planning for start-up - scoar · the focus of design is commonly on equipment and individual...
TRANSCRIPT
![Page 1: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/1.jpg)
Planning for Start-Up
CII Education Module
![Page 2: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/2.jpg)
Session 1
• Facility logistics
• Introduction
• Agenda
2
![Page 3: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/3.jpg)
Facility Logistics
• Safety Topic
• Emergency exit and gathering place
• Restrooms
• Breakout rooms
• Break refreshments and lunch plans
3
![Page 4: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/4.jpg)
Introduction
• Introduction • Jonah Collins
• Background
• Why am I here?
• Startup Manager with 23 years experience in the power generation, and petrochemical industries.
• Southern Company
• Southern Company is one of the largest energy providers in the United States producing 45,502 megawatts of electric generating capacity. Based in Atlanta, Ga., Southern Company owns electric utilities in four states (Alabama Power, Georgia Power, Gulf Power and Mississippi Power) and a growing competitive generation company (Southern Power) as well as a licensed operator of three nuclear generating plants (Southern Nuclear). 4
![Page 5: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/5.jpg)
Agenda Session 1
• Commissioning and Startup Overview
• Critical Success Factor Overview
• Critical Success Factor Detailed Discussion
• War Story
• Break out to groups
• Project Lessons Learned
5
![Page 6: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/6.jpg)
Terminology
• Commissioning and Start-Up (CSU)
• CSU Team
• Critical Success Factor (CSF)
6
![Page 7: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/7.jpg)
Commissioning & Start-Up Overview
Start-up is defined as the transitional phase between plant
construction completion and commercial operations, that
encompasses all activities that bridge these two phases,
including systems turnover, check-out of systems,
commissioning of systems, introduction of feed stocks, and
performance testing
7
![Page 8: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/8.jpg)
Course Reference Material
• Current thinking RT312 reference material
• RT312 Critical Success Factors (CSF’s)
• RT312 CSU Planning Model
• RT312 CSU Phase Chart
8
![Page 9: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/9.jpg)
CSU Planning Model
• Project Phases
• Concept Development & Feasibility
• Front End Engineering (FEED)
• Detailed Design
• Construction
• Checkout and Commissioning
• Initial Operations
9
![Page 10: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/10.jpg)
Project Progress
CSU Phase
Post Commissioning
Operations
Phase/ Activity
Mile
sto
ne
Do
cum
ents
Conceptual Development &
Feasibility
Front-End Engineering
Detailed Design
Procurement
Construction
Fabrication
Insp
ecti
on
an
d T
esti
ng
Rec
ord
s
Fact
ory
Acc
epta
nce
Rec
ord
s
Pu
nch
Lis
t
Mec
han
ical
Co
mp
leti
on
ce
rtif
icat
es
Rea
dy
for
Co
mm
issi
on
ing
Cer
tifi
cate
Rea
dy
for
Star
tup
Cer
tifi
cate
Rea
dy
for
Intr
od
uct
ion
of
Feed
sto
cks
Safe
ty V
erif
icat
ion
Testing by Manufacture/
Fabricator - Un-witnessed - Witnessed
Pu
nch
Lis
t Ta
bu
late
d
Pu
nch
Lis
t C
lose
d O
ut
Mec
han
ical
Co
mp
leti
on
Han
do
ver
(Co
nst
ruct
ion
to
C
om
mis
sio
nin
g)
Rea
dy
for
Co
mm
issi
on
ing
Commissioning
Syst
em C
om
mis
sio
nin
g C
om
ple
te
Rea
dy
for
Star
tup
Intr
od
uct
ion
of
Feed
sto
ck
Initial Operations / Startup
Performance & Acceptance
Testing
Ramp-up and Performance &
Acceptance Testing
Co
mm
erci
al O
per
atio
ns
Component Level System Level Plant / Unit Level
Pre-commissioning
Pre
-co
mm
issi
on
ing
Def
icie
ncy
Lis
t
Construction Testing
Star
t Sy
stem
s Te
stin
g
Intr
od
uce
Tes
t M
edia
Co
mm
issi
on
ing
Def
icie
ncy
Li
st
Turn
ove
r (C
om
mis
sio
nin
g to
B
usi
nes
s U
nit
)
10
![Page 11: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/11.jpg)
1
ALIGNMENT AMONG OWNER PM, OPERATIONS, CSU, ENGINEERING, AND
CONSTRUCTION
The project and CSU will benefit substantially by getting early alignment among CSU,
Operations, Project Management, Engineering, and Construction representatives on the
key issues of CSU terminology, CSU success drivers, and CSU strategies. Lack of such
alignment may pose a threat to CSU success. Sustained alignment between these entities
can only be achieved with effective collaboration throughout the life of the project.
