

Requirements Analysis

Systems Design & Integration

New ERP Evaluation &

Selection

BDO ERP

Page 8: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

BACKGROUND ON ICS

Page 9: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

9 DCAA ICS Audits and How to Leverage Costpoint for Success

What is an Incurred Cost Submission (ICS)?

Formally known as an Indirect Cost Rate Proposal (ICP, ICRP, or ICS); used interchangeably.

Purpose is to establish final annual indirect cost rates and determine over/under billing for the period covered by the ICS (presented on Schedule I).

The submission includes the direct and indirect expenses incurred by the contractor during its fiscal year.

ICS schedules show the detailed calculations of indirect pool(s) and base(s), a summary of costs incurred by contract, other supporting schedules, and the Certificate of Final Indirect Costs.

Rates developed from this submission are used for a variety of purposes, typically as the source or starting point for calculations such as Provisional Billing rates, Forward Pricing rates, etc.

Page 10: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

10 DCAA ICS Audits and How to Leverage Costpoint for Success

Requirements

FAR 52.216-7 - Allowable Cost and Payment requires Government contractors to “submit an adequate final indirect cost rate proposal to the Contracting Officer (or cognizant Federal agency official) and auditor within the 6-month period following the expiration of each of its fiscal years.”

Reasonable extensions may be requested in writing by the Contractor and granted in writing by the Contracting Officer.

The proposed rates shall be based on the Contractor’s actual cost experienced for that period.

The Allowable Cost and Payment clause applies to cost-reimbursement type and T&M contracts (FAR 16.307).

All federal contracts should be included and reported individually. It is permissible to lump or group all commercial and fixed price work together. In total, all contract costs should reconcile to the Trial Balance and other books of record.

For Subcontractors: Refer back to your subcontract agreement to ascertain whether the Allowable Cost and Payment clause has been flowed-down; thus requiring subcontractors to prepare and provide an incurred cost submission.

Page 11: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

11 DCAA ICS Audits and How to Leverage Costpoint for Success

Why is an ICS Significant?

Finalized indirect cost rates provide for a timely settlement of costs under cost-reimbursement and T&M contracts.

• The establishment of final rates shall be used for contract closeout (unless quick-closeout procedures are used).

The ICS is the contractor’s final opportunity to voluntarily disallow costs (pre-audit) that could be perceived or determined to be unallowable.

Adjusts provisional or interim billing rates as necessary to establish the final indirect cost rates after year end.

Final indirect cost rates are used in negotiating the final price of Federal contracts and in other situations requiring that indirect costs be settled before contract prices are established.

Contractors must update billings on all contracts to reflectthe final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within60 days after settling final rates (per FAR 52.216-7(d)(2)(v)).

Concluding the audit of an ICS, the contractor and contracting officer will execute a written understanding specifying the terms and finalization of indirect rates.

Page 12: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

TIMELINE AND SUBMISSION

Page 13: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

13 DCAA ICS Audits and How to Leverage Costpoint for Success

Timeline for an Incurred Cost Submission

Per FAR 52.216-7, an incurred cost submission is due within six (6) months after the contractor’s fiscal year end (FYE).

If the contractor does not submit the proposal within six (6) months of its FYE the DCAA may send reminder letters to the contractor.

Once the submission becomes six (6) months overdue (one year after the end of the fiscal year) and no extension has been granted by the Contracting Officer, the DCAA auditor may provide the CO with unilateral rate recommendations. As a result, the Contracting Officer can make a unilateral determination as authorized by FAR 42.703-2(c)(1) and FAR 42.705(c)(1).

Delinquent ICS’ result in rate recommendations that will be based on either (1) a decrement factor applied to indirect rates using relevant contractor historical data or (2) a company-wide decrement factor based on questioned costs at high risk contractors applied to total contract costs, if no relevant historical data exists.

The rate recommendation will apply to active contracts, as well as physically complete contracts for the overdue fiscal year end.

Page 14: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

14 DCAA ICS Audits and How to Leverage Costpoint for Success

Incurred Cost Submission Audit

After submission, and the determination has been made that a contractor’s incurred cost submission is adequate, then typically the cognizant DCAA Field Audit Office (FAO) will initiate the incurred cost audit within six months after receipt of an adequate proposal.

The audit is guided by DCAA’s Post Year End Incurred Cost Audit Program.

