    Operation Manual of ADMA

    Planned Maintenance Syste(Headquarters System)

    CAUTION

    THIS DRAWING IS THE PROPERTY OF IHIMARINE CO.,LTD., AND AS SUCH CLAIMS

    TREATMENT AS A CONFIDENTIAL DOCUMENT.REPRODUCTION, COPYING, TRACING,

    UTILIZATION FOR PURPOSES OTHER THAN AGREED, DISCLOSURE TO A THIRD PARTY,

     ARE STRICTLY SUBJECT TO PRIOR WRITTEN AGREEMENT BY IMC.

     ABC Marine Co., LTD.

      M X M X

    Planned Maintenance System

  • 8/18/2019 Pms(Hqs) Manual

    2/35

  • 8/18/2019 Pms(Hqs) Manual

    3/35

    IHI Marine Co., Ltd.

    INDEX

    1. System Outline

    1.1 Main Function

    1.2 Basic Operational Flow

    2. System Start/Stop

    3. Screen Description

    3.1 [Menu] screen

    3.2 [Long Term Plan] screen3.3 [Short Term Plan] screen

    3.4 [Work History] screen

    3.5 [Equipment Run Hrs] screen

    4. Data Import / Export

    4.1 Data Import

    4.2 Data Export

    5. Approval of Long Term Plan6. Input of Company's Comments

    7. Confirmation of Work Report

    8. Review Equipment Run Hour 

    9. Modification of Maintenance Item Data

    10. Setting of User Authority and Password

    11. Setting of Controls

    12 Database Backup / Restore

  • 8/18/2019 Pms(Hqs) Manual

    4/35

    Output Sample

    Long Term Plan

    Short Term Plan

    Work Procedure

    Work Report (Repair & Maintenance)

    Work Report (Trouble)Equipment Running Hour 

    IHI Marine Co., Ltd.

  • 8/18/2019 Pms(Hqs) Manual

    5/35

    1. System Outline

    IHI Marine Co., Ltd.

    This system facilitates the maintenance management for onboard machinery. There are major functio

    schedule, reporting of maintenance/repair work and data export/import etc. It consists of Headquarte

    installed on the ships managed under this system. Moreover, the user are restricted for each function

    -Update

    S

    S

    S

    SInput Company's Comment

    Confirmation

    Equipment Run Hour 

    -CheckShort Term Plan

    - Approval

     Approval

    -UpdateLong Term Plan

    -InputWork Report

    Confirmation

    HeadquarterFunctionItem

    1.1 Main Function User :  Administrator Approval  A B

    B

    C

    B

    C

  • 8/18/2019 Pms(Hqs) Manual

    6/35

    IHI Marine Co., Ltd.

    1.2 Basic Operational Flow

    Data Import

    (Sec.4.10)

    Headquarters

    Sending of export data to

    Headquarters via E-mail

    First of every month

    User :  Administrator  A B

    Input of Company's Comments

    (Sec.6 P.13)

    C

     Approval of Long Term Plan

    (Sec.5 P.12)

    B

    C

    Long Term Plan

    Screen

    Data Export

    (Sec.4 P.11)

    D

    Work History

    Screen

    Work History

    Screen

    - Che

    - Rep

    - Inp

    App

  • 8/18/2019 Pms(Hqs) Manual

    7/35

    IHI Marine Co. Ltd.

    XGA (1024 x 768) or higher-resolution monitor with 25Monitor50MB (Depend on Package software number and kindsFree hard-disk space

    128MB (256MB recommended)RAM

    Windows98SE/2000/XPOS

    IBM PC/AT compatible with Intel Pentium II processorPC

    The system requirement is as follows.

    1.3 System requirement

    1.4 About the version up of program

  • 8/18/2019 Pms(Hqs) Manual

    8/35

    1. On the MS-Windows Desktop screen, double-click "ADMAX"folder and “Planned Maintenance System" icon in that folder.

    .

    2. ”Password Input Dialog”(Fig.2-1) is displayed.Enter password and press [Enter] key.

     As default set, “MAN" Manager) for administrator authority is

    registered. Please change user authority and password before

    actual operation.

     As for user authority and password, refer to Section 10(P.17).

    "Guidance Dialog”(Fig.2-2) is displayed.

