![Page 1: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/1.jpg)
OMV Downstream
Electronic Turnaround Optimization Platform –eTOP
Valencia, October 2018
![Page 2: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/2.jpg)
|
AustriaGermanyRomania
PlanningCoordination
Execution
Petro-chemical
Plants
OMV Turnaround ManagementManaging Complexity, Managing 3.000 People
OMV Downstream, Stefan Krebich & Rene Leitner, October 20182
Fuel Plants
Health, Safety &
Enviroment
![Page 3: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/3.jpg)
|
Turnaround Execution PhasePaper Based Wallpaper Coordination
OMV Downstream, Stefan Krebich & Rene Leitner, October 20183
![Page 4: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/4.jpg)
|
Downsides & ConsequencesScrutinize Paper Based Wallpaper
OMV Downstream, Stefan Krebich & Rene Leitner, October 20184
Paper BasedCoordination..
..tool ofchoice in
2018?
►lack reporting quality/mentality
►complex data screening & reporting
►reduntant progress tracking
►stationary info location
?
?
?
►lack of data quality
►realtime status accuracy
►resources coordination efficiency
►TAR goal attainment
![Page 5: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/5.jpg)
|
Impact of „Gamification“ Change a „No“ to a „Yes“
OMV Downstream, Stefan Krebich & Rene Leitner, October 20185
![Page 6: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/6.jpg)
|
Performance & Architecture
OMV Downstream, Stefan Krebich & Rene Leitner, October 20186
Process
Arc
hitectu
re
Data SourceOnline Realtime Data& Front End loading
Ad-hoc Reports, TAR process optim.
Qualified IT Resources
familiar with New
Technologies
(e.g. SAP process
integration, iOS App)
![Page 7: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/7.jpg)
| OMV Downstream, Stefan Krebich & Rene Leitner, October 20187
Infrastructure & Availability
RISK: Usage of Devices in Plants
Management of Change
Just allowed in Turnaround Plants
Sub-Equipment for Exp Measurements
Training
![Page 8: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/8.jpg)
| OMV Downstream, Stefan Krebich & Rene Leitner, October 20188
Infrastructure & Availability
RISK: Type of Mobile Hardware
Standard Device in Company
Lifecycle
Update & Security Policy
Availability of Hardware
User Interface with Stylus
![Page 9: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/9.jpg)
| OMV Downstream, Stefan Krebich & Rene Leitner, October 20189
Infrastructure & Availability
RISK: Availability of Network
Upgrade Infrastructure (fiber wire)
Data Cubes & LTE Antennas
Backup Scenarios (Paper, Digital Upload)
Spareparts
![Page 10: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/10.jpg)
| OMV Downstream, Stefan Krebich & Rene Leitner, October 201810
Plug for eTOPNetwork
Infrastructure
Smartphone
Student
![Page 11: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/11.jpg)
| OMV Downstream, Stefan Krebich & Rene Leitner, October 201811
Security
RISK: Theft of Hardware, unauthorized Access
Typing a password in field will not work
User & Identity Management
Smart log on/off at station
Electronic Locks on Container
Remote Lock/ Maintenance for (mobile) devices
![Page 12: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/12.jpg)
| OMV Downstream, Stefan Krebich & Rene Leitner, October 201812
Acceptance
RISK - People have no experience
Training on device
Provide devices well before Turnaround
Simplified User Interface
Support in the field
![Page 13: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/13.jpg)
| OMV Downstream, Stefan Krebich & Rene Leitner, October 201813
Acceptance
RISK – New Processes
Unit Management covered with SAP Standard Processes
QR Technology / no RFID
Risk Based Inspection Methods covered with SAP Standard Processes
Using GPS Data
![Page 14: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/14.jpg)
|
Statistics & Data Mining
OMV Downstream, Stefan Krebich & Rene Leitner, October 201814
38 Mio
10k
157k
227k1k
Server Calls (Activities)
Log-In (PC & Board)
Log-In (iOS)
Opened DocsInspections
![Page 15: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/15.jpg)
| OMV Downstream, Stefan Krebich & Rene Leitner, October 201815
![Page 16: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/16.jpg)
OMV Downstream
ContactOMV Downstream
Trabrennstrasse 6-8
1020 Vienna
www.omv.com
www.omv.com/socialmedia
Stefan Krebich
Rene Leitner
![Page 17: Electronic Turnaround Optimization Platform eTOP · eTOP Valencia, October 2018 | Austria Germany Romania Planning Coordination Execution Petro-chemical Plants OMV Turnaround Management](https://reader033.vdocuments.us/reader033/viewer/2022053117/60995adb48632e57ef5f9897/html5/thumbnails/17.jpg)
|
Legal Disclaimer
OMV Downstream, Stefan Krebich & Rene Leitner, October 201817
This presentation is prepared in order to outline our expression of interest. Nothing in this presentation shallbe construed to create any legally binding obligations on any of the parties. Neither party shall be obligated toexecute any agreement or otherwise enter into, complete or affect any transaction in relation to thispresentation.
All figures and information in this presentation are strictly confidential, they are by no means binding and thusindicative only.
© 2018 OMV Aktiengesellschaft, all rights reserved, no reproduction without our explicit consent.