TEPL/ENV/201718/TMC_01 1 PreFeasibility Report for “Inland Water Transportation for Passenger and RoRo Services in Vasai CreekUlhas River including Construction of 10 Terminals, consisting of RoRo Jetty, Shore Protection if required, Terminal Building, Parking Area, Utilities, Bunkering and Fuelling Centres, Banking and Recreational Facilities, Restaurants and Rest Areas including other Passenger Amenities” by Thane Municipal Corporation Prepared by

Upload: phunghanh

Post on 28-Mar-2018

214 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

1

 

Pre‐Feasibility Report  

 

for 

 

“Inland Water Transportation for Passenger and Ro‐Ro 

Services in Vasai Creek‐Ulhas River including 

Construction of 10 Terminals, consisting of Ro‐Ro Jetty, 

Shore Protection if required, Terminal Building, Parking 

Area, Utilities, Bunkering and Fuelling Centres, Banking 

and Recreational Facilities, Restaurants and Rest Areas 

including other Passenger Amenities”  

 

by 

Thane Municipal Corporation 

Prepared by 

Page 2: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

2

Table of Contents 

1.  Brief Summary ........................................................................................................................ 5 

2.  Introduction to the Project ..................................................................................................... 5 

2.1.  Project Proponent ............................................................................................................ 6 

2.2.  Brief Description of Project .............................................................................................. 6 

2.3.  Need of the Project .......................................................................................................... 7 

3.  Project Description ................................................................................................................. 9 

3.1.  Project Location .............................................................................................................. 10 

3.2.  Raw Materials ................................................................................................................. 12 

3.3.  Workforce ....................................................................................................................... 12 

3.4.  Water Requirements ...................................................................................................... 12 

3.5.  Wastewater Generation and Management ................................................................... 12 

3.6.  Solid Waste Generation and Management .................................................................... 12 

3.7.  Energy Requirements ..................................................................................................... 13 

4.  Site Analysis .......................................................................................................................... 13 

4.1.  Land Use and Land Cover ............................................................................................... 13 

4.2.  Climate ........................................................................................................................... 13 

4.3.  Temperature .................................................................................................................. 13 

4.4.  Wind and Humidity ........................................................................................................ 13 

4.5.  Rainfall ............................................................................................................................ 14 

4.6.  Social Infrastructure and Connectivity ........................................................................... 14 

4.7.  Eco‐Sensitive Zone and Critically Polluted Area ............................................................. 15 

4.8.  Site Specific Details ........................................................................................................ 18 

4.8.1.  Vasai Fort ................................................................................................................ 18 

4.8.2.  Jasal Park (Mira Bhayandar).................................................................................... 18 

4.8.3.  Ghodbunder ............................................................................................................ 19 

4.8.4.  Nagla Bunder ........................................................................................................... 20 

4.8.5.  Kolshet .................................................................................................................... 20 

Page 3: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

3

4.8.6.  Bhiwandi (Kalher) .................................................................................................... 21 

4.8.7.  Parsik Bunder .......................................................................................................... 22 

4.8.8.  Bhiwandi (Anjurdive) .............................................................................................. 22 

4.8.9.  Dombivli .................................................................................................................. 23 

4.8.10.  Kalyan .................................................................................................................. 24 

5.  Project Schedule and Cost Estimate ..................................................................................... 24 

5.1.  Capital Cost ..................................................................................................................... 25 

5.2.  Cost of Dredging ............................................................................................................. 26 

5.3.  Maintenance Cost .......................................................................................................... 26 

6.  Conclusion ............................................................................................................................. 26 

  

List of Tables 

Table 3.1: Geographical locations of the proposed sites ............................................................. 10 

Table 3.2: General Information ..................................................................................................... 11 

Table 3.3: Details of Municipal Waste .......................................................................................... 12 

Table 4.1: List of the Bridges and Structures ................................................................................ 15 

Table 4.2: Aerial Distance and Direction from ESZs and Critically Polluted Area ......................... 16 

Table 5.1: Onshore Cost ................................................................................................................ 25 

Table 5.2: Offshore Cost ............................................................................................................... 25 

 

List of Figures 

Figure 2.1: Map of Vasai Creek‐Ulhas River Route ......................................................................... 6 

Figure 3.1: Locations of the proposed sites .................................................................................. 11 

Figure 4.1: Map showing the Eco‐Sensitive Zones ....................................................................... 17 

Figure 4.2: Proposed Project Site at Vasai Fort ............................................................................ 18 

Figure 4.3: Proposed Project Site at Jasal Park (Mira Bhayandar) ............................................... 19 

Figure 4.4: Proposed Project Site at Ghodbunder ........................................................................ 19 

Figure 4.5: Proposed Project Site at Nagla Bunder....................................................................... 20 

Page 4: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

4

Figure 4.6: Proposed Project Site at Kolshet ................................................................................ 21 

Figure 4.7: Proposed Project Site at Bhiwandi (Kalher) ................................................................ 21 

Figure 4.8: Proposed Project Site at Parsik Bunder ...................................................................... 22 

Figure 4.9: Proposed Project Site at Bhiwandi (Anjurdive) .......................................................... 23 

Figure 4.10: Proposed Project Site at Dombivli ............................................................................ 23 

