po box 65384 323 lynnwood road tel: +27 12 000 2562 ... · po box 65384 erasmusrand 0165 pretoria...
TRANSCRIPT
PO Box 65384 Erasmusrand 0165 Pretoria RSA
323 Lynnwood Road Menlo Park 0181 Pretoria RSA
Tel: +27 12 000 2562 Mobile: +27 73 232 4312 Fax: +27 86 465 2526 Email:
11/12/2019
ATTENTION: STAKEHOLDER/ INTERESTED AND AFFECTED PARTY
Dear Sir/Madam
INVITATION: REVIEW OF A DRAFT AMENDMENT MOTIVATION REPORT AND ATTENDANCE OF
PUBLIC MEETING- TO PART 2 AMENDMENT PROCESS FOR THE PROPOSED AMENDMENT OF AN
EXEMPTION AUTHORISATION FOR THE ASH DISPOSAL FACILITY AT KENDAL POWER STATION,
MPUMALANGA
You are receiving this letter because you have either; [1] being identified as a relevant stakeholder or, [2] you
have registered your interest in the above-mentioned project.
Green Gold Group was appointed as an independent Environmental Assessment Practitioner (EAP) to
facilitate the Part 2 amendment process on behalf of the applicant, Eskom Holdings SOC Ltd. You are
therefore invited to attend a Public Meeting as part of the Public Participation Process (PPP), the details of
the meeting are tabled below.
Meeting Date and Time Tuesday 19 November 2019 at 14:00
Venue Combined Accommodation, Plot 9 Balmoral Road, Kendal (Behind Kuhle premium fuel station)
Contact Person Basetsana Motha
Contact Details Mobile: 071 550 7696 Email: [email protected]
Green Gold Group further encourages you to review the draft Amendment Motivation Report and
accompanying specialist’s studies and submit comments on or before 30 November 2019 at 16:00. Details
of the draft Amendment Motivation Report’s availability are stipulated below:
Hard Copy Venue
Kendal Power Station main gate from 8am to 4pm
Kuhle Premium Fuels Station from 8am to 7pm
Zomhlaba Resources Mine main gate from 8am to 4pm
We Transfer Sharing
Send sharing request by email to [email protected]
Websites
www.greengoldgroup.co.za/Documents.aspx;
https://www.eskom.co.za/OurCompany/SustainableDevelopment/EnvironmentalImpactAssessments/Pages/Environment_Impact_Assessments.aspx
Should you need further clarification, please do not hesitate to contact Basetsana Motha at the contact details
provided above.
We look forward to your active participation.
Regards,
Basetsana Motha
For Green Gold Group
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:28 AM
To: '[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; 'fanniem@legal-
aid.co.za'; '[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
Cc: '[email protected]'
Subject: RE: Public Participation Process: Draft Report - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
From: [email protected] <[email protected]>
Sent: Friday, November 1, 2019 10:21 PM
To: '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>
Cc: '[email protected]' <[email protected]>
2
Subject: Public Participation Process: Draft Report - Amendment of An Exemption Authorisation For Ash Disposal Facility
at Kendal Power Station, Mpumalanga
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the Draft Amendment Motivation Report in the link below for your attention.
https://we.tl/t-owizB0vzrh
Kindly submit your comments and/or concerns to the undersigned by 30 November 2019 at Email:
[email protected] or Postal address: PO Box 65384, Erasmusrand, 0165
Regards,
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:29 AM
To: '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
Cc: '[email protected]'
Subject: RE: Public Participation Process: Draft Report - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
From: [email protected] <[email protected]>
Sent: Friday, November 1, 2019 10:29 PM
To: '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>
Cc: '[email protected]' <[email protected]>
Subject: Public Participation Process: Draft Report - Amendment of An Exemption Authorisation For Ash Disposal Facility
at Kendal Power Station, Mpumalanga
Dear Stakeholder
2
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the Draft Amendment Motivation Report in the link below for your attention.
https://we.tl/t-owizB0vzrh
Kindly submit your comments and/or concerns to the undersigned by 30 November 2019 at Email:
[email protected] or Postal address: PO Box 65384, Erasmusrand, 0165
Regards,
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:30 AM
To: '[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'
Cc: '[email protected]'
Subject: RE: Public Participation Process: Draft Report - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
From: [email protected] <[email protected]>
Sent: Friday, November 1, 2019 10:33 PM
To: '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>
Cc: '[email protected]' <[email protected]>
2
Subject: Public Participation Process: Draft Report - Amendment of An Exemption Authorisation For Ash Disposal Facility
at Kendal Power Station, Mpumalanga
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the Draft Amendment Motivation Report in the link below for your attention.
