preliminary design of some hydraulic structures, hydraulic circuit … · preliminary design of...

70
Preliminary design of some hydraulic structures, hydraulic circuit and powerhouse of a hydropower case study Teacher: Helena M. Ramos Professor at IST 2013

Upload: others

Post on 19-Feb-2021

20 views

Category:

Documents


3 download

TRANSCRIPT

  • Preliminary design of some hydraulic structures, hydraulic circuit and

    powerhouse of a hydropower case study

    Teacher: Helena M. Ramos

    Professor at IST

    2013

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    2

    Abstract

    This support document deals with the optimization study on the discharge design of the

    turbine/generator units are established inquiry of the developed adaptation mechanism for optimum

    cash flow, design of the hydraulic circuit, verification of the powerhouse including the analysis of

    the hydraulic transients. In this report students will find further material than the one for the work to

    be developed under the hydropower course.

    Key words: Hydropower systems, optimization, hydraulic structures, hydraulic transient

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    3

    Table of Contents 1. Introduction........................................................................................................................................... 5

    1.1 Remarks………………………………………………………………………………………………………………………………………….5

    1.2. Small Scale Hydropower (SHP)........................................................................................................ 5

    1.3. Objectives ...................................................................................................................................... 6

    2. Main Components of Small Hydropower Scheme ................................................................................... 7

    2.1. Water ways .................................................................................................................................... 8

    2.2. Power house and Tailrace ............................................................................................................ 35

    2.3. Forces applied to a solid anchor ................................................................................................... 42

    3. Transient and safety analysis (system dynamics) .................................................................................. 48

    3.1. The Method of Characteristics...................................................................................................... 48

    3.2. Hydraulic transient analysis: Preventing water hammer ............................................................... 50

    3.3. Transient flow due to fast/ slow manoeuvre................................................................................. 65

    3.4. Transient flow due to valve closure operations............................................................................. 66

    3.5. Recommendations ....................................................................................................................... 69

    4. References ........................................................................................................................................... 70

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    4

    LIST OF FIGURES FIGURE 1: SHP OVERVIEW ................................................................................................................................................... 6

    FIGURE 2: RESERVOIR OPERATING RULE .................................................................................................................................. 9

    FIGURE 3: MONTHLY VOLUME FLOW RATE .............................................................................................................................10

    FIGURE 4: MONTHLY VOLUME VARIATION 1 ............................................................................................................................14

    FIGURE 5: MONTHLY VOLUME VARIATION 2 ............................................................................................................................15

    FIGURE 6: MONTHLY VOLUME VARIATION 3 ............................................................................................................................16

    FIGURE 7: MONTHLY VOLUME VARIATION 4 ............................................................................................................................17

    FIGURE 8: MONTHLY VOLUME VARIATION 5 ............................................................................................................................18

    FIGURE 9: MONTHLY VOLUME VARIATION 6 ............................................................................................................................19

    FIGURE 10: MONTHLY VOLUME VARIATION 7 ..........................................................................................................................20

    FIGURE 11: MONTHLY VOLUME VARIATION 8 ..........................................................................................................................21

    FIGURE 12: MONTHLY VOLUME VARIATION 9 ..........................................................................................................................22

    FIGURE 13: MONTHLY VOLUME VARIATION 10 ........................................................................................................................23

    FIGURE 14: CASH FLOW AND TURBINE DISCHARGE ....................................................................................................................24

    FIGURE 15: CASH FLOW AND OPTIMUM TURBINE DISCHARGE ......................................................................................................25

    FIGURE 16: MONTHLY OPTIMUM VOLUME VARIATION ...............................................................................................................26

    FIGURE 17 INTAKE SCHEME WITH SUBMERGENCE .....................................................................................................................29

    FIGURE 17: PENSTOCK ......................................................................................................................................................29

    FIGURE 18: HYDRAULIC GRADIENT ........................................................................................................................................34

    FIGURE 19: HEAD LOSS WITH DISCHARGE ...............................................................................................................................35

    FIGURE 20: OPERATIONAL ENVELOPES OF TURBINES ..................................................................................................................37

    FIGURE 21: SPECIFIC SPEED VS NET HEAD...............................................................................................................................39

    FIGURE: 22 GROUP G FRANCIS TURBINES OPERATIONAL PARAMETERS ...........................................................................................41

    FIGURE 23: SUCTION HEAD ................................................................................................................................................42

    FIGURE 24: RESULTANT FORCES PRODUCED BY WEIGHT, PRESSURE AND CHANGE IN MOMENTUM .........................................................43

    FIGURE 25: SCHEMATIC VIEW OF THE MODEL POWERHOUSE .......................................................................................................44

    FIGURE 26: POWER HOUSE LAYOUT.......................................................................................................................................45

    FIGURE 27: POWERHOUSE FLOOR AREA REQUIRED ....................................................................................................................45

    FIGURE 28: TAIL RACE SHAPE ..............................................................................................................................................46

    FIGURE 29: POWER HOUSE DISCHARGE CURVE .........................................................................................................................46

    FIGURE 30: TAIL RACE LAYOUT .............................................................................................................................................47

    FIGURE 31: NOMENCLATURE FOR THE INTEGRATED EQUATIONS ...................................................................................................50

    FIGURE 32: SUMMARY OF DIFFERENT CLOSURE TYPES AND TIMES..................................................................................................52

    FIGURE 33: HYDRAULIC HEAD IN THE SHUTTER (VALVE) - TIME VARIATION ......................................................................................59

    FIGURE 34: MAXIMUM AND MINIMUM HEAD ENVELOPE AND PIPE LINE PROFILE ..............................................................................64

    FIGURE 35: VARIATION OF HYDRAULIC HEAD IN THE SHUTTER WITH CLOSURE TIME ...........................................................................68

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    5

    1. Introduction

    1.1. Remarks

    Flowing water, either falling directly upon paddles or filling buckets attached to a wheel, was

    humankind’s first source of mechanical power. The origin of waterwheels can be traced to ancient

    Egypt, China, and Persia where these devices took over many tasks such as raising water for

    irrigation purposes and water supply as well as grinding grain for flour. As demands for power

    increased, large water wheels were built.

    Water is, thus, one of the most important renewable energy sources already exploited by man on a

    large scale with a well-developed technological base to support its continued exploitation.

    Hydropower is, in fact, a form of none depleting, self-replenishing energy. It is usually the cheapest

    form of bulk energy; and, in most cases, it is also the most efficient and least pollution form of

    power. To date, it is the only practical means to store electrical power through pumped storage for

    use at a later time.

    1.2. Small Scale Hydropower (SHP)

    There is no consensus in the definition of small hydropower: Some countries like Portugal, Spain,

    Ireland and now, Greece and Belgium, accept 10 MW as the upper limit for installed capacity. In

    Italy the limit is fixed at 3 MW and in Sweden 1.5 MW. In France the limit has been recently

    established at 12 MW, not as an explicit limit of SHP, but as the maximum value of installed power

    for which the grid has the obligation to buy electricity from renewable energy sources. In the UK

    20MW is generally accepted as the threshold for small hydro. For the purposes of this text any

    scheme with an installed capacity of 20 MW or less will be considered as small.

    Small hydropower plants offer several advantages for today’s energy aesthetically acceptable.

    Effects upon stream ecology are minor compared to those caused by large hydropower facilities.

    Small dams may, in fact, enhance the stream by maintaining water depths sufficient to support

    aquatic life. Ideally, a small hydro system should serve several purposes in addition to power, such

    as water supply, flood control, irrigation, and recreation.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    6

    Figure 1: SHP overview

    1.3. Objectives

    This Project work is one part of a small scale hydropower carried out by the group of students listed

    in the front page, Recognizing that the small scale hydro can be a Viable and appropriate renewable

    energy technology, our project effort is to Optimize discharge to the turbine and verify a given

    hydraulic structures of a small scale hydro power system and so that it could solve major problems

    by providing adequate domestic electricity.

    The main aims of this project work are:

    To Optimize Design flow

    To check the minimum submergence in water intake design provided

    Calculation of losses, analysis of equipment, calculation of forces applied to a solid anchor

    To determine the flow curve in the area of powerhouse, verify the general layout and preliminary

    design of the building of the powerhouse

    To carry out an analysis of hydraulic transients adaptive for a given small hydroelectric power

    scheme.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    7

    2. Main Components of Small Hydropower Scheme

    This stage and the next section are the most critical stages in this project work as it determines the

    feasibility and achievability of the proposed small hydropower system. There are many factors that

    determine the feasibility and achievability of the system. This includes:

    i. The capacity of the reservoir to supply water for the small hydro system

    ii. The cost of developing the project and the net profit

    iii. The amount of power available from the water flow

    iv. The turbine selection and availability of required power house, suction head and transient

    condition.