Figure 4.11: Proposed Project Site at Kalyan ................................................................................ 24 

 

Annexure 

Layout Plan of the proposed sites 

Page 5: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

5

1. BRIEF SUMMARY 

The Government  of Maharashtra  plans  to  develop water transport  in  the  Vasai  Creek‐Ulhas 

River connecting Vasai, Mira‐Bhayandar and Kalyan at the cost of Rs. 501 crore with an aim to 

ease congestion  in the Mumbai Metropolitan Region (MMR) and to reduce stress on the  land 

environment. Thane Municipal Corporation (TMC)  is the nodal agency for development of the 

inland  water  transportation  in  Vasai  Creek‐Ulhas  River  (National  Waterway  53)  including 

passengers’ Roll on‐Roll off (Ro‐Ro) services along with associated facilities and amenities. The 

proposed  jetties/terminals are  to be constructed  in 10  locations  in  the MMR. Three  types of 

terminals are proposed along  the Vasai Creek‐Ulhas River which  is 54  km  long.  Some of  the 

passenger  jetties  are  designed  to  handle  Ro‐Ro  vessels  which  carry  passengers  as  well  as 

vehicles. 

Average  travel  time  between  Vasai  and  Kalyan  including  boarding  and  alighting  will  be  70 

minutes. It is a socially beneficial project and would reduce environmental pollution, create job 

opportunities and save commuting time by shifting  load from the presently congested road to 

the waterways.  

The proposed constructions  involve  setting‐up of  the  terminal building, covered waiting area 

for  passengers,  parking  spaces,  sewage  treatment  plant,  central  administration  building, 

canteen  building/food  court/stalls,  electrical  sub‐station  &  switchyard,  service  buildings, 

driver’s  shelter house,  staff hostel, permanent  staff quarters,  security  cabins  and  compound 

wall. Three types of terminals (type I, type II and type III) are proposed in the Vasai Creek‐Ulhas 

River.  Ulhas  River  harbors  mangrove  habitat  in  some  segments.  Sites  for  construction  of 

terminals will be selected without disturbing mangrove vegetation. 

Sanjay  Gandhi  National  Park,  Thane  Creek  Wildlife  Sanctuary  and  Tungareshwar  Wildlife 

Sanctuary,  the  Eco‐Sensitive  Zones  declared  by MoEFCC,  are within  10  km  radius  from  the 

proposed project sites. Dombivli  industrial area  is one of the critically polluted areas declared 

by CPCB and this area also comes within 10 km radius from the proposed site at Dombivli and 

Kalyan. 

2. INTRODUCTION TO THE PROJECT 

Water transport is the cheapest and the most environmentally attractive mode of transport. It 

is encouraged by proactive governments for the transportation of men and material to cope up 

with  increasing  environmental  pollution.  Accordingly,  Inland  Waterways  Authority  of  India 

(IWAI) has taken the important decision of nationalizing 111 waterways all over India. 

Maharashtra coastline of 720 km with an extensive network of creeks, rivers, canals, and lakes 

has 2 major ports and 48 minor ports. Greater Mumbai, Thane, Palghar, Raigad, Ratnagiri and 

Sindhudurg are the 6 coastal districts in Maharashtra. Thane Municipal Corporation (TMC) has 

Page 6: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

6

taken  up  the  Vasai  Creek‐Ulhas  River  (National  Waterway  53)  for  development  of  the 

passengers  and  Ro‐Ro  Services.  The  waterway  once  developed  would  ensure  comfortable 

transit of personnel and bulk movement of  cargo  (in  future)  far  inland without affecting  the 

present road traffic. The map of the Vasai Creek–Ulhas River is illustrated in Figure 2.1. 

 

 

2.1. PROJECT PROPONENT 

Thane  city  in Maharashtra  is  situated  on  the  banks  of  the  Thane  creek  (Extension  of  Vasai 

creek). Since ancient times, Thane creek has not only given natural protection but also provided 

transportation  facilities  for  large  and  small  ships.  Thane  city  has  always  been  working  to 

promote local and international trade.  

Thane Municipal Corporation (TMC) was established on October 1, 1982. Since 1982 TMC has 

undertaken a number of projects and schemes for the development of the city, out of which, 

transportation  related projects have always been  in  the  forefront. With a  view  to  improving 

transportation  facilities  for  the  people,  TMC  in  association with  IWAI wishes  to  establish  10 

jetties/terminals along the Vasai Creek‐Ulhas River.  

2.2. BRIEF DESCRIPTION OF PROJECT 

The proposed project involves the construction of the following structures: 

i. Jetty terminal building (with embarking & disembarking facilities) 

ii. Covered waiting area for passengers 

iii. Central administration building 

iv. Canteen building/food court/stalls 

v. Electrical sub‐station & switchyard 

Figure 2.1: Map of Vasai Creek‐Ulhas River Route 

Page 7: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

7

vi. Service  buildings  (workshop,  fire  station,  telephone  exchange,  emergency  medical 

center, post office) 

vii. Driver’s shelter house 

viii. Staff hostel 

ix. Permanent staff quarters 

x. Security cabins 

xi. Compound wall  

xii. Sewage Treatment Plant 

The proposed  jetties  are  to be  constructed  at 10  locations  in Mumbai Metropolitan Region. 