2
INTEGRATED CONSTRUCTION/CSU SCHEDULE
A fully integrated construction/pre-commissioning/commissioning schedule is critical to
achieving CSU objectives. This schedule should integrate all checks, tests, and approval-
milestones for each component and all systems, and show development of supportive
documentation.
3
COLLABORATIVE APPROACH TO CONSTRUCTION-CSU TURNOVER
CSU managers should work collaboratively with construction managers in managing
construction completion & systems turnover. Proactive communications are needed to
minimize construction-CSU conflicts.
4
CSU TEAM CAPABILITY
CSU team has a good understanding of the operations performance metrics-oriented
requirements.
5
SYSTEM MILESTONE ACCEPTANCE CRITERIA AND DELIVERABLES
Establish specific detailed systems/subsystems acceptance criteria and associated
deliverables for each major milestone: mechanical completion, turnover, pre-
commissioning, commissioning, and handover. All project parties should understand
these expectations from the beginning of construction.
6
CRITICAL INTERFACES ON BROWNFIELD PROJECTS
For brownfield projects identify early-on all critical interfaces with existing plant facilities
and plant operational approaches. Examples include isolation design, system controls,
worker access, permitting, and interim operations, among others.
List of CSU Critical Success Factors (CSF’s)
11
![Page 12: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/12.jpg)
7
RECOGNITION OF CSU SEQUENCE DRIVERS
The planned sequence of commissioning should be coordinated with construction
planners and based on such considerations as construction sequence, plant operations
philosophy, ramp-up objectives, plant controls automation objectives, HAZOP awareness,
modularization scope, clean-build procedures, sequence of flushing, sequence of
leak/hydro testing, preservation steps, system tagging, and sequence of loop checks,
among other issues.
8
CSU VALUE RECOGNITION
Establish the business case (including CSU staffing plan) for effective CSU leadership.
Recognize the value added from successful CSU (e.g., the value of one day of successful
operations). Avoid being “dollar foolish” – the Owner and all contractors must buy into
(and be aligned on) the economics of effective planning, and the investment required.
9
DETAILED CSU EXECUTION PLAN
CSU success requires timely and thorough execution planning, which integrates project
planning with CSU planning. Execution Plans should address the appropriate skill mix
necessary in both CSU craft and CSU management. Plant operations must be an effective
contributor to this planning effort, and common challenges that must be addressed (in the
plan) include Operations staff availability, continuity, authority, breadth of experience, and
timeliness of input.
10
ADEQUATE FUNDING FOR CSU
Project funding for CSU must be sufficiently adequate and budgeted up-front. The
common threat from failure to do so is lack of enough operators, with subsequent delays
in CSU progress.
11
CSU SYSTEMS ENGINEERING DURING FEED
CSU Systems Engineering during FEED is the activity of defining CSU systems within a
facility. As the design of facilities has a major impact on how they are fabricated, tested,
integrated, and started up, effective FEED design efforts can reduce commissioning and
startup challenges. Preliminary P&IDs are key documents for this effort.