During the course of the audit, the DCAA auditor should discuss audit findings with the government contractor as they arise.

The contractor is expected to provide timely feedback on these issues to ensue prompt resolution of audit findings and facilitate an efficient and effective audit process.

An exit conference will be held to summarize issues and resolutions identified during the audit process when significant audit findings are found.

Page 15: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

15 DCAA ICS Audits and How to Leverage Costpoint for Success

The contractor will be given a final opportunity to respond to the audit findings and comments submitted by the contractor and will be included in the audit report (as comments should have been relayed during the audit process as questioned costs were identified).

The DCAA office provides the final report to the contracting officer (CO) (or cognizant Federal agency official) for establishing the final indirect cost and billing rates.

The Contracting Officer may provide the government contractor an opportunity to personally address the results of the audit report during “Negotiations.”

During negotiations the contractor’s position and supporting documentation is presented and considered prior to the CO issuing its final decision regarding questioned costs and final indirect cost rates. DCAA auditors can be extended the invitation to attend negotiations.

Within 120 days, or longer if approved in writing by the CO, after settlement of the final annual indirect cost rates for all years of a physically complete contract, the contractor must submit a completed invoice or voucher reflecting the settlement amount and rates (e.g., “ICS True-up”).

Incurred Cost Submission Audit (continued)

Page 16: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

16 DCAA ICS Audits and How to Leverage Costpoint for Success

What DCAA Looks For

An adequate incurred cost submission: use of the ICE Model (or similar format) containing all of the required schedules.

Schedule N is signed by an authorized party (usually CFO or above).

A contractor’s submission of all claimed costs incurred for cost type and/or T&M reimbursable government contracts, including adjustments and explanatory notes.

Identification of unallowable costs (voluntary deletions) and expressly unallowable costs with notes accompanying adjustments.

Identification, by contract, of awards containing FAR 52.242-3 - Penalties for Unallowable Costs (penalty clause).

If costs are reasonable, allocable, and allowable in accordance with GAAP, CAS, FAR, and contract provisions.

Page 17: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

17 DCAA ICS Audits and How to Leverage Costpoint for Success

Certain “trigger” accounts that may contain unallowable costs. The process for identifying accounts with a higher probability of being selected for testing consists of, but is not limited to:

If there have been any changes to the indirect cost rate structure between the last audited fiscal year and the year in review. Both direct and indirect costs will be evaluated

The results of performing a comparative analysis between the CFY and prior fiscal year pool expenses and direct costs

New accounts

Prior years incurred cost audit or other audit findings

Audit Leads

Fraud Risk Indicators

Audit history/experience with the government contractor

Auditor judgment

What DCAA Looks For (continued)

Page 18: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

PREPARATION TECHNIQUES AND BEST PRACTICES

Page 19: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

19 DCAA ICS Audits and How to Leverage Costpoint for Success

ICE Model and DCAA Adequacy Checklist

The purpose of the DCAA ICE Model is to assist contractors in meeting its requirement for submitting an adequate final indirect cost rate proposal as required by FAR 52.216-7(d).

The ICE Model schedules present the minimum information needed to begin an audit and can be obtained at: ICE Model.

Use of the Model is preferred, although not mandatory, as long as the submission includes the required schedules and support.

A separate schedule needs to be prepared for each final and intermediate indirect expense pool. If pool costs are accumulated by department, departmental expenses should be identified within each pool.

DCAA prefers that contractors include an index, similar to that used in the model, and note if certain schedules are not applicable.

Best Practice: Use the DCAA Incurred Cost Submission Adequacy Checklist as a basis for internally reviewing the ICS prior to submission. The checklist can be found at: Adequacy Checklist.

Page 20: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

20 DCAA ICS Audits and How to Leverage Costpoint for Success

Incurred Cost Audits Materiality Guidance

DCAA recently issued MRD: “Guidance on Using Materiality in Incurred Cost Audits”

Background: Essentially DCAA’s respond to Section 803 of FY2018 NDAA which required them to adopt commercially accepted standards of materiality for incurred cost audits.

Highlights: Incorporates use of quantified materiality threshold to facilitate a consistent approach in determining the nature, timing, and extent of audit procedures on cost elements and accounts that are significant to audit opinion.