Planned jetty facilities are presented below.  

Following  facilities  are  considered  for  Vasai  Fort,  Jasal  Park,  Ghodbunder,  Nagla  Bunder, 

Bhiwandi (Kalher), Parsik Bunder, Bhiwandi (Anjurdive), Dombivli and Kalyan: 

1. Area of Terminal Building  437.58 sq. m.

2. Parking Area  310 sq. m.

3. Area of approach bund  2880 sq. m.

4.Other  facilities  at  Terminal  Building  and  on  the 

approach bund  

Security Cabin = 8.75 sq. m. 

Septic Tank = 8.75 sq. m. 

For Kolshet: 

1. Area of Terminal Building  437.58 sq. m.

2. Parking Area  310 sq. m.

3. Area of approach bund  2880 sq. m.

4.  Other  facilities  at  Terminal  Building  and  on  the 

approach bund  

Water Tank = 32 sq. m. 

Septic Tank = 10.64 sq. m. 

Pump Room = 48.84 sq. m. 

Sub‐station = 89.49 sq. m. 

Collection Tank = 4.20 sq. m. 

Security Cabin = 25 sq. m. 

 

Additionally, Kolshet site will also have a Boat Repair Yard  for servicing of vessels, which will 

operate in Vasai Creek‐Ulhas River. 

2.3. NEED OF THE PROJECT 

In Maharashtra, there are 35 creeks and rivers which flow deep  into the  landmass hinterland. 

These creeks and rivers have a vast potential for vessel traffic movement and are largely under‐

utilized  thus  far, due  to  lack of  infrastructure  for  inland movement of passengers and cargo. 

Development of these creeks and rivers will help in diversion of a part of road and rail traffic to 

the waterways. This will  lead  to decongestion of  road and  rail  routes and will aid  in efficient 

Page 8: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

8

utilization  of  the  waterways  bestowed  by  the  nature  especially  near  the  busy  suburbs  of 

Mumbai, apart from reducing pollution.   

There are various creeks originating from the sea and stretching up to a length of 10 to 150 km 

into  the hinterland and merging  in  the various  rivers. Majority of  these creeks  lie  in  the hilly 

terrains  of  Konkan  region.  This  region  is water  affluent  and  the  creeks  have  good  draught 

available mostly throughout the year to support navigation of vessels. Hence, the creeks can act 

as an alternate route for movement of passengers and cargo to nearby destinations especially 

for  the  habitation  and  industries  located  along  the  river/creek  banks.  There  is  large‐scale 

industrialization and urbanization along  the  segments of  the Ulhas River, which may prompt 

number of organizations to opt for moving their cargo through the waterways. This is because 

the  roads  are  highly  congested  as  the  industries  fall  in  the  contiguity  of  densely  populated 

cities. The waterways will also provide an alternate mode of travel to the population staying in 

the cities  served by  the Ulhas River. Additionally,  the cargo  from  JNPT and Mumbai Ports,  in 

form of containers, project cargo and over dimensional cargo can also be conveniently diverted 

to  the  waterways  with  least  intrusions  in  road  transport.  Hence,  if  this  creek  is  properly 

developed, it shall unveil the underutilized potential of a cheap, efficient, low pollution mode of 

transport. 

The  Non‐Major  ports  have  a  large  number  of  passenger  jetties  where  about  18  million 

passengers  transit  annually  on  an  average.  Some  of  the  passenger  jetties  are  designed  to 

handle  Ro‐Ro  vessels  which  carry  passengers  as  well  as  vehicles.  The  Ro‐Ro  facilities  are 

operating in Rajpuri creek, Bankot creek (Savitri river), Dabhol creek (Vashishti river) and Jaigad 

creek  (Shashtri  river). All  the passenger  jetties  fall under  the  jurisdiction of  the Maharashtra 

Maritime Board (MMB). 

Additionally  there  is  existing  fair‐weather  ferry  service  for  passengers  from  the Gateway  of 

India  to Mandwa  Jetty. Even  JNPT has a  regular  ferry service  from  the Gateway of  India. The 

scope  of  these  services  could  be  enlarged  to  include  Passenger  ferry  service  where  the 

passenger cars and motorcycles could be handled along with the traveling passengers. This way 

the last mile connectivity need of the passengers could be reduced to a large extent.  

The full exploitation of the available waterways has not happened so far due to the following 

shortcomings: 

1. Regularity of service 

2. Last mile connectivity 

3. Waterway network 

4. Lack of infrastructure for handling cargo and passengers from same terminal 

Page 9: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

9

However,  with  better  understanding  and  awareness  for  harnessing  the  capability  of  the 

waterway and utilizing it for the common good of the people especially in an area like Mumbai 

would not be a very difficult task. 

3. PROJECT DESCRIPTION 

The  proposed  project of  Inland Water  Transport  in Vasai Creek  and Ulhas River will  require 

Environmental Clearance for Category ‘A’ from MoEFCC due to the presence of 3 Eco‐Sensitive 

Zones  (Sanjay Gandhi National  Park,  Tungareshwar Wildlife  Sanctuary,  Thane  Creek Wildlife 

Sanctuary)  and  CRZ  Clearance  from  the Maharashtra  Coastal  Zone Management  Authority 

(MCZMA).  

