plc phases: overview - mpc

31
1

Upload: others

Post on 17-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PLC Phases: Overview - MPC

1

Page 2: PLC Phases: Overview - MPC

PLC Phases: Overview

2

Exploration

Program Termination

Approval (PTA)

Concept

Approval

(CA)

Development

Investment

Approval

(DIA)

Implementation

Plan Approval

(IPA)

Approval

Meetings:Product

Readiness

Approval

(PRA)

Ship

Release

Approval

(SRA)

Product

Readiness

Review

(PRR)

PDT

Postmortem

Product

Documents

and Reviews:

Product

Requirements

Document or

Statement of

Work

(PRD/SOW)

Project

Management

Plan

(PMP)Technical

Product

Specification

(TPS)

Product

Discontinuance

Approval

(PDA)

Planning ProductionDevelopmentExploration

Market

Segment

Analysis

(MSA)

Business

Inputs:

Business

Requirements

Document

(BRD)

Mid-Point

Review

(MPR)

Product

Certification

Compliance

(PCC)

Product

Materials

Approval

(PMA)

Risk

Assessment

(RA)

Quality

Plan

(QP)Technology

Inputs:

12 3 4

56 7

AB

C

D

E

F

G H

I

Page 3: PLC Phases: Overview - MPC

Project Selection

3

Exploration

◼ Nonnumeric Models

➢ The Sacred Cow / Boss

➢ The Operating Necessity

➢ The Product Line Extension

➢ Comparative Benefit

◼ Numeric Models : Profit / Profitability

➢ Payback Period

➢ Average Rate of Return

Value Capability BudgetRational Resource

Page 4: PLC Phases: Overview - MPC

Key Points in Project Set-up

◼ Create Project Management Plan (PMP)

◼ Be clear of scope and objectives

◼ Establish clear statement of what is to be

done (WBS)

◼ Establish Risks to be Managed

◼ Establish Costs and Durations

◼ Establish Resources Required

4

Page 5: PLC Phases: Overview - MPC

Project Management Plan - PMP

◼ Master Document for Project

◼ Defines the following:-

Project Objectives, Scope, Deliverables

Stakeholders (Internal & External)

Work to be done (WBS)

Project Organisation and Resources

Project Costings

Project Schedule

Procurement/Contract Strategy

Risk Management

Quality management

Change Management

5

Page 6: PLC Phases: Overview - MPC

Project Planning

6

Page 7: PLC Phases: Overview - MPC

Project Planning

◼ Adequate planning leads to the correct

completion of work

7

◼ Inadequate planning leads to frustration

towards the end of the project & poor

project performance

Project Start Project End

Page 8: PLC Phases: Overview - MPC

Work Breakdown Structure (WBS)◼ The Work Breakdown Structure is the

foundation for effective project planning, costing

and management.

◼ It is the most important aspect in setting-up a

Project

◼ It is the foundation on which

everything else builds

8

“A Work Breakdown Structure (WBS) is a hierarchical

(from general to specific) tree structure of

deliverables and tasks that need to be performed

to complete a project.”