• Provides calculation/formula for determining materiality

• If Subject Matter from $1 to $1,000,000,000 use the following formula: Materiality Threshold = $5,000 x ((Total Subject Matter / $100,000) .75)

• If Subject Matter greater than $1,000,000,000 use the following formula: Materiality Threshold percentage of 0.50 percent

Page 21: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

21 DCAA ICS Audits and How to Leverage Costpoint for Success

Required vs. Supplemental Schedules

Required Schedules

To be completed and provided to DCAA at the time of submission, if applicable.

Some schedules, while identified as required, do not have to be completed if the schedule does not apply to the company (i.e., Capital Cost of Money, Intermediate Schedules).

Supplemental Schedules

Additional schedules which are not required to be provided at the time of submission for the determination of an adequate submission; however, may be required during the audit process.

Can be requested to be provided at the entrance conference to help determine audit risk, preliminary and field audit steps.

Federal contractors should consider completing and including the supplemental schedules at the time of submission to decrease delays in facilitating the audit.

Page 22: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

22 DCAA ICS Audits and How to Leverage Costpoint for Success

Required Schedules

Per FAR 52.216-7(d)(2)(iii): An adequate indirect cost rate proposal shall include the following data unless otherwise specified by the cognizant Federal agency official:

Indirect Cost Pools

• Schedule A – Summary of all Claimed Indirect Expense Rates

• Schedule B – General and Administrative (G&A) Expenses (final)

• Schedule C – Overhead Expenses (final)

• Schedule D – Intermediate/Occupancy Expenses (e.g., Facilities, Homogeneous Service Centers, Home Office)

• Schedule E - Claimed Allocation Bases by element of cost used to distribute indirect costs

• Fringe* - Schedule of Fringe Benefit Expenses

• Schedule F – Facilities Capital Cost of Money Factors Computation

*Although not individually listed as a required schedule for adequacy, a separate schedule for these expenses are normally created. An alternative is to include the fringe expenses on Schedule D-x.

Page 23: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

23 DCAA ICS Audits and How to Leverage Costpoint for Success

Contract Costs

• Schedule G – Reconciliation of Books of Account and Claimed Direct Costs by Major Cost Element

• Schedule H – Schedule of Direct Costs by Contract/Subcontract and Indirect Expense Applied at Claimed Rates (as well as a subsidiary schedule of Government Participation percentages in each of the allocation base amounts)

• Schedule I – Cumulative Direct and Indirect Costs Claimed and Billed by Contract and Subcontract

• Schedule J – Subcontract Information

• Schedule K – Summary of Time-and-Materials and Labor-Hours contract, including labor categories, labor rates, hours, direct materials, other direct costs, and indirect expenses applied at claimed rates

Other Schedules

• Schedule L – Reconciliation of Total Payroll per IRS Form 941 to Total Labor Distribution Costs

• Schedule M – Listing of Decisions/Agreements/Approvals and Description of Accounting/Organizational Changes

• Schedule N – Certificate of Final Indirect Costs

• Schedule O – Contract Closing Information for Contracts Completed in this Fiscal Year

Required Schedules (continued)

Page 24: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

24 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules

Schedule A Summary of all Claimed Indirect Expense Rates

• This schedule shows each Indirect rate with cost and base amounts • Each Indirect Rate is shown and ties to referenced schedules

Page 25: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

25 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules: Schedule B, C, D – Indirect Cost Pools

Schedule B: G&A costs broken down by account name and number (before intermediate allocations) Any intermediate allocation amounts from Service Center, Home Office, Fringe, etc. B&P costs broken out separately into Labor, Fringe, Overhead, and ODC’s Total expense pool amount All unallowable costs should be deducted out in the adjustments column in the scheduleSchedule C Schedule of Overhead claimed expenses by element of cost as identified in accounting records for each final

indirect cost pool Calculates overhead expenses, those costs that are closely associated with contract performance

• Support functions for direct labor, subcontractors, etc. Schedule includes details of costs by account name and number (before intermediate allocations)

• One schedule per O/H Pool (e.g., Manufacturing, Engineering, Onsite, Offsite, FCCOM)• Any intermediate allocation amounts from Service Center, Fringe, etc.

Schedule D Intermediate pools, containing costs not specifically associated with any one pool Schedule must include an allocation table providing:

• Allocation base by recipient (i.e., direct labor, overhead, G&A, subcontract costs);• The percentage of the total base for each recipient; and• The total dollars allocated to each recipient.