    Table1: List of Givens

    No. Description Value

    1 Purpose

    1.1 Small hydro electric power plant

    2 Working range

    2.1 Discharge To be Determined

    2.2 Gross Head 63 m

    2.3 Head Loss 5% of gross head

    4 Efficiency 82%

    5 Power and cost

    5.1 1 MW 2100 €/kW

    5.2 20 MW 1530 €/kW

    6 Discount rate 5%-10% (10%)

    7 Life 20 years

    8 Energy cost 0.08 €/kWh

    9 Reservoir capacity

    9.1 Vmax given

    9.2 Vmin calculate

    10 Velocity

    10.1 Intake 1 m/s

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    8

    No. Description Value

    10.2 Pipe 3 m/s - 4 m/s

    11 Opening

    11.1 Intake 2.4 m

    11.2 Pipe 1.5 m

    12 Penstock length 486.47 m

    13 Height

    13.1 Intake 94.4 m

    13.2 Pipe 93.5 m

    13.3 Limit 97.5 m

    14 Bends

    14.1 Number of Bends 5

    15 Butterfly Valve Fully opened

    16 Discharge range

    16.1 Maximum 110%

    16.2 Minimum 40%

    2.1. Water ways

    A hydropower development includes a number of structures, the design of which will be dependant

    upon the type of scheme, local conditions, access to construction material and also local building

    traditions in the country or region. The following structures are common in a hydro scheme:

    • Diversion structure

    o Dam

    o Spillway

    o Energy dissipation arrangement

    o Residual flow arrangements

    • Water conveyance system

    o Intake

    o Canals and Tunnels

    o Penstocks

    o Power house

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    9

    2.1.1. Optimization of flow design

    Way of organizing discharge data and reservoir capacity is by plotting a reservoir operating rule

    volumetric curve, that shows for a particular point on a reservoir the proportion of time during which

    the discharge there equals or exceeds certain limit values. This can be obtained from the hydrograph

    by organizing the data by monthly volume flow rate. If the individual daily flows for one year are

    organized in categories as shown in Figure 3 the reservoir volumetric curve can be determined by

    arranging the data in the range of the boundary conditions and calculating the relative values via

    excel as shown in Figure 2.

    Figure 2: Reservoir operating rule

    The requirements of the discharge at the given head and the site where the power plant can be

    founded was also computed parallel with the cash flow to choose the optimum discharge in both

    safety and net profit as shown in the next tables and figures.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    10

    Given Data

    Figure 3: Monthly Volume flow rate

    Values of discharge converted to volume within a month using excel are depicted in the table below:

    Table 2: monthly volumetric flow

    Month Qm (m3/s) No. of day Vin(hm

    3)

    Jan 80 31 214.27

    Feb 40 28 96.77

    Apr 30.2 31 80.89

    Mar 20.3 30 52.62

    May 15.1 31 40.44

    Jun 10 30 25.92

    Jul 3 31 8.04

    Aug 0 31 0

    Sep 1 30 2.59

    Oct 5.6 31 14.99

    Nov 10.9 30 28.25

    Dec 30 31 80.35

    Total 365 645.14

    Month Qm

    (m3/s)

    Jan 80

    Feb 40

    Apr 30,2

    Mar 20,3

    May 15,1

    Jun 10

    Jul 3

    Aug 0

    Sep 1

    Oct 5,6

    Nov 10,9

    Dec 30

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    11

    Summary of values required for the optimization is also presented in the table below:

    Table 3: summary of given Data

    QT(m

    3/s) η Hb (m)

    HL (m)

    Hu (m)

    P (MW) Cost(€/kW) Discount rate (a)

    Life(n) (yrs)

    s (€/kWh)

    arbitrated 0.82 63 3.15 59.85 1 2100 0.10 20 0.08

    Vfull (hm3) Vmin (hm

    3) 20 1530

    50 20

    Using the data summarized above we first tried to determine the cash flow at a low discharge value

    knowing the net profit increases with increasing flow rate of the turbine to some optimum value.

    Trial 1: when the discharge to the turbine (QT =2.9 m3/s)

    Given formulas

    Power to be installed

    [1]

    =9.8KN/m3*2.9m

    3/s*59.85m*0.82

    = 1394.77 kW

    Since the calculated power is between the given limits for a small hydro scheme then by linear

    interpolation the cost per kW (C/kW) will be:

    C/kW=2088.16 €/kW

    Global cost (C)

    C = P*C/kW [2]

    = 1394.77kW*2088.16 €/kW

    = 2912495.20 €

    Turbine volume (VT)

    VT = Q*number of seconds of turbining [3]

    = Q*days*24hr/day*3600sec/hr

    = 2.9*31*24*3600/1000000 (January - 31 days)

    = 7.77 hm3

    This is for January and the procedure is similar for the other months.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    12

    Energy production (E)

    E = (9.8ηHuVT total)/3600 [4]

    = 9.8*0.82*59.85*91.45*106/3600

    =12218170.66 kWh

    Gross profit (Bb) [5]

    Bb =E*0.08 €/kWh

    =12218170.66 KWh*0.08 €/kWh

    =977453. 65 €

    Net profit (Bl)

    Bl =0.9*Bb [6]

    =0.9*977453. 65 €

    =879708.29 €

    Discount factor (actualization factor)

    [7]

    Where: n - life of the power plant

    a - discount rate

    = 10.96

    Updated new profit (Bla) = Bl*F [8]

    = 879708.29 €*10.96

    = 9640791.92 €

    Cash flow (VAL) = Bla – C [9]

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    13

    = 9640791.92€-2912495.20 €

    = 6728296.72 €

    This result is obtained only for a small discharge value of 2.9 m3/s using excel. The calculation of

    the various characteristics is rather bulky; thus all the established values were calculated via Excel as

    shown in the tables below:

    Where:

    Qm-mean monthly flow rate

    Vin-mean monthly volume to the reservoir

    VT-mean monthly volume to the turbine

    ∆V = Vin-VT+VR

    VR-mean monthly reservoir volume

    HR-monthly reservoir height

    Table 4: Summary of trial 1 (QT =2.9 m3/s)

    Description Value Month Qm

    (m3/s) No. of

    day Vin(hm

    3) VT(hm3) ∆V (hm3) VR(hm

    3) HR(m)

    Global cost ( € ) 2912495.20 Jan 80 31

    214.27

    7.77 256.50

    50.00

    5.00

    Power (kW) 1394.77 Feb 40 28

    96.77

    7.02 139.75

    50.00

    5.00

    C/kW 2088.16 Apr 30.2 31

    80.89

    7.77 123.12

    50.00

    5.00

    Energy production (kWh) 12218170.66 Mar 20.3 30

    52.62

    7.52 95.10

    50.00

    5.00

    Gross profit (€) - Bb 977453.65 May 15.1 31

    40.44

    7.77 82.68

    50.00

    5.00

    Net profit (€) - BL 879708.29 Jun 10 30

    25.92

    7.52 68.40

    50.00

    5.00

    Discount factor - f 10.96 Jul 3 31

    8.04

    7.77 50.27

    50.00

    5.00

    Updated net profit (€)- Bla 9640791.92 Aug 0 31 -

    7.77 42.23

    42.23

    4.22

    Cash flow (€) - VAL 6728296.72 Sep 1 30

    2.59

    7.52 37.31

    37.31

    3.73

    Oct 5.6 31

    15.00

    7.77

    44.54

    44.54

    4.45

    Nov 10.9 30

    28.25

    7.52

    65.28

    50.00

    5.00

    Dec 30 31

    80.35

    7.77

    122.58

    50.00

    5.00

    Total 365

    645.14

    91.45

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    14

    Figure 4: monthly volume variation 1

    From table 4 and figure 4 we can understand that the volume flow to the turbine is almost constant

    only due to the small variation in number of days for different months and our reservoir is full for

    the first seven months and starts to decrease from July to November but it can deliver the calculated

    power the whole year. Since our concern is to maximize profit this is not sufficient enough then we

    have to search other options. Hence, all the other results were calculated with the same procedure

    like the first trial via excel we present the outcomes only in a tables and figures.

