pre feasibility report (pfr) - welcome to … feasibility report (pfr) for ... kv substation in the...
TRANSCRIPT
PRE FEASIBILITY REPORT (PFR)
For
PRIOR ENVIRONMENTAL CLEARANCE
Environmental Impact Assessment for
Proposed Expansion of High Rubber Graft-
HRG (Rubber rich ABS) at Satnoor Plant,
Dist. Chindwara (MP)
Project Proponent:
M/s. Bhansali Engineering Polymers Ltd.
Environmental Consultant
QCI-NABET Accredited EIA Consultant for Synthetic Organic Industries (Sector 21), MoEF&CC (GOI) and NABL Recognized Laboratory
ISO 9001:2008, ISO 14001:2004, OHSAS 18001:2007 60, Bajiprabhu Nagar, Nagpur - 440 033, MS
Lab. & Consultancy: FP-34, 35, Food Park, MIDC, Butibori, Nagpur – 441122 Ph.: (0712) 2242077, 9373287475
Email: [email protected], [email protected] website: www.anaconlaboratories.com
Report No. ANqr /PD/20A/2017/101
July 2017
Pre-Feasibility Report
Page 2 of 42 Anacon Laboratories Pvt. Ltd.
Contents 1.0 EXECUTIVE SUMMARY ................................................................................................................................ 3
2.0 INTRODUCTION ........................................................................................................................................... 5
3.0 PROJECT DESCRIPTIONS .............................................................................................................................. 7
4.0 SITE ANALYSIS ........................................................................................................................................... 16
5.0 PLANNING BRIEF ....................................................................................................................................... 18
6.0 PROPOSED INFRASTRUCTURE .................................................................................................................. 19
7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN ................................................................................. 20
8.0 PROJECT SCHEDULE & COST ESTIMATES .................................................................................................. 22
9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) ........................................................................... 22
Annexure I- Google Map ....................................................................................................................................... 23
Annexure II-Land Document ................................................................................................................................. 23
Annexure III-Factory Licenses ............................................................................................................................... 32
Annexure IV-CHW-TSDF Membership .................................................................................................................. 33
Annexure V-Consent to Operate .......................................................................................................................... 34
Annexure –VI – Water Balance ............................................................................................................................. 41
Pre-Feasibility Report
Page 3 of 42 Anacon Laboratories Pvt. Ltd.
1.0 EXECUTIVE SUMMARY 1.1 Project Proponent: : M/s. Bhansali Engineering Polymers Ltd.
1.2 Location : M/s. Bhansali Engineering Polymers Ltd. (BEPL),
Bhansali Nagar, Near Satnoor Village,
Taluka – Sausar, District – Chhindwara,
Madhya Pradesh - 480108
Latitude: 21°30'48.0"N
Longitude: 78°50'33.2"E
(Figures 1 & 2)
1.3 Office (Regd.) : M/s. Bhansali Engineering Polymers Ltd.,
Unit No. 401, 4th Floor, Peninsula Heights,
C.D. Barfiwala Road, Andheri (West),
Mumbai, Maharashtra, India - 400058
Email: [email protected]
Phone: +22-26731779-84 Fax: +22-26731796
1.4 Name of
Promoter/Director
: Mr. B. M. Bhansali,
Promoter & Managing Director
1.5 Proposed Project :
Sr. Name of
product
Existing
Capacity
Proposed
Capacity
addition
Total capacity after
expansion
1. High Rubber
Graft -HRG
(Rubber rich
ABS)
15000
TPA HRG
35,000
TPA HRG
50,000 TPA HRG
1.6 Total Project Area : 35.775 Ha (Plant area 15.775 ha & Greenbelt 20 ha)
1.7 Water Requirement : Total Water Requirement – Existing 592 KLD, Proposed 1360 KLD
Total 1952 KLD after expansion. Final fresh water requirement
after recycling & reuse will be 1516 KLD.
1.8 Power Requirement : Presently, Electricity is sourced from Madhya Pradesh Poorva
Kshetra Vidyut Vitaran Co. by 33 KV dedicated supply line with 33
KV substation in the plant premises with 2 MVA ( 33 KV/440 V)
transformer. The contract demand is 1300 KVA. After the proposed
expansion, estimated contract demand will be 4000 KVA. It is
planned to install one more 2 MVA transformer in the sub-station to
meet the enhanced demand.
Since the process is continuous, it is necessary to ensure
uninterrupted power supply. Presently, 2 x 500 KVA + 1 x 1250
KVA DG sets are provided as emergency power supply which is
automatically switched on in case of power failure. It is planned to
install 4 x 1250 KVA DG sets to meet the enhanced demand. DG
will be in stand by mode.
Note - Present Grid supply is at 33 KV which is capable of catering to 5 MVA load which is adequate to meet increased demand
Pre-Feasibility Report
Page 4 of 42 Anacon Laboratories Pvt. Ltd.
1.9 Number of Shift : Three Shift Basis ( Round the clock)
1.10 No. of Working Days : 365 Days
1.11 Total Cost of Project : 13270 Lacs
1.12 Man Power Utilization : Existing 187 persons Proposed 90
1.13 Means of Finance
: Entire funding for the project will be through internal accruals.
