M cKenney’s upgraded and enhanced cooling tower operation to improve system performance and lower energy costs at a nine-floor hotel in Charlotte, North Carolina. THE CHALLENGE The cooling tower had to be replaced with minimal disruption to the hotel and guests. The project required expert planning, precise coordination of the sub teams and continual communication with the hotel’s management to remain on schedule. THE SOLUTION To ensure a timely completion, the McKenney’s team created a logistics plan and execution strategy that ensured all materials and labor were on site as needed. They also worked with the hotel’s corporate controls team to pre-cool common areas prior to shut down, and then flushed large volumes of outdoor air in as needed to help keep temperatures at acceptable levels. In addition, a tower isolation redesign has eliminated future cooling disrup- tions by allowing one area to remain opera- tional while other areas are being serviced. THE RESULTS Increased cooling tower performance has reduced tower make up water and resulted in lower utility bills. On-going monitoring is projected to reveal further cost savings. Precise Coordination and Execution PROJECT NAME Urban Hotel Cooling Tower Replacement PROJECT LOCATION Charlotte, North Carolina PROJECT TEAM Owner: Global Hospitality Company Contractor: McKenney’s, Inc. SPECIALIZATIONS Design/Build Pipe Shop Prefab MARKETS Hospitality Central Plants The content of this document is not intended as an endorsement. www.mckenneys.com © 2014 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A. McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners. 404-622-5000 [email protected] 1056 Moreland Industrial Boulevard Atlanta, Georgia 30316 704-357-1200 [email protected] 3601 Performance Road Charlotte, North Carolina 28214

Upload: mckenneys-inc

Post on 18-Dec-2014

25 views

Category:

Business


1 download

DESCRIPTION

McKenney’s upgraded and enhanced cooling tower operation to improve system performance and lower energy costs at a nine-floor hotel in Charlotte, North Carolina.

TRANSCRIPT

Page 1: Precise Coordination and Execution - Cooling Tower Replacement

McKenney’s upgraded and enhanced cooling tower operation to improve system

performance and lower energy costs at a nine-floor hotel in Charlotte, North Carolina.

THE CHALLENGEThe cooling tower had to be replaced with minimal disruption to the hotel and guests. The project required expert planning, precise coordination of the sub teams and continual

communication with the hotel’s management to remain on schedule.

THE SOLUTIONTo ensure a timely completion, the McKenney’s team created a logistics plan and execution strategy that ensured all materials and labor were on site as needed. They also worked with the hotel’s corporate controls team to pre-cool common areas prior to shut down, and then flushed large volumes of outdoor air

in as needed to help keep temperatures at acceptable levels. In addition, a tower isolation redesign has eliminated future cooling disrup-tions by allowing one area to remain opera-tional while other areas are being serviced.

THE RESULTSIncreased cooling tower performance has reduced tower make up water and resulted in lower utility bills. On-going monitoring is projected to reveal further cost savings.

Precise Coordination and ExecutionPROJECT NAME

� Urban Hotel Cooling Tower Replacement

PROJECT LOCATION

� Charlotte, North Carolina

PROJECT TEAM

� Owner: Global Hospitality Company

� Contractor: McKenney’s, Inc.

SPECIALIZATIONS

Design/Build

Pipe Shop Prefab

MARKETS

� Hospitality

� Central Plants

The content of this document is not intended as an endorsement.

www.mckenneys.com© 2014 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A.

McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners.

404-622-5000 [email protected] 1056 Moreland Industrial Boulevard Atlanta, Georgia 30316

704-357-1200 [email protected]

3601 Performance Road Charlotte, North Carolina 28214