List of CSU Critical Success Factors CSF’s
12
![Page 13: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/13.jpg)
12
SYSTEMS- FOCUS IN DETAILED DESIGN
The focus of design is commonly on equipment and individual technical disciplines, rather
than on systems. A systems-focus during design, involving CSU and Operations, will raise
awareness of how systems will be handed over, tested, and started up. With this
approach more design attention will be given to such issues as high/low point drains,
removable spools for critical inline equipment, critical isolation points, and LOTO
requirements/supports, among other issues. In addition, the 3D design model should be
reviewed to ensure access for operations and maintenance.
13
DEFINITION OF CHECK-SHEETS AND PROCEDURES
Insure component/system functional checkouts include adequate check sheet criteria and
detailed system commissioning procedures.
14
CSU LEADERSHIP CONTINUITY
Continuity of CSU management leadership throughout the project is critical. The
necessary qualifications of the CSU leadership should be well defined.
15
TRANSITION TO SYSTEMS-BASED MANAGEMENT
Plan to transition from construction progress tracking on an area basis to a systems-
completion basis so that construction forces may be most effectively redirected as
needed. Involve CSU staff in construction planning at approximately 60-80% system
construction complete (for each single major system) in order to help mitigate
construction punch list items (with particular early focus on utility systems).
16
ACCURATE AS-BUILT INFORMATION
Accurate as-built drawings and asset database are needed to ensure effective planning,
implementation, and close-out of CSU activities.
List of CSU Critical Success Factors CSF’s
13
![Page 14: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/14.jpg)
War Story
• Project and CSU-Related Performance and Outcome
• Ammonia Release Incident;
• At 1 a.m. a high ammonia concentration was detected at a storage tank area sensor and am Emergency-Stop Pushbutton was activated, which automatically closed supply valves from ammonia tanks.
• The anhydrous ammonia was placed back in service while an environmental emergency response team and plant operations monitored for leakage. The leak began to wisp again. The emergency response team tightened the union and leaked stopped.
• The area of the incident remained barricaded for the remainder of the weekend as a precaution. 14
![Page 15: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/15.jpg)
War Story
• CSU-Related Problems, Opportunities, & Contributing Factors • Installation of a fallible component (union) in a pressurized NH3 system
• Inadequate communications
• Neither the Startup Team, Engineering, nor the Customer were aware of the installed union on the pressurized NH3 piping.
• Field personnel were unaware of issues experienced on other projects in the Company System with unions in pressurized NH3 piping
• Plant personnel onsite during incident were not aware the Unit forwarding line was pressurized with NH3.
• Inspection, examination, and testing of ammonia piping system was not conducted according to required procedure ASME B31.1. • Roles and responsibilities relative to proper testing procedures were not understood • Requirements of testing protocol were not understood by startup team; Startup utilized a typical “O&M” type leak
test, which was the only integrity test performed prior to pressurizing with NH3 • The union was insulated making visual inspection impossible.
15
![Page 16: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/16.jpg)
War Story
• Take-Away Lessons-Learned or How to Have a More Successful CSU Next Time • On NH3 and similar systems, construction should be given (or take) less latitude to make
field modifications without engineering review. “As-Built” drawings critically associated with a pressurized NH3 system should be reviewed prior to performing testing on the system
• Critical information regarding pressurization and testing of the NH3 system needs to be communicated to appropriate plant personnel
• Enhance the system of communication for system owners, technical services, etc. to share lessons learned and best practices in accordance with company compliance guidelines
• For NH3 and similar systems, integrity testing should be assigned to construction and performed to applicable codes/standards, and functionality testing should be assigned to Startup. Review turnover packages to ensure testing roles and responsibilities are clearly defined 16
![Page 17: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/17.jpg)
17
Socket Weld Union Installed on Pipe
War Story
![Page 18: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/18.jpg)
18
Pipe Trench and Location of Release
War Story
![Page 19: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/19.jpg)
Discussion of Project Lessons Learned Breakout Session (10 minutes)
• Breakout Session
• What CSF would have had the most impact on the project success?
(Refer back to slides 11-13)
• In what Project Phase would you have implemented the CSF you
chose to have the most impact on the project success?