https://we.tl/t-owizB0vzrh
Kindly submit your comments and/or concerns to the undersigned by 30 November 2019 at Email:
[email protected] or Postal address: PO Box 65384, Erasmusrand, 0165
Regards,
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:31 AM
To: '[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]'; 'health2
@webmail.co.za'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; 'chrisvoigt8
@gmail.com'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'
Cc: '[email protected]'
Subject: RE: Public Participation Process: Draft Report - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
From: [email protected] <[email protected]>
Sent: Friday, November 1, 2019 10:40 PM
To: '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
2
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>
Cc: '[email protected]' <[email protected]>
Subject: Public Participation Process: Draft Report - Amendment of An Exemption Authorisation For Ash Disposal Facility
at Kendal Power Station, Mpumalanga
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the Draft Amendment Motivation Report in the link below for your attention.
https://we.tl/t-owizB0vzrh
Kindly submit your comments and/or concerns to the undersigned by 30 November 2019 at Email:
[email protected] or Postal address: PO Box 65384, Erasmusrand, 0165
Regards,
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:32 AM
To: '[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]'
Cc: '[email protected]'
Subject: RE: Public Participation Process: Draft Report - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
From: [email protected] <[email protected]>
Sent: Friday, November 1, 2019 10:46 PM
To: '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
2
Cc: '[email protected]' <[email protected]>
Subject: Public Participation Process: Draft Report - Amendment of An Exemption Authorisation For Ash Disposal Facility
at Kendal Power Station, Mpumalanga
Dear
Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the Draft Amendment Motivation Report in the link below for your attention.
https://we.tl/t-owizB0vzrh
Kindly submit your comments and/or concerns to the undersigned by 30 November 2019 at Email:
[email protected] or Postal address: PO Box 65384, Erasmusrand, 0165
Regards,
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:37 AM
To: '[email protected]'; '[email protected]'; '[email protected]'
Cc: '[email protected]'
Subject: RE: Public Participation Process: Draft Report - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
From: [email protected] <[email protected]>
Sent: Friday, November 1, 2019 11:13 PM
To: '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
Cc: '[email protected]' <[email protected]>
Subject: Public Participation Process: Draft Report - Amendment of An Exemption Authorisation For Ash Disposal Facility
at Kendal Power Station, Mpumalanga
Dear
Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the Draft Amendment Motivation Report in the link below for your attention.
https://we.tl/t-owizB0vzrh
Kindly submit your comments and/or concerns to the undersigned by 30 November 2019 at Email:
[email protected] or Postal address: PO Box 65384, Erasmusrand, 0165
Regards,
2
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:37 AM
To: '[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]'; 'hbooyse5
@gmail.com'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
Cc: '[email protected]'
Subject: RE: Public Participation Process: Draft Report - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
From: [email protected] <[email protected]>
Sent: Friday, November 1, 2019 11:11 PM
To: '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
Cc: '[email protected]' <[email protected]>
Subject: Public Participation Process: Draft Report - Amendment of An Exemption Authorisation For Ash Disposal Facility
at Kendal Power Station, Mpumalanga
2
Dear
Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the Draft Amendment Motivation Report in the link below for your attention.
https://we.tl/t-owizB0vzrh
Kindly submit your comments and/or concerns to the undersigned by 30 November 2019 at Email:
[email protected] or Postal address: PO Box 65384, Erasmusrand, 0165
Regards,
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:37 AM
To: '[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]'; 'vvuurej2
@telkom.co.za'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]'; '[email protected]';
Cc: '[email protected]'
Subject: RE: Public Participation Process: Draft Report - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
From: [email protected] <[email protected]>
Sent: Friday, November 1, 2019 11:07 PM
To: '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
2
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>
Cc: '[email protected]' <[email protected]>
Subject: Public Participation Process: Draft Report - Amendment of An Exemption Authorisation For Ash Disposal Facility
at Kendal Power Station, Mpumalanga
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the Draft Amendment Motivation Report in the link below for your attention.