Page 9: PLC Phases: Overview - MPC

Example WBS - Top Level Project

Key ProjectMilestones

1.1.1.0.0

Key Project

Deliverables1.1.2.0.0

Key ITER

Milestones & IPL1.1.3.0.0

Overall

Management1.1.4.0.0

Safety & HP

Management1.1.5.0.0

Risk

Management

1.1.6.0.0

Quality

Management

1.1.7.0.0

LIDAR Project

Management1.1.0.0.0

Overall ClusterCo-ordination

1.2.1.0.0

Performance

Analysis1.2.2.0.0

LIDAR

Neutronics1.2.3.0.0

Scattering

Theory1.2.4.0.0

R&D

Tasks1.2.5.0.0

Radiation

Effects Data

1.2.6.0.0

Remote

Handling

1.2.7.0.0

Item

Test Unit

1.2.8.0.0

Engineering

Analysis

1.2.9.0.0

LIDAR System

Concepts1.2.0.0.0

Lasers1.3.1.0.0

Laser

Layout1.3.2.0.0

Laser Beam

Combiner1.3.3.0.0

Laser

Systems1.3.0.0.0

Collection Optical Design

1.4.1.0.0

Collection

Windows1.4.2.0.0

In-Vacuum

Collection Mirrors1.4.3.0.0

Ex-Vacuum

Collection Optics1.4.4.0.0

Collection Optics

Mechanical Design1.4.5.0.0

Spectrometer

System

1.4.6.0.0

Detectors

1.4.7.0.0

Alignment

System

1.4.8.0.0

Calibration

System

1.4.9.0.0

Collection

Optics1.4.0.0.0

Laser PathOptical Design

1.5.1.0.0

Laser

Windows1.5.2.0.0

Plasma Facing

Laser Mirrors1.5.3.0.0

Other Laser

Mirrors1.5.4.0.0

Laser Path

Mechanical Design1.5.5.0.0

Beam

Dump

1.5.6.0.0

Alignment

System

1.5.7.0.0

Calibration

System

1.5.8.0.0

Laser Path

Optics1.5.0.0.0

Control SystemInterface Definition

1.6.1.0.0

Control

System1.6.2.0.0

Acquisition

System1.6.3.0.0

LIDAR

Instrumentation1.6.4.0.0

Safety

Interlocks1.6.5.0.0

Safety

System

1.6.6.0.0

Control &

Acquisition1.6.0.0.0

Shutters1.7.1.0.0

Labyrinth

1.7.2.0.0

Extension Tubes &

Mirror Mounting1.7.3.0.0

External Port Optics

Mounting1.7.4.0.0

Bioshield

1.7.5.0.0

BSM

Penetrations

1.7.6.0.0

EM Analysis for

In-Port Comp.

1.7.7.0.0

LIDAR

Port Engineering1.7.0.0.0

WaterServices

1.8.1.0.0

Interspace

Vacuum1.8.2.0.0

LIDAR

Power1.8.3.0.0

Spectrometer

Area1.8.4.0.0

Laser

Room1.8.5.0.0

Port Cell/

Interspace

1.8.6.0.0

LIDAR

Services1.8.0.0.0

LIDARInterfaces

1.9.1.0.0

Mock-up

Facility1.9.2.0.0

Basic Mock-up

Tests1.9.3.0.0

Tokamak

Tests1.9.4.0.0

Final System

Testing1.9.5.0.0

System Assembly

& Dis-assembly

1.9.6.0.0

Interfaces &

Integrated Testing1.9.0.0.0

Thomson ScatteringCore (LIDAR)

5.5.C.1.0.0.0.0

Optical

Systems

5.5.C.0.0.0.0.0

9

Page 10: PLC Phases: Overview - MPC

Project Planning – WBS (1)

◼ Lowest Level of WBS is the Work Package

(WP)

◼WP can be clearly defined allowing package

to be costed, scheduled and resourced

◼WP contains a list of Tasks to be Performed

that form the basis for the Schedule

◼WP allows assignment of responsibilities

(Work Package Leader, WPL)

10

Page 11: PLC Phases: Overview - MPC

Project Planning – WBS (2)

◼WBS allows hierarchical build-up of costs

and schedule

◼Cost and Schedule can be reported at any

level of the WBS

◼WBS facilitates strong management during

project execution (Cost and Schedule

control)

◼WBS can be used for many other things -

Document Management, Risk Management

etc.11

Page 12: PLC Phases: Overview - MPC

Project Planning

◼A word about Scheduling

– Schedules (task durations) can have a wide

variation

– There is no unique answer. Rather, there is a

statistical variation depending on assumptions

– Need to understand the basis of scheduling

(Most challenging; Most likely; Absolute certainty

- bet your life on it!)

– Most people are very optimistic / naive

12

Page 13: PLC Phases: Overview - MPC

Calculating Activity Times

0

1

2

3

4

5

6

13

a = optimistic time estimate

b = pessimistic time estimate

m = most likely time estimate

TE = expected time

a bm TE

TE =( a + 4m + b )

6

TE =( 10 + 4[20] + 40 )

6

= 22

If :

a = 10

b = 40

m = 20

TE = ?