1.14 Schedule of
Implementation
: Particulars Implementation Date/Time
Period
Commercial Production
will be started
After 12 months from Receipt of
Environmental Clearance
1.15 Environment Consulting
Organization
: Anacon Laboratories Pvt. Ltd.
HO: 60, Bajiprabhu Nagar, Nagpur - 440 033, MS. Ph.: (0712) 2242077 Lab. & Consultancy: FP-34, 35, Food Park, MIDC, Butibori, Nagpur – 441122 Mob.(CONSULTANCY): +91-9372960077
Email: [email protected] website: www.anaconlaboratories.com
Pre-Feasibility Report
Page 5 of 42 Anacon Laboratories Pvt. Ltd.
2.0 INTRODUCTION 2.1 Identification of project and project proponent
Company Background
M/s. Bhansali Engineering Polymers Limited (BEPL) was incorporated in the year 1986. The
company was promoted by Shri B. M. Bhansali, a first generation entrepreneur. BEPL was the first
company in India to start manufacturing Quality Acrylonitrile Butadiene Styrene (ABS) resins using
foreign technology. The plant at Satnoor has been setup in technical collaboration with Sumitomo
Chemical Engineering Co. Limited / Sumitomo Nagautuck Limited, Japan. With an expected turnover
of 1000 Crores by 2017 and current workforce of 450 dedicated employees (BEPL has two plants in
India - Satnoor plant, Madhya Pradesh and Abu road Rajasthan), BEPL has a vision to progress
positively towards consolidating its leadership position in the domestic market.
2.2 Brief Description and Nature of the Project
ABS is a ter-polymer manufactured by compounding (blending) High Rubber Graft resin-HRG
(Rubber rich ABS) with Styrene, Acrylonitrile resin (SAN). While HRG can be manufactured through
Emulsion Polymerisation route only, SAN can be manufactured through Emulsion polymerisation or
Bulk polymerisation or Suspension polymerisation routes. However, the cheapest route is to
manufacture SAN through Bulk polymerisation route.
After opening of the Indian economy in 1990 onwards, the ABS market was getting dominated by
cheaper imports. Therefore, it was deemed expedient to modify the technology and bring the
manufacturing cost down at competitive level with imports. Hence, the technology of manufacturing
ABS was revamped to manufacture High rubber graft (HRG) with polybutadiene rubber content from
57 to 60 % through Emulsion polymerisation route. And subsequently dilute HRG with SAN
manufactured through bulk polymerisation route. Thereafter compound (blend) HRG and SAN to
bring high rubber concentration/content down to 15 to 25 % to manufacture various saleable grades
of ABS at import price parity level, conforming to the performance requirement by customers in
automotive, consumer durables and telecommunication products etc.
The entire HRG manufactured at BEPL Satnoor plant is being dispatched/delivered to BEPL Abu
road plant. The activities pertaining to manufacture of SAN and compounding with HRG are being
carried out at Abu road unit of BEPL which was acquired in the year 2003 from Greaves Limited.
EXISTING AND PROPOSED EXPANSION PRODUCTION DETAILS
2.3 Need for the project and its importance to the country and/or region
BEPL is manufacturing ABS Polymers since 1990, Requirement of the ABS is increased in India
owing to the growth in the Indian middle class expenditure in home appliances and automobiles,
which is driving the core demand for ABS. ABS have been witnessing healthy growth due to its wide
ranging usage in consumer electronics, appliances and automotive sectors. In current market
scenario, almost all the Refrigerator manufacturers have shifted to ABS from HIPS for refrigerator
Liners, hence the demand for ABS will continue to remain vibrant witnessing phenomenal jump
therein.
Sr.
No
Name of product Existing Capacity Proposed
Capacity addition
Total capacity
after expansion
2. High Rubber Graft -HRG
(Rubber rich ABS)
15000 TPA HRG 35,000 TPA HRG 50,000 TPA HRG
Pre-Feasibility Report
Page 6 of 42 Anacon Laboratories Pvt. Ltd.
As of now in India there only two manufacturers of the ABS polymers and BEPL has share of approx.
70000 TPA in the Indian market and there is import of ABS of approximately 150000 TPA. Today’s
India’s total market demand is 3,00,000 TPA. Hence, BEPL deems it expedient to quickly expand the
capacity to conserve outflow of foreign exchange.
2.4 Demand-Supply Gap
There are only two manufacturing companies in India which produce ABS and are not able to cater to the whole demand of ABS in India, so the deficit in supply is fulfilled through imports.
The demand for ABS in India is largely dependent on two sectors namely Appliance and Automobile which account for nearly 85% of consumption. The Appliance sector contributes to nearly 45% of demand while Automobile accounts for 40% of demand. Hence the demand variance in the above sector directly influence the consumption of ABS.
There is a huge opportunity for company to exploit the growing market and to substitute import of ABS.