    Table 5: Trial 2- when the discharge to the turbine (QT = 7m3/s)

    Description Value Month Qm

    (m3/s)

    No. of day

    Vin(hm3) VT(hm

    3) ∆V (hm3) VR(hm3) HR(m)

    Global cost ( € ) 6830996.61 Jan 80.00 31.00 214.27 18.75 245.52 50.00 5.00

    Power (kW) 3366.68 Feb 40.00 28.00 96.77 16.93 129.83 50.00 5.00

    C/kW 2029.00 Apr 30.20 31.00 80.89 18.75 112.14 50.00 5.00

    Energy production (kWh) 24563313.33 Mar 20.30 30.00 52.62 18.14 84.47 50.00 5.00

    Gross profit (€) - Bb 1965065.07 May 15.10 31.00 40.44 18.75 71.70 50.00 5.00

    Net profit (€) - BL 1768558.56 Jun 10.00 30.00 25.92 18.14 57.78 50.00 5.00

    Discount factor - f 10.96 Jul 3.00 31.00 8.04 18.75 39.29 39.29 3.93

    Updated net profit (€)- Bla 19381771.58 Aug 0.00 31.00 0.00 18.75 20.54 20.54 2.05

    Cash flow (€) - VAL 12550774.96 Sep 1.00 30.00 2.59 0.00 23.13 23.13 2.31

    Oct 5.60 31.00 15.00 0.00 38.13 38.13 3.81

    Nov 10.90 30.00 28.25 18.14 48.24 48.24 4.82

    Dec 30.00 31.00 80.35 18.75 109.84 50.00 5.00

    Total 365.00 645.14 183.86

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    15

    Figure 5: monthly volume variation 2

    Table 5 and figure 5 are evidence for the volume flow to the turbine is almost constant until august

    and decreases to zero on September and October with no energy production and our reservoir is full

    until May, decreases to the minimum value and it returns back to its full state on November. But

    since our concern is to get maximum net profit and comparably trial 2 is better than trial1 in cash

    flow we have to search for other trials which have a maximum cash flow by increasing the flow to

    the turbine.

    With similar reasoning only the values of trials 3, 4, and 5 are presented in the next three tables and

    figures.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    16

    Table 6: Trial 3- when the discharge to the turbine (QT =11m3/s)

    Description Value Month Qm

    (m3/s) No. of

    day Vin(hm

    3) VT(hm

    3) ∆V (hm

    3) VR(hm

    3) HR(m)

    Global cost ( € ) 10429084.38 Jan 80 31.00 214.27 29.46 234.81 50.00 5.00

    Power (kW) 5290.50 Feb 40 28.00 96.77 26.61 120.16 50.00 5.00

    C/kW 1971.28 Apr 30.2 31.00 80.89 29.46 101.43 50.00 5.00

    Energy production (kWh) 34663359.93 Mar 20.3 30.00 52.62 28.51 74.11 50.00 5.00

    Gross profit (€) - Bb 2773068.79 May 15.1 31.00 40.44 29.46 60.98 50.00 5.00

    Net profit (€) - BL 2495761.92 Jun 10 30.00 25.92 28.51 47.41 47.41 4.74

    Discount factor - f 10.96 Jul 3 31.00 8.04 29.46 25.98 25,98 2.60

    Updated net profit (€)- Bla 27351250.02 Aug 0 31.00 0.00 0.00 25.98 25.98 2.60

    Cash flow (€) - VAL 16922165.64 Sep 1 30.00 2.59 0.00 28.57 28.57 2.86

    Oct 5.6 31.00 15.00 0.00 43.57 43.57 4.36

    Nov 10.9 30.00 28.25 28.51 43.31 43.31 4.33

    Dec 30 31.00 80.35 29.46 94.20 50.00 5.00

    Total 365.00 645.14 259.46

    Figure 6: monthly volume variation 3

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    17

    Table 7: Trial 4- when the discharge to the turbine (QT =15m3/s)

    Figure 7: monthly volume variation 4

    Description Value Month Qm

    (m3/s)

    No. of

    day Vin(hm

    3) VT(hm3) ∆V (hm3) VR(hm

    3) HR(m)

    Global cost ( € ) 13805107.51 Jan 80 31 214.27 40.18 224.10 50.00 5.00

    Power (kW) 7214.32 Feb 40 28 96.77 36.29 110.48 50.00 5.00

    C/kW 1913.57 Apr 30.2 31 80.89 40.18 90.71 50.00 5.00

    Energy production (kWh) 42073908.41 Mar 20.3 30 52.62 38.88 63.74 50.00 5.00

    Gross profit (€) - Bb 3365912.67 May 15.1 31 40.44 40.18 50.27 50.00 5.00

    Net profit (€) - BL 3029321.41 Jun 10 30 25.92 38.88 37.04 37.04 3.70

    Discount factor - f 10.96 Jul 3 31 8.04 0.00 45.08 45.08 4.51

    Updated net profit (€)- Bla 33198570.21 Aug 0 31 0.00 0.00 45.08 45.08 4.51

    Cash flow (€) - VAL 19393462.7 Sep 1 30 2.59 0.00 47.67 47.67 4.77

    Oct 5.6 31 15.00 40.18 22.49 22.49 2.25

    Nov 10.9 30 28.25 0.00 50.74 50.00 5.00

    Dec 30 31 80.35 40.18 90.18 50.00 5.00

    Total 365 645.14 314.93

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    18

    Table 8: Trial 5- when the discharge to the turbine (QT =19m3/s)

    Description Value Month Qm

    (m3/s) No. of days

    Vin(hm3) VT(hm

    3) ∆V (hm

    3) VR(hm

    3) HR(m)

    Global cost ( € ) 16959066.01 Jan 80 30 207.36 49.25 208.11 50.00 5.00

    Power (kW) 9138.14 Feb 40 28 96.77 45.96 100.80 50.00 5.00

    C/kW 1855.86 Apr 30.2 31 80.89 50.89 80.00 50.00 5.00

    Energy production (kWh) 46275527.79 Mar 20.3 30 52.62 49.25 53.37 50.00 5.00

    Gross profit (€) - Bb 3702042.22 May 15.1 31 40.44 50.89 39.55 39.55 3.96

    Net profit (€) - BL 3331838.00 Jun 10 30 25.92 0.00 65.47 50.00 5.00

    Discount factor - f 10.96 Jul 3 31 8.04 0.00 58.04 50.00 5.00

    Updated net profit (€)- Bla 36513873.24 Aug 0 31 0.00 0.00 50.00 50.00 5.00

    Cash flow (€) - VAL 19554807.23 Sep 1 30 2.59 0.00 52.59 50.00 5.00

    Oct 5.6 31 15.00 0.00 65.00 50.00 5.00

    Now 10.9 30 28.25 49.25 29.00 29.00 2.90

    Dec 30 31 80.35 50.89 58.47 50.00 5.00

    Total 364 638.23 346.38

    Figure 8: monthly volume variation 5

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    19

    Table 9: Trial 6- when the discharge to the turbine (QT = 23m3/s)

    Description Value Month Qm

    (m3/s) No. of

    day Vin(hm

    3) VT(hm

    3) ∆V (hm

    3) VR(hm

    3) HR(m)

    Global cost ( € ) 19890959.87 Jan 80 31 214.27 61.60 202.67 50.00 5.00

    Power (kW) 11061.96 Feb 40 28 96.77 55.64 91.13 50.00 5.00

    C/kW 1798.14 Apr 30.2 31 80.89 61.60 69.28 50.00 5.00

    Energy production (kWh) 48318622.93 Mar 20.3 30 52.62 59.62 43.00 43.00 4.30

    Gross profit (€) - Bb 3865489.84 May 15.1 31 40.44 61.60 21.84 21.84 2.18

    Net profit (€) - BL 3478940.85 Jun 10 30 25.92 0.00 47.76 47.76 4.78

    Discount factor - f 10.96 Jul 3 31 8.04 0.00 55.80 50.00 5.00

    Updated net profit (€)- Bla 38125984.88 Aug 0 31 0.00 0.00 50.00 50.00 5.00

    Cash flow (€) - VAL 18235025.01 Sep 1 30 2.59 0.00 52.59 50.00 5.00

    Oct 5.6 31 15.00 0.00 65.00 50.00 5.00

    Nov 10.9 30 28.25 0.00 78.25 50.00 5.00

    Dec 30 31 80.35 61.60 68.75 50.00 5.00

    Total 365 645.14 361.67

    Figure 9: monthly volume variation 6

    Now, as table 9 and figure 9 indicates the volume of the reservoir is within the reservoir operating rule

    but the water flow to the turbine is very high for the first five months with no flow to the turbine in the

    next five months the cash flow also starts to drop down therefore we have to do another trial to prove

    whether the cash flow continues to decrease or not as shown in the next tables and figures.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    20

    Table 10: Trial 7- when the discharge to the turbine (QT = 27m3/s)

    Figure 10: monthly volume variation 7

    Description Value Month Qm

    (m3/s)

    No. of day

    Vin(hm3) VT(hm

    3) ∆V (hm

    3) VR(hm

    3) HR(m)

    Global cost ( € ) 22600789.10 Jan 80 31 214.27 72.32 191.96 50.00 5.00

    Power (kW) 12985.77 Feb 40 28 96.77 65.32 81.45 50.00 5.00

    C/kW 1740.43 Apr 30.2 31 80.89 72.32 58.57 50.00 5.00

    Energy production (kWh) 47060445.70 Mar 20.3 30 52.62 69.98 32.63 32.63 3.26

    Gross profit (€) - Bb 3764835.66 May 15.1 31 40.44 0.00 73.08 50.00 5.00

    Net profit (€) - BL 3388352.09 Jun 10 30 25.92 0.00 75.92 50.00 5.00

    Discount factor - f 10.96 Jul 3 31 8.04 0.00 58.04 50.00 5.00

    Updated net profit (€)- Bla 37133215.57 Aug 0 31 0.00 0.00 50.00 50.00 5.00

    Cash flow (€) - VAL 14532426.47 Sep 1 30 2.59 0.00 52.59 50.00 5.00

    Oct 5.6 31 15.00 0.00 65.00 50.00 5.00

    Now 10.9 30 28.25 0.00 78.25 50.00 5.00

    Dec 30 31 80.35 72.32 58.04 50.00 5.00

    Total 365 645.14 352.25

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    21

    Table 11: Trial 8- when the discharge to the turbine (QT = 31m3/s)