    3. Confirm your login name and authority.

    4. If you want to skip "Guidance Dialog” at next time, put checkmark on the check box of ④.

    Fig.2-2 Guidance DialogIHI Marine Co., Ltd.

    5. Select [Close] button.

    ”PMS Main Screen”(Fig.2-3)

    6. If you want to end the system

    button of right upper corner.

    2. System Start / Stop

    Fig.2-3 PMS Main Screen

    Fig.2-1 Password Input Dialog

  • 8/18/2019 Pms(Hqs) Manual

    9/35

    Ship List

    Workflow

    IHI Marine Co., Ltd.

    3. Screen Description

    Fig.3-1 PMS Main Screen3.1 [Menu] screen Department

    Menu

  • 8/18/2019 Pms(Hqs) Manual

    10/35

    Maintenance

    Item Data

    Fig.3-2 Long Term Plan Screen

    Menu

    Calendar view stile

    Operation button

    IHI Marine Co., Ltd.

    3.2 [Long Term Plan] screen

    (1) CODE : Equipment code and

    (2) ITEM : Maintenance item

    (3) PIC : Person In Charge

    (Deck:D0-D9, Engin(4) SMS : Safety Management

    (A-N, P-U)

    (5) D/S/L : Worker (D: Dry Dock

    (6) INTERVAL : Interval and Unit of m

    H (Hour), M (Month)

    (7) LAST : Last completion date

    (8) DUE : Due date ("LAST"+"

    (9) OVER DUE O D (DUE

  • 8/18/2019 Pms(Hqs) Manual

    11/35

    Calculation Method for "DUE DATE" of running hour based maintenance

    I : Interval (H)

    Ld : Last DateLh : Total Run Hrs at Last Date (H)

    Ud : Latest Update Date of Total Run Hrs (H)

    Uh : Total Run Hrs at Latest Update Date

     Ave : Averaged Run Hrs per Month (H)

    Dd : Due Date

    Ld

    Lh

    I/Ave

    Ld

    Lh

    Ud, Uh

    (I-(Uh-Lh))/

    Case 3: Ld<Ud & Lh>=Uh

    Case 2: Ld<Ud & Lh<Uh & I>(Uh-Lh)

    Case 1: Ld<Ud & Lh<Uh & I<=(Uh-Lh)

    Ld

    Lh

    Ud, Uh

    I/Ave

  • 8/18/2019 Pms(Hqs) Manual

    12/35

    Maintenance

    Item Data

    IHI Marine Co., Ltd.

    Fig.3-3 Short Term Plan Screen

    3.3 [Short Term Plan] screen

    Menu

    Displayed data view stile

    Operation button

    (1) CODE : Equipment code and

    (2) ITEM : Maintenance item

    (3) PIC : Person In Charge

    (Deck:D0-D9, Engin(4) SMS : Safety Management

    (A-N, P-U)

    (5) D/S/L : Worker (D: Dry Dock

    (6) INTERVAL : Interval and Unit of m

    H (Hour), M (Month)

    (7) LAST : Last work date

    (8) DUE : Due date ("LAST"+"

    (9) OVER DUE O D (DUE

  • 8/18/2019 Pms(Hqs) Manual

    13/35

    Work History

    Data

    IHI Marine Co., Ltd.

    Fig.3-4 Work History Screen

    3.4 [Work History] screen

    Menu

    Operation button

    (1) CODE : Equipment code and

    (2) ITEM : Maintenance item

    (3) PIC : Person In Charge

    (Deck:D0-D9, Engin(4) SMS : Safety Management

    (A-N, P-U)

    (5) WORK DATE : Worker (D: Dry Doc

    (6) FILE NO : Interval and Unit of m

    H (Hour), M (Month)

    (7) VOY NO : Last work date

    (8) DR : Docking Repair  

    (9) PR P di f R i

  • 8/18/2019 Pms(Hqs) Manual

    14/35

    Equipment List

    IHI Marine Co., Ltd.

