    Route & Site selection Surveys

    And

    Clearances from Statutory Bodies

    in Pipeline Projects

    U K Palon

    26-07-2010

  • 8/8/2019 Pre Construction Surveys &Clearences

    2/28

    Contents

    Concept of Route Survey & Types thereof

    Reconnaissance Survey or REKI

    Detailed Route Survey. Cadastral Survey

    ROW & its acquisition

    Other Miscellaneous Surveys

    Site selection for Terminals, Pump-stations,

    Tank Farms, RCPs etc.

    Clearances and permits from Statutory Bodies

  • 8/8/2019 Pre Construction Surveys &Clearences

    3/28

    What is Surveying?

    Surveying is a pro-active action for

    collecting information/data for either

    enabling a decision making process or forexecuting an activity in a Project

  • 8/8/2019 Pre Construction Surveys &Clearences

    4/28

    Data/Information

    (For Pipeline Projects)

    The Information/data collected in Pipeline Route Survey

    helps in deciding following parameters for Project

    execution:

    Length & Profile

    Hydraulics

    Investment Cost

    Long-term Operating & Maintenance Cost

    Project Completion Time

  • 8/8/2019 Pre Construction Surveys &Clearences

    5/28

    Types of Survey in Pipeline

    Projects Reconnaissance Survey or REKI

    Detailed Engineering Survey

    Detailed Route Survey

    Soil Stratification Survey

    Soil Resistivity Survey

    Acquisition of ROW

    Cadastral Survey

    Other Miscellaneous Survey

    Sub-soil Investigation

    Topography Survey

  • 8/8/2019 Pre Construction Surveys &Clearences

    6/28

    LIFESPAN OF PROJECT

    Conception Approval Execution Operation

    Approval ofProjectPre-Project Activities

    FirstStageApproval

    Pre-Constn.activities

  • 8/8/2019 Pre Construction Surveys &Clearences

    7/28

    Surveying Activity vs Project Phase

    Reconnaissance Survey

    or REKI

    Detailed Route Survey.

    Also called as Detailed

    Engineering Survey

    Cadastral Survey

    Acquisition of ROW

    Other Miscellaneous

    Survey

    Project Conceptual

    StageFor FR Details

    After First stage

    clearance for Detailed

    Feasibility Report (DFR)

    Project Approval Stage-

    Prior to Start of Field

    work for Mainline

    Laying

    As and when necessary

  • 8/8/2019 Pre Construction Surveys &Clearences

    8/28

    Reconnaissance Survey

    Carried out during Project Conceptual Stage

    The details are required for Feasibility

    Report

    A technically feasible shortest & cost-effective

    route is identified

    Various important features and information

    en-route that may affect the Project anyway

    are listed

  • 8/8/2019 Pre Construction Surveys &Clearences

    9/28

    Reconnaissance Survey

    Desk-Top study to identify various alternatives

    Verification of ground truth

    Establishing Ground Control Points Listing of Crossings, details, rough profiles

    Land-use pattern en-route

    Development/expansion plan, contact Nos., addressesof various Authorities

    Unit rates of Materials and Manpower

  • 8/8/2019 Pre Construction Surveys &Clearences

    10/28

    Reconnaissance Survey

    No major surveying tool is used

    Usually require 1 wk to 6 wks depending on length,

    terrain & manpower used

    Verification of Ground Truth is important People of local origin/ language is very helpful

    Information/ data/ sketch/ documentation are most

    important

  • 8/8/2019 Pre Construction Surveys &Clearences

    11/28

    Desk-Top Study

    Extensive use of SOI Topo-sheets

    Few alternatives are chalked outs

    Comparative merits/demerits are listed GIS Packages are extremely helpful

    Extensive Use of Satellite Imagery & Google

    Earth Software now-a-days

  • 8/8/2019 Pre Construction Surveys &Clearences

    12/28

  • 8/8/2019 Pre Construction Surveys &Clearences

    13/28

  • 8/8/2019 Pre Construction Surveys &Clearences

    14/28

    Route Finalisation

    To connect originating, terminating & obligatory points.

    To avoid densely populated area & city limits.

    To avoid reserved forest, wild life sanctuary, maritime

    zone.

    Passage through forest area should be minimum, if not

    avoidable.

    Approachability to ROW for maintenance.

    To avoid hilly and highly undulated zone/ broken lands.

    To avoid permanently marshy/ waterlogged/ flood pronearea.

    To avoid mining areas.

    Minimum crossings.

  • 8/8/2019 Pre Construction Surveys &Clearences

    15/28

    Verification of Ground-Truths

    This is carried out on the finally selected route,unless otherwise required

    This is necessary, since, Topo-sheets are updatedafter 2-3 decades

    Expansion plans, urbanisation scenario,Developmental activities, river-course &aforestation programme keeps on changing

    Any strech of restricted ROW

    Prospect for aquiring additional ROW in case offuture lines

  • 8/8/2019 Pre Construction Surveys &Clearences

    16/28

    Establishing Ground-Control Points

    These should be at prominent places and easilyidentifiable at a later date

    Locations are serially documented w.r.t. nearbystructures, KM post, Electric/ Telephone

    pole/tower etc. Should be well discussed with local villagers

    Photographs are taken for easy identification infuture

  • 8/8/2019 Pre Construction Surveys &Clearences

    17/28

    Collection of Data

    River course profile with approximate dimensions

    Sketches of Road crossings with future widening

    plan, if any

    Addresses, Telephone Nos. & contact persons of

    Various authorities en-route

    Unit cost of various construction materials andmanpower for estimation purpose

  • 8/8/2019 Pre Construction Surveys &Clearences

    18/28

    Detail Engineering Survey

    This activity is taken up during approval stage,

    when approval is considered almost certain

    Prior to this, route was on maps and paper. This

    is the first field activity taken up for PipelineProjects

    Detailed Engineering Survey primarily consists

    of:

    Detailed Route Survey &

    Soil stratification Survey &

    Soil Resistivity Survey

  • 8/8/2019 Pre Construction Surveys &Clearences

    19/28

    Detailed Route Survey

    By this time, the obligatory points of the routesare already identified and the configuration ofPipeline is also known

    In this activity, route is progressively staked on

    ground preferably from one obligatory pointand demarcated with TPs and IPs andrelated reference points.