    Description Value Month Qm

    (m3/s) No. of

    day Vin(hm

    3) VT(hm

    3) ∆V (hm

    3) VR(hm

    3) HR(m)

    Global cost ( € ) 25088553.69 Jan 80 31 214.27 83.03 181.24 50.00 5.00

    Power (kW) 14909.59 Feb 40 28 96.77 75.00 71.77 50.00 5.00

    C/kW 1682.71 Apr 30.2 31 80.89 83.03 47.86 47.86 4.79

    Energy production (kwh) 54032363.58 Mar 20.3 30 52.62 80.35 20.12 20.12 2.01

    Gross profit (€) - Bb 4322589.09 May 15.1 31 40.44 0.00 60.57 50.00 5.00

    Net profit (€) - BL 3890330.18 Jun 10 30 25.92 0.00 75.92 50.00 5.00

    Discount factor - f 10.96 Jul 3 31 8.04 0.00 58.04 50.00 5.00

    Updated net profit (€)- Bla 42634432.69 Aug 0 31 0.00 0.00 50.00 50.00 5.00

    Cash flow (€) - VAL 17545878.99 Sep 1 30 2.59 0.00 52.59 50.00 5.00

    Oct 5.6 31 15.00 0.00 65.00 50.00 5.00

    Nov 10.9 30 28.25 0.00 78.25 50.00 5.00

    Dec 30 31 80.35 83.03 47.32 47.32 4.73

    Total 365 645.14 404.44

    Figure 11: monthly volume variation 8

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    22

    Table 12: Trial 9- when the discharge to the turbine (QT =35m3/s)

    Description Value Month Qm

    (m3/s)

    No. of day

    Vin(hm3) VT(hm

    3) ∆V (hm3) VR(hm3) HR(m)

    Global cost ( € ) 27354253.65 Jan 80 31 214.27 93.74 170.53 50.00 5.00

    Power (kW) 16833.41 Feb 40 28 96.77 84.67 62.10 50.00 5.00

    C/kW 1624.99 Apr 30.2 31 80.89 93.74 37.14 37.14 3.71

    Energy production (kWh) 48884225.54 Mar 20.3 30 52.62 0.00 89.76 50.00 5.00

    Gross profit (€) - Bb 3910738.04 May 15.1 31 40.44 0.00 90.44 50.00 5.00

    Net profit (€) - BL 3519664.24 Jun 10 30 25.92 0.00 75.92 50.00 5.00

    Discount factor - f 10.96 Jul 3 31 8.04 0.00 58.04 50.00 5.00

    Updated net profit (€)- Bla 38572275.67 Aug 0 31 0.00 0.00 50.00 50.00 5.00

    Cash flow (€) - VAL 11218022.02 Sep 1 30 2.59 0.00 52.59 50.00 5.00

    Oct 5.6 31 15.00 0.00 65.00 50.00 5.00

    Nov 10.9 30 28.25 0.00 78.25 50.00 5.00

    Dec 30 31 80.35 93.74 36.61 36.61 3.66

    Total 365 645.14 365.90

    Figure 12: monthly volume variation 9

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    23

    Table 13: Trial 10- when the discharge to the turbine (QT = 39m3/s)

    Description Value Month Qm

    (m3/s)

    No. of day

    Vin(hm3) VT(hm

    3) ∆V (hm3) VR(hm3) HR(m)

    Global cost ( € ) 29397888.98 Jan 80 31 214.27 104.46 159.81 50.00 5.00

    Power (kW) 18757.23 Feb 40 28 96.77 94.35 52.42 50.00 5.00

    C/kW 1567.28 Apr 30.2 31 80.89 104.46 26.43 26.43 2.64

    Energy production (kWh) 54470994.18 Mar 20.3 30 52.62 0.00 79.05 50.00 5.00

    Gross profit (€) - Bb 4357679.53 May 15.1 31 40.44 0.00 90.44 50.00 5.00

    Net profit (€) - BL 3921911.58 Jun 10 30 25.92 0.00 75.92 50.00 5.00

    Discount factor - f 10.96 Jul 3 31 8.04 0.00 58.04 50.00 5.00

    Updated net profit (€)- Bla 42980535.75 Aug 0 31 0.00 0.00 50.00 50.00 5.00

    Cash flow (€) - VAL 13582646.77 Sep 1 30 2.59 0.00 52.59 50.00 5.00

    Oct 5.6 31 15.00 0.00 65.00 50.00 5.00

    Nov 10.9 30 28.25 0.00 78.25 50.00 5.00

    Dec 30 31 80.35 104.46 25.89 25.89 2.59

    Total 365 645.14 407.72

    Figure 13: monthly volume variation 10

    At this stage from the figures and tables of trials seven to ten though the cash flow is flactuating it is

    with a pick value of lower than the trials perior to seven as shown in the summary of all values,

    table 14 and figure 14 below thus from trial 5 and 6 we can estimate that the optimum discharge

    value is between 19 and 23 m3/s .

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    24

    Table 14: Summary

    Tri

    al

    Q (

    m3/s

    )

    VA

    L (

    €)

    Glo

    bal

    cost

    ( €

    )

    Po

    wer

    (k

    W)

    C/k

    W

    En

    erg

    y p

    rod

    uct

    ion

    (k

    Wh

    )

    Gro

    ss p

    rofi

    t (€

    ) -

    Bb

    Net

    pro

    fit

    (€)

    - B

    L

    Dis

    cou

    nt

    fact

    or

    - f

    Up

    da

    ted

    net

    pro

    fit

    (€)-

    Bla

    Ca

    sh f

    low

    (€

    ) -

    VA

    L

    1 2,9 6728296.7 2912495.20 1394.77 2088.16 12218170.66 977453.65 879708.29 10.96 9640791.92 6728296.72

    2 7 12550775 6830996.61 3366.68 2029.00 24563313.33 1965065.07 1768558.56 10.96 19381771.58 12550774.96

    3 11 16922166 10429084.38 5290.50 1971.28 34663359.93 2773068.79 2495761.92 10.96 27351250.02 16922165.64

    4 15 19393463 13805107.51 7214.32 1913.57 42073908.41 3365912.67 3029321.41 10.96 33198570.21 19393462.70

    5 19 19554807 16959066.01 9138.14 1855.86 46275527.79 3702042.22 3331838.00 10.96 36513873.24 19554807.23

    6 23 18235025 19890959.87 9138.14 1798.14 48318622.93 3865489.83 3478940.85 10.96 38125984.88 18235025.01

    7 27 14532426 22600789.10 12985.77 1740.43 47060445.70 3764835.66 3388352.09 10.96 37133215.57 14532426.47

    8 31 17545879 25088553.69 14909.59 1682.71 54032363.58 4322589.09 3890330.18 10.96 42634432.69 17545878.99

    9 35 11218022 27354253.65 16833.41 1625.00 48884225.54 3910738.04 3519664.24 10.96 38572275.67 11218022.02

    10 39 13582647 29397888.98 18757.23 1567.28 54470994.18 4357679.53 3921911.58 10.96 42980535.75 13582646.77

    Figure 14: cash flow and turbine discharge

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    25

    There fore, with similar analysis for the range 19 – 23 m3/s using excel a value of 22.45 m

    3/s is found to

    be the optimum discharge in both ecnomic and safety considerations with a cash flow of 23847505.75€

    as shown in figure 15 with the other details in table 15 and figure 16.

