planning for start-up - scoar · the focus of design is commonly on equipment and individual...

74
Planning for Start-Up CII Education Module

Upload: others

Post on 30-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Planning for Start-Up

CII Education Module

Page 2: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Session 1

• Facility logistics

• Introduction

• Agenda

2

Page 3: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Facility Logistics

• Safety Topic

• Emergency exit and gathering place

• Restrooms

• Breakout rooms

• Break refreshments and lunch plans

3

Page 4: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Introduction

• Introduction • Jonah Collins

• Background

• Why am I here?

• Startup Manager with 23 years experience in the power generation, and petrochemical industries.

• Southern Company

• Southern Company is one of the largest energy providers in the United States producing 45,502 megawatts of electric generating capacity. Based in Atlanta, Ga., Southern Company owns electric utilities in four states (Alabama Power, Georgia Power, Gulf Power and Mississippi Power) and a growing competitive generation company (Southern Power) as well as a licensed operator of three nuclear generating plants (Southern Nuclear). 4

Page 5: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Agenda Session 1

• Commissioning and Startup Overview

• Critical Success Factor Overview

• Critical Success Factor Detailed Discussion

• War Story

• Break out to groups

• Project Lessons Learned

5

Page 6: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Terminology

• Commissioning and Start-Up (CSU)

• CSU Team

• Critical Success Factor (CSF)

6

Page 7: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Commissioning & Start-Up Overview

Start-up is defined as the transitional phase between plant

construction completion and commercial operations, that

encompasses all activities that bridge these two phases,

including systems turnover, check-out of systems,

commissioning of systems, introduction of feed stocks, and

performance testing

7

Page 8: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Course Reference Material

• Current thinking RT312 reference material

• RT312 Critical Success Factors (CSF’s)

• RT312 CSU Planning Model

• RT312 CSU Phase Chart

8

Page 9: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

CSU Planning Model

• Project Phases

• Concept Development & Feasibility

• Front End Engineering (FEED)

• Detailed Design

• Construction

• Checkout and Commissioning

• Initial Operations

9

Page 10: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Project Progress

CSU Phase

Post Commissioning

Operations

Phase/ Activity

Mile

sto

ne

Do

cum

ents

Conceptual Development &

Feasibility

Front-End Engineering

Detailed Design

Procurement

Construction

Fabrication

Insp

ecti

on

an

d T

esti

ng

Rec

ord

s

Fact

ory

Acc

epta

nce

Rec

ord

s

Pu

nch

Lis

t

Mec

han

ical

Co

mp

leti

on

ce

rtif

icat

es

Rea

dy

for

Co

mm

issi

on

ing

Cer

tifi

cate

Rea

dy

for

Star

tup

Cer

tifi

cate

Rea

dy

for

Intr

od

uct

ion

of

Feed

sto

cks

Safe

ty V

erif

icat

ion

Testing by Manufacture/

Fabricator - Un-witnessed - Witnessed

Pu

nch

Lis

t Ta

bu

late

d

Pu

nch

Lis

t C

lose

d O

ut

Mec

han

ical

Co

mp

leti

on

Han

do

ver

(Co

nst

ruct

ion

to

C

om

mis

sio

nin

g)

Rea

dy

for

Co

mm

issi

on

ing

Commissioning

Syst

em C

om

mis

sio

nin

g C

om

ple

te

Rea

dy

for

Star

tup

Intr

od

uct

ion

of

Feed

sto

ck

Initial Operations / Startup

Performance & Acceptance

Testing

Ramp-up and Performance &

Acceptance Testing

Co

mm

erci

al O

per

atio

ns

Component Level System Level Plant / Unit Level

Pre-commissioning

Pre

-co

mm

issi

on

ing

Def

icie

ncy

Lis

t

Construction Testing

Star

t Sy

stem

s Te

stin

g

Intr

od

uce

Tes

t M

edia

Co

mm

issi

on

ing

Def

icie

ncy

Li

st

Turn

ove

r (C

om

mis

sio

nin

g to

B

usi

nes

s U

nit

)

10

Page 11: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

1

ALIGNMENT AMONG OWNER PM, OPERATIONS, CSU, ENGINEERING, AND

CONSTRUCTION

The project and CSU will benefit substantially by getting early alignment among CSU,

Operations, Project Management, Engineering, and Construction representatives on the

key issues of CSU terminology, CSU success drivers, and CSU strategies. Lack of such

alignment may pose a threat to CSU success. Sustained alignment between these entities

can only be achieved with effective collaboration throughout the life of the project.