2.5 Imports vs. Indigenous production
The typical nature of ABS business in India is exposed to the risk of Foreign exchange fluctuations as
the key raw materials i.e. Styrene monomer & Acrylonitrile monomer are import dependent, as there
is no indigenous producer for the same. The only raw material which is indigenously available is
Butadiene monomer which contributes only 16% to 17% out of the total raw material composition.
2.6 Export possibility
HRG powder manufactured at Satnoor plant is sent to BEPL’s Abu Road unit for production of ABS.
2.7 Domestic/ Export Markets
As of now in India there only two manufacturers of the ABS polymers and BEPL has share of approx. 70000 TPA in the Indian market and there is import of ABS of approximately 150000 TPA. Today’s India’s total market demand is 3,00,000 TPA. 2.8 Employment Generation (Direct and Indirect) due to the project
The project will be having overall positive impact. It will generate direct & indirect employment to
around ~90 persons.
Pre-Feasibility Report
Page 7 of 42 Anacon Laboratories Pvt. Ltd.
3.0 PROJECT DESCRIPTIONS
3.1 Type of project including interlinked and interdependent projects, if any.
HRG manufactured at Satnoor plant is sent to Abu road plant for captive consumption to produce
ABS which is sold in the market. The Abu road plant of BEPL is dependent on Satnoor plant of BEPL
and has obtained environmental clearance for production of ABS.
3.2 Location (map showing general location, specific location and project boundary and
project site layout) with coordinates.
Details about the Project area are presented in Table 1.
TABLE 1 DETAILS ABOUT THE PROJECT AREA
Plot No. M/s. Bhansali Engineering Polymers Ltd. (BEPL), Bhansali Nagar, Near Satnoor Village, Taluka – Sausar, District – Chhindwara, Madhya Pradesh - 480108
Toposheet No. 55K/14; 55K/15
Geo-coordinates Latitude: 21°30'48.0"N; Longitude: 78°50'33.2"E
The index map is presented in Figure 1, Location map showing 10 km radius of study area shown in
Figure 2 and layout plan is given in Figure 3.
Pre-Feasibility Report
Page 8 of 42 Anacon Laboratories Pvt. Ltd.
FIGURE 1: INDEX MAP
Figure 1: LOCATION MAP SHOWING
Project Site:
M/s. Bhansali Engineering
Polymers Ltd.
Madhya Pradesh
Pre-Feasibility Report
Page 9 of 42 Anacon Laboratories Pvt. Ltd.
FIGURE 2: STUDY AREA MAP
(10 KM RADIAL DISTANCE FROM THE PROJECT SITE)
Pre-Feasibility Report
Page 10 of 42 Anacon Laboratories Pvt. Ltd.
FIGURE 3: LAYOUT PLAN
Pre-Feasibility Report
Page 11 of 42 Anacon Laboratories Pvt. Ltd.
3.3 Details of alternate sites considered and the basis of selecting the proposed site,
particularly the environmental considerations gone into should be highlighted.
Total 35.775 Hector land was allotted by Revenue Department to BEPL in 1988 for establishing the
plant. The proposed expansion will be carried out in the existing premises of the plant and there is no
requirement of acquiring additional land. Hence no alternative site is examined by project proponent.
3.4 Size or Magnitude of Project.
The plant is established in total 35.775 Hector land including manufacturing area and green belt and
other infrastructure. There is no requirement of additional land for proposed expansion.
3.5 Project description with process details
Manufacturing process:
HRG Resin manufacturing is done utilizing Emulsion Polymerization Technology transfer from M/s.
Sumitomo Naugatuck Co. Ltd and Sumitomo Chemical Engineering Co. Ltd., Japan.
The process of manufacturing of HRG is divided into following steps;
1. Chemical mixing
2. Polymerisation
i. Polymerisation of Butadiene to Polybutadiene (PBDE)
ii. Agglomeration
iii. Polymerisation of Graft
3. Master Batch Scaling
4. Flocculation
5. Filtration
6. Drying
1. CHEMICAL MIXING :
Different chemical solutions required for emulsion polymerisation are prepared in this section. These
solutions are tested by Quality Assurance Department and after clearance, used in polymerisation
process.
2. POLYMERISATION
i. Polymerisation of Butadiene to Polybutadiene (PBDE)
Butadiene from storage tanks is scrubbed with NaOH solution to reduce its TBC content as TBC
inhabits the rate of polymerisation. Scrubbed Butadiene is taken into the reactor alongwith water
and other required chemicals / chemical solutions. Temperature of the mixture is increased to 65
°C. The reaction takes place at 65 Deg. C and under a pressure of about 5.0 - 9.5 kg/sq.m.
Turbidity (TB) of PBDE is controlled by staggered addition of emulsifier as TB has direct bearing
on particle size of PBDE. As the reaction proceeds, reaction temperature is increased gradually to
75 °C. After completion of the reaction, the latex is stripped off unreacted butadiene and stored in
specified storage tanks.
ii. Agglomeration
PBDE latex acts as a colloidal solution having charge (both + ve & - ve). This SPS latex is taken
in reactor & agitator speed kept 10 rpm. After that ABSNA solution is added & agitator speed kept
Sr.