Page 14: PLC Phases: Overview - MPC

Critical Path and Time – PERT / CPM

14

2

1 3

4 5

6

7

PERT – Program Evaluation and Review Technique CPM – Critical Path Method

a

b

c

d

e

f

g

h

i

j

Activity Expected Time (TE) Cost Estimate

a 20

b 20

c 10

d 15

e 10

f 14

g 4

h 11

i 18

j 8

No Path Add Days

1 a-d-j 20 + 15 + 8 43

2 b-e-j 20 + 10 + 8 38

3 b-f 20 + 14 34

4 b-g-i 20 + 4 + 18 42

5 c-h-i 10 + 11 + 18 39

Page 15: PLC Phases: Overview - MPC

Gantt Chart

15

Day

01

Day

03

Day

05

Day

07

Day

09

Day

11

Day

13

Day

15

Day

17

Day

19

Day

21

Day

23

Day

25

Day

27

Day

29

Day

31

Day

33

Day

35

Day

37

Day

39

Day

41

Day

43

Day

45

Day

47

Day

49

Day

51Activity

a

d

j

b

e

f

g

i

c

h No Path Add Days

1 a-d-j 20 + 15 + 8 43

2 b-e-j 20 + 10 + 8 38

3 b-f 20 + 14 34

4 b-g-i 20 + 4 + 18 42

5 c-h-i 10 + 11 + 18 39

Page 16: PLC Phases: Overview - MPC

16

eDashboard vs eNotepad schedule

WW

01

WW

02

WW

03

WW

04

January

WW

05

WW

06

WW

07

WW

08

WW

09

WW

10

WW

11

WW

12

WW

13

WW

14

WW

15

WW

16

WW

17

WW

18

WW

19

WW

20

WW

21

February March April May

Eval

Complete

with EMI

WW

22

WW

23

WW

24

WW

25

WW

26

WW

27

WW

28

WW

29

WW

30

June July

Mfg

site

Fab A

TO

Legal

ODMFab A

PO

WCIT

2008

BOM

Freeze

Pilot

Regulatory

Compliance

Start PRR PRA SRA

Fab A

BIOS

ICT

Fixture start

ICT

Fixture

Ready

Design

review

Legal

OEM

IPA

CBAFab A

Eval

Start

Fab B

TO

MPR

Fab B

Eval

Start

Qual

Build

(MST)

Prod

BIOSECO

Control

Mfg

site

Fab A

TO

Legal

ODM

Fab A

Valid.

start

Fab A

PO

BOM

Freeze

Pilot

Regulatory

Compliance

Start

IPA

PRR PRA

CAD

Freeze

Fab A

BIOS

ICT /FT

Fixture

start

Design

review

CBA

Legal

OEM

CAD

Freeze

Full

Regulatory

Compliance

iDOLA

Showcase

JEN-ii

ShowcaseValidation

Complete

eDashboard

eClipboard

eNotepad

eNotebook

JEN-ii

Launch

iDOLA

Launch

Prototype

SampleCPU

PRQ

SRA

Page 17: PLC Phases: Overview - MPC

17

eNotepad Project Schedule (Master Plan)

WW

52

WW

53/01

WW

02

WW

03

January WW

04

WW

05

WW

06

WW

07

WW

08

WW

09

WW

10

WW

11

WW

12

WW

13

WW

14

WW

15

WW

16

WW

17

WW

18

WW

19

WW

20

February March April May

Standard

PCB ready

SMT

Phase 2

Tape Out

Validation

Start

Design

Review

Validation

End

Prototype

End

Phase 2

Kickoff

Standard

PCB ready

SMTPhase 2

Tape Out

Validation

Start

Design

Review

EMI

Scanning

Validation

End

Project

Completion

(PRA)

Prototype

End

Phase 2

Kickoff

ECO,

Production

BIOS,

BOM ready

HVM

Pilot

Board

Assembly

(MSCSB)

19/3/09

Board

Assembly

(MSCSB)

MPR SRA

MPR

SRA

PoC

Deployment

eNotepad

PRA

EMI

1st Scan

EMI

2nd Scan

SIRIM,

MCMC

& UL

Certificate

EMI

3rd Scan

EMI

4th Scan

Page 18: PLC Phases: Overview - MPC

Driving Schedule – Intel experience

18

Day

01

Day

03

Day

05

Day

07

Day

09

Day

11

Day

13

Day

15

Day

17

Day

19

Day

21

Day

23

Day

25

Day

27

Day

29

Day

31

Day

33

Day

35

Day

37

Day

39

Day

41

Day

43

Day

45

Day

47

Activity

Committed

Aggressive

(Planned / IPA)

Extreme

No Path Add Days

1 Committed (IPA) 20 + 15 + 8 43

2 Aggressive (20 + 15 + 8 ) x 80% 34.5

3 Extreme (20 + 5 + 8 ) x 65% 28

(Bonus)

(Bonus + Share)

Actual

20%

35%

Page 19: PLC Phases: Overview - MPC

Project Costing

19

Activity Expected Time

(TE)

Cost

Estimate

Weeks

1 2 3 4 5 6 7

a 20 20,000 7,000 7,000 6,000

b 20 10,000 3,500 3,500 3,000

c 10 10,000 7,000 3,000

d 15 15,000 1,000 7,000 7,000

e 10 20,000 2,000 14,000 4,000

f 14 14,000 1,000 7,000 6,000

g 4 12,000 3,000 9,000

h 11 11,000 4,000 7,000

i 18 9,000 3,500 3,500 2,000

j 8 8,000 7,000 1,000

Total / Sub Total 129,000 17,500 17,500 23,000 40,500 20,500 9,000 1,000

2

1 3

4 5

6

7

a

b

c

d

ef

g

h

i

j

Page 20: PLC Phases: Overview - MPC

Project Risk Management

20

Page 21: PLC Phases: Overview - MPC

Project Risk – Definition

“Project risk is an uncertain event or condition

that, if it occurs, has a positive or negative

effect on a project objective”