    Fig.3-5 Equipment Run Hrs Screen

    3.5 [Equipment Run Hrs] screen

    Menu

    Operation button

    Update date of total runnin

    (1) CODE : Equipment code(2) EQUIPMENT : Equipment name

    (3) RUN HOURS PER MONTH :

     Ave = Uh / ( (Ud - Sd) / 30.5 )

    (4) TOTAL RUN HOURS :

    Total Run Hrs at Update Date

    (5) EXPECTED RUN HOURS PER MON

    E t d R H M th

  • 8/18/2019 Pms(Hqs) Manual

    15/35

    "Long Term Plan" and "Work Report" shall be approved or confirmed

    by Headquarters' responsible person regularly.

    For that purpose, when receive the reported data from each ship and

    import those data.

    1. On the “PMS Main Screen”(Fig.4-1), select [Data Import].

    "Open File Screen"(Fig.4-2) is displayed.

    4. Data Import / Export

    Fig.4-1 PMS Main Screen

    IHI Marine Co., Ltd.

    Fig.4-2 Open File Screen

    2. Select file for import. Then, sele

    File name is decided by your co

    Standard file name of our systePMS_SBS_aaa_yymmdd-m

    aaa: Ship code

    yymmdd-mmdd: Export p

    3. Select [OK] at completion mess

    4. Import history is recorded on "Im

    4.1 Data Import

  • 8/18/2019 Pms(Hqs) Manual

    16/35

    "Long Term Plan" and "Work Report" shall be approved or confirmedby Headquarters' responsible person regularly. This information shall be

    informed to the ship.

    For that purpose, please export data and send to the subject ship.

    1. On the “PMS Main Screen”(Fig.4-3), select [Data Export].

    "Export Period Dialog" is displayed.

    2. Enter export period or select from calendar by [▼]button.Then, select [OK] button.

    "Save File Screen"(Fig.10-2) is displayed.

    Fig.4-3 PMS Main Screen

    IHI Marine Co., Ltd.

    Fig.4-4 Save File Screen

    3. Select folder for saving export

    File name is given as below.

    PMS_HQS_aaa_yymmdd-

    aaa: Ship code

    yymmdd-mmdd: Export

    Modify file name if necessary.

    4. Select [OK] at completion mes

    5. Export history is recorded on "

    6. Send export file to the subject

    4.2 Data Export

    ⑤ Over Due Rate

  • 8/18/2019 Pms(Hqs) Manual

    17/35

    "Long Term Plan" shall be approved by Headquarters' responsible

    person regularly according to the following step.

    1. On the “PMS Main Screen”(Fig.5-1), select [Approve Long Term Plan].

    "Long Term Plan Screen"(Fig.5-2) is displayed.

     At that time, [Approve Plan] button is blinked several times for your 

    guidance of next operation.

    2. Check situation of "Long Term Plan".

    3. Screen scrolling can be made by each scroll bars.4. If you select option button of "View", displayed calendar is changed

    for "1 Year" or "5 Years".

    5. If you select [Menu] button, screen is returned to "PMS Main Screen".

    5. Approval of Long Term Plan

    Fig.5-1 PMS Main Screen

    IHI Marine Co., Ltd.

    Fig.5-2 Long Term Plan Sc

    6. If calculated "Due Date" is alre

    Term Plan", Over Due mark"*"

    Over Due => Due Date < U

  • 8/18/2019 Pms(Hqs) Manual

    18/35

    "Work Report" shall be confirmed by Headquarters' responsible

    person regularly. And then, input company's comments according

    to the following step, if necessary.

    1. On the “PMS Main Screen”(Fig.6-1), select [Input Company's

    Comment]. "Work History Screen"(Fig.6-2) is displayed.

     At that time, [Modify] button is blinked several times for your 

    guidance of next operation.

    2. Select maintenance wok item and [Modify] button.“Work Report Screen”(Fig.6-3) is displayed.

    3. Enter Company's Comments. Then, select [Save].

    4. Select [Close].

    5. If you select [Menu] button, screen is returned to "PMS Main

    Screen".

    6. Input of Company's Comment

    Fig.6-1 PMS Main Screen

    IHI Marine Co., Ltd. Fig.6-2 Work History Scree

    Fig.6-3 Work Report Scree

  • 8/18/2019 Pms(Hqs) Manual

    19/35

    "Work Report" shall be confirmed by Headquarters' responsible person

    regularly according to the following step.

    1. On the “PMS Main Screen”(Fig.7-1), select [Confirm Work Report].

    "Work History Screen"(Fig.7-2) is displayed.