No
Name of product Existing Capacity Proposed
Capacity addition
Total capacity
after expansion
1. High Rubber Graft-HRG
(Rubber rich ABS)
15000 TPA HRG 35,000 TPA HRG 50,000 TPA HRG
Pre-Feasibility Report
Page 12 of 42 Anacon Laboratories Pvt. Ltd.
20 rpm. ABSNA solution is a strong electrolyte (polar & non polar) which disperse the charges of
SPS latex. With ABSNA SPS latex is agitated for 30 min. & PH checked comes about 11.5. Now
agitator rpm reduced to 10 & 3% H3PO4 acid solution dosing started with flowrate 0.85 lit/hr till PH
of latex comes < 4.0. H3PO4 acid aggregates the molecules of PBDE latex (partial coagulation) &
Turbidity increases. Cut off H3PO4 solution feeding at PH <4.0 & 10% KOH solution feeding
started at the flow rate of 0.47 lit/hr. KOH neutralize the added quantity of acid but turbidity as it is.
Cut off KOH feeding at PH >11.0 & agitator RPM increased to 20 rpm for half an hour. Then
Agglo latex transferred to latex storage after receiving results from QC. Dept. This latex is used
for production of GRAFT latex.
iii. Polymerisation of Graft
In polymerisation of graft, polybutadiene is used as backbone on to which a mixture of styrene
and acrylonitrile in fixed proportion (blended liquid monomer or BLM) is grafted Polybutadiene
alongwith water and other chemicals is added to the reactor. The mixture is heated to 65 °C and
emulsifier and BLM are continuously added in fixed proportion to the reactor. Reaction occurs
under vacuum. Here degree of polymerisation plays an important role which is governed by
turbidity measurement. The polymer lattices contains rubber domain i.e. polybutadiene and plastic
part i.e. polymer of styrene and acrylonitrile.
3. MASTER BATCH SCALING
Different Graft lattices are blended in fixed proportion as per the recipe for obtaining the desired
properties of final product. Antioxidants and colour stabilizers are added to this blend to inhibit
polymer oxidation, which would otherwise degrade the polymer. The blended is agitated for 2
hours for thorough mixing.
4. FLOCCULATION
Flocculated slurry is taken on to a vacuum belt filter where the water part is separated as filtrate
and the resin powder particles, after washing, are fed to dryer for drying.
5. FILTRATION
Flocculated slurry is taken on to a vacuum belt filter where the water part is separated as filtrate
and the resin powder particles, after washing, are fed to dryer for drying.
6. DRYING
The resin powder cake from belt filter contains about 40% moisture which is reduced to less than
20% in flash dryer using hot air at 95 - 100 °C and less than 0.9% in fluidised bed dryer using
hot water and hot air at 95 - 100 °C. The dried powder is stored in specified resin bin.
Pre-Feasibility Report
Page 13 of 42 Anacon Laboratories Pvt. Ltd.
FIGURE 4: HRG MANUFACTURING PROCESS FLOW DIAGRAM
BUTADIENE
STORAGE
STYRENE
STORAGE
ACRYLONITRILE
STORAGE
PBDE
STRIPPING
PBDE
REACTOR
GRAFT
REACTOR
GRAFT LATEX
STORAGE
MASTER BATCH
PREPARATION
DRYING
BUTADIENE
SCRUBBING
CHEMIMIX
SOLUTION
PBDE
LATEX
STORAGE
FLOCCULATION
FILTRATION
POWDER
PACKING
AGGLOMER-
ATION
FLARE
STACK
Pre-Feasibility Report
Page 14 of 42 Anacon Laboratories Pvt. Ltd.
3.6 Raw material required along with estimated quantity, likely source, marketing area of
final product/s, Mode of transport of raw Material and Finished Product.
Estimated raw materials quantity, mode of transportation is given in Table 2.
TABLE 2
ESTIMATED RAW MATERIAL QUANTITY
Sr.
No.
Raw
Material
Quantity
required for
15000 TPA
capacity
Quantity
required for
35000 TPA
capacity
Total Quantity
required for
50000 TPA
capacity
Mode of
transport
Source
1. Butadiene 8460.9 19742.1 28203.1 by road IOCL
2.
Styrene 4834.8 11281.2 16116.0
by road
from port
Imported
3.
Acrylonitrile 1813.1 4230.5 6043.5
by road
from port
Imported
4. Total 15108.8 35253.8 50362.6
3.7 Resource optimization/ recycling and reuse envisaged in the project, if any, should be
briefly outlined.
By adopting continuous improvement in technology and process, the reduction in process waste
generation will be achieved.
Plant has a pilot plant for carrying in-house R&D.
By proper and efficient handling of raw materials, wastages of raw materials will be reduced.
3.8 Environmental and Infrastructural Aspects
Availability of water its source, Energy/ Power requirement and source:
3.8.1 Availability of water and its source:
Water is sourced from Water Resource Department (WRD). BEPL has already taken requisite
permissions for drawl of water from Kanhan river through Jack well situated near Sawanga Village.
Pipeline network has been already established. Total fresh water requirement will be 1516 m3/day for
proposed expansion.
Please refer Annexure – VI Water Balance for further details.