    Figure 15: cash flow and Optimum turbine discharge

    Table 15: maximum cash flow with optimum discharge (QT = 22.45m3/s)

    Description Value Month Qm

    (m3/s) No. of

    day Vin(hm

    3) VT(hm3) ∆V (hm3) VR(hm

    3) HR(m)

    Global cost ( € ) 19500992.20 Jan 80 31 214.27 60.13 204.14 50.00 5.00

    Power (kW) 10797.43 Feb 40 28 96.77 54.31 92.46 50.00 5.00

    C/kW 1806.08 Apr 30.2 31 80.89 60.13 70.76 50.00 5.00

    Energy production (kWh) 54937327.76 Mar 20.3 30 52.62 58.19 44.43 44.43 4.44

    Gross profit (€) - Bb 4394986.221 May 15.1 31 40.44 60.13 24.74 24.74 2.47

    Net profit (€) - BL 3955487.60 Jun 10 30 25.92 0.00 50.66 50.00 5.00

    Discount factor - f 10.96 Jul 3 31 8.04 0.00 58.04 50.00 5.00

    Updated net profit (€)- Bla 43348497.96 Aug 0 31 0.00 0.00 50.00 50.00 5.00

    Cash flow (€) - VAL 23847505.75 Sep 1 30 2.59 0.00 52.59 50.00 5.00

    Oct 5.6 31 15.00 0.00 65.00 50.00 5.00

    Nov 10.9 30 28.25 58.19 20.06 20.06 2.01

    Dec 30 31 80.35 60.13 40.28 40.28 4.03

    Total 365 645.14 411.21

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    26

    Figure 16: monthly optimum volume variation

    2.1.2. Intake structures

    A water intake must be able to divert the required amount of water into the power canal or into the

    penstock without producing a negative impact on the local environment and with the minimum

    possible head loss. The intake serves as a transition between a stream that can vary from a trickle to

    a raging torrent, and a controlled flow of water both in quality and quantity. Its design, based on

    geological, hydraulic, structural and economic considerations, requires special care to avoid

    unnecessary maintenance and operational problems that cannot be easily remedied and would have

    to be tolerated for the life of the project.

    Intake location

    The location of the intake depends on a number of factors, such as submergence, geotechnical

    conditions, and environmental considerations especially those related to fish life, sediment exclusion

    and ice formation-where necessary.

    Power intake

    The power intake is an alternative of the conventional intake, usually located at the end of a power

    canal, although sometimes it can replace it. Hence it has to supply water to a pressure conduit

    (penstock) where its hydraulic requirements are more inflexible than those of a conveyance intake.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    27

    In this particular project we are only considering the minimum submergence and it is calculated

    using the given data and is verified with the available model via excel as presented in the analysis

    below.

    Minimum submergence is based on the fact that if the intake does not have sufficient submergence it

    is going to be prone to vortex formation. The vortex formation by insufficient intake submergence

    can induce air dragging or even solid material to the intake, reducing the turbine efficiency.

    Therefore, the design of intake is based on the minimum submergence which will enable the power

    house not to suffer from entrance of foreign materials like air and solid materials which will reduce

    the performance of the power house and reduce the life of the turbine.

    The following model equation (developed by Gordon) is the most widely used to estimate the

    minimum submergence of the intake to avoid vortex formation. The equation can equally be used for

    the intake opening and the pipe given by:

    [10]

    Where: -

    S - is the submergence [m]

    d -is the intake opening [m]

    V -is the mean flow velocity at the inlet [m/s]

    g -is the gravity acceleration [m/s2]

    Given parameters and assumptions:

    1. The intake line is assumed to be symmetric ( C = 1.7 for symmetric and 2.3 for asymmetric

    intakes, for this case we took 1.7)

    2. The gravitational acceleration, g is equal to [9.81 m/s2]

    3. The mean velocity in the pipe intake opening should be between 3m/s and 4m/s. for this case

    we took 3.5m/s and that of intake opening should be 1m/s.

    4. The Pipe is given to be 1.5 m in diameter on the model and the Intake opening is 2.5m (need

    adaptation and verification based on the velocity criteria).

    Pipe

    Now, by rearranging and substituting the above values on equation 10 it results

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    28

    S=

    However, this value of minimum submergence should comply with the parameters given on the

    model i.e. the sum of the pipe opening, the minimum submergence and the piezometric head of the

    penstock inlet should not exceed 97.5m. The total piezometric head of the pipe is given to be 93.5m

    and the pipe opening is 1.5 m. Now the sum of these three parameters is given by:

    Since the value is below 97.5m the given model is verified for minimum submergence at the pipe

    section.

    Intake

    With similar approach the minimum submergence of the intake opening is given by equation 10 as:

    S=

    Once again the sum of the height of the intake opening, the intake opening diameter and

    submergence should not exceed 97.5 m. The intake opening is 2.5 m; the height of the penstock from

    the intake opening is 94.4 m. Now their sum is:

    But this value is a bit higher than the limit 97.5 m thus we decide to decrease the opening of the

    intake to 2.25 m in order to verify the minimum submergence at the intake opening and we found a

    value as shown below:

    S =

    Now the sum < 97.5

    The Minimum submergence values of both the pipe and the intake opening via excel is summarized

    in the table below:

    Table 16: Minimum submergence

    Component S [m] Htotal [m] Hlimit [m] d [m] dmodified [m] Smodified [m]

    Pipe 2.33 97.33 97.5 1.5 1.5 2.33

    Intake 0.86 97.46 97.5 2.5 2.25 0.81

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    29

    Figure 17 Intake scheme with submergence

    2.1.3. Hydraulic circuit

    Penstocks

    Conveying water from the intake to the powerhouse (this is the purpose of a penstock) may not

    appear a difficult task. However deciding the most economical arrangement for a penstock is not so

    simple. Penstocks can be installed over or under the ground, depending on factors such as the nature

    of the ground itself, the penstock material, the ambient temperatures and the environmental

    requirements.

    Figure 17: penstock

    Economic Diameter

    The economic diameter is given by the following correlation developed by JIANDONG et al., 1997

    [11]

    Where:

    CEC - coefficient of energy cost (zones where the energy cost is low = 1.2, medium = 1.4 and high or

    no alternative source = 1.6)

    CMP = coefficient for the pipe materials (for steel = 1 to 1.2; or plastic = 0.9)

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    30

    Ho = net head [m]

    Q = design discharge [m3/s].

    Given parameters and assumptions

    1. The penstock is made of steel (CMP =1.2 )

    2. The coefficient of energy is given to be 1.6

    3. The net head is taken to be 95% of the gross height assuming 5% loss ( = 59.85m )

    4. Another criteria based on the maximum velocity of flow in the penstock can give a first

    estimation for the diameter: 2-3 m/s low head plants; 3-4 m/s for medium head and 4-5 m/s

    for high head plants. These are typical values based on real cases. For our case the power

    plant is medium head, the velocity in the penstock should be between 3 and 4 m/s.

    The design flow rate is the optimum discharge from the previous section with a value of 22.45 m3/s

    and as a general rule; the number of turbines should be kept as low as possible i.e between 1 and 3

    for SHP. The need to install more than one turbine arises with a variable stream flow. Hence it is

    given small hydropower plants with long hydraulic conveyance circuit work effectively at a flow

    rate of less than 10 m3/s we decide to have three turbines with three penstocks for each working at a

    flow rate of 7.48 m3/s where the maximum flow rate is 110% of the optimum discharge and the

    minimum flow rate is 40% of the optimum discharge.

    Now substituting these values:

    = = 1.708 m

    However, being economic diameter could not be a guarantee to fulfill the criterion imposed by

    velocity. Based on this the velocity of the water inside the penstock is going to be

    = [12]

    This velocity is within the range but we can still modify the diameter (reduce) to optimize it as long

    as the velocity is within the range of 3 – 4 m/s because a penstock with large diameter is more

    costly.

    For this reason we changed the economic diameter to1.65 m and see if the velocity is in the range.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    31

    =

    As a result this is enough because reducing more will drive the velocity to be out of range and we

    took the diameter of the penstock as 1.65 m

    Thickness of the pipe

    The thickness of the pipe is given by the following correlation

    t’ = 0.0084*D = 0.014 m, including 1mm for corrosion, [13]

    t = t’+0.001 = 0.015m [14]

    Thus, considering the empirical formulas to calculate the economic diameter and arranging the

    calculated value to the allowable values using excel is presented in the table below.

    Table 17: Penstock Dimensions

    Penstock

    Do (m) 1.65

    t (m) 0.015

    Head losses

    In any real moving fluid, energy is dissipated due to friction (major losses) proportional to the length

    associated and singular losses (minor losses) associated with bends, fittings, valves, etc. here, with

    respect to the given data we calculated the head losses for friction and singularities as follows for

    design, maximum and minimum discharge by the well known empirical formulas.

    [15]

    [16]

    The mean velocity is given by the ratio of the flow rate and the cross sectional area of the penstock

    with economic diameter of 1.65 m.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    32

    [17]

    where:

    D – is the economic diameter of the pipe [m]

    Reynolds Number, Re is given by the equation

    = [18]

    where:

    V – is the mean velocity [m/s]

    d – is the economic diameter of the pipe [m]

    [ kg/m3]

    [kg/sm]

    [m2/s]

    Friction Loss through a pipe is proportional to the length of the pipe and given by the product of

    hydraulic gradient and length of the pipe.

    [19]

    Where:

    J- is the hydraulic gradient

    L- is the total length of the penstock.

    The hydraulic gradient is proportional to the square of the velocity and friction factor f.