21

“A combination of the probability of a defined

threat or opportunity (Likelihood) and the

magnitude of the consequences of the

occurrence (Impact) defines a Risk Index”

Page 22: PLC Phases: Overview - MPC

Risk Impact

Threat → Scope → Poor Quality Product

Threat → Schedule → Late Delivery

Threat → Cost → Overspend

◼ In addition there are health, safety and

environmental threats that must be

managed (OSHA Regulations)

22

Page 23: PLC Phases: Overview - MPC

Risk Management Process

◼ Identify Risks

◼Assess likelihood and impact

◼Rank risks and prioritise

◼Define risk management approach & actions

◼ Implement actions

◼Monitor & review

23

Page 24: PLC Phases: Overview - MPC

Project Monitoring and Control

24

Page 25: PLC Phases: Overview - MPC

25

25

Product Life Cycle & Gate System

Project Management OfficeProject Mgt by PMO,

Labs & Finance

Technology Transfer or

Commercialization by TPM & Finance

Exploit

IP?

IP Protection IP ExploitationIP Management Process

Redefine

National Roadmaps

Yes

No

End

Ministry

Updating

IP disclosures IP disclosures

Funding request

BoD

No

Approved

project

TRB

(EOL)

Yes

PlanningAnalysis

TRB

Secretariat

TCRCExploration

MarketTRB

University

Termination

No No

Updating

Area of research study & project initiator by

TPM, TSP, Labs & Finance

Commercialization

Development

Technology

Shelf

Yes

CB

IPA MPR PRA

Page 26: PLC Phases: Overview - MPC

26

Advanced Technology (AT) Product Life Cycle Gates Criteria

Commitment Book

Development

• G4 Criteria:

• Gather market and technology inputs

• Commitment Book Development & Approval by Stakeholders (IP due diligence)

Project

Kick-off

• G3 Criteria:

• Project Code assignment

• Detail Project Schedule

• Risk Management Plan (including IP Risk Chart)

• Legal requirement identified

• Budget breakdown by cost element

• Project team formation & development

• Procurement Plan

ProjectDevelopment

• G2 Criteria:

• Project >50% completion

• Test Plan & Requirement Book baseline

• IP Matrix Card completion, audit & mining

• Product specifications freeze

• ECN signed (if applicable)

Project Completion

• G1 Criteria:

• Project 100% Completion

• Technology Transfer Team list (by Lab)

• IP disclosure, IPC approval, IP search, drafting & filing

• Release Readiness Review (RRR) achieved.

Shipped Release

Readiness

• G0 Criteria:

• Refer to Ministry / Agency Process

• Aligned with SMEs

product marketing / launching strategy

• Spins out option

• Outcome Study Report

• Impact Study Report

1-3 months 3 months

Technology Commercialization Process

CBA

(G4)

‘x’ months ‘y’ months

Legend: CBA – Commitment Book Approval IPA – Implementation Plan Approval

PRA – Product Release Approval SRA – Shipped Release Approval MPR – Mid-Point Review

PRA

(G1)

MPR

(G2)

IPA

(G3)

SRA

(G0)

LAB/TPM PMO TMDPMO PMO

Page 27: PLC Phases: Overview - MPC

Project Monitoring

◼Typical Monitoring Activities

– regular reviews of progress against schedule

using WBS as basis (Plan against Baseline)

– regular review of actual costs (O/P from SAP)

against budgeted costs and Earned Value at

WBS level

– regular review of resource loading

– regular progress meetings with project team

– regular meetings with contractors

– production of periodic progress reports

– risk reviews

– inspections/ audits27

Page 28: PLC Phases: Overview - MPC

Project Control

◼Typical Control Activities

– assign responsibilities at Work Package level

– staged authorisation of work to be done

– staged release of budgets (staged release of

WBS(e) numbers)

– ensure PM has a ‘Management Reserve’ under

his control

– seek corrective action reports when WPs go ‘off

track’ (overrunning or overspending)

– release Management Reserve carefully

28

Page 29: PLC Phases: Overview - MPC

29

Schedule

Budget

BehindAhead

Under

Over

Project : Budget vs Schedule

Page 30: PLC Phases: Overview - MPC

Project Monitoring and Control

Summary

◼Monitor against the plan – status regularly

◼Take a factual approach to decisions

◼ Identify management action early

◼Check that defined controls are being

applied – correct if necessary

◼Apply change control

30

Page 31: PLC Phases: Overview - MPC

Confidential © 2020 Winnotech Solutions Sdn Bhd. All Rights Reserved. 31