3.8.2 Energy/ Power requirement and source:
Presently, Electricity is sourced from Madhya Pradesh Poorva Kshetra Vidyut Vitaran Co. by 33 KV
dedicated supply line with 33 KV substation in the plant premises with 2 MVA ( 33 KV/440 V)
transformer. The contract demand is 1300 KVA. After the proposed expansion, estimated contract
demand will be 4000 KVA. It is planned to install one more 2 MVA transformer in the sub-station to
meet the enhanced demand.
Since the process is continuous, it is necessary to ensure uninterrupted power supply. Presently, 2 x
500 KVA + 1 x 1250 KVA DG sets are provided as emergency power supply which is automatically
switched on in case of power failure. It is planned to install 4 x 1250 KVA DG sets to meet the
enhanced demand.
Sr. Particular Existing Proposed Total
1. Contract demand 1300 KVA 2700 KVA 4000 KVA
2. Connected Load 2975 KW 5950 KW 8925 KW
Pre-Feasibility Report
Page 15 of 42 Anacon Laboratories Pvt. Ltd.
Sr. Particular Existing Proposed Total
3. DG Sets (Plant) 1x1250 KVA;
2x500 KVA
4x1250 KVA 5x1250 KVA;
2x500 KVA = 7250 KVA
4. DG Set (Pump
house)
1x62.5 KVA No 1x62.5 KVA
Note – Present Grid supply is at 33 KV which is capable of catering to 5 MVA load which is adequate
to meet increased demand. MPPKVVCL permission for enhanced capacity will be submitted during
EIA presentation.
DG sets are kept standby mode only.
Fuel Requirement:
Coal is supplied from WCL, Savner through E-auction. LPG & HSD is procured from
IOCL/BPCL/HPCL as per requirement.
Sr. Particular Existing Proposed Total
1. Coal 30 Tonns/day 70 Tonns/day 100 Tonns/day
2. HSD As per requirement
3. LPG 40 kg/day 80 kg/day 120 kg/day
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their
Management/disposal
3.9.1 Wastewater generation & management plan
The wastewater generation from the proposed plant will be 1078 m3/day. . The industrial effluent will
be treated in proposed effluent treatment plant. The industry shall reuse the treated effluent in order
to reduce the fresh water requirement.
Please refer Annexure – VI Water Balance for further details.
3.9.2 Effluent Treatment scheme
Liquid waste effluents is treated in the existing wastewater treatment plant (ETP). The entire ETP will
be upgraded for enhanced load and to suit discharge norms. Recycling options will be explored to
conserve water. Sewage will be treated in STP.
Zero discharge norms will be followed.
3.9.3 Solid/hazardous waste generation and Management plan
Presently, the solid/hazardous waste is being sent to Pithampur TSDF site, 480 kms away from the
plant. BEPL is exploring the possibility of disposing of the solid waste for brick manufacturing/
proposed fly ash based product cluster near Koradi thermal Power station, Nagpur which is just 45
kms away from the Satnoor plant. In this respect, necessary permissions will be obtained.
3.9.4 Stack details and air pollution measures
Presently, requirement is met by 320 Nm3/hour capacity flare stack having LPG fired burner tip. It is planned to install 640 Nm3/hour capacity new flare stack to meet the requirement of additional production. Boiler stack of 30 m height is connected through cyclone & bag filters for air pollution control. DG sets are equipped with stacks as per CPCB norms.
Pre-Feasibility Report
Page 16 of 42 Anacon Laboratories Pvt. Ltd.
4.0 SITE ANALYSIS 4.1 Connectivity.
The plant is located near Satnoor village on State Highway No. 250 (Nagpur – Chinddwara).
The site is well connected with Road/Rail/Airport. The details are as follows:
Nagpur Railway Station ~48.00 Km, SSE
Nagpur Airport ~52 Km, SSE
4.2 Land Form, Land use and Land ownership.
Total 35.775 Hector land was allotted by Revenue Department to BEPL in 1988 for establishing the
plant. The proposed expansion will be carried out in the existing premises of the plant and there is no
requirement of acquiring additional land. Hence no alternative site is examined by project proponent.
The details regarding the breakup of the land for the various activities of the proposed project is as
follows (Tables 3)
TABLE 3
AREA STATEMENT
Sr. No. Description Existing Area in Sq. M. Proposed Area in Sq. M.
1. Utility area 1887.7 3469.42
2. Admin Building 2640 0
3. Storage 911.1 300
4. Process area 6008 2904
5. ETP Area 11803 As per requirement
6. Green belt 200000 0
7. Roads 19535 0
8. Other 114965.2 0
9. Total (Existing + Proposed ) 357750 M2
4.3 Topography of the project area
The site is situated on hilly terrain. The project site lies at the Latitude: 21°30'48.0" N & Longitude:
78°50'33.2" E on the Topo sheet No. 55K/14; 55K/15. The site specific Topography is shown in study
area map.
4.4 Existing land use pattern (agriculture, non-agriculture, forest, water bodies
(distance from HFL to the river), CRZ. In case of notified industrial area, a copy of Gazette
Notification should be given:-
The proposed expansion will be carried out in the existing plant premises. The land is already
converted for industrial use. Land documents are enclosed as Annexure-III.