The length of the creek along the inland water transport route where the proposed jetties are 

to be constructed is 54 km. Three types of the terminal are proposed in the Vasai Creek‐Ulhas 

River. They are given below. 

i. Upgradation of the existing sloping Jetties and with minimum infrastructure for enabling 

operation  would  be  known  as  Type  I  terminal.  These  can  serve  the  immediate 

requirements as per availability of tide, however the same will need to be modified or 

reconstructed to account for all round operations at all stages of the tide.  

ii. The type II terminal would consist of  locations where Ro‐Ro service would be provided 

with better facilities and infrastructure  

iii. Type III terminals would have facilities to handle cargo (in future) along with passengers. 

a) Type– I Terminals 

These are minor  terminals envisaged  to cater  to  the  local passengers. These  terminals would 

offer minimum facilities for passengers to travel with or without light motor vehicles. This is up‐

gradation of the existing terminals and facilities with additions for the comfort and operations 

of the terminals. The facilities at the terminal would include the following. 

i. Sloping Jetty 

ii. Terminal Building for the ticketing and attendance services 

iii. Supervisors and ticket checking offices 

iv. Passenger waiting area 

v. Parks and ATMs  

vi. Connecting transport to the City  

vii. Lighting and signaling facility for night operations  

viii. Storage for life‐saving gear 

b) Type – II Terminals 

These are full‐fledged operational terminals with additional facilities for,  

Page 10: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

10

i. Direct roll on and roll off passenger vehicles 

ii. Small cargo carrying vehicles 

iii. Amusement parks 

iv. Kids Zone 

v. Restaurants and malls 

vi. Banks and ATMs 

vii. Integrated connectivity 

c) Type – III Terminals 

Type  III Terminals will be with  facilities to handle cargo  (in  future) along with passengers and 

will mainly cater for the following: 

i. Terminal Building for the ticketing and attendance services 

ii. Supervisors and ticket checking offices 

iii. Passenger waiting area 

iv. Parks and ATMs  

v. Lighting and signaling facility for night operations  

vi. Direct roll on and roll off passenger vehicles 

vii. Small cargo carrying vehicles 

viii. Amusement parks 

ix. Kids Zone 

x. Restaurants and malls 

xi. Integrated connectivity 

xii. Warehousing facility  

xiii. Parking for trucks, cargo vehicles 

xiv. Weighbridge 

Layout plans and cross sections of the sites are given in Annexure I.  

3.1. PROJECT LOCATION  

Geographical coordinates of the sites of the project are given in Table 3.1. 

Table 3.1: Geographical locations of the proposed sites 

Sr. No.  Jetty Sites Geographical Co‐ordinates 

Latitude   Longitude  

1  Vasai Fort  19° 19' 45.84'' N  72° 49' 10.2936'' E 

2  Jasal Park (Mira‐Bhayandar)  19° 19' 3.7884'' N  72° 51' 26.7408'' E 

3  Ghodbunder  19° 17' 36.1212'' N  72° 53' 30.9048'' E 

4  Nagla Bunder  19° 17' 40.506'' N  72° 56' 56.2128'' E 

5  Kolshet  19° 14' 42.2808'' N  72° 59' 52.6092'' E 

6  Bhiwandi (Kalher)  19° 14' 48.9552'' N  73° 0' 13.3164'' E 

Page 11: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

11

Sr. No.  Jetty Sites Geographical Co‐ordinates 

Latitude   Longitude  

7  Parsik Bunder  19° 12' 48.5568'' N  73° 0' 51.2604'' E 

8  Bhiwandi (Anjurdive)  19° 13' 14.07'' N  73° 0' 53.748'' E 

9  Dombivli (Thakurli Village)  19° 13' 37.9956'' N  73° 4' 4.6308'' E 

10  Kalyan  19° 14' 38.4576'' N  73° 7' 2.1972'' E 

These  coordinates may undergo  changes  as detailed  investigations  are  conducted. However, 

the final coordinates will be included in the EIA. The locations of the proposed jetties are shown 

in Figure 3.1. 

 

 

General information about the proposed project is given in Table 3.2. 

Table 3.2: General Information 

Sr. No.  Particulars Details 

1  Distance along the Route  25 Nautical Miles 

2  Average Travel Time  70 min (including boarding and alighting)

3  No. of Transport Hub  1 

4  Estimated Passenger Demand (Peak Hour) 13,500 

5  Estimation of Passengers to be Served 2880 

6  Carrying Capacity of the Boat 60  

7  Vessels Required  48 

Figure 3.1: Locations of the proposed sites 

Page 12: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

12

 

3.2. RAW MATERIALS 

Sand, brick,  rubbles,  stones of various  sizes, cement,  reinforcement,  soil,  structural  steel etc. 

will be used for construction purpose as per requirement.  

 

3.3. WORKFORCE 

About  30  persons  per  terminal would  be  deployed  for  construction  and  20  persons  for  the 

operation  of  each  terminal.  There  will  be  other  associated  activities  as  suggested  above 

including recreational facilities, fuel centers, eateries etc. 

3.4. WATER REQUIREMENTS 

During construction phase water would be brought  in tankers or by water barges. Total water 

requirement will be approximately 150  liters per day (LD) per site for 50 persons out of which 

60 LD will be used for the domestic purpose and 90 LD will be used for flushing. 

There would be a dedicated water supply scheme and would be managed without affecting the 

local supply.  