Page 26: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

26 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules: Schedule B, C – Indirect Cost Pools (continued)

Page 27: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

27 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule E Calculates the allocation bases for all final indirect pools Costs in each base should be broken down and by line item and entered as a link to other

inputs in the ICS, such as schedules H or otherwise Schedule A should reference base amounts included on Schedule E Adjustments should be thoroughly explained via footnotes No information should be hardcoded Allocation bases for intermediate pools are sometimes incorporated as well* Example allocations bases include:

• G&A: Total Cost Input (TCI) or Value Added (TCI less direct subcontracts and direct materials)

• Subcontracts and Material Handling (SM&H): direct subcontracts and direct materials• Overhead: direct labor, and fringe, plus B&P/IR&D labor and B&P/IR&D fringe• Fringe: total labor, FTE, headcount• Facilities: square footage or headcount

*The intermediate allocation bases will also need to be included on Schedule D

Page 28: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

28 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule E

Explanation of all allocation bases must be included and match its description.

Page 29: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

29 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule F

Facilities Capital Cost of Money (FCCM)

• Costs associated with facilities capital used to perform a contract

• Cost of money rate is the arithmetic mean of the interest rates (most recent) specified by the Secretary of the Treasury (CAS 414)

• Applies the cost of money to the capital used, as long as it is allocated correctly and is allowable

Page 30: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

30 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule G

Booked and Claimed Direct Costs

Any adjustments to Direct Costs are shown here

Page 31: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

31 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule H

This schedule is one of the most important and the basis for a large portion of the submission

Calculates actual incurred costs by contract, broken out by contract type and element of cost

Indirect rates (as calculated in Schedule A) are applied to the direct contract costs to determine the total indirect expenses for each contract

Only Flexibly Priced Federal awards are required to be separately identified on Schedule H (at billing level), commercial or other non-Federal contracts can be aggregated as one line item

Best Practices:

• Include federal agency/customer name, by award

• Differentiate between claimed and unclaimed (non-billable) direct costs by cost element and applied indirect costs

• Include a column which totals both claimed and unclaimed amounts, by cost element

• Reconcile total costs incurred on Schedule H to Trial Balance or detailed General Ledger

• Include attributes of clients accounting structure (i.e., project codes) into schedule to allow for simple edits

• Calculate indirect rate caps on this schedule for greatest efficiency and easy linkage to Schedule I

• Use commercial ‘plug’ to save time, if appropriate

Page 32: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

32 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule H

Prime/Sub Contract numbers must be included on the Schedule H and be consistentacross Schedules H, I,J, and K.

Prepared at the billing level.

Best Practice: Include customer name/federal agency, by award.SCHEDULE H

Sch. A Sch. A Sch. A Sch. A20.56% 15.45% 8.35% 4.56%

Award Type Customer Name

Project No.

Project Name

Contract No.

Subcontract No. Direct Labor

Travel ODCs Total Direct Costs -

Value Add

Materials Subcontracts Allowable Fringe

Allowable Overhead

Value Add Direct Costs

Plus Fringe & OH

G&A Total M&S

M&S Handling

Grand Total

COST TYPECPAF (Agency) 100 ABC ABC-123-000 3,255 5,554 6,644 15,453 - - 669 606 16,729 1,397 - - 18,125 CPFF (Agency) 101 DEF ABC-234-000 STU 4,523 4,344 55,533 64,400 4,663,000 344,422 930 842 66,172 24,592 5,007,422 228,338 5,326,525 COST TYPE TOTAL 7,778 9,898 62,177 79,853 4,663,000 344,422 1,599 1,449 82,901 25,988 5,007,422 228,338 5,344,650

T&M (Agency) 200 GHI CDE-456-000 VWX 345,435 43,533 6,332 395,300 - 553,322 71,021 64,343 530,664 46,417 553,322 25,231 1,155,635 345,435 43,533 6,332 395,300 - 553,322 71,021 64,343 530,664 46,417 553,322 25,231 1,155,635

Fixed Price (Agency) 300 JKL EFG-678-000 15,345 2,567 664 18,576 55,633 - 3,155 2,858 24,589 2,265 55,633 2,537 85,024 FIXED PRICE TOTAL 15,345 2,567 664 18,576 55,633 - 3,155 2,858 24,589 2,265 55,633 2,537 85,024

