pre construction surveys &clearences
TRANSCRIPT
-
8/8/2019 Pre Construction Surveys &Clearences
1/28
Route & Site selection Surveys
And
Clearances from Statutory Bodies
in Pipeline Projects
U K Palon
26-07-2010
-
8/8/2019 Pre Construction Surveys &Clearences
2/28
Contents
Concept of Route Survey & Types thereof
Reconnaissance Survey or REKI
Detailed Route Survey. Cadastral Survey
ROW & its acquisition
Other Miscellaneous Surveys
Site selection for Terminals, Pump-stations,
Tank Farms, RCPs etc.
Clearances and permits from Statutory Bodies
-
8/8/2019 Pre Construction Surveys &Clearences
3/28
What is Surveying?
Surveying is a pro-active action for
collecting information/data for either
enabling a decision making process or forexecuting an activity in a Project
-
8/8/2019 Pre Construction Surveys &Clearences
4/28
Data/Information
(For Pipeline Projects)
The Information/data collected in Pipeline Route Survey
helps in deciding following parameters for Project
execution:
Length & Profile
Hydraulics
Investment Cost
Long-term Operating & Maintenance Cost
Project Completion Time
-
8/8/2019 Pre Construction Surveys &Clearences
5/28
Types of Survey in Pipeline
Projects Reconnaissance Survey or REKI
Detailed Engineering Survey
Detailed Route Survey
Soil Stratification Survey
Soil Resistivity Survey
Acquisition of ROW
Cadastral Survey
Other Miscellaneous Survey
Sub-soil Investigation
Topography Survey
-
8/8/2019 Pre Construction Surveys &Clearences
6/28
LIFESPAN OF PROJECT
Conception Approval Execution Operation
Approval ofProjectPre-Project Activities
FirstStageApproval
Pre-Constn.activities
-
8/8/2019 Pre Construction Surveys &Clearences
7/28
Surveying Activity vs Project Phase
Reconnaissance Survey
or REKI
Detailed Route Survey.
Also called as Detailed
Engineering Survey
Cadastral Survey
Acquisition of ROW
Other Miscellaneous
Survey
Project Conceptual
StageFor FR Details
After First stage
clearance for Detailed
Feasibility Report (DFR)
Project Approval Stage-
Prior to Start of Field
work for Mainline
Laying
As and when necessary
-
8/8/2019 Pre Construction Surveys &Clearences
8/28
Reconnaissance Survey
Carried out during Project Conceptual Stage
The details are required for Feasibility
Report
A technically feasible shortest & cost-effective
route is identified
Various important features and information
en-route that may affect the Project anyway
are listed
-
8/8/2019 Pre Construction Surveys &Clearences
9/28
Reconnaissance Survey
Desk-Top study to identify various alternatives
Verification of ground truth
Establishing Ground Control Points Listing of Crossings, details, rough profiles
Land-use pattern en-route
Development/expansion plan, contact Nos., addressesof various Authorities
Unit rates of Materials and Manpower
-
8/8/2019 Pre Construction Surveys &Clearences
10/28
Reconnaissance Survey
No major surveying tool is used
Usually require 1 wk to 6 wks depending on length,
terrain & manpower used
Verification of Ground Truth is important People of local origin/ language is very helpful
Information/ data/ sketch/ documentation are most
important
-
8/8/2019 Pre Construction Surveys &Clearences
11/28
Desk-Top Study
Extensive use of SOI Topo-sheets
Few alternatives are chalked outs
Comparative merits/demerits are listed GIS Packages are extremely helpful
Extensive Use of Satellite Imagery & Google
Earth Software now-a-days
-
8/8/2019 Pre Construction Surveys &Clearences
12/28
-
8/8/2019 Pre Construction Surveys &Clearences
13/28
-
8/8/2019 Pre Construction Surveys &Clearences
14/28
Route Finalisation
To connect originating, terminating & obligatory points.
To avoid densely populated area & city limits.
To avoid reserved forest, wild life sanctuary, maritime
zone.
Passage through forest area should be minimum, if not
avoidable.
Approachability to ROW for maintenance.
To avoid hilly and highly undulated zone/ broken lands.
To avoid permanently marshy/ waterlogged/ flood pronearea.
To avoid mining areas.
Minimum crossings.
-
8/8/2019 Pre Construction Surveys &Clearences
15/28
Verification of Ground-Truths
This is carried out on the finally selected route,unless otherwise required
This is necessary, since, Topo-sheets are updatedafter 2-3 decades
Expansion plans, urbanisation scenario,Developmental activities, river-course &aforestation programme keeps on changing
Any strech of restricted ROW
Prospect for aquiring additional ROW in case offuture lines
-
8/8/2019 Pre Construction Surveys &Clearences
16/28
Establishing Ground-Control Points
These should be at prominent places and easilyidentifiable at a later date
Locations are serially documented w.r.t. nearbystructures, KM post, Electric/ Telephone
pole/tower etc. Should be well discussed with local villagers
Photographs are taken for easy identification infuture
-
8/8/2019 Pre Construction Surveys &Clearences
17/28
Collection of Data
River course profile with approximate dimensions
Sketches of Road crossings with future widening
plan, if any
Addresses, Telephone Nos. & contact persons of
Various authorities en-route
Unit cost of various construction materials andmanpower for estimation purpose
-
8/8/2019 Pre Construction Surveys &Clearences
18/28
Detail Engineering Survey
This activity is taken up during approval stage,
when approval is considered almost certain
Prior to this, route was on maps and paper. This
is the first field activity taken up for PipelineProjects
Detailed Engineering Survey primarily consists
of:
Detailed Route Survey &
Soil stratification Survey &
Soil Resistivity Survey
-
8/8/2019 Pre Construction Surveys &Clearences
19/28
Detailed Route Survey
By this time, the obligatory points of the routesare already identified and the configuration ofPipeline is also known
In this activity, route is progressively staked on
ground preferably from one obligatory pointand demarcated with TPs and IPs andrelated reference points.