     At that time, note is blinked several times for your guidance of next

    operation.

    2. Select item and [Detail Work Report] button.

    "Work Report Screen"(Fig7-3) is displayed.3. Confirm detail work report. Then, [Close] button.

    4. Select check box of maintenance item to be confirmed.

    Check mark is put on check box for confirmation.

    If you select same check box again, check mark is taken off.

    5. If you select [Confirm All] button, check marks of all report are put

    on the block.

    7. Confirmation of Work Report

    Fig.7-1 PMS Main Screen

    IHI Marine Co., Ltd.Fig.7-2 Work History Scree

    Fig.7-3 Work Report Scree

    6. If you select [Menu] button

    Screen".

  • 8/18/2019 Pms(Hqs) Manual

    20/35

    1. On the “PMS Main Screen”(Fig.8-1), select [Equipment Run Hrs] tab."Equipment Run Hrs Screen"(Fig.8-2) is displayed.

    2. Review total running hour and actual running hour per month.

    "Equipment Running Hour" can be updated only Shipboard System.

    3. The actual average value of run hour per month are calculated

    according to the following formula for your reference.

    Run hour per month =Total run hour / (Update date - Ship's delivery date) x 30.5

    4. If you select [Menu] button, screen is returned to "PMS Main Screen".

    8. Review of Equipment Run Hour 

    Fig.8-1 PMS Main Screen

    IHI Marine Co., Ltd.

    Fig.8-2 Equipment Run Hr

  • 8/18/2019 Pms(Hqs) Manual

    21/35

    "Maintenance Item Data" can be modified only by Shipboard System.However, only SMS category can be modified by Headquarters System.

    Please modify according to the following step if necessary.

    1. On the “PMS Main Screen”(Fig.9-1), select [Long Term Plan] tab.

    "Long Term Plan Screen"(Fig.9-2) is displayed.

    2. Select [SMS] button.

    "SMS Dialog" is displayed.3. SMS codes are preset as A~N and P~U (total 20 codes).User can change only category name.

    Select [Modify] button. Then, enter category name.

    9. Modification of Maintenance Item Data

    Fig.9-1 PMS Main Screen

    IHI Marine Co., Ltd.

    Fig.9-2 Long Term Plan Sc

    4. Select [Save] button.

    5. Select [Close] button..

  • 8/18/2019 Pms(Hqs) Manual

    22/35

    "User Authority and Password" can be set for each user.Management of password only can be performed by the user 

    who has administrator authority. Other users can't select

    [Password Change] button.

    1. Select [Password Change] button on the "PMS Initial Screen"

    (Fig.10-1).

    “Password Control Dialog"(Fig.10-2) is displayed.

    10. Setting of User Authority and Password

    Fig.10-2 Password Cha

    Fig.10-1 PMS Initial Screen

    ① 2. Select [Modify] button.

    3 Ch "P d" "N

    IHI Marine Co., Ltd.

  • 8/18/2019 Pms(Hqs) Manual

    23/35

    "Various Controls" can be set by the user who has administrator or approve authority. Other users can't select [Control Change]

    button.

    1. Select [Control Change] button on the "PMS Initial Screen"

    (Fig.11-1).

    “Control Dialog"(Fig.11-2) is displayed.

    11. Setting of ControlsFig.11-2 Controls Dialo

    Fig.11-1 PMS Initial Screen

    2. Select various setting for t

    - Guidance View

    Sh T Ti l

    IHI Marine Co., Ltd.

  • 8/18/2019 Pms(Hqs) Manual

    24/35

    IHI Marine Co., Ltd.

    12. Database Backup / Restore

    1. Select [Database Backup & Restore] button on the "PMS

    Initial Screen"(Fig.12-1).

    “Backup & Restore Dialog"(Fig.12-2) is displayed.

    Fig.12-1 PMS Initial Screen

    12.1 Database Backup

    If the PC using ADMAX is troubled, the PC must be repaired or renewed. In such case, it's impossible to recover the database in

    the hard disk. Therefore, we recommend that you should take

    database backup into outside media (MO, CD, DVD etc.)

    periodically.The database in the install CD is a only initial database. Therefore,

    the database can’t be recovered for operational data.