2

INTEGRATED CONSTRUCTION/CSU SCHEDULE

A fully integrated construction/pre-commissioning/commissioning schedule is critical to

achieving CSU objectives. This schedule should integrate all checks, tests, and approval-

milestones for each component and all systems, and show development of supportive

documentation.

3

COLLABORATIVE APPROACH TO CONSTRUCTION-CSU TURNOVER

CSU managers should work collaboratively with construction managers in managing

construction completion & systems turnover. Proactive communications are needed to

minimize construction-CSU conflicts.

4

CSU TEAM CAPABILITY

CSU team has a good understanding of the operations performance metrics-oriented

requirements.

5

SYSTEM MILESTONE ACCEPTANCE CRITERIA AND DELIVERABLES

Establish specific detailed systems/subsystems acceptance criteria and associated

deliverables for each major milestone: mechanical completion, turnover, pre-

commissioning, commissioning, and handover. All project parties should understand

these expectations from the beginning of construction.

6

CRITICAL INTERFACES ON BROWNFIELD PROJECTS

For brownfield projects identify early-on all critical interfaces with existing plant facilities

and plant operational approaches. Examples include isolation design, system controls,

worker access, permitting, and interim operations, among others.

List of CSU Critical Success Factors (CSF’s)

11

Page 12: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

7

RECOGNITION OF CSU SEQUENCE DRIVERS

The planned sequence of commissioning should be coordinated with construction

planners and based on such considerations as construction sequence, plant operations

philosophy, ramp-up objectives, plant controls automation objectives, HAZOP awareness,

modularization scope, clean-build procedures, sequence of flushing, sequence of

leak/hydro testing, preservation steps, system tagging, and sequence of loop checks,

among other issues.

8

CSU VALUE RECOGNITION

Establish the business case (including CSU staffing plan) for effective CSU leadership.

Recognize the value added from successful CSU (e.g., the value of one day of successful

operations). Avoid being “dollar foolish” – the Owner and all contractors must buy into

(and be aligned on) the economics of effective planning, and the investment required.

9

DETAILED CSU EXECUTION PLAN

CSU success requires timely and thorough execution planning, which integrates project

planning with CSU planning. Execution Plans should address the appropriate skill mix

necessary in both CSU craft and CSU management. Plant operations must be an effective

contributor to this planning effort, and common challenges that must be addressed (in the

plan) include Operations staff availability, continuity, authority, breadth of experience, and

timeliness of input.

10

ADEQUATE FUNDING FOR CSU

Project funding for CSU must be sufficiently adequate and budgeted up-front. The

common threat from failure to do so is lack of enough operators, with subsequent delays

in CSU progress.

11

CSU SYSTEMS ENGINEERING DURING FEED

CSU Systems Engineering during FEED is the activity of defining CSU systems within a

facility. As the design of facilities has a major impact on how they are fabricated, tested,

integrated, and started up, effective FEED design efforts can reduce commissioning and

startup challenges. Preliminary P&IDs are key documents for this effort.

List of CSU Critical Success Factors CSF’s

12

Page 13: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

12

SYSTEMS- FOCUS IN DETAILED DESIGN

The focus of design is commonly on equipment and individual technical disciplines, rather

than on systems. A systems-focus during design, involving CSU and Operations, will raise

awareness of how systems will be handed over, tested, and started up. With this

approach more design attention will be given to such issues as high/low point drains,

removable spools for critical inline equipment, critical isolation points, and LOTO

requirements/supports, among other issues. In addition, the 3D design model should be

reviewed to ensure access for operations and maintenance.

13

DEFINITION OF CHECK-SHEETS AND PROCEDURES

Insure component/system functional checkouts include adequate check sheet criteria and

detailed system commissioning procedures.

14

CSU LEADERSHIP CONTINUITY

Continuity of CSU management leadership throughout the project is critical. The

necessary qualifications of the CSU leadership should be well defined.

15

TRANSITION TO SYSTEMS-BASED MANAGEMENT

Plan to transition from construction progress tracking on an area basis to a systems-

completion basis so that construction forces may be most effectively redirected as

needed. Involve CSU staff in construction planning at approximately 60-80% system

construction complete (for each single major system) in order to help mitigate

construction punch list items (with particular early focus on utility systems).

16

ACCURATE AS-BUILT INFORMATION

Accurate as-built drawings and asset database are needed to ensure effective planning,

implementation, and close-out of CSU activities.