COMMERCIAL 500 MNO HIJ-932-029 125,555 13,000 1,409 139,964 - - 25,814 23,387 189,165 15,795 - - 204,960

IR&D/B&P 900 PQR 34,229 986 283 35,498 - - 7,037 6,376 48,911 - - - 48,911

GRAND TOTAL 528,342 69,984 70,865 669,191 4,718,633 897,744 108,627 98,412 876,230 90,466 5,616,377 256,107 6,839,180

Sch. C Sch. B Sch. C-15,616,377

Sch. E- Mat. & Sub Handling

T&M TOTAL

SCHEDULE OF DIRECT COSTS BY CONTRACT/SUBCONTRACTFISCAL YEAR ENDED 12/31/14

Anywhere, VAABC, LLC.

AND INDIRECT EXPENSE APPLIED AT CLAIMED RATES

Page 33: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

33 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule K Overview

Breaks out all T&M contracts to calculate labor hours and costs

Page 34: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

34 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule K Best Practice

Ensure that T&M rates are current and be aware of potential mid-year rate changes (due to escalation or an exercised option year)

Material and travel costs should be added and loaded with the claimed G&A rate, if applicable

For each contract the total costs and task ceilings should be calculated

Details should be in the same level used for billing

All contracts identified as T&M on Schedule H should be reported on Schedule K

ODCs and Travel costs must tie to Schedule H

Page 35: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

35 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule I Determines the costs claimed versus those billed for all Federal cost reimbursement and T&M awards

(subcontracts are traditionally included) All cost reimbursement and T&M contracts are identified separately on schedule and should be sorted by

Federal Agency Information on Schedule I should be presented at the billing level for each award Current year claimed costs must be linked from Schedule H (cost reimbursement) and Schedule K (time and

materials) and added to prior year settled/claimed costs Billed costs are determined from the final invoice of the Contractor's fiscal year and should be the

cumulative billing figure for the award Intent of Schedule I is to calculate the total over or (under) billing on all Federal awards Other considerations:

• ‘Contract Limitations, Rebates, Credits’ column should be used for adjustments to claimed costs such as:

− Excess costs above contract ceiling rates/amounts, − Unallowable costs per contract terms, and− Cost incurrence outside of the period of performance.

• ‘Net Cumulative Settled or Claimed’ column should not exceed the total contract ceiling• Indicate whether awards are ‘physically complete’ and reported on Schedule O• Cumulative Billings should identify Fee amounts, where appropriate, and not include these amounts

‘Over/Under Billing’ column

Page 36: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

36 DCAA ICS Audits and How to Leverage Costpoint for Success

Schedule I Fiscal Year current dollars should reconcile to Sch. K for T&M contracts and Sch. H for cost type contacts. Contracts identified as physically complete are reported on Schedule O Contracts subject to penalty provision are identified Prior FYEs’ costs should be carried forward from and reconcile to prior FYE ICS’ Cumulative billed costs should exclude fee amounts for cost-type contracts Inclusion of contract limitations to prevent overstating claimed costsSchedule I on a CPFF contract:

Key Schedules (continued)

Page 37: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

37 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule I for a T&M contract:

Page 38: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

38 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule J Intent is to provide identification of subcontracts you have awarded to companies for which you are the prime or

upper-tier contractor for a cost-type contract, including inter-divisional effort Information that must be included:

• Subcontract number• Prime contract number• Subcontractor name and address• Subcontractor point of contact and phone number• Total value of subcontract• Costs incurred in that fiscal year• Award type

Costs incurred on Schedule H must agree with the amounts reported on Schedule J

Page 39: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

39 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule L

Reconciliation of Total Payroll to Total Labor Distribution

• Ties total labor expense to IRS Form 941's

• Payroll information should be entered directly from Form 941

• Labor distribution information is entered using links from schedule H (for direct labor) and schedules B, C, and D (indirect labor expenses)

• Total 941 amount needs to reconcile to the labor totals from the rest of the ICS

Schedule O

Contract Closing Information

• Use only for contracts ‘physically’ completed the fiscal year of ICS

• Includes the following information on each closed contract, broken out by contract type:

− Contract Number

− Performance Period

− Whether or not it is ready to close

− Contract ceiling amount

− Contract fee

− Level of Effort cumulative hours, actual and required

Page 40: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

40 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule L

Salary and Wages reported on Schedule L must reconcile to corresponding pools.