There is no forest, national park, wild life sanctuary, eco sensitive areas in surrounding 10 Km from
the plant boundary. CRZ is not applicable to the project.
Existing infrastructure
Existing facilities are sufficient for 15000 TPA HRG production. Photographs are attached in following
Figure 5.
Pre-Feasibility Report
Page 17 of 42 Anacon Laboratories Pvt. Ltd.
FIGURE 5: PROJECT SITE PHOTOGRAPHS
Pre-Feasibility Report
Page 18 of 42 Anacon Laboratories Pvt. Ltd.
5.0 PLANNING BRIEF 5.1 Planning concept (type of industries, facilities transportation Town and Country
Planning Development authority Classification.
Type of Industry
HRG resin manufacture (As per EIA notification dated 14 September 2006 and subsequent
amendments, this project falls under schedule No. 5 (f) Manufacturing of Synthetic organic chemical
Industry)
Town and Country Planning Development authority Classification
The proposed project falls under Gram panchayat Satnoor village. Adequate road facilities are
already available for transportation of raw materials as well as finished products.
5.2 Population Projection
The proposed expansion will be providing employment to 90 people in addition to existing 187 people
directly and indirectly. Since the proposed plant is located in the Chhindwara district in which trained
manpower are readily available, therefore the employment will be given mostly to local people, so
there will not be any substantial increase in the population of local villages. However, due to increase
economic growth, the local youth will be benefited with respect to employment.
5.3 Land use planning (breakup along with green belt etc.)
The total land area is 35.775 hectors and the greenbelt is already developed on 20 hector area of the
total land.
The breakup of the land for the proposed project is given in Table 4 above.
5.4 Assessment of Infrastructure Demand
The basic infrastructure (Connective roads, Water resource vicinity) required for the proposed
expansion is available at the project site as the industry has existing unit. Apart from that the
additional infrastructure will be developed by the company as per the requirement.
5.5 Facilities Availability
Major basic facilities are available for the proposed project. Road, electricity, water, transportation
facility etc. are well developed in the surrounding area. The major new facilities required to be set for
the proposed project will be installation of process equipment at site within the premises along with all
the necessary infrastructures like additional storage tanks and equipment sheds etc.
Pre-Feasibility Report
Page 19 of 42 Anacon Laboratories Pvt. Ltd.
6.0 PROPOSED INFRASTRUCTURE
6.1 Industrial Area (Processing Area)
The proposed expansion will be carried out in the existing plant premises. The total land area is
35.775 hectors and the greenbelt is already developed on 20 hector area of the total land as given in
land use statement (Table 4).
6.2 Residential Area (Non Processing Area)
There is no residential area proposed in the plant premises.
6.3 Green Belt
The total land area is 35.775 hectors and the greenbelt is already developed on 20 hector area of the
total land which constitutes more than 50%.
6.4 Social Infrastructure
The project area lies within the district of Chhindwara. There is no requirement to build any social
infrastructure within the proposed plant area. The management of M/s. BEPL is already running a
public school (Nursary to class 10th) as social service.
6.5 Connectivity (Traffic and Transportation Road, Rail/Metro/Waterways etc.).
The proposed project is situated near Satnoor village on Nagpur- Chhindwara highway. The site is
well connected with Road/Rail. The details are as follows:
Sawanga Railway Station ~2.83 Km, E
Nagpur Railway Station ~48.00 Km, SSE
Nagpur Airport ~52 Km, SSE
6.6 Drinking Water Management (Source & Supply of water)
Drinking water is sourced from Kanhan River near Sawanga village.
6.7 Sewerage system
Additional infra-structural services including water supply, sewage, drainage facilities and
electrification will be made for proposed expansion. Currently domestic sewage is treated in septic
tanks and treated water is used for irrigation within plant. No wastewater will be discharged on land.
Process wastewater will be treated in ETP and reused and recycled. STP is proposed and treated
water will be used for cooling tower. Zero discharge norms will be followed.
6.8 Industrial Waste/ Solid Waste Management
The industrial wastes generated in the form of solid wastes, and hazardous wastes will be collected,
segregated and disposed off as per CPCB guideline.
Presently, the solid/hazardous waste is being sent to Pithampur TSDF site, 480 kms away from the
plant. BEPL is exploring the possibility of disposing of the solid waste for brick manufacturing/
proposed fly ash based product cluster near Koradi thermal Power station, Nagpur which is just 45
kms away from the Satnoor plant. In this respect, necessary permissions will be obtained.
Pre-Feasibility Report
Page 20 of 42 Anacon Laboratories Pvt. Ltd.
7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN
7.1 Policy to be adopted (Central/ State) in respect of the project affected persons
including home oustees, land oustees and landless laborers (a brief outline to be
given).
The proposed project does not have any directly displaced persons, as land acquisition is not
involved. There are also no land oustees or project affected persons or home oustees, thus R&R plan
is not applicable here. However, the priority for employment will be given to local persons living in the
adjoining villages. In addition to this, company will continue to contribute for the welfare of the people
of local surrounding under company’s CSR policy.