During  operation  phase water would  be  brought  through  local municipal  supply  and  tanker 

water, based on the need and the market dynamics.  In any case, the terminals are owned by 

the Municipal bodies. 

3.5. WASTEWATER GENERATION AND MANAGEMENT 

During  the  construction phase,  the wastewater  generation mainly  consists of  sanitary waste 

and sewage from workers. Mobile toilets will be provided in order to manage the wastewater. 

During operation phase, the entire wastewater (majorly sewage and sanitary waste) generated 

from the sites will be recycled and reused for non‐potable purposes.  

3.6. SOLID WASTE GENERATION AND MANAGEMENT 

Details of municipal waste (domestic and/or commercial wastes) for all terminals are given  in 

Table 3.3. 

Table 3.3: Details of Municipal Waste 

Construction Phase

Bio‐degradable   2700 kg/day

Non‐biodegradable  12000 kg/day

Total  14700 Kg/day             

Operation Phase

Page 13: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

13

Bio‐degradable   5600 kg/day

Non‐biodegradable  3000 kg/day

Total  8600 kg/day

 

During construction and operation phase, solid waste will be collected, segregated and handed 

over to the local body or authorized vendor for reuse and safe disposal.  

3.7. ENERGY REQUIREMENTS 

The energy requirements would be minimal. It is for the lighting, and terminal operations. Total 

requirements for the entire terminal together may not exceed 20 MW.  It will be taken from the 

State’s grid. The other fuel is for the ferries which would be partly by solar energy and partly by 

fossil fuels. The quantity would depend on the trips and demand shift of the local population. 

A standby generator (Diesel Generator) will be installed on the jetty providing sufficient power 

for basic lighting and operation of the linkspan and also as a backup in case of power failure. 

 

4. SITE ANALYSIS 

4.1. LAND USE AND LAND COVER 

This region has different  land use/land cover categories  like vegetation, mangroves, mudflats, 

saltpan, rocky outcrop area, sand and water bodies. Mangroves are one of the most valuable 

coastal resources in this region. Urban built‐up areas cover the majority of the coastal plains. 

4.2. CLIMATE  

The climate of the project region is subtropical and characterized by high humidity throughout 

the  year,  an  oppressive  summer  followed  by well  distributed  and  heavy  rainfall  during  the 

southwest monsoon season. The mean daily maximum temperature  is 32.9°C and mean daily 

minimum temperature at 26.8°C. The place experiences the onset of the monsoon in the month 

of June to September with an average rainfall of 1500 mm to 2000 mm. 

4.3. TEMPERATURE 

In  January during  the winter season,  the mean variation  in  temperature  is about 20.0°C. The 

northern  portions  of  the  basin  experience  lower  temperatures  than  the  southern.  April  is 

generally the hottest month of the summer and January  is the coldest month. The mean max 

temperature over the region varies from 15.69°C to 30°C.  In the monsoon and post‐monsoon 

seasons, mean temperatures are moderate in the range of 22°C to 27.5°C.  

4.4. WIND AND HUMIDITY 

Page 14: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

14

The  average  relative  humidity  varies  from  67%  to  86%  in  this  region.  An  increase  in  the 

humidity levels by nearly 2% especially during the day whereas 3% decrease in the evening with 

the variations remaining more or  less the consistent with no specific trend  identified over the 

years. However,  it was observed,  that  the wind  speed  showed a  sudden and  sharp decrease 

from 12 km/hr to 6.5 km/hr in four decades. 

4.5. RAINFALL  

The creek sites come under the direct  influence of the southwest monsoon and receive heavy 

and assured rainfall between June and August. The southwest monsoon rainfall  is usually very 

heavy with 90% of the rainfall occurring from June to November. 

The highest annual rainfall recorded in the Vasai Creek region in the year 1993 was 2444.42 mm 

whereas minimum annual rainfall was recorded as 1364.51 mm in the year 1972. 

The  communities have experienced  an  increased  rainfall  along with  a prominent delay  in  its 

onset. 

4.6. SOCIAL INFRASTRUCTURE AND CONNECTIVITY 

Panju  Island  is a village  located  in the middle of the creek at a distance of nearly 500 meters 

from  the mainland on  the  right bank. A  large part of  the  area of  the  village  is  swampy  and 

mostly covered with mangroves. More than 1,300 people, the majority of whom are fishermen, 

live on the island. Their residences are mostly confined to the dry patches of the island.  

Densely populated Mira‐Bhayandar Municipal Corporation  is  located on  the  left bank of  the 

creek. The area has the required infrastructure with low‐level industrialization. Sopara creek, a 

small water flow from Pelhar lake area meets the Vasai creek near the railway track. Gaimukh 

gaon is a village located near the state highway SH 48 on the left bank of the creek.  

Bharati Defence and  Infrastructure Limited shipyard are  located  just downstream of the state 

highway bridge  (spread over 12 acres of  land) across the creek near Ghodbunder village.  It  is 

equipped with four slipways for building ships up to 125 m length.