Acceptable variance regarded as “immaterial” varies depending on auditor judgment.

Page 41: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

41 DCAA ICS Audits and How to Leverage Costpoint for Success

Key Schedules (continued)

Schedule O Contracts identified as physically complete on Schedule I are reported on Schedule O (and vice

versa, should reconcile). Schedule O should contain LOE information, period of performance and ceiling information,

where applicable.

Page 42: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

42 DCAA ICS Audits and How to Leverage Costpoint for Success

Supplemental Schedules

Supplemental A – Comparative Analysis of Indirect Expense Pools Detailed by Account with Prior Year and Budgetary Data

Supplemental B – General Organization and Executive Compensation Information

Supplemental C – Identification of Prime Contracts Under Which the Contractor Performs as a Subcontractor

Supplemental D – Description of Accounting System

Supplemental E – Procedures for Identifying and Excluding Unallowable Costs from the Costs Claimed and Billed

Supplemental F – Certified Financial Statements and Other Financial Data

Supplemental G – Management Letter from Outside Certified Public Accountants (CPAs) Concerning any Internal Control Weaknesses

Supplemental H – Actions that have been and/or will be implemented to correct the weaknesses described in the Management Letter

Supplemental I – List of all internal audit reports issued since the last disclosure of internal audit reports to the Government

Supplemental J – Annual internal audit plan of scheduled audits to be performed in the fiscal year when the final indirect cost rate submission is made

Supplemental K – Federal and State Income Tax Returns

Supplemental L – Securities and Exchange Commission 10-K Annual Report

Supplemental M – Minutes from Board of Directors (or Trustees) meetings

Supplemental N – Listing of delay claims and termination claims submitted which contain costs relating to the subject fiscal year

Supplemental O – Contract Briefings (typically includes a synopsis of all pertinent contract provisions)

Page 43: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

43 DCAA ICS Audits and How to Leverage Costpoint for Success

Total Cost Reconciliation

Amount Reference NotesTotal Costs per ICS:Total Claimed Costs 11,743,498 Sch HUnbillable Direct Costs 314,811 Sch HG&A Adjustments (6,080,424) Sch B

Total Costs per ICS 5,977,885

Costs per TB:Costs per TB 5,977,885 TB to ICS

Variance -

NOTES:

Reconciliation of Total Costs per ICS to TBICS FY 2016

Reconciliation of Total Costs per ICS to TB

Purpose is to ensure total costs per the trial balance reconcile to total cost claimed

Page 44: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

44 DCAA ICS Audits and How to Leverage Costpoint for Success

Reconciliation of ICS Rates Between Schedules

Reconciliation of ICS Rates between SchedulesFY2016

Diff from Diff from Sch H-1 Diff fromCost Element Schedule A Schedule E Sch A Description Schedule H Sch A Description Amount Sch A

Fringe PoolFringe on Direct Labor 483,508 Fringe BaseFringe on OH Labor 10,698 Direct Labor 1,044,349

Fringe (Full) Fringe on G&A Labor 44,245 G&A Labor 95,566 POOL 538,450 538,450 - 538,450 - Indirect Labor 23,107 BASE 1,163,022 1,163,022 - 1,163,022 - FRINGE RATE 46.30%

Fringe (Limited)POOL 142,208 142,208 - Fringe Pool 142,208 - BASE 625,223 625,223 - Fringe Base 625,223 - FRINGE RATE 22.75%

Fringe (Other)POOL - - - Fringe Pool - - BASE 1,523 1,523 - Fringe Base 1,523 - FRINGE RATE 0.00%

Fringe (SCA)POOL 700,714 700,714 - Fringe Pool 700,714 - BASE 1,913,100 1,913,100 - Fringe Base 1,913,100 - FRINGE RATE 36.63%

Overhead ExpensesPOOL 109,252 109,252 - Overhead Pool 109,252 - BASE 4,910,624 4,910,624 - Overhead Base 4,910,624 - O/H RATE 2.22%

General and Administrative (G&A) ExpensesPOOL 1,803,762 1,803,762 - G&A Pool 1,803,762 - BASE 10,254,547 10,254,547 - G&A Base 10,254,547 - G& A RATE 17.59%

Purpose is to ensure the rates identified on Schedule A reconcile to:

Schedule E

Schedule H

Schedule H-1

Page 45: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

45 DCAA ICS Audits and How to Leverage Costpoint for Success

The sources below may help address any outstanding questions before submission to theclient.