List of CSU Critical Success Factors CSF’s

13

Page 14: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

War Story

• Project and CSU-Related Performance and Outcome

• Ammonia Release Incident;

• At 1 a.m. a high ammonia concentration was detected at a storage tank area sensor and am Emergency-Stop Pushbutton was activated, which automatically closed supply valves from ammonia tanks.

• The anhydrous ammonia was placed back in service while an environmental emergency response team and plant operations monitored for leakage. The leak began to wisp again. The emergency response team tightened the union and leaked stopped.

• The area of the incident remained barricaded for the remainder of the weekend as a precaution. 14

Page 15: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

War Story

• CSU-Related Problems, Opportunities, & Contributing Factors • Installation of a fallible component (union) in a pressurized NH3 system

• Inadequate communications

• Neither the Startup Team, Engineering, nor the Customer were aware of the installed union on the pressurized NH3 piping.

• Field personnel were unaware of issues experienced on other projects in the Company System with unions in pressurized NH3 piping

• Plant personnel onsite during incident were not aware the Unit forwarding line was pressurized with NH3.

• Inspection, examination, and testing of ammonia piping system was not conducted according to required procedure ASME B31.1. • Roles and responsibilities relative to proper testing procedures were not understood • Requirements of testing protocol were not understood by startup team; Startup utilized a typical “O&M” type leak

test, which was the only integrity test performed prior to pressurizing with NH3 • The union was insulated making visual inspection impossible.

15

Page 16: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

War Story

• Take-Away Lessons-Learned or How to Have a More Successful CSU Next Time • On NH3 and similar systems, construction should be given (or take) less latitude to make

field modifications without engineering review. “As-Built” drawings critically associated with a pressurized NH3 system should be reviewed prior to performing testing on the system

• Critical information regarding pressurization and testing of the NH3 system needs to be communicated to appropriate plant personnel

• Enhance the system of communication for system owners, technical services, etc. to share lessons learned and best practices in accordance with company compliance guidelines

• For NH3 and similar systems, integrity testing should be assigned to construction and performed to applicable codes/standards, and functionality testing should be assigned to Startup. Review turnover packages to ensure testing roles and responsibilities are clearly defined 16

Page 17: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

17

Socket Weld Union Installed on Pipe

War Story

Page 18: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

18

Pipe Trench and Location of Release

War Story

Page 19: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Discussion of Project Lessons Learned Breakout Session (10 minutes)

• Breakout Session

• What CSF would have had the most impact on the project success?

(Refer back to slides 11-13)

• In what Project Phase would you have implemented the CSF you

chose to have the most impact on the project success?

(Refer back to slide 9)

• Open Discussion of Project Lessons Learned 19

Page 20: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

My Answers on Lessons Learned

• What CSF would have had the most impact on the project success?

• CSF #5 - SYSTEM MILESTONE ACCEPTANCE CRITERIA AND DELIVERABLES

Establish specific detailed systems/subsystems acceptance criteria and associated deliverables for each major

milestone: mechanical completion, turnover, pre-commissioning, commissioning, and handover. All project

parties should understand these expectations from the beginning of construction.

• In what Project Phase would you have implemented the CSF you chose to

have the most impact on the project success?

• Construction Phase

20

Page 21: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Assumptions Made During the Project

• CSU Assumptions

• System was installed per construction installation drawings

• Pressure testing was performed by construction

• Startup coordinator was properly trained to perform leak

testing

21

Page 22: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Agenda Session 2

• Introduction

• Understanding the importance of early start-up planning

• Project War Story

• Break out into groups

• Project Lessons Learned

22

Page 23: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Introduction

• Introduction • Edward McDaniel

• Background

• Why am I here?

• 25 years of Instrument & Controls, and electrical experience with start-ups around the world

• CH2M HILL

• Global leader in Consulting, Design, Design Build, Operations and Program Management. We are 26,000 employees strong spanning six continents.

• Company is organized into business groups: WBG, Environmental/Nuclear, Transportation, Energy, Facilities/Urban Development, and tunneling.

23

Page 24: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Learning Objective

• Understanding the importance of early start-up planning

24

Page 25: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Open Discussion Questions

• Why is start-up often difficult or challenging?

• Why is start-up important?

• Why is start-up planning often neglected?