    Exact distances between TPs & IPs, included

    angles, elevations etc. are accurately measuredand recorded by theodelite /total stations

    The levels are taken at every 50 M distance ofthe staked route

  • 8/8/2019 Pre Construction Surveys &Clearences

    20/28

    Detailed Route Survey

    Crossing locations are identified and detaileddimensions are taken A basis for detailedwork estimate and tendering

    Salient features on both side of the stakedroutes are recoded and indicated on the routemap prepared in a scale of 1: 10,000

    TPs, IPs & crossings are serially numbered and

    marked on route maps Profile Maps are prepared to a scale H 1:5000

    & V 1:100

    Ri h f W (ROW) & I

  • 8/8/2019 Pre Construction Surveys &Clearences

    21/28

    Right of Way (ROW) & Its

    acquisition Right of Way is acquired through PMP Act 1962

    Through this Act, Corporation acquires right of use of this

    land for laying a Pipeline, operating and maintaining the

    same by paying a specified compensation

    This is a very lengthy and complicated legal process, often

    dictating the total completion period of the Project

    Whenever ROW is acquired on a land, land use pattern

    can not be changed by the owner

    ROW acquisition is accomplished by dedicated team

    deputed for this purpose from state Land revenue deptt.

    Unless planned in advance and monitored properly, this

    activity is mainly responsible for time over-run

  • 8/8/2019 Pre Construction Surveys &Clearences

    22/28

    Cadastral Survey

    This is carried out for the purpose of ROW acquisitionand calculation of compensation

    On village revenue maps, the ROW of 18 M width is

    plotted and affected survey nos. are identified.

    The area calculations are made and amount of compensation are calculated based on the prevalent land-

    rates

    Ownership records, e.g. 7/12 are sorted and

    compensation amount is disbursed before taking up pipe

    laying works

    During this survey, few diversions of route may take

    place to accommodate unavoidable circumstances

  • 8/8/2019 Pre Construction Surveys &Clearences

    23/28

    ROW Acquisition

    The land schedule including ownership details are preparedand notification under section 3(i) and individual notices are

    issued

    Objection are heard by Competent Authority (CA) and these

    are either dismissed or held resulting in diversion

    After attending to objections, notification under section 6(i)

    and individual notices are issued

    The compensation is disbursed after hearing of objection, if

    any

    The acquisition process starts with collection of village

    revenue map and cadastral survey

    After payment of compensation, ROW can be opened by the

    owner for construction purpose

  • 8/8/2019 Pre Construction Surveys &Clearences

    24/28

    Other Miscellaneous Survey

    Soil Investigation

    Soil Resistivity Survey

    Soil stratification

    Survey

    Topography &

    Contour

    Soil Investigation and

    River Profile

    For taking up foundation

    Design

    Carried out at 500 M interval

    along the route at 1M, 1.5M, 2

    M and 2.5M depth for CP

    design

    For ascertaining terrain

    details and taking proper care

    in Mainline tender for coating

    as well as earthwork Station Construction

    For design of HDD crossings

  • 8/8/2019 Pre Construction Surveys &Clearences

    25/28

    Site Selection

    Sites are selected for:

    Tank Farms Area as per requirement (> 60 70

    acres ) Pump Stations 1012 acres

    Delivery Stations 6 -10 acres

    RCPs 0.5 acre

    Valve Locations 5M x 5M

    Permanent Land Acquisition Act 1894

  • 8/8/2019 Pre Construction Surveys &Clearences

    26/28

    Criteria for Site Selection

    Shall fall on selected route

    Fairly level high-land requiring less earthwork

    Easy Approachability through Major Road

    (No Levelcrossing or Road blocks in Approach) Availability of Water & Power

    Away from Urban Development and Residential

    Area

    Maintenance Facility nearby

    Sub-soil Properties suitable for Required

    Foundation Systems

    Drainage outlet

  • 8/8/2019 Pre Construction Surveys &Clearences

    27/28

    CLEARANCES & PERMITS

    Clearance from State Pollution Control Boards (NOCthrough Public Hearing) Water preservation & Pollution

    Control Act 1974 amended in 1978 & 1988

    Forest clearance under Forest Act, 1980 amended in 1988

    Consent to establish under water and Air Act from State

    PCBs

    Clearance from Mining Authorities (wherever required)

    MOE&F clearance and clearance from Maritime Board &

    CRZ Authorities (wherever applicable)

    NOC from DMs of encountered districts CCE and OISD clearance

    Permits from Railway/ Irrigation/ Highway Authorities

    Clearance from State fire Brigade

    Factory license/ Clearance from Electrical Inspector.

  • 8/8/2019 Pre Construction Surveys &Clearences

    28/28

    Thank You