https://we.tl/t-owizB0vzrh
Kindly submit your comments and/or concerns to the undersigned by 30 November 2019 at Email:
[email protected] or Postal address: PO Box 65384, Erasmusrand, 0165
Regards,
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:37 AM
To: '[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]'; 'andre.cherry3
@gmail.com'; '[email protected]'; '[email protected]'; 'rstrydom32
@gmail.com'; '[email protected]'; '[email protected]'; 'za';
'[email protected]'; '[email protected]'; '[email protected]'; 'dcat9
@tiscali.co.za'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]'; 'a321
@lantic.net'; '[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'
Cc: '[email protected]'
Subject: RE: Public Participation Process: Draft Report - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
From: [email protected] <[email protected]>
Sent: Friday, November 1, 2019 10:55 PM
To: '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
2
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>; 'za'
<[email protected].>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>
Cc: '[email protected]' <[email protected]>
Subject: Public Participation Process: Draft Report - Amendment of An Exemption Authorisation For Ash Disposal Facility
at Kendal Power Station, Mpumalanga
Dear
Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project.
Please find the Draft Amendment Motivation Report in the link below for your attention.
https://we.tl/t-owizB0vzrh
Kindly submit your comments and/or concerns to the undersigned by 30 November 2019 at Email:
[email protected] or Postal address: PO Box 65384, Erasmusrand, 0165
Regards,
3
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:44 AM
To: '[email protected]'
Cc: '[email protected]'
Subject: RE: Public Participation Process: Draft Report - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
From: [email protected] <[email protected]>
Sent: Friday, November 1, 2019 11:15 PM
To: '[email protected]' <[email protected]>
Cc: '[email protected]' <[email protected]>
Subject: Public Participation Process: Draft Report - Amendment of An Exemption Authorisation For Ash Disposal Facility
at Kendal Power Station, Mpumalanga
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the Draft Amendment Motivation Report in the link below for your attention.
https://we.tl/t-owizB0vzrh
Kindly submit your comments and/or concerns to the undersigned by 30 November 2019 at Email:
[email protected] or Postal address: PO Box 65384, Erasmusrand, 0165
Regards,
2
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:44 AM
To: '[email protected]'; '[email protected]'
Cc: '[email protected]'; '[email protected]'
Subject: Public Participation Process: Public Meeting Invitation - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Ward Councilor
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:44 AM
To: '[email protected]'
Cc: '[email protected]'
Subject: RE: Public Participation Process: Draft Report - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
From: [email protected] <[email protected]>
Sent: Monday, November 4, 2019 4:01 PM
To: '[email protected]' <[email protected]>
Cc: '[email protected]' <[email protected]>
Subject: Public Participation Process: Draft Report - Amendment of An Exemption Authorisation For Ash Disposal Facility
at Kendal Power Station, Mpumalanga
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the Draft Amendment Motivation Report within the link below for your attention.
https://we.tl/t-owizB0vzrh
Kindly submit your comments and/or concerns to the undersigned by 30 November 2019 at Email:
[email protected] or Postal address: PO Box 65384, Erasmusrand, 0165
Regards,
2
1
From: [email protected]
Sent: Wednesday, November 13, 2019 9:44 AM
To: '[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'; '[email protected]';
'[email protected]'; '[email protected]'
Cc: '[email protected]'
Subject: RE: Public Participation Process: Draft Report - Amendment of An Exemption
Authorisation For Ash Disposal Facility at Kendal Power Station, Mpumalanga
Attachments: Invitation letter- Public Meeting.pdf
Dear Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the attached invitation letter to the Public Meeting for your attention.
Kind regards
From: [email protected] <[email protected]>
Sent: Friday, November 1, 2019 11:01 PM
To: '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
2
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]'
<[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>; '[email protected]' <[email protected]>;
'[email protected]' <[email protected]>
Cc: '[email protected]' <[email protected]>
Subject: Public Participation Process: Draft Report - Amendment of An Exemption Authorisation For Ash Disposal Facility
at Kendal Power Station, Mpumalanga
Dear
Stakeholder
We at Green Gold Group (Pty) Ltd, kindly invite you to participate in the Part 2 Amendment Process for the above-
mentioned project
Please find the Draft Amendment Motivation Report in the link below for your attention.
https://we.tl/t-owizB0vzrh
Kindly submit your comments and/or concerns to the undersigned by 30 November 2019 at Email:
[email protected] or Postal address: PO Box 65384, Erasmusrand, 0165
Regards,