    [20]

    For bends, valves, expansions and contractions the same equation can be used by replacing f by ᶓ

    (singularity factor) whose value is given for different bend angles and valves.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    33

    [21]

    Friction factor f, is a factor given by the following correlation

    [22]

    Where: -

    k – is the absolute roughness of the pipe [0.00025m for steel]

    Using the above equations the friction factor, f, the hydraulic gradient, J and Reynolds number Re for

    the optimum, maximum and minimum flow rates via excel are summarized in the following table:

    Table 18: Summary

    Q (m3/s) Mean velocity

    (m/s) Re f J (H-gradient ) Bend αb (0) ξ

    Optimum 3.50 5956214.49 0.010667286 0.003897291 1 29 0.2

    Maximum 3.85 6551835.94 0.010618327 0.004694079 2 10 0.2

    Minimum 1.40 2382485.80 0.011349384 0.000663439 3 26 0.2

    4 47 0.55

    5 28 0.2

    The head loss for the bends and valves is a function of ξ that its value depends on the respective

    angles indicated in the following table.

    Table 19: singularity factor

    α [o] 30 40 60 80 90

    ξ 0.2 0.3 0.55 0.99 1.10

    The modeled penstock has five bends and a butterfly valve at the entrance to the turbine. The

    butterfly valve is considered to be fully opened that there will be no loss associated with it. The

    actual bend angles are tabulated in table 18 and the tabulated values are not the exact values at that

    angle rather the next higher angle from table 19.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    34

    The table below also shows the sum of all the head losses and their percentage share with respect to

    the gross head for the optimum, minimum and maximum discharge.

    Table 20: Head losses

    Head Losses

    Component Type of head loss

    Qopt(m3/s) % Qmax(m3/s) % Qmin(m3/s) %

    Penstock Friction 1.92 3.01 2.32 3.62 0.33 0.51

    Bend 1 singular 0.12 0.2 0.15 0.24 0.02 0.03

    Bend 2 singular 0.12 0.2 0.15 0.24 0.02 0.03

    Bend 3 singular 0.12 0.2 0.15 0.24 0.02 0.03

    Bend 4 singular 0.34 0.55 0.42 0.66 0.05 0.09

    Bend 5 singular 0.12 0.2 0.15 0.24 0.02 0.03

    Butterfly valve

    singular 0 0 0 0 0 0

    Total 2.77 4.35 3.34 5.24 0.46 0.73

    From table 20 the percentage of the head losses is a bit less than 5% for the optimum discharge and a

    bit higher than 5% for the maximum flow with a very small head loss for the minimum flow. Thus

    the 5% loss given for the model is verified.

    There fore, the hydraulic grade line is verified using the next figure:

    Figure 18: Hydraulic grade line

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    35

    Generally figure 19 from the excel analysis dipicts the variation of head loss with discharge

    (minimum to maximum) in which the Head loss increases exponentially.

    Figure 19: Head loss with discharge

    2.2. Power house and Tailrace This subtopic gives the main description of the electromechanical equipment, some preliminary

    design rules and some selection criterion which is helpful to size our power house.

    2.2.1. Hydraulic turbines

    The purpose of a hydraulic turbine is to transform the water potential energy to mechanical

    rotational energy. It is appropriate to provide a few criteria to guide the choice of the right turbine

    for a particular application and even to provide appropriate formulae to determine its main

    dimensions.

    Turbine selection criteria

    The type, geometry and dimensions of a turbine will be fundamentally conditioned by the following

    criteria:

    • Net head

    • Range of discharges through the turbine

    • Rotational speed

    • Cavitations problems

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    36

    • Cost

    Net head

    The gross head is well defined, as the vertical distance between the upstream water surface level at

    the intake and the downstream water level for reaction turbines or the nozzle axis level for impulse

    turbines.

    The first criterion to take into account in the turbine's selection is the net head. Table 21 specifies the

    range of operating heads for each type of the most known turbines. The table shows some

    overlapping, as for a certain head several types of turbines can be used.

    Table 21: Range of heads

    Turbine type Head range in meter

    Kaplan and propeller 2 < Hn < 40

    Francis 25 < Hn < 450

    Pelton 50 < Hn < 1000

    Discharge

    It is necessary to know the flow regime, commonly represented by the Flow Duration Curve (FDC)

    or the Reservoir Storage Capacity for Regulation schemes. The rated flow and net head determine

    the set of turbine types applicable to the site and the flow environment. Suitable turbines are those

    for which the given rated flow and net head plot within the operational envelopes of the graph

    below. A point defined as above by the flow and the head will usually plot within several of these

    envelopes. All of those turbines are appropriate for the job, and it will be necessary to compute

    installed power and electricity output against costs before taking a decision. It should be

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    37

    remembered that the envelopes vary from manufacturer to manufacturer and they should be

    considered only as a guide.

    Figure 20: Operational range of application

    Using the above graph it is clear that for an optimum discharge of 7.48 m3/s and a net head of 59.85

    m Francis turbine is selected and the selection is verified for the model given to be installed at the

    small hydro power plant.

    Francis turbines

    Francis turbines are reaction turbines, with fixed runner blades and adjustable guide vanes (or wicket

    gates), used for medium heads. In this turbine the admission is always radial but the outlet is axial.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    38

    Francis turbines can have vertical or horizontal axis, this configuration being really common in small

    hydro.

    Photo1: Horizontal axis Francis turbine

    The water enters the turbine by the spiral case that is designed to keep its tangential velocity constant

    along the consecutive sections and to distribute it peripherally to the distributor.

    The draft tube of a reaction turbine aims to recover the kinetic energy still remaining in the water

    leaving the runner. As this energy is proportional to the square of the velocity one of the draft tube

    objectives is to reduce the turbine outlet velocity.

    Specific speed

    The specific speed constitutes a reliable criterion for the selection of the type and dimensions of

    turbine, given by:

    ns= N 4

    5

    H

    P [23]

    ns- is known as specific speed [rpm]

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    39

    N- is rotational speed of the generator [rpm]

    P- is power developed by the turbine in Horse power [HP]

    H- is net head [m]

    The specific speed can be chosen from the graph of specific speed and net head for different turbines

    as shown below:

    Figure 21: Specific speed Vs net Head

    Using the given net head of 59.85 m and the selected Francis turbine an average specific speed

    between the two curves for Francis turbine is taken by:

    ns= [24]

    =250.77 rpm

    For the hydraulic power

    when

    where the maximum efficiency is 0.90.

    Therefore rearranging the above equation for specific speed the rotational speed N will be 401.74

    rpm.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    40

    Generators

    Generators transform mechanical energy into electrical energy. Depending on

    characteristics of the network supplied, the generator can be chosen between:

    Synchronous generators

    Asynchronous generators

    Below 1 MW, synchronous generators are more expensive and are used in power systems where the

    output of the generator represents a substantial proportion of the power system load. But here since

    the power produced from each turbine is 3.6 MW we choose synchronous generator.

    The number of poles for the chosen synchronous generator with the selected specific speed of the

    Francis turbine from the graph at a 50 Hz grid is given by:

    [25]

    where:

    nPP- number of pair of poles

    N- Rotational speed [rpm]

    Using equation 23 the number of pair poles is found to be 7.5 but this is not synchronous we have to

    re-arrange the nPP to the nearest integer (npp=8) and calculate the modified values of N (375 rpm)

    and ns (234.08 rpm) using the above equations and this is done in excel in a similar way as

    presented in the Table 22.

    Table 22: summary of specific speed

    N (rpm) npp nppnew Nnew (rpm) nsnew(rpm)

    401.74 7.46 8 375 234.08

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    41

    Now, using the net head, optimum discharge, power output (for Q/Qmax=1) and the rotational speed

    from the standard manufacturer’s graphs we select a group G Francis turbine which suits our

    parameters as shown in the Figure 22.

    Figure: 22 Group G Francis turbines operational parameters

    The value of the suction head for the selected turbine can also be established from the same given

    standard manufacturer’s graphs as shown below based on the net head and group of turbine (G).

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    42

    Figure 23: Suction Head

    Therefore, the summary of all the calculated and selected values of the Francis turbine are presented

    in Table 23.

    Table 23: Summary of scheme parameters

    Scheme Parameters

    Turbine Type G

    Turbine size (m2) 13.5

    Q (m3/s) 7.48

    P(KW) 3599.14

    N (rpm) 375

    Ho (m) 59.89

    Hs (m) 5

    2.3. Forces applied to a solid anchor Net forces due to pressure and momentum change are computed as follows:

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    43

    Figure 24: Resultant forces produced by weight, pressure and change in momentum

    [26]

    [27]

    [28]

    [29]

    where:

    P- maximum pressure in penstock ( from the transient analysis - next section Hmax = 133 m)

    A-Cross-section area of penstock (2.14m2)

    Q-Discharge (7.48m3/sec)

    θ1 and θ2 – angles as shown in figure above

    At each pipe change direction, the penstock and its supporting structures must be designed to resist

    the forces resulting from changes in direction calculated by equation 26 to 29 via excel and are

    presented in Table 24.