25

Page 26: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

What Is at Stake with Start-up

•Owner profitability

•Overall project success

26

Page 27: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Project Success vs. Start-Up Success

27

Unsuccessful

Successful

START-UP SUCCESS

PROJECT

SUCCESS

Low

High

Low High

Page 28: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Project Lessons Learned

What Causal Factors can lead to UNsuccessful Startups?

• Lack of planning

• (CSF #2 Construction/CSU schedule)

• Lack of management resources

• (CSF #14 CSU Leadership Continuity)

• Lack of alignment between engineering and startup priorities

• (CSF #1 CSU/Operations/Engineering/Construction Alignment)

• Lack of clear roles and responsibilities

• (CSF #3 CSU/Construction Turnover )

• Minimal O&M input

• (CSF #6 Brownfield critical interfaces)

• Failure to recognize and manage risks

• (CSF #7 CSU Sequence Drivers) 28

Page 29: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

As I tell the story keep in mind the causal factors from the previous slide and the CSF’s from (slides 11-

13). Think about how they could have impacted the overall success of the project if implemented.

29

War Story

Page 30: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Project Overview: 96” Pipeline feeding three 48” pipelines that filled a tank. That tank fed six 3000hp pumps. Those

pumps filled tanks with potable water that fed all the hotels on the Las Vegas Strip. This is a major distribution line for

the City of Las Vegas.

30

War Story

Page 31: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Project Scope:

Replace the existing relay logic control system with an Allen Bradley Programmable Logic Control (PLC) system.

Replace the existing motorized valve actuators with new hydraulic valve actuators

31

War Story

Page 32: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Chain of Events:

Maintenance arrived as scheduled to lock out and tag out (LOTO) the ROFC train #1. They closed the upstream and down stream valve

and placed the LOTO on each valve. They also closed the valve that was getting the new hydraulic actuator.

The contractor was not onsite when maintenance performed this task

The valve close or open position was not marked.

The contractor proceeded with the demolition of the existing valve actuator. They took dimensions to make a spool connector piece to

mate up the existing valve with the new actuator.

The spool piece was completed and the new actuator was installed. The contractor energized the valve actuator to stroke the valve prior

to the arrival of the factory representative.

The valve stoked in the wrong direction, instead of opening the valve closed further reversing the seat inside the valve and binding the

valve further closed.

The valve actuator electronics thought the valve was closed they could not open move the valve back into position

and continue to open the valve. They had to wait for the factory representative to arrive and correct the situation. The spool

piece was made incorrectly because the valve close direction was assumed and not properly marked.

They had to wait get a new spool piece made for all three valves, they had to wait for the factory rep to arrive, and then when the valve

was opened the client wanted the valve leak tested. This entire process caused a two week delay. 32

War Story

Page 33: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Commissioning Day:

All the repairs have been made the valve actuator is now ready for commissioning.

This is a list of all the people that were onsite for the commissioning and startup of the valve

actuator.

Owner Project Manager Owner Software Engineer

Owner Inspector Owner 3rd party SCADA inspector

Design Electrical I&C Engineer Electrical Contractor

I&C Contractor

I&C Start-up Manager (Note: There had been 3 start-up managers on this project)

33

War Story

Page 34: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Initial Operations:

The valve Open/Close time was documented at 90 seconds three separate times.

The Owners Software Engineer started to tune the valve PID.

All the safety interlocks at the station were tested with the new valve actuator. The station Flood

signal was checked to ensure that when activated the valve would close.

The contractor was given permission to decommission the second valve. In the process the third

existing valve had to be repaired and was taken offline. The only active valve was the one with the

new actuator.

The Flood switch activated in the facility causing the valve to close in 90 seconds. The down stream

pumping station supplying the 96” line did not have enough time to shut down and this caused the

pipeline to rupture with water flowing down the street until the downstream motors were shut down.

The entire station was out of commission at this time. 34

War Story

Page 35: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Repairs:

Maintenance arrived to make the repairs to the leak in the pipeline. During the discussions

maintenance commented on the existing valve had a closing time of 15 minutes from full open,

not 90 seconds.

After the repairs were made and the pipeline disinfected, the project was not allowed to

proceed until the new electronics for the valve actuators had been re-programmed to for a total

stroke time of 15 minutes.

Once the two valves were tested and ready to be put back on line the project had suffered a two

month delay.