(Refer back to slide 9)
• Open Discussion of Project Lessons Learned 19
![Page 20: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/20.jpg)
My Answers on Lessons Learned
• What CSF would have had the most impact on the project success?
• CSF #5 - SYSTEM MILESTONE ACCEPTANCE CRITERIA AND DELIVERABLES
Establish specific detailed systems/subsystems acceptance criteria and associated deliverables for each major
milestone: mechanical completion, turnover, pre-commissioning, commissioning, and handover. All project
parties should understand these expectations from the beginning of construction.
• In what Project Phase would you have implemented the CSF you chose to
have the most impact on the project success?
• Construction Phase
20
![Page 21: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/21.jpg)
Assumptions Made During the Project
• CSU Assumptions
• System was installed per construction installation drawings
• Pressure testing was performed by construction
• Startup coordinator was properly trained to perform leak
testing
21
![Page 22: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/22.jpg)
Agenda Session 2
• Introduction
• Understanding the importance of early start-up planning
• Project War Story
• Break out into groups
• Project Lessons Learned
22
![Page 23: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/23.jpg)
Introduction
• Introduction • Edward McDaniel
• Background
• Why am I here?
• 25 years of Instrument & Controls, and electrical experience with start-ups around the world
• CH2M HILL
• Global leader in Consulting, Design, Design Build, Operations and Program Management. We are 26,000 employees strong spanning six continents.
• Company is organized into business groups: WBG, Environmental/Nuclear, Transportation, Energy, Facilities/Urban Development, and tunneling.
23
![Page 24: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/24.jpg)
Learning Objective
• Understanding the importance of early start-up planning
24
![Page 25: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/25.jpg)
Open Discussion Questions
• Why is start-up often difficult or challenging?
• Why is start-up important?
• Why is start-up planning often neglected?
25
![Page 26: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/26.jpg)
What Is at Stake with Start-up
•Owner profitability
•Overall project success
26
![Page 27: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/27.jpg)
Project Success vs. Start-Up Success
27
Unsuccessful
Successful
START-UP SUCCESS
PROJECT
SUCCESS
Low
High
Low High
![Page 28: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/28.jpg)
Project Lessons Learned
What Causal Factors can lead to UNsuccessful Startups?
• Lack of planning
• (CSF #2 Construction/CSU schedule)
• Lack of management resources
• (CSF #14 CSU Leadership Continuity)
• Lack of alignment between engineering and startup priorities
• (CSF #1 CSU/Operations/Engineering/Construction Alignment)
• Lack of clear roles and responsibilities
• (CSF #3 CSU/Construction Turnover )
• Minimal O&M input
• (CSF #6 Brownfield critical interfaces)
• Failure to recognize and manage risks
• (CSF #7 CSU Sequence Drivers) 28
![Page 29: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/29.jpg)
As I tell the story keep in mind the causal factors from the previous slide and the CSF’s from (slides 11-
13). Think about how they could have impacted the overall success of the project if implemented.
29
War Story
![Page 30: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/30.jpg)
Project Overview: 96” Pipeline feeding three 48” pipelines that filled a tank. That tank fed six 3000hp pumps. Those
pumps filled tanks with potable water that fed all the hotels on the Las Vegas Strip. This is a major distribution line for
the City of Las Vegas.
30
War Story
![Page 31: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/31.jpg)
Project Scope:
Replace the existing relay logic control system with an Allen Bradley Programmable Logic Control (PLC) system.
Replace the existing motorized valve actuators with new hydraulic valve actuators
31
War Story
![Page 32: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/32.jpg)
Chain of Events:
Maintenance arrived as scheduled to lock out and tag out (LOTO) the ROFC train #1. They closed the upstream and down stream valve
and placed the LOTO on each valve. They also closed the valve that was getting the new hydraulic actuator.
The contractor was not onsite when maintenance performed this task
The valve close or open position was not marked.
The contractor proceeded with the demolition of the existing valve actuator. They took dimensions to make a spool connector piece to
mate up the existing valve with the new actuator.