    Table 24: Forces due to pressure and momentum

    Forces Value (kN) Resultant – R (kN)

    Fpx -107.2830242 393.63913

    Fpy 374.1403682

    Fmx -1.218625807

    Fmy 4.249853241

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    44

    2.2.3 Powerhouse

    Due to the presence of large and heavy equipment units the powerhouse stability must be completely

    secured. In a small hydropower scheme the role of the powerhouse is to protect the

    electromechanical equipment that convert the potential energy of water into electricity from the

    weather hardships. The number, type and power of the turbo-generators, their configuration, the

    scheme head and the geomorphology of the site determine the shape and size of the building.

    In order to mitigate the environmental impact the powerhouse can be entirely submerged. In this way

    the level of sound is sensibly reduced and the visual impact is nil.

    Figure 25: Schematic view of the model powerhouse

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    45

    Area of power house

    The layout of the given model power house is shown below and from the figure the area of the

    power house can be approximated to be (150 m2).

    Figure 26: power house layout

    Here to verify the general lay out we chose the area of the power house from a given standard graph

    presented below and we found a value of 152 m2

    for each turbine and since we select three turbines

    to handle the available discharge the total area must be three times greater and it results to 150 m2

    with a very small deviation the area of the power house is verified for the given model.

    Figure 27: powerhouse floor area required

    Flow discharge curve in the area of powerhouse

    The flow curve in the power house area is determined assuming a rectangular shape tail race shown

    below schematically and using the relation:

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    46

    Q = K s RH 2/3 i1/2 [30]

    where:

    K=30 m1/3

    s-1

    RH = s/p is the hydraulic radius

    S = 6*h is the area

    P- is the perimeter

    Figure 28: tail race shape

    Thus, the values of h at the tail race for different values of Q are established in excel and presented

    as shown in the table and graph below.

    Figure 29: Power house discharge curve

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    47

    Maximum suction head

    Based on the tail race layout given in the model the allowable head for flood prevention and the

    maximum height for the given maximum discharge which is 34.29 m from equation 31 as shown in

    the table below calculated via excel.

    Figure 30: Suction head and tail race layout

    Hmax=hsmax+Ht [31]

    where: Ht-tail race piezometric head (FSWL(NPA) -Hgross)[m] (Figure 30)

    hsmax- maximum suction head [m]

    Hmax-the level of the characteristic point of the turbine runner [m]

    Table 25: Summary of tail race head

    Ht (m) hmax (m) Hmax (m)

    32.8 2 34.29

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    48

    3. Transient and safety analysis (system dynamics)

    3.1. The Method of Characteristics Turbines are designed for a certain net head and discharge. Any deviation from these parameters

    must be compensated for by opening or closing the control devices, such as the wicket-gates, vanes,

    spear nozzles or valves, to keep either the outlet power, the level of the water surface in the intake,

    or the turbine discharge constant and more over huge load variation at for instance start-up and close

    down. This will give huge pressure fluctuation caused by the retardation of the water masses.

    The Method of Characteristics (MOC) is a numerical method for solving so called hyperbolical

    differential equations, the wave equations. For all kinds of pipe net work analysis, the method is very

    common and is described in several text books.

    In order to use MOC, one thing is to set up a system of the equation of motion and the continuity

    equations for all the pipe or conduit elements, another thing is to describe the boundary conditions

    like valves, turbines, shafts etc.

    Nomenclature for the integrated equations

    [32]

    C ~1000 m/s

    where:

    C - the celerity of the elastic waves in circular pipelines.

    - is the fluid bulk modulus of elasticity (2×10³ MPa for water),

    - is the fluid specific mass (10³ kg/m³ for water),

    E- is Young’s modulus of elasticity of the pipe wall ( steel = 2,5 Gpa)

    D- is the diameter of the pipeline and e is thickness (1.65 m, 0.15 m)

    e

    D

    E

    ε1ρ

    εc

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    49

    2

    CCH 21P

    [33]

    2B

    CCQ 21P

    [34]

    ΔtcΔx [35]

    2Q

    ΔxJR

    [36]

    AAA1 QQRBHC [37]

    BBB2 QQRBHC [38]

    gA

    cB

    [39]

    where:

    Hp- is the hydraulic head of internal point p

    Qp - The discharge of internal point p

    C - The elastic waves celerity

    g - The acceleration of gravity

    A - The section of the pipeline

    J- The hydraulic gradient and

    x,t- the space and time variables

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    50

    Figure 31: Nomenclature for the integrated equations

    Numerical procedure

    The numerical procedure for calculating the pressure propagation in a pipe line will be:

    1. The pipe line is made discrete and each part is Δx = cΔt. In order to fit in the border

    conditions, the total length of the pipe line must be n Δx where n is an integer

    2. Qp and Hp for all the internal points of the pipeline at time to is found

    3. Equation 33 and 34 are solved with respect to the P-points, i.e. the condition at time to+Δt is

    found

    4. When the condition at time to+Δt is known, the procedure is repeated in order to find the

    condition at to+2Δt etc

    Boundary Conditions

    At the ending points of the pipe line, there is only one characteristic equation, C+ or C-.

    Another equation is needed. This equation is the relation between the flow and head defined by the

    border condition. For instance a reservoir will keep a constant head and will give the following

    equation:

    RP ZH [40]

    Where:

    ZR- is the hydraulic head in the reservoir.

    If in the boundary there is a shutter (valve) the following equation:

    PPVRP QQCHH [41]

    Where:

    HR- is the hydraulic head of the other side of the shutter, CV - the flow coefficient that can be time-

    function. The signal + or – depends on the position of the valve and the pipeline.

    3.2. Hydraulic transient analysis: Preventing water hammer Water hammer is a type of hydraulic transient that refers to rapid changes of pressure in a pipe

    system that can have devastating consequences, such as collapsing pipes and ruptured valves. It is

    therefore important to understand the phenomena that contribute to transient formation and be able

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    51

    to accurately calculate and analyze changes as well as maximum and minimum pressures occurring

    in a pipe system for different conditions knowing that closure time for fast manoeuvre is less than

    2L/c and that of slow manoeuvre is greater than 2L/c as follows:

    Table 26: summary of data and trial times

    Data

    Q (m³/s) 7.483

    L (m) 486.47

    D (m) 1.65

    c (m/s) 981.8

    Zm (m) 103

    Zj (m) 100

    tf (s) 16

    i) Linear

    ii) Bi-linear

    Trial 1 2 3 4

    Time (s) L/c 3L/c 20L/c 50L/c

    Value 0.5 1.5 10 25

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    52

    iii) Upward parabolic

    iv) Down ward parabolic

    Figure 32: summary of different closure types and times

    Table 27: Maximum and minimum pressure of penstock for different closure types and times

    i) Linear

    Section 0 1 2 3 4 5 6 7 8 9 10

    L/c

    H Máx (m) 103 172,6 242 311,3 380,3 449 452,1 452,2 452,4 452,5 452,7

    H mín (m) 103 33,95 -35,03 -103,9 -172,4 -240,6 -243,6 -243,7 -243,9 -244 -244,2

    3L/c

    H Máx (m) 103 126,2 149,4 172,6 195,7 218,8 241,8 264,7 287,6 310,3 333

    H mín (m) 103 79,82 56,67 33,56 10,49 -9,635 -10,06 -10,42 -10,71 -10,94 -11,11

    20L/c

    H Máx (m) 103 106,4 109,7 113,1 116,4 119,7 123,1 126,4 129,7 133 136,3

    H mín (m) 103 100,3 100,2 100,1 99,93 99,8 99,66 99,51 99,35 99,19 99,02

    50L/c

    H Máx (m) 103 104,3 105,5 106,8 108 109,3 110,6 111,8 113,1 114,3 115,5

    H mín (m) 103 102,7 102,4 102,1 101,8 101,5 101,2 100,9 100,6 100,3 100

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    53

    ii) Bi-linear

    Section 0 1 2 3 4 5 6 7 8 9 10

    L/c

    H Max (m) 103 241.2 346.1 380.9 415.8 450.7 452.3 452.4 452.6 452.7 452.9

    H mín (m) 103 -34.3 -138.4 -173 -207.6 -242.1 -243.7 -243.9 -244 -244.2 -244.3

    3L/c

    H Max (m) 103 149.3 195.5 241.5 287.4 333.1 346.2 357.9 369.6 381.3 393

    H mín (m) 103 68.43 33.94 -0.422 -34.6 -68.54 -80.16 -91.8 -103.5 -115.1 -126.8

    20L/c

    H Max (m) 103 109.9 116.7 123.5 130.3 137.1 143.9 150.6 157.3 164 170.7

    H mín(m) 103 97.86 92.73 87.61 82.51 77.43 72.36 70.48 70.63 70.79 70.49

    50L/c

    H Max (m) 103 105.6 108.3 110.9 113.5 116.1 118.7 121.3 123.9 126.5 129

    H mín (m) 103 101 99.07 97.12 95.17 95.22 95.32 95.41 95.5 95.59 95.67

    iii) Upward parabolic

    Section 0 1 2 3 4 5 6 7 8 9 10

    L/c

    H Máx (m) 103 227.1 324.4 394.4 437 452.1 452.2 452.4 452.5 452.7 452.8

    H mín (m) 103 -20.16 -116.7 -186.3 -228.5 -243.5 -243.7 -243.8 -244 -244.1 -244.3