Exact distances between TPs & IPs, included
angles, elevations etc. are accurately measuredand recorded by theodelite /total stations
The levels are taken at every 50 M distance ofthe staked route
-
8/8/2019 Pre Construction Surveys &Clearences
20/28
Detailed Route Survey
Crossing locations are identified and detaileddimensions are taken A basis for detailedwork estimate and tendering
Salient features on both side of the stakedroutes are recoded and indicated on the routemap prepared in a scale of 1: 10,000
TPs, IPs & crossings are serially numbered and
marked on route maps Profile Maps are prepared to a scale H 1:5000
& V 1:100
Ri h f W (ROW) & I
-
8/8/2019 Pre Construction Surveys &Clearences
21/28
Right of Way (ROW) & Its
acquisition Right of Way is acquired through PMP Act 1962
Through this Act, Corporation acquires right of use of this
land for laying a Pipeline, operating and maintaining the
same by paying a specified compensation
This is a very lengthy and complicated legal process, often
dictating the total completion period of the Project
Whenever ROW is acquired on a land, land use pattern
can not be changed by the owner
ROW acquisition is accomplished by dedicated team
deputed for this purpose from state Land revenue deptt.
Unless planned in advance and monitored properly, this
activity is mainly responsible for time over-run
-
8/8/2019 Pre Construction Surveys &Clearences
22/28
Cadastral Survey
This is carried out for the purpose of ROW acquisitionand calculation of compensation
On village revenue maps, the ROW of 18 M width is
plotted and affected survey nos. are identified.
The area calculations are made and amount of compensation are calculated based on the prevalent land-
rates
Ownership records, e.g. 7/12 are sorted and
compensation amount is disbursed before taking up pipe
laying works
During this survey, few diversions of route may take
place to accommodate unavoidable circumstances
-
8/8/2019 Pre Construction Surveys &Clearences
23/28
ROW Acquisition
The land schedule including ownership details are preparedand notification under section 3(i) and individual notices are
issued
Objection are heard by Competent Authority (CA) and these
are either dismissed or held resulting in diversion
After attending to objections, notification under section 6(i)
and individual notices are issued
The compensation is disbursed after hearing of objection, if
any
The acquisition process starts with collection of village
revenue map and cadastral survey
After payment of compensation, ROW can be opened by the
owner for construction purpose
-
8/8/2019 Pre Construction Surveys &Clearences
24/28
Other Miscellaneous Survey
Soil Investigation
Soil Resistivity Survey
Soil stratification
Survey
Topography &
Contour
Soil Investigation and
River Profile
For taking up foundation
Design
Carried out at 500 M interval
along the route at 1M, 1.5M, 2
M and 2.5M depth for CP
design
For ascertaining terrain
details and taking proper care
in Mainline tender for coating
as well as earthwork Station Construction
For design of HDD crossings
-
8/8/2019 Pre Construction Surveys &Clearences
25/28
Site Selection
Sites are selected for:
Tank Farms Area as per requirement (> 60 70
acres ) Pump Stations 1012 acres
Delivery Stations 6 -10 acres
RCPs 0.5 acre
Valve Locations 5M x 5M
Permanent Land Acquisition Act 1894
-
8/8/2019 Pre Construction Surveys &Clearences
26/28
Criteria for Site Selection
Shall fall on selected route
Fairly level high-land requiring less earthwork
Easy Approachability through Major Road
(No Levelcrossing or Road blocks in Approach) Availability of Water & Power
Away from Urban Development and Residential
Area
Maintenance Facility nearby
Sub-soil Properties suitable for Required
Foundation Systems
Drainage outlet
-
8/8/2019 Pre Construction Surveys &Clearences
27/28
CLEARANCES & PERMITS
Clearance from State Pollution Control Boards (NOCthrough Public Hearing) Water preservation & Pollution
Control Act 1974 amended in 1978 & 1988
Forest clearance under Forest Act, 1980 amended in 1988
Consent to establish under water and Air Act from State
PCBs
Clearance from Mining Authorities (wherever required)
MOE&F clearance and clearance from Maritime Board &
CRZ Authorities (wherever applicable)
NOC from DMs of encountered districts CCE and OISD clearance
Permits from Railway/ Irrigation/ Highway Authorities
Clearance from State fire Brigade
Factory license/ Clearance from Electrical Inspector.
-
8/8/2019 Pre Construction Surveys &Clearences
28/28
Thank You