Reti Bunder is just beside the shipyard towards Vasai end. The banks of the creek from Bharati 

Shipyard  to Bhayandar pada near Gaimukh gaon  is  covered with mangroves. Construction of 

residential and industrial complexes is in full flow in the area.   

The  proposed  jetty  at Dombivli  is  2  km  from Dombivli  Railway  Station  and  1  km  from  Reti 

Bunder bus stop. 

NH  222  is  very  near  to  the  proposed  location  at  Kalyan.  Kala  Talao  and  Kalyan  Dombivli 

Municipal Corporation  (KDMC) Bhoiwada  Lake are within 1.5  km  from  the proposed  jetty  at 

Kalyan. 

Page 15: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

15

Bridges  and  other  cross  structures:  List  of  the  bridges  and  structures  that  would  be 

encountered as one move from Vasai entrance to Kalyan along the creek is given in Table 4.1. 

Table 4.1: List of the Bridges and Structures 

Sr. No.  Name/Type of Construction  Sr. No. Name/Type of Construction 

1  Old Railway Bridge (Panju  Island)  11  Pipeline near old Agra road Bridge 

2  New  Railway  Bridge‐1  (Mira Bhayandar) 

12  Bhiwandi Road Bridge 

3  New  Railway  Bridge‐2(Mira Bhayandar) 

13  Parsik‐Reti Bunder Road 

4  Power  Transmission  line  (Ranuja Ramdev Park) 

14  Power  Transmission  line  near  water Pipeline bridge 

5  Ghodbunder Old Road Bridge  15  Ganesh Ghat Water Pipeline 

6  Ghodbunder New Road Bridge  16  Power  Transmission  line  near  Reti bunder 

7  Power  transmission  lines  near Ghodbunder Road Bridge 

17  Vasai Diva Railway Line 

8  Power transmission lines near Bangla Pada 

18  Old Road Bridge 

9  Old Agra Road Bridge  19  New Road Bridge 

10  Pipe Line cum Road Bridge     

 

4.7. ECO‐SENSITIVE ZONE AND CRITICALLY POLLUTED AREA 

Sanjay  Gandhi  National  Park,  Thane  Creek  Wildlife  Sanctuary  and  Tungareshwar  Wildlife 

Sanctuary are within 10 km radius from the proposed sites for construction of jetties. 

Eco‐Sensitive  Zones (ESZs)  are  areas  notified  by  the Ministry  of  Environment,  Forests  and 

Climate  Change (MoEFCC), Government  of  India  around Protected  Areas, National 

Parks and Wildlife Sanctuaries. The purpose of declaring ESZs  is to create some kind of “shock 

absorbers” to the protected areas by regulating and managing the activities around such areas. 

They  also  act  as  a  transition  zone  from  areas  of  high  protection  to  areas  involving  lesser 

protection. 

The  Central  Pollution  Control  Board  (CPCB)  has  developed  a  Comprehensive  Environmental 

Pollution  Index  (CEPI). CPCB has done  a nation‐wide  environmental  assessment of  Industrial 

Clusters based on CEPI and 43 such industrial clusters having CEPI greater than 70, on a scale of 

0 to 100, has been identified as critically polluted. 

The  data  refers  to  the  Comprehensive  Environmental  Pollution  Index  (CEPI)  scores  of  the 

critically polluted  industrial  clusters/areas. The  index  captures  the  various dimensions of  the 

environment including air, water and land. 

Page 16: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

16

Dombivli  industrial area  is one of  the critically polluted areas declared by CPCB and  this area 

comes within 10 km radius from the proposed site at Dombivli. 

Distances of the proposed sites from these Eco‐Sensitive Zones and Critically Polluted Area are 

given in Table 4.2. and the map is given in Figure 4.1. 

Table 4.2: Aerial Distance and Direction from ESZs and Critically Polluted Area 

Sr. No. 

Site Name Sanjay Gandhi National Park 

Thane Creek WLS 

Tungareshwar WLS 

Dombivli Critically 

Polluted Area 

1  Vasai Jetty  ‐  ‐  ‐  ‐ 

2 Jasal  Park  (Mira Bhayandar) 

4.7 Km (SE)  ‐  ‐  ‐ 

3  Ghodbunder  200 m (S)  ‐  ‐  ‐ 

4  Nagla Bunder  1.2 Km (SW)  ‐  2.4 Km (N) 

5  Kolshet  2.4 Km (W)  ‐  ‐  ‐ 

6  Bhiwandi (Kalher)  3 Km (W)  ‐  ‐  ‐ 

7 Bhiwandi (Anjurdive) 

4.6 Km (NW) 2.8 Km (SW) 

‐  ‐ 

8  Parsik Bunder  ‐  2.5 Km (W)  ‐  ‐ 

9 Dombivli  (Thakurli Village) 

‐  ‐  ‐  2.8 Km (SE) 

10  Kalyan  ‐  ‐  ‐  2.5 Km (S) 

 

Page 17: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

 

Figure 4.1: Map showing the Eco‐Sensitive Zones 

Page 18: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

18

4.8. SITE‐SPECIFIC DETAILS 

4.8.1. VASAI FORT 

Approximately 12‐15 m wide area on both sides of the jetty in the inter‐tidal zone can be used 

with  the  approvals  from  the  Maharashtra  Maritime  Board  (MMB)  and  the  Archaeological 

Survey of India (ASI), for terminal building and other facilities. Some mangroves could be seen 

on  both  sides  of MMB  jetty. The  nearest  road  from  the  proposed  jetty  is  Killa  Road.  The 

proposed project site is illustrated in Figure 4.2. 