    Fig.12-2 Backup & Restore

    2. [Database Backup] tab is

    S

  • 8/18/2019 Pms(Hqs) Manual

    25/35

    IHI Marine Co., Ltd.

    1. Before restore operation, PC shall be repaired or renewed. And, ADMAX PMS shall be installed.

    Then, database backup file shall be copied into proper folder on

    the PC.

    2. Select [Database Backup & Restore] button on the "PMS

    Initial Screen"(Fig.12-3).

    “Backup & Restore Dialog"(Fig.12-4) is displayed.

    Fig.12-3 PMS Initial Screen

    12.2 Database Restore

    Fig.12-4 Backup & Restore

    3. Select [Database Restore

  • 8/18/2019 Pms(Hqs) Manual

    26/35

    IHI Marine Co., Ltd.

    13. Common Utility Functions

    Fig.13-1 Long Term Plan Screen

    Fig.13-2 Long Term Plan Sc

    On the “Long Term Plan Screen”, "Short Term Plan Screen" and

    "Work History Screen", "Code Search" function can be used for 

    searching objective data easily.

    1. Select [Code Search] button on the “Long Term Plan Screen”

    (Fig.13-1).

    2. Select [+]mark of equipment and maintenance item data.

    Then, select [Ok].

    3. Selected data is displayed on top of data list.

    13.1 Code Search Function

  • 8/18/2019 Pms(Hqs) Manual

    27/35

    On the “Long Term Plan Screen”, "Short Term Plan Screen" and

    "Work History Screen", "Filter" function can be used for extracting

    by setting of extraction conditions.

    1. Select [Filter] button on the “Long Term Plan Screen”(Fig.13-3).

    2. Select or enter extracting conditions.

    Then, select [Ok].

    Multiple extracting conditions can be set at the same time.3. Extracted data are displayed.

    Fig.15-4 Long Term Plan S

    Fig.13-3 Long Term Plan Screen①

    IHI Marine Co., Ltd.

    (1) Code : Equipment cod

    (2) Item : Maintenance it

    (3) Interval : Maintenance in

    (4) Unit : Unit for mainte

    H (Run Hour),

    13.2 Filter Function

  • 8/18/2019 Pms(Hqs) Manual

    28/35

    IHI Marine Co., Ltd.

    Fig.13-5 Work History Screen①

    On the "Work History Screen", "Sort" function can be used for 

    sorting of work history data.

    1. Select [Sort] button on the “Work History Screen”(Fig.13-5).

    2. Select sort key and sort order of "Ascend" or "Descend".

    Then, select [Ok].

    Sort keys can be set up to 3rd priority at the same time.

    3. Sorted data are displayed.

    13.3 Sort Function

  • 8/18/2019 Pms(Hqs) Manual

    29/35

    IHI Marine Co., Ltd.

    14. Appendix of Managed Ship

    Fig.14-1 PMS Initial Screen ②

    Fig.14-2 PMS Initial Screen

    4. If you want to modify ship

    Modify ship list data, then

    5. If you want to delete ship l

    [Delete] button. Then, sele

    If you want to append the new managed ship into ADMAX PMS(HQS), database for subject ship should be made and set into

    proper database folder on your PC by IMC.

     As for the detail, please contact to IMC.

    1. Set database for new managed ship. (by IMC)

    2. Select [Append] button on the "PMS Initial Screen"(Fig.14-1).

    New record is appended on ship list.

    3. Enter "SHIP NAME", "CODE" and "DELIVERY".

    Then, select [Save] button.

  • 8/18/2019 Pms(Hqs) Manual

    30/35

    Updated by on

     Approved by on

    Captain 2007/01/29

    CODE PIC SMS D/S/L INTERVAL LAST DUE'07Jan

     __ Feb

     __ Mar 

    '07 Apl

     __ May

     __ Jun

    '07Jul

     __  Aug

     __ Sep

    '07Oct

     __ Nov

     _ Dec

    Work comletion date O Due date * Over dueLong Term Plan (1 Year)   n

    ITEM

    E100Z 000 XXEMain Engine

    E100Z 010 CE 1 M 05/07/08 05/08/08 *   n O O O O O O O O O O OM/E General Condition check