    3L/c

    H Máx (m) 103 147.2 188.5 226.9 262.3 294.8 324.3 350.8 374.3 394.7 412

    H mín (m) 103 72.52 42.15 11.9 -18.21 -48.15 -77.33 -103.7 -127.1 -147.4 -164.6

    20L/c

    H Máx (m) 103 109.6 116.1 122.6 129 135.4 141.7 148 154.2 160.4 166.5

    H mín (m) 103 99.68 96.38 93.09 89.81 86.55 83.31 80.08 76.87 73.68 70.5

    50L/c

    H Máx (m) 103 105.5 107.9 110.4 112.8 115.2 117.7 120.1 122.6 125 127.4

    H mín (m) 103 101.8 100.7 99.53 98.38 97.24 96.11 94.98 93.86 92.75 91.64

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    54

    iv) Downward parabolic

    Section 0 1 2 3 4 5 6 7 8 9 10

    L/c

    H Máx [m] 103 227 323.1 391.5 432.4 448.4 451.8 451.9 452.1 452.2 452.4

    H mín [m] 103 -20.07 -115.5 -183.5 -224 -239.8 -243.2 -243.3 -243.5 -243.6 -243.8

    3L/c

    H Máx [m] 103 133.9 164.8 195.6 226.3 256.9 285.9 311.8 334.5 354.2 370.8

    H mín [m] 103 72.28 41.57 10.88 -19.72 -50.23 -79.12 -104.9 -127.6 -147.1 -157.9

    20L/c

    H Máx [m] 103 106.5 109.9 113.4 116.9 120.3 123.8 127.2 130.7 134.1 137.5

    H mín [m] 103 99.53 96.07 92.61 89.15 85.7 82.25 78.8 75.36 71.93 69.65

    50L/c

    H Máx [m] 103 104.4 105.8 107.2 108.6 110 111.4 112.8 114.2 115.6 117

    H mín [m] 103 102.7 102.4 102.1 101.8 101.5 101.2 100.9 100.6 100.3 100

    i. Linear

    a) L/c

    b) 3L/c

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    55

    c) 20L/c

    d) 50L/c

    ii. Bi-linear

    a. L/c

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    56

    b. 3L/c

    c. 20L/c

    d. 50L/c

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    57

    iii. Upward parabolic

    a. L/c

    b. 3L/c

    c. 20L/c

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    58

    d. 50L/c

    iv. Down ward parabolic

    a. L/c

    b. 3L/c

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    59

    c. 20L/c

    d. 50L/c

    Figure 33: Hydraulic head in the shutter (valve) - time variation

    i. Linear

    a) L/c

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    60

    b) 3L/c

    c) 20L/c

    d) 50L/c

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    61

    ii. Bi-linear

    a. L/c

    b. 3L/c

    c. 20L/c

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    62

    d. 50L/c

    iii. Upward parabolic

    a. L/c

    b. 3L/c

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    63

    c. 20L/c

    d. 50L/c

    iv. Down ward parabolic

    a. L/c

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    64

    b. 3L/c

    c. 20L/c

    d. 50L/c

    Figure 34: Maximum and Minimum head envelope and pipe line profile

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    65

    3.3. Transient flow due to fast/ slow manoeuvre

    3.3.1 Fast manoeuvre: Causes and effects of water hammer

    Rapid pressure changes are a result of rapid changes in flow, which generally occur in a pipe system

    at valve opening or closing as shown in figure 33 (L/c). Because of the compressibility of water and

    the elasticity of pipes, pressure waves will then propagate in the pipe until they are attenuated at a

    velocity, which is dependent upon pipe material and wall thickness. The effects of the water hammer

    vary, ranging from slight changes in pressure and velocity to sufficiently high pressure or vacuum

    through to failure of fittings, burst pipes and turbine damage.

    Due to liquid inertia in the pipe sections downstream of the valve the pressure decreases, and vapour

    bubbles are formed near the valve. As a result of fast re-condensation of vapour bubbles, the liquid

    being transported is stopped rapidly at the closed valve. This pressure surge is referred to as

    cavitational hammer.

    While it is difficult to determine when the risk of water hammer exists and calculations are required,

    there are several factors that generally indicate when taking precautions against water hammer are

    advisable.

    Pipeline profile

    The minimum pressure line (red profiles in figure 34) depends upon various factors such as the wave

    speed. Therefore the minimum pressure line will retain the same shape regardless of the pipeline

    profile (pink profiles in figure 34) as long as no vaporization occurs. The magnitude of the sub

    pressure that the pipe will experience will therefore depend on the pipeline profile, i.e., the distance

    between the minimum pressure line and the pipeline profile (see figures 34 above).

    Pipeline length

    Pipe length will influence the reflection time and the inertia of water inside the pipe. The longer the

    pipe is, the longer the reflection time, that is, the time it takes for the wave to reflect at the outlet and

    return to the starting point. In addition, the longer the pipe the larger the mass of water that will

    affect the moment of inertia of the water column. Generally speaking, whenever the pipe length is

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    66

    greater than 300 m in length, the risk of sub pressures exists and water hammer calculations should

    be conducted.

    3.3.2 Slow manoeuvre: means for reducing the transient pressure, Prevention of Water Hammer

    and Cavitation

    A simple and often the best method to prevent water hammer are to close or open the valves slowly.

    The question whether a valve closes slowly enough can be easily calculated by the use of Excel. The

    minimum closing time depends on the pipe length and profile upstream the valve to the next point

    where pressure is fixed (i.e. minimum). Furthermore one has to take into account that there are

    different valve characteristics (figure 32) so that pressure increase due to closing process occurs at

    different times. In practice, 3 - 10 times the minimum closing time is needed to avoid high water

    hammer pressure peaks. Another possibility is to use air vessels, surge shafts or bladder

    accumulators, which are installed upstream the shut-off valve.

    3.4. Transient flow due to valve closure operations

    The results of closing the valve in different times shown in table 26 and figure 32 can be seen in

    Figure 33 and 35 for comparison. The maximum and minimum pressure varies from T = L/c to T =

    50L/c. The details of the maximum and minimum pressures of the valve closure operations for

    different types and times of closure are tabulated and are summarized in Table 28 below to show

    how the system responds to the different closure types and times.

    Table 28: Summary of shutter valve head variation for different closure types and times

    L/C Linear Bi-Linear Upward parabolic Downward parabolic

    Hmax[m] 452.7 452.9 452.8 452.4

    Hmin [m] -244.2 -244.3 -244.3 243.8

    3L/C Linear Bi-Linear Upward parabolic Downward parabolic

    Hmax[m] 333 393 412 370.8

    Hmin [m] -11.1 -126.8 -164.6 -157.9

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    67

    20L/C Linear Bi-Linear Upward parabolic Downward parabolic

    Hmax[m] 136.3 170.7 166.5 137.5

    Hmin [m] 99.02 70.49 70.5 69.65

    50L/C Linear Bi-Linear Upward parabolic Downward parabolic

    Hmax[m] 115.5 129 127.4 117

    Hmin [m] 100 98.67 91.64 100

    i. Linear

    ii. Bi-linear

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    68

    iii. Upward parabolic

    iv. Down ward parabolic

    Figure 35: Variation of Hydraulic head in the shutter with closure time

    Therefore, the closure type with higher positive minimum pressure from the higher penstock profile

    level and low maximum pressure for the chosen time of closure (which is Linear at T = 20L/C = 10

    sec) is selected from tables 28 above . The maximum pressure ( at Hmax =133 m) of the bend

    positioned at a distance of 473.52 m at this closure time from tables 27 is also used to calculate the

    occurring forces in section two of this report.

  • Preliminary design of hydraulic structures, hydraulic circuit and powerhouse of a hydroelectric scheme

    69

    3.5. Recommendations

    Slow-closing valves: as a solution for waterhammer

    To prevent the occurrence of high and low pressures, slow-closing valves gradually decrease the

    flow before the power to the turbine is shut off. It can be a time-consuming procedure, especially for

    long pipe systems, so for cases such as these, the use of valves with multi-stage motors is

    recommended. This enables the speed at which the valve is closed to occur at a slightly faster rate

    during the first stage of the valve closure and then at an extremely slow rate during the last stage of

    the valve closure.

    Advantages: these can be an economical alternative to other protection methods.

    Disadvantages: slow-closing valves are not suitable for the protection of the pipeline in the event of

    power failure.

    For a total pressurised circuit with pipes followin