powerpoint presentation principles... · 2008-11-12 · excavation shotcrete as soon as possible...

48

Upload: others

Post on 28-Mar-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 2: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 3: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 4: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 5: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 6: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 7: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 8: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 9: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 10: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 11: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 12: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 13: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 14: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 15: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no

Tunnel Excavation by Drilling and Blasting

• a. The excavation cycle. The typical cycle of excavation

• by blasting is performed in the following steps:

• (1) Drilling blast holes and loading them with explosives.

• (2) Detonating the blast, followed by ventilation to remove blast fumes.

• (3) Removal of the blasted rock (mucking).

• (4) Scaling crown and walls to remove loosened pieces of rock.

• (5) Installing initial ground support.• (6) Advancing rail, ventilation, and

utilities.

Page 16: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 17: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no

Tunnel Excavation by Mechanical Means

•a. Roadheader excavation.

Page 18: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 19: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no

d. TBM performance parameters.

Page 20: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 21: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 22: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no

Tunneling Design According to Rock Quality

Page 23: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 24: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 25: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 26: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 27: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 28: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 29: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 30: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 31: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 32: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 33: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no

SUPPORTING

Page 34: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 35: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 36: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 37: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 38: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 39: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 40: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 41: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 42: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 43: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 44: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 45: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 46: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 47: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no
Page 48: PowerPoint Presentation principles... · 2008-11-12 · excavation Shotcrete as soon as possible after blasting. Rock bolts (20 mm dlamctcr, ftlly grouted) Steel sets Generally no