    E100Z 020 E 12 M 05/07/08 06/07/08 * OM/E Bed Check Foundation Bolt

    E100Z 030 E 12 M 05/07/08 06/07/08 * OM/E Frame Check Tie Rod & Bolt

    E100Z 040 E 700 H 05/07/08 05/07/08 *M/E Crankcase Check Inside of Crankcase

    E100Z 050 E 6 M 05/07/08 06/01/08 * O OM/E Crankcase Measurement of Crank Deflection

    E100Z 060 E 700 H 05/07/08 05/07/08 *M/E Crankcase Check Tim'g Gear 

    E100Z 07A E 700 H 05/07/08 05/07/08 *M/E #1 Piston Check Piston Ring

    E100Z 07B E 700 H 05/07/08 05/07/08 *M/E #2 Piston Check Piston Ring

    E100Z 07C E 700 H 05/07/08 05/07/08 *M/E #3 Piston Check Piston Ring

    E100Z 07D E 700 H 05/07/08 05/07/08 *M/E #4 Piston Check Piston Ring

    E100Z 07E E 700 H 05/07/08 05/07/08 *M/E #5 Piston Check Piston Ring

    E100Z 07F E 700 H 05/07/08 05/07/08 *M/E #6 Piston Check Piston Ring

    E100Z 07G E 700 H 05/07/08 05/07/08 *M/E #7 Piston Check Piston Ring

    Demo System (Exp.date:2007/7/31)

    Date:2007/01/29

     ADMAX2000

    IHI-MARU (Engine)

    - 26  -

  • 8/18/2019 Pms(Hqs) Manual

    31/35

    E100Z

    010

    E

    C

    1

    M

    07/01/29

    07/02/28  nM/E General Condition check

    E100Z

    300

    E

    B

    1

    M

    05/07/08

    05/08/08 * OM/E Protection Equip. Operation Test

    E100Z

    310

    E 1

    M

    05/07/08

    05/08/08* OM/E Over Speed Device

    E100Z

    320

    E 1

    M

    05/07/08

    05/08/08* OM/E Auto-stop & Alarm LO Supply or Press Drop

    E100Z

    330

    E 1

    M

    05/07/08

    05/08/08* OM/E Other Safety Device

    E200Z

    010

    E

    C

    1

    M

    05/07/08

    05/08/08* OShafting General Condition Check

    F100Z

    090

    E 1

    W

    05/07/08

    05/07/15* O O O O O Aux. Boiler Water Gauge Blow

    F100Z

    100

    E 1

    M

    05/07/08

    05/08/08* O Aux. Boiler Protection Equip. Operation Test & Adjustment

    G100A

    010

    E

    C

    1

    M

    05/07/08

    05/08/08* O#1 G/E General Condition Check

    G100A

    230

    E 1

    M

    05/07/08

    05/08/08* O#1 G/E Protection Equipment Operation Test & Adjustment

    G100B

    010

    E

    C

    1

    M

    05/07/08

    05/08/08* O#2 G/E General Condition Check

    G100B

    230

    E 1

    M

    05/07/08

    05/08/08* O#2 G/E Protection Equipment Operation Test & Adjustment

    G100C010

    EC

    1M

    05/07/0805/08/08

    * O#3 G/E General Condition Check

    G100C

    230

    E 1

    M

    05/07/08

    05/08/08* O#3 G/E Protection Equipment Operation Test & Adjustment

    G400Z

    010

    E

    C

    1

    M

    05/07/08

    05/08/08* OEm'cy G/E. Operation Test & Battery Check

    H200A

    050

    E 1

    M

    05/07/08

    05/08/08* O#1 FO Purifier Bowl Overhaul

    CODEPIC

    SMSD/S/L

    Demo System (Exp.date:2007/7/31)

    Date:2007/01/29

     ADMAX2000

    IHI-MARU (Engine)

    Period:

    INTERVAL

    LAST

    DUEJan1

     ___ 2

     ___ 3

     ___ 4

     ___ 5

     ___ 6

     ___ 7

     ___ 8

     ___ 9

     ___ 10

     ___ 11

     ___ 12

     ___ 13

     ___ 14

     ___ 15

     ___ 16

     ___ 17

     ___ 18

     ___ 19

     ___ 20

     ___ 21

     ___ 22

     ___ 23

     ___ 24

     ___ 25

     ___ 26

     ___ 27

     ___ 28

     ___ 29

     ___ 30

     ___ 31

    2007/01/01 - 2007/01/31

    Short Term Plan (Monthly Plan)Work completion date O Due date which is corresponding to DUE column * Over Duen