35

War Story

Page 36: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Discussion of Project Lessons Learned Breakout Session (10 minutes)

• What Causal Factor would have had the most impact on the

project success? (slide 26)

• What CSF would have had the most impact on the project

success? (slides 11-13)

• What Project Phase would you have implemented the CSF you

chose to have the most impact on the project success? (slide 9)

36

Page 37: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

My Answers on Lessons Learned

• What causal factor could have made the most impact to the project success?

• (Minimal O&M input CSF #6)

• What CSF would have had the most impact on the project success?

• (CSF #14 Lack of Startup Management Continuity)

• What project phase should the start-up planning have started?

• (FEED)

37

Page 38: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Assumptions Made During the Project

• This project was only a Electrical and Control System upgrade. (No process or

mechanical on CSU Team)

• CSU Team did not require a member of Maintenance to be part of the team

because Operations, and Engineering were already involved. (Budget

driven???)

• We do not need to think about the Hydraulics of the system because it has

been running like this for 20 years. We are only changing the control system.

(Typical Electrical and I&C mentality focus on what you know) 38

Page 39: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Agenda Session 3

• Drop Zone Project Startup

• Break Out to Groups

• Tie to CSF’s and CSU Planning Model

• Discuss Group Answers

39

Page 40: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Drop Zone (DZ) Overview

• Project Objective

• Provide a safe DZ for skydivers to enjoy their sport. • Goals:

• Provide a Landing Zone (LZ)

• Provide a parachute packing area

• Provide an airplane and all support items for the plane

• Tools

• CSU Planning Model

• CSU Critical Success Factors CSF’s

• CSU Phase Chart 40

Page 41: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Choosing a CSU Team • Owner – Provides funding only, does not have any technical understanding or knowledge of the sport.

• CSU Manager

• Load Master/DZ Operations Lead

• Operations

• Pilot

• Skydivers

• Airport Staff • Fueling Station

• Air Traffic Control

• Choose Two CSF’s that you think will have the most impact on the DZ startup as it relates to the CSU team.

• Choose from the CSU planning model when each CSU team member is introduced and should start participating in the project. 41

Page 42: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

What CSU team member helped with defining the landing patterns?

42

Page 43: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

What team member has primary responsibility for this system?

43

Page 44: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

What team member thought of and installed the wheel guard?

44

Page 45: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

What CSU team members decided to modify the interior of the plane?

45

Page 46: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

System Based Focus • Areas

• Hangers, Runway, LZ • Systems

• Parachute, Airplane, Fueling Equipment

• Parachutes need assembly by a certified rigger

• Airplane arrives on a truck and needs assembly by a certified mechanic and all modifications inside the plane need to be made to accommodate jumpers.

• The Plane needs fuel and a runway to make the maiden flight.

• Choose Two CSF’s that you think will have the most impact on the DZ startup as it relates to Systems verse Areas.

• Choose from the CSU planning model when a shift to a System based focus should be initiated and in what other project phases a System focus is critical.

46

Page 47: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

This system has a AAD, Container, Main Parachute, and Reserve Parachute all of which need to be assembled by a certified rigger.

47

Page 48: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Final assembly is almost complete for this system.

48

Page 49: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

System is complete and ready for Pre-commissioning

49

Page 50: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Pre-Commissioning/Commissioning • Construction has turned over the project to the CSU team

• Detailed Pre-commissioning and Commissioning can start • Fuel Station

• Radio Communications

• Airplane (Factory Acceptance Testing) Instrument Calibrations

• Parachute riggers certifications of the rig

• Plane’s first flight

• Choose Two CSF’s that you think will have the most impact on the DZ startup as it relates to the Commissioning activities.

• Choose from the CSU planning model when the commissioning activities should be introduced.

50

Page 51: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

First Flight

51

Page 52: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

First use of Runway

52

Page 53: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Initial Operations • Ready for Startup

• Startup of the DZ can begin

• Detailed Plane Loading Plan • Jumper exit plan is important, need to maintain plane balance • What are the upper wind speeds and directions

• Detailed Dive Flow Plan • Gear Safety Checks • What maneuvers are we going to perform, Star, Ring • What is the break away altitude • What is the opening altitude for the first jump, compared to other jumps

• What is the landing pattern • How do we communicate ground wind changes to pilot and jumpers

• How many jumps before Commercial Operation

• Choose Two CSF’s that you think will have the most impact on the DZ startup as it relates to the Initial Operation of the DZ.