DETAILS OF CORPORATE SOCIAL RESPONSIBILITY:
CSR Programs
The policy outlines the Company’s strategy to bring about a positive impact on society through activities/ programs relating to Health, Happy Childhood, Education, Employment, Hunger eradication, Environmental Sustainability, Promoting Gender Equality, Gender upliftment for deserving sections of society, Sports Promotion etc.
Monitoring
CSR committee authorized by board of directors will monitor CSR activities and proper utilization of
funds. The CSR committee will be fully authorized to delegate appropriate authority to any employee
of the company for properly carrying out CSR activities.
Environment Impacts and Measures
Schematic representations of the feasibility drawing which give information of EIA purpose:
S. No. Particulars Impacts Remediation Proposed
1. Change in
land use.
There will be change in land
use on permanent basis due
to installation of machineries
and equipment.
The proposed expansion will be carried
out adjacent to existing structure. No
additional land is required for the
proposed expansion.
Water is sourced with permission of
Water Resource Department (WRD)
from Kanhan River near Sawanga
village. No groundwater will be
abstracted for the project activities
hence, and natural recharge of
groundwater level will not be affected
through proposed project activities.
2. Transportation
of material
The existing network of
transport gets pressurized
The proposed activity will marginally
increase in Traffic density. The project
site is adjacent to state highway thus,
infrastructural facilities/road accessibility
are already developed.
3. Gaseous and
Particulate
Emission to
The
atmosphere
Air quality All necessary steps will be followed to
minimize the emission from point sources
as well as line sources. Thus the
standards of Stack Emission and Ambient
Air quality will be maintained as per
prescribed limits.
Pre-Feasibility Report
Page 21 of 42 Anacon Laboratories Pvt. Ltd.
S. No. Particulars Impacts Remediation Proposed
4. Discharge of
effluent
Impact of water quality. Zero discharge is proposed.
5. Withdrawal of
ground /
surface water
Availability of ground/surface
water is affected.
Water is sourced from Kanhan river, no
ground water will be abstracted for the
project activities hence, and natural
recharge of groundwater level is not
affected through project activities.
Permission regarding drawl of river water
is granted from Water Resource
Department.
6. Operation of
equipment
and vehicles
likely to
generate
noise.
Impact on human health due
to excess noise level beyond
permissible level.
All the process equipment will be installed
on anti-vibration pad with sufficient
provisions to minimize generation of
noise. The high noise generating
equipment like generator will be enclosed
with noise suppressing enclosures.
The buildings as well as boundary wall
and green belt will ensure the attenuation
of noise outside the boundary within the
prescribed limits.
7. Fire Hazard
due to storage
of fuel etc.
Risk to the surrounding
habitation.
Necessary precautions to prevent fire and
all the provisions to control fire shall be
provided.
8. Employment
to outsiders
Socio-economic disparity with
local community
Priority of employment will be given to
local people, as already sufficient
qualified and trained local youth area
available.
9. Cultural impact Local population feels
isolated
The promoters proposed to employ local
masses in the project hence no such
impact on cultural diversity is likely to take
place.
10. Disposal of
solid and
hazardous
wastes
Create odorous problem,
nuisance condition related to
the disposal of solid wastes.
Deterioration of soil,
productivity pollution in
ground water/surface water
due to leaching and surface
runoff.
Domestic wastes will be segregated for
organics and Inorganics. Organic wastes
will be used for composting and
inorganics for approved vendors.
Disposal of hazardous wastes will be
done as per hazardous wastes handling
and disposal rule.
Pre-Feasibility Report
Page 22 of 42 Anacon Laboratories Pvt. Ltd.
8.0 PROJECT SCHEDULE & COST ESTIMATES SCHEDULE FOR APPROVAL AND IMPLEMENTATION
Proposed Project
The project will start only after obtaining Environmental Clearance and other statutory permissions.
Project will be completed in 12 months after getting all the regulatory approvals.
8.2 Estimated project cost along with analysis in terms of economic viability of the project.
The proposed project cost is estimated to be Rs. 13270 Lacs.
9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
9.1 Financial and social benefits with special emphasis on the benefit to the local People
Including Tribal Population, If Any, in the Area.
On overall assessment of the project with consideration of technical and financial aspects, it is
concluded that the proposed expansion is technically feasible and financially viable. There are
only two manufacturing companies in India which produce ABS and are not able to cater to the
whole demand of ABS in India, so the deficit in supply is fulfilled through imports. BEPL deems it
expedient to quickly expand the capacity to conserve outflow of foreign exchange.
Project will create direct & indirect employment opportunities within the surrounding region. Unit will use
good faith efforts to employ local people from the nearby villages depending upon the availability of
skilled & un-skilled man-power surrounding the project site. The project will continue to benefit socio-
economic benefits for the society with Company’s employment and CSR activities.
Pre-Feasibility Report
Page 23 of 42 Anacon Laboratories Pvt. Ltd.
ANNEXURE I- GOOGLE MAP
Pre-Feasibility Report
Page 24 of 42 Anacon Laboratories Pvt. Ltd.