Furthermore, the sources should be used as guidance during the preparation of the ICS.

Audit Program for Incurred Costs - Post Year End Audit (Activity Code 10100)

FAR 42.7, DFARS 242.7

FAR 31.2, DFARS 231.2

CAM 1-504, Access to Contractor Records

CAM 3-3S1 Special Considerations Audits of Selected Contract Types

CAM 4-400, Audit working Papers

CAM Chapter 6, Incurred Costs Audit Procedures

CAM 10-200 Audit Reports Format and Contents - General

Incurred Cost Audits - Additional References

Page 46: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

WHAT ELSE CAN YOU DO TO PREPARE?

Page 47: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

47 DCAA ICS Audits and How to Leverage Costpoint for Success

Communication – The Key to Success

Interface with auditors before, during and upon conclusion of the audit

Contractors should strive to stay in constant communication with their auditors

• Hold weekly meetings to ensure continued communication

Insist on formal kick-off and exit meetings - required by GAGAS

Audit requests & responses should be communicated in writing and documented

• Keep a log of everything given to the auditors

• Use a separate email account for any audit related email

• Use SharePoint or Dropbox to post reporting

Ensure that you have the opportunity to respond to findings before the audit is finalized

• Request to submit additional data in response to proposed findings

Ensure any responses to audit findings are incorporated into the Final Report (required by GAGAS)

Page 48: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

48 DCAA ICS Audits and How to Leverage Costpoint for Success

Negotiations/Dispute After an Audit

Ensure that you have the opportunity to respond to findings before the audit is finalized

Request to submit additional data in response to proposed findings

Ensure any responses to audit findings are incorporated into the Final Report (required by GAGAS)

Page 49: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

HOW CAN COSTPOINT HELP?

Page 50: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

50 DCAA ICS Audits and How to Leverage Costpoint for Success

Costpoint - Getting Started

Costpoint makes setting up Indirect Rates easy with the Manage Cost Pools application.

Page 51: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

51 DCAA ICS Audits and How to Leverage Costpoint for Success

Statement of Indirect Expenses Example

Cost:

Base:

Calculated Rate:

Page 52: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

52 DCAA ICS Audits and How to Leverage Costpoint for Success

Pool Rates Here you can see the pool rates for the pool at Actual, Target, and Provisional:

Page 53: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

53 DCAA ICS Audits and How to Leverage Costpoint for Success

Incurred Cost Audits - How can Costpoint help?

Out of the box and/or customized Accounting reports (i.e., Costpoint Enterprise Reporting (CER), formerly known as Cognos) to prepare incurred cost submissions and reconcile it to financial and project records.

Page 54: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

54 DCAA ICS Audits and How to Leverage Costpoint for Success

Incurred Cost Audits - How Can Costpoint Help? (continued)

Systematic controls over cost accumulation (e.g., general ledger, job cost ledgers)

Access

Processing

System modification

Monitoring

Best Practice

Dry run Reports before June to ensure full universe is captured and schedule reconciles!

Page 55: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

55 DCAA ICS Audits and How to Leverage Costpoint for Success

Accounting System Reviews - How Costpoint Helps

Widely used/DCAA is comfortable reviewing reports Out of the box capabilities to meet cost recording, tracking, allocation, billing,

and internal control requirements Tie in between T&E and GL module Statement of indirects and real time monitoring All functionality required for government contract accounting compliance is

built into Costpoint. If configured properly, it’s difficult to “break” Costpoint

Page 56: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

AUDIT TRENDS

Page 57: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

57 DCAA ICS Audits and How to Leverage Costpoint for Success

Audit Trends

Consultants

Standardize documentation required from consultants (e.g., consulting agreements, sufficient detail for invoices)

Market analysis of billing rates should help support agreements

Substance of the documentation is key to supporting cost incurred

Executive Compensation

Ensure your HR Department has a standard processes for developing “compensation bands” (Written Compensation Plan/Policy)

Utilize salary surveys to the maximum extent practicable (e.g., Towers Watson, ERI, Mercer, Radford)

The executive compensation limit for government contractors for the year ending December 31, 2019 will be $540,000. Section 702 of the Bipartisan Budget Act of 2013 (BBA) established a compensation cap on all government contractor personnel