• Choose from the CSU planning model when the CSU team should start thinking about the initial operations 53

Page 54: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Safety meeting before going to the plane

54

Page 55: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Instructions on plane loading and plane exits

55

Page 56: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Plane loaded and ready for take off

56

Page 57: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Jumpers out at 12,000 Ft AGL

57

Page 58: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Landing pattern established on final approach

58

Page 59: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Safe Landing the first jump was a success

59

Page 60: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Initial operations were successful, ready to move into the Performance Testing phase of the project

60

Page 61: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Breakout Session (10 minutes)

• Choosing CSU Team Answers • CSF #4 CSU Team Capability • CSF #1 Alignment among Owner PM, Operations, CSU Engineering and

Construction • Owner Phase: Concept Development & Feasibility • CSU Manager Phase: FEED • Operations Phase: Detailed Design • Airport Staff Phase: Construction

• System Based Focus Answers • CSF # 12 Systems-Focus in Detailed Design • Phase: Detailed Design • CSF # 15 Transition to Systems-Based Management • Phase: Construction 61

Page 62: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Breakout Session (10 minutes)

• Pre-Commissioning & Commissioning Answers • CSF #13 Definition of Check-Sheets and Procedures

• Phase: Detailed Design

• CSF #3 Collaborative Approach to Construction-CSU Turnover

• Phase: Construction

• Initial Operation • CSF #1 Alignment among Owner PM, Operations, CSU Engineering and

Construction

• Phase: Concept Development & Feasibility

• CSF # 10 Adequate Funding for CSU

• Phase: Detailed Design 62

Page 63: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Agenda Session 4

• Power Plant Overview

• Power Plant System Startup

• Break Out Group Objectives

• Discuss Group Answers

63

Page 64: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Power Plant Overview

•3 Major Areas

•Generator

• Turbine

•Boiler

• Boiler Overview Presentation

64

Page 65: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Power Plant System Start-up

•Project Objective

• Safely Commission Boiler Water Circulation System

• Boiler Water Circulation Pump

• BWCP Presentation

65

Page 66: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Power Plant System Start-up

•Break Out Group #1 Objectives

• Factory Acceptance Test (Pump & Motor)

• Reference CSF #5, 4 items required for adequate check sheet criteria prior to accepting from factory

• In which project phase should this be addressed?

66

Page 67: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Power Plant System Start-up

•Break Out Group #2 Objectives

• Specific Milestone Acceptance Criteria and Deliverables from CSU Team

• Reference CSF #13, 4 items required for functional checkouts prior to commissioning system

• In which project phase should this be addressed?

67

Page 68: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Power Plant System Start-up

•Break Out Group #3 Objectives

• Issues with installing new BWCP on Brownfield Projects

• Reference CSF #6, identify 4 areas of opportunity with existing plant facilities

• In which project phase should this be addressed?

68

Page 69: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Power Plant System Start-up

•Break Out Group #4 Objectives • Issues with incorrect drawings from design

engineering • Reference CSF #16, what actions should be taken if

drawings are incorrect from Design Engineering i.e. P&IDs, Piping Isometrics, Electrical Single Lines etc.

• Who is responsible for making corrections to incorrect drawings from Design Engineering?

• In which project phase should this be addressed?

69

Page 70: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Group Discussion

• My Answers

• Group #1 - 4 items required for adequate check sheet criteria prior to accepting from factory? • Installation Manual

• PM Procedure

• Bill of Material

• Factory Operational tests

• In what phase? Construction

70

Page 71: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Group Discussion

• My Answers

• Group #2 - 4 items required for functional checkouts prior to commissioning system? • Motor Test Report

• Pump/Motor Alignment Report

• As built Drawings

• System Specific Commissioning Procedure

• In what phase? Checkout and Commissioning

71

Page 72: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Group Discussion

• My Answers

• Group #3 - 4 areas of opportunity with existing plant facilities • System Isolation

• Up-to-date drawings of existing plant systems

• Personnel training

• Additional Spare Parts

• In what phase? Front End Engineering (FEED)

72

Page 73: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Group Discussion

• My Answers • Group #4 – What actions should be taken if drawings are incorrect from

Design Engineering? • Design Engineering should be notified and any “field” modifications should be

approved by Design Engineering before being constructed or commissioned. Once approved, “As-built” drawings should be developed by “field” personnel and submitted to Design Engineering so that the corrections can be properly documented.

• Who is responsible for making the corrections to the incorrect drawings from Design Engineering? • Any “ field” personnel that finds the discrepancy and gets approval from Design

Engineering

• In what phase? Construction and Checkout and Commissioning

73

Page 74: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving

Questions

74