ANNEXURE II-LAND DOCUMENT
Pre-Feasibility Report
Page 25 of 42 Anacon Laboratories Pvt. Ltd.
Pre-Feasibility Report
Page 26 of 42 Anacon Laboratories Pvt. Ltd.
Pre-Feasibility Report
Page 27 of 42 Anacon Laboratories Pvt. Ltd.
Pre-Feasibility Report
Page 28 of 42 Anacon Laboratories Pvt. Ltd.
Pre-Feasibility Report
Page 29 of 42 Anacon Laboratories Pvt. Ltd.
Pre-Feasibility Report
Page 30 of 42 Anacon Laboratories Pvt. Ltd.
Pre-Feasibility Report
Page 31 of 42 Anacon Laboratories Pvt. Ltd.
Pre-Feasibility Report
Page 32 of 42 Anacon Laboratories Pvt. Ltd.
Annexure III-Factory Licenses
Pre-Feasibility Report
Page 33 of 42 Anacon Laboratories Pvt. Ltd.
ANNEXURE IV-CHW-TSDF MEMBERSHIP
Pre-Feasibility Report
Page 34 of 42 Anacon Laboratories Pvt. Ltd.
ANNEXURE V-CONSENT TO OPERATE
Pre-Feasibility Report
Page 35 of 42 Anacon Laboratories Pvt. Ltd.
Pre-Feasibility Report
Page 36 of 42 Anacon Laboratories Pvt. Ltd.
Pre-Feasibility Report
Page 37 of 42 Anacon Laboratories Pvt. Ltd.
Pre-Feasibility Report
Page 38 of 42 Anacon Laboratories Pvt. Ltd.
Pre-Feasibility Report
Page 39 of 42 Anacon Laboratories Pvt. Ltd.
Pre-Feasibility Report
Page 40 of 42 Anacon Laboratories Pvt. Ltd.
ANNEXURE –VI – WATER BALANCE
EXISTING WATER BALANCE PROPOSED WATER BALANCE FINAL WATER BALANCE
Sr.
No.
Water Uses Water
Required
(m3/d)
Waste
Water
Generation
(m3/d)
Evaporation
Losses/Process
Consumption
(m3/d)
Reuse /
Recycle
Water
Required
(m3/d)
Waste
Water
Generation
(m3/d)
Evaporation
Losses/Process
Consumption
(m3/d)
Reuse /
Recycle
Water
Required
(m3/d)
Waste
Water
Generation
(m3/d)
Evaporation
Losses/Process
Consumption
(m3/d)
Reuse /
Recycle
Initial Raw
Water
Requirement
592 1360 1952
I Multi Directional Filter (MDF)
Raw Water treat before uses
20 Nil 572*
Raw Water treat before uses 46 Nil 1314*
Raw Water treat before uses
66 Nil 1886*
This 572* m3/day Multi Directional Filter (MDF) treated is using in
different purposes in the plant, details are shown below. This 1886* m
3/day Multi Directional Filter
(MDF) treated is using in different purposes in the plant, details are shown below.
A Different use 92 215 307
i Water hydrant 3 1.5 1.5 7 3.5 3.5 10 5 5
ii ETP 36 34 2 84 79 5 120 113 7
iii Flore cleaning 45 30 15 75 70 35 150 100 50
iv Land scaping 8 Nil 8 19 Nil 19 27 Nil 27
B DM Water 308 719 1027
i Cation+Anion +Mixed Bed Filter
308 23 Nil 285* 719 54 Nil 665* 1027 77 Nil 950*
ii Polymerization & Flocculation
285* 195 30 eva.+60 Steam
60 665* 455 70 eva.+140 Steam
140 950* 650 100 eva.+200 Steam
200
C Industrial Water
161 376 537
I Softener 161 6 Nil 155* 376 14 Nil 362* 537 20 Nil 517*
This 155* m3/day soft water is generated are using in various
process. This 362* m
3/day soft water is generated are
using in various process. This 517* m
3/day soft water is generated are
using in various process.
Pre-Feasibility Report
Page 42 of 42 Anacon Laboratories Pvt. Ltd.
ii Hydro get cleaning
4 3 1 4 9 7 2 9 13 10 3 10
iii Cooling tower 66 11 55 11 155 26 129 26 221 37 184 37
iv Boiler 85 Nil 85 Nil 198 Nil 198 Nil 283 Nil 283 Nil
D Domestic
Use
11 8 3 8 4 3 1 3 15 11 4 11
Total
592 331.5 260.5 23 (8-
Reuse*
+ 15-
Recycle)
1360 746.5 613.5 38 (3-
Reuse*
+ 35-
Recycle)
1952 1078 874 58 (11-
Reuse* +
47-
Recycle)
Initial Fresh Water
requirement 592 m
3/day
1360 m
3/day
1952 m
3/day
Out of 1078 [432 evaporation losses in ETP & Sludge Drying bed and 190 will use in green belt, (No change)] Recycle in process: 1078-432-190=456 finally treated by RO and RO Permeate 436 will Recycle in process where as Ron reject 20 will send again in ETP. In this way daily water intake will reduce by 1952-436=1516