    ITEM

    - 27  -

    D S t (E d t 2007/7/31)ADMAX2000

  • 8/18/2019 Pms(Hqs) Manual

    32/35

    Code E100Z010 Item M/E General Condition check

    Interval 1M PIC SMSE C Worker Dry Dock Ship's Crew Port Helper  

    Work Procedure

    Demo System (Exp.date:2007/7/31)Date:2007/01/29

     ADMAX2000

    IHI-MARU (Engine)

    Work Procedure

    - 28  -

    D S t (E d t 2007/7/31)ADMAX2000

  • 8/18/2019 Pms(Hqs) Manual

    33/35

    Work Report (Repair & Maintenance)

    Place

    Machinery Name

    Trouble Parts(Maker / Model)

    Trouble Point

    Outline of Trouble

    Ship's Comments &Desired Articles

    Ship's Hand Working Hours 0.0 Ship's Hand Nos Working Member 0

    Company's Comments

    Item M/E General Condition check

    Total Run Hours 0

    Reported by Approved by Comfirmed byCaptain

    Code E100Z010 PIC E SMS C Reported Date Work Date2007/01/29 2007/01/29

    File No. Voy. No.

    Demo System (Exp.date:2007/7/31)

    Date:2007/01/29

     ADMAX2000

    IHI-MARU (Engine)

    - 29  -

    Demo System (Exp date:2007/7/31)ADMAX2000

  • 8/18/2019 Pms(Hqs) Manual

    34/35

    Work Report (Trouble)

    Reported by Approved by Comfirmed byCaptain

    Place

    Machinery / Place

    Reason

    M/E Stop Hours 0.0

    M/E Speed Reduction Hours 0.0

    Delay Hours for Repair 0.0

    Cargo Work Delay Hours 0.0

    Outline of Trouble

    Presumed Cause

    Countermeasures &Disposal

    Ship's Comments &Desired Articles

    Ship's Hand Working Hours 0.0

    Ship's Hand Nos Working Member 0

    Repair by Ship's Hand. Repair by Shore

    Docking Repair Pending for Repair  

    Company's Comments

    Code E100Z010 PIC E SMS C Reported Date Work Date2007/01/29 2007/01/29

    Item M/E General Condition check

    File No. Voy. No. Total Run Hours 0

    Demo System (Exp.date:2007/7/31)

    Date:2007/01/29

     ADMAX2000

    IHI-MARU (Engine)

    - 30  -

    Demo System (Exp date:2007/7/31)ADMAX2000

  • 8/18/2019 Pms(Hqs) Manual

    35/35

    E100Z Main Engine 0 0 0

    F100Z Aux. Boiler 0 0 0

    G100A #1 G/E 0 0 0

    G100B #2 G/E 0 0 0

    G100C #3 G/E 0 0 0

    H200A #1 FO Purifier 0 0 0

    H200B #2 FO Purifier 0 0 0

    H230Z LO Purifier 0 0 0

    H240Z G/E LO Purifier 0 0 0

    H408A #1 G/E Air Cooler 0 0 0

    H408B #2 G/E Air Cooler 0 0 0

    H408C #3 G/E Air Cooler 0 0 0

    H424A #1 M/E FO Heater 0 0 0

    H424B #2 M/E FO Heater 0 0 0

    H428A #1 G/E FO Heater 0 0 0

    H428B #2 G/E FO Heater 0 0 0

    H430A #1 Purifier FO Heater 0 0 0

    H430B #2 Purifier FO Heater 0 0 0

    H520Z Incinerator 0 0 0

    CODE EQUIPMENT

    Total Run Hours Update on: 2005/07/08

    Demo System (Exp.date:2007/7/31)

    Date:2007/01/29

     ADMAX2000

    IHI-MARU (Engine)

    Equipment Running Hour 

    From SHIP'S DELIVERY

      RUN HOURSPER MONTH

    TOTAL RUNHOURS

    EXPECTED RUNHOURS PER

    MONTH

    31