Bonuses

Documented bonus plan establishing parameters (e.g., who is eligible, timing of payouts, and how bonuses are calculated)

Employment agreements outlining potential compensation

Page 58: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

58 DCAA ICS Audits and How to Leverage Costpoint for Success

Audit Trends (continued)

DCAA has caught up on ICS audits

Medium and small contractors will receive more attention from DCAA

Quicker contract close outs

• Contracting officers can avoid negotiations and go straight to closing out contractsusing rates established by DCAA

Commercially Accepted Standards for Risk and Materiality

• DCAA’s response to Section 803 of FY2018 NDAA which required them to adopt commercially accepted standards of materiality for incurred cost audits

• Provide for both qualitative and quantitative considerations

• Incorporates use of quantified materiality threshold to facilitate a consistentapproach in determining the nature, timing, and extent of audit procedures oncost elements and accounts that are significant to audit opinion

Statute of Limitations (6 years per FAR 33.206(b))

• If an Indirect Cost Rate Proposal is not submitted DCMA may establish rates withthe option of a unilateral cost decrement (FAR 42.703-2(c)(1) & 42.705(c)(1))

• The current rate, updated in 2016, is 16.4 percent

Page 59: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

HOW CAN BDO HELP?

Page 60: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

60 DCAA ICS Audits and How to Leverage Costpoint for Success

How BDO Can Help

Preparing a successful ICS is heavily dependent on having accurate, complete, and reliable data readily available

An accounting system that is planned and configured correctly can significantly simplify the ICS preparation process and support a DCAA audit

Our Services

As a participant in Deltek’s Partner Program, BDO can assist with the following:

System design & new implementation

Data conversion of historical ERP to Costpoint

Integration and reporting services

Current system review and reconfiguration services

Accounting and/or indirect rate structure updates, cost pool design, configuration, and best practices to include written policies & procedures

Outsourced accounting services provided by BDO’s Business Services and Outsourcing (BSO) practice

Page 61: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

61 DCAA ICS Audits and How to Leverage Costpoint for Success

How BDO Can Help

Deltek Services:Implementation Services

On-Premise to Cloud Conversion

System Check-ups

Indirect Rate Structure

Company Re-organizations/Consolidations

Time Collection, Expense and Self Service support

Costpoint Training

Budget & Planning

Subcontract Management

Page 62: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

62 DCAA ICS Audits and How to Leverage Costpoint for Success

Contact us:

Jonathan Reynolds

Managing Director, ERP

Direct: 703-336-1674

Mobile: 571-205-5757

[email protected]

Darlene Mihaly

Sr. Manager, ERP

Direct: 703-770-9045

Mobile: 937-572-4580

[email protected]

Page 63: PREPARING INCURRED COST SUBMISSIONS: GOVERNMENT …€¦ · the final indirect cost rates and update the schedule of cumulative direct and indirect costs claimed and billed within

BDO is the brand name for BDO USA, LLP, a U.S. professional services firm providing assurance, tax, and advisory services to a wide range of publicly traded and privately held companies. For more than 100 years, BDO has provided quality service through the activeinvolvement of experienced and committed professionals. The firm serves clients through more than 65 offices and over 650 independent alliance firm locations nationwide. As an independent Member Firm of BDO International Limited, BDO serves multi-national clients through a global network of more than 88,000 people working out of over 1,600 offices across 167 countries.

BDO USA, LLP, a Delaware limited liability partnership, is the U.S. member of BDO International Limited, a UK company limited byguarantee, and forms part of the international BDO network of independent member firms. BDO is the brand name for the BDO network and for each of the BDO Member Firms. For more information please visit: www.bdo.com.

Material discussed is meant to provide general information and should not be acted on without professional advice tailored to your needs.

www.bdo.com

This document contains information that is proprietary and confidential to BDO USA, LLP, the disclosure of which could provide substantial benefit to competitors offering similar services. Thus, this document may not be disclosed, used, or duplicated for any purposes other than to permit you to evaluate BDO to determine whether to engage BDO. If no contract is awarded to BDO, this document and any copies must be returned to BDO or destroyed.

Material discussed in this publication is meant to provide general information and should not be acted on without professional advice tailored to your needs.

© 2020 BDO USA, LLP. All rights reserved. www.bdo.com