4.8.2. JASAL PARK (MIRA BHAYANDAR) 

The proposed jetty  is  located near Jasal Park, east of the railway bridge on south bank (Figure 

4.3). Currently, boats are available  for a  local cruise which operate based on  the  time on  the 

tidal  prism.  There  is  a  public  park  beside  the  proposed  terminal  and  likely  to  serve  the 

passenger amenities well. Though 2‐3  road approaches are available,  they are mostly narrow 

and often congested. One new  road  is under construction and  is  likely  to be better  than  the 

existing roads. 

Figure 4.2: Proposed Project Site at Vasai Fort

Page 19: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

19

 

 

4.8.3. GHODBUNDER 

Reclaimed  land of about 2‐acre  is available at Reti Bunder near Ghodbunder village, which  is 

just right for the development of a passenger terminal or Ro‐Ro terminal. Adequate depths are 

available near the site. This proposed location is well connected with Ghodbunder road, Thane 

and adjacent to NH 8 also called Western Express highway. There are open land parcels are also 

available near the proposed location. The proposed project site is illustrated in Figure 4.4. 

 

 

Figure 4.3: Proposed Project Site at Jasal Park (Mira Bhayandar) 

Figure 4.4: Proposed Project Site at Ghodbunder 

Page 20: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

20

4.8.4. NAGLA BUNDER 

The  proposed  jetty  is  located  about  1.5  km  from  Ghodbunder  Road  Highway,  NH  42.  This 

proposed jetty has the advantage of location, as passengers from Bhiwandi and Thane both can 

use  the  ferry  service.  The  closeness  from  NH  42  will  make  the  connectivity  smooth.  The 

proposed project site is illustrated in Figure 4.5. 

4.8.5. KOLSHET 

There is no infrastructure at Kolshet and so jetties could be developed for better services. This 

jetty could be used for Ro‐Ro ferries as well. Kolshet  is slowly developing as a residential area 

and  in  near  future,  the  population  of  the  area would  likely  to  be  increased.  The  proposed 

project site is illustrated in Figure 4.6. 

 

Figure 4.5: Proposed Project Site at Nagla Bunder

Page 21: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

21

 

 

4.8.6. BHIWANDI (KALHER) 

There  is no  infrastructure  at Bhiwandi  (Kalher)  and  so  jetties  could be developed  for better 

services  (Figure 4.7). This  jetty could be used  for Ro‐Ro  ferries as well. The connectivity  from 

nearest  Bhiwandi  Road  is  an  advantage  for  this  jetty  as  no  additional  investment would  be 

required and road connectivity would make transportation easier and faster.  

 

 

 

Figure 4.6: Proposed Project Site at Kolshet 

Figure 4.7: Proposed Project Site at Bhiwandi (Kalher) 

Page 22: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

22

4.8.7. PARSIK BUNDER 

About 2 acre of Government  land  is available and  it  is partially reclaimed. The current of  the 

creek water in this area appears to be strong. After leveling, the area would be suitable for the 

development of jetty. This site is suitable for terminal building as well as a jetty. The proposed 

project site is shown in Figure 4.8. 

 

 

 

4.8.8. BHIWANDI (ANJURDIVE) 

The current of the creek water in this area appears to be strong. The available land is close to 

the bridge  and  the  approach  from  the  site  to  the main  road needs  to be  constructed.    The 

proposed project site is illustrated in Figure 4.9. 

 

Figure 4.8: Proposed Project Site at Parsik Bunder 

Page 23: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

23

 

 

4.8.9. DOMBIVLI 

The proposed site is in Thakurli village on the bank of the Vasai Creek/Ulhas River (Figure 4.10). 

A small piece of land is available next to the jetty, which may be just enough for the passenger 

amenities, required for such facilities. Local boats operate from here for extraction of sand.  

 

 

 

 

Figure 4.10: Proposed Project Site at Dombivli 

Figure 4.9: Proposed Project Site at Bhiwandi (Anjurdive) 

Page 24: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

24

4.8.10. KALYAN 

The proposed terminal  is  located on the  left bank of the River Ulhas, downstream of the road 

bridge at the Reti Bunder. This area comes under Kalyan Dombivli Municipal Corporation. One 

shipyard near  the Ganesh Ghat exists on  the north side of  the bridge. The site  is suitable  for 

developing a Passenger as well as the Cargo terminal. The proposed project site is illustrated in 

Figure 4.11. 

 

 

 

5. PROJECT SCHEDULE AND COST ESTIMATE 

Sr. No. 

Site Name  Construction Phase 

1  Vasai Jetty 

~12 months 

2  Jasal Park (Mira Bhayandar) 

3  Ghodbunder 

4  Nagla Bunder 

5  Kolshet 

6  Bhiwandi (Kalher) 

7  Bhiwandi (Anjurdive) 

8  Parsik Bunder 

9  Dombivli (Thakurli Village) 

10  Kalyan 

Proposed project activity will start after getting the approval for Environmental Clearance & CRZ clearance from MoEF&CC. 

Figure 4.11: Proposed Project Site at Kalyan 

Page 25: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

25

5.1. CAPITAL COST 

The estimated Capital Cost (Onshore and Offshore) for infrastructural development are given in 

Table 5.1 and Error! Reference source not found..  

Table 5.1: Onshore Cost 

Onshore Cost 

Sr. No. 

Proposed Location 

Area of Terminal 

Building (sq. m.) 

Area of Terminal (sq. m.) 

Cost of Terminal 

Building (Rs.)

Cost of Terminal (Rs.) 

Total Cost (Rs.) 

1  Vasai Fort  437.58  2880  17962252.51  50889350.6  68851603.11 

2 Jasal  Park (Mira Bhayandar) 

437.58  2880  17962252.51  50889350.6  68851603.11 

3  Ghodbunder  437.58  2880  17962252.51  50889350.6  68851603.11 

4 Nagla Bunder 

437.58  2880  17962252.51  50889350.6  68851603.11 

5  Kolshet  761.566  20900  28594034.8  313500000  342094034.8 

6 Bhiwandi (Kalher) 

437.58  2880  17962252.51  50889350.6  68851603.11 

7 Parsik Bunder 

437.58  2880  17962252.51  50889350.6  68851603.11 

8 Bhiwandi (Anjurdive) 

437.58  2880  17962252.51  50889350.6  68851603.11 

9 Dombivli (Thakurli Village) 

437.58  2880  17962252.51  50889350.6  68851603.11 

10  Kalyan  437.58  2880  17962252.51  50889350.6  68851603.11 

Total Cost  961758462.8 

 

Table 5.2: Offshore Cost  

Offshore Cost  

Sr. No.  Proposed Location  Area of Jetty (sq. m.)  Total Cost (Rs.)  

1  Vasai Fort  3177.5  312123000 

2 Jasal  Park  (Mira Bhayandar) 

2710.42  288769000 

3  Ghodbunder  2441.63  275329500 

4  Nagla Bunder  2710.42  288769000 

5  Kolshet  5006  403548000 

Page 26: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

26

Offshore Cost  

Sr. No.  Proposed Location  Area of Jetty (sq. m.)  Total Cost (Rs.)  

6  Bhiwandi (Kalher)  3021.43  403548000 

7  Parsik Bunder  4431.14  366797000 

8  Bhiwandi (Anjurdive)  3021.43  403548000 

9 Dombivli  (Thakurli Village) 

3021.43  304319500 

10  Kalyan  3021.43  304319500 

Total Cost  3351070500 

  

5.2. COST OF DREDGING 

An estimated quantity of total dredging is 1962194 cubic meters (approximately 2 million cubic 

meters), out of which 1895806.5  cubic meters of  soft dredging and 66387.5  cubic meters of 

hard dredging off‐lying rocks is anticipated. At an average cost of about Rs. 290/cubic meter for 

soft dredging and Rs. 2000/cubic meter  for hard dredging  is anticipated  to cost about Rs. 69 

Crore. 

Total project cost will be Rs. 500.28 Crore (approximately Rs. 501 Crore). 

5.3. MAINTENANCE COST 

As  a  guiding  principle  about  5%  cost  of  the  infrastructure  is  considered  for  maintenance 

purposes every 3 years. However, as  the  terminals would be  in  regular use  for  Inland Water 

Transport (IWT) operations, about 1.5% cost of the infrastructure should spend as maintenance 

cost per year. 

 

6. CONCLUSION 

TMC and IWAI have planned to develop inland water transportation along the route from Vasai 

to Kalyan (National Waterway 53) in Vasai Creek‐Ulhas River in order to have a cheap, efficient, 

pollution free mode of transport. Some of the passenger  jetties are designed to handle Ro‐Ro 

vessels  which  carry  passengers  as  well  as  vehicles.  During  construction  of  terminals,  no 

mangrove vegetation will be disturbed. 

Page 27: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

27

 

 

  

AnnexureI

Page 28: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

Figure 1: Site Layout of Vasai  

Page 29: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

 

Figure 2: Site Layout of Vasai  

Page 30: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

Figure 3: Layout Plan of Mira Bhayandar  

Page 31: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

Figure 4: Layout Plan of Mira Bhayandar  

Page 32: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

 

Figure 5: Layout Plan of Ghodbunder 

Page 33: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

Figure 6: Layout Plan of Ghodbunder  

Page 34: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

Figure 7: Layout Plan of Kolshet 

Page 35: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

Figure 8: Layout Plan of Kolshet  

Page 36: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

Figure 9: Layout Plan of Kolshet  

Page 37: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

Figure 10: Ground Floor Plan of Main Terminal Building at Kolshet  

Page 38: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

Figure 11: Layout Plan of Kolshet  

Page 39: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

Figure 12: Layout Plan of Nagla Bunder  

Page 40: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

Figure 13: Layout Plan of Nagla Bunder  

Page 41: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/16_Jan_2018...Project Proponent ... Average travel time between Vasai and Kalyan

 

 

  TEPL/ENV/2017‐18/TMC_01 

 

 

Figure 14: Layout Plan of Bhiwandi (Anjurdive), Bhiwandi (Kalher), Dombivli and Kalyan