The spool piece was completed and the new actuator was installed. The contractor energized the valve actuator to stroke the valve prior
to the arrival of the factory representative.
The valve stoked in the wrong direction, instead of opening the valve closed further reversing the seat inside the valve and binding the
valve further closed.
The valve actuator electronics thought the valve was closed they could not open move the valve back into position
and continue to open the valve. They had to wait for the factory representative to arrive and correct the situation. The spool
piece was made incorrectly because the valve close direction was assumed and not properly marked.
They had to wait get a new spool piece made for all three valves, they had to wait for the factory rep to arrive, and then when the valve
was opened the client wanted the valve leak tested. This entire process caused a two week delay. 32
War Story
![Page 33: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/33.jpg)
Commissioning Day:
All the repairs have been made the valve actuator is now ready for commissioning.
This is a list of all the people that were onsite for the commissioning and startup of the valve
actuator.
Owner Project Manager Owner Software Engineer
Owner Inspector Owner 3rd party SCADA inspector
Design Electrical I&C Engineer Electrical Contractor
I&C Contractor
I&C Start-up Manager (Note: There had been 3 start-up managers on this project)
33
War Story
![Page 34: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/34.jpg)
Initial Operations:
The valve Open/Close time was documented at 90 seconds three separate times.
The Owners Software Engineer started to tune the valve PID.
All the safety interlocks at the station were tested with the new valve actuator. The station Flood
signal was checked to ensure that when activated the valve would close.
The contractor was given permission to decommission the second valve. In the process the third
existing valve had to be repaired and was taken offline. The only active valve was the one with the
new actuator.
The Flood switch activated in the facility causing the valve to close in 90 seconds. The down stream
pumping station supplying the 96” line did not have enough time to shut down and this caused the
pipeline to rupture with water flowing down the street until the downstream motors were shut down.
The entire station was out of commission at this time. 34
War Story
![Page 35: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/35.jpg)
Repairs:
Maintenance arrived to make the repairs to the leak in the pipeline. During the discussions
maintenance commented on the existing valve had a closing time of 15 minutes from full open,
not 90 seconds.
After the repairs were made and the pipeline disinfected, the project was not allowed to
proceed until the new electronics for the valve actuators had been re-programmed to for a total
stroke time of 15 minutes.
Once the two valves were tested and ready to be put back on line the project had suffered a two
month delay.
35
War Story
![Page 36: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/36.jpg)
Discussion of Project Lessons Learned Breakout Session (10 minutes)
• What Causal Factor would have had the most impact on the
project success? (slide 26)
• What CSF would have had the most impact on the project
success? (slides 11-13)
• What Project Phase would you have implemented the CSF you
chose to have the most impact on the project success? (slide 9)
36
![Page 37: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/37.jpg)
My Answers on Lessons Learned
• What causal factor could have made the most impact to the project success?
• (Minimal O&M input CSF #6)
• What CSF would have had the most impact on the project success?
• (CSF #14 Lack of Startup Management Continuity)
• What project phase should the start-up planning have started?
• (FEED)
37
![Page 38: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/38.jpg)
Assumptions Made During the Project
• This project was only a Electrical and Control System upgrade. (No process or
mechanical on CSU Team)
• CSU Team did not require a member of Maintenance to be part of the team
because Operations, and Engineering were already involved. (Budget
driven???)
• We do not need to think about the Hydraulics of the system because it has
been running like this for 20 years. We are only changing the control system.
(Typical Electrical and I&C mentality focus on what you know) 38
![Page 39: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/39.jpg)
Agenda Session 3
• Drop Zone Project Startup
• Break Out to Groups
• Tie to CSF’s and CSU Planning Model
• Discuss Group Answers
39
![Page 40: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/40.jpg)
Drop Zone (DZ) Overview
• Project Objective
• Provide a safe DZ for skydivers to enjoy their sport. • Goals:
• Provide a Landing Zone (LZ)
• Provide a parachute packing area
• Provide an airplane and all support items for the plane
• Tools
• CSU Planning Model
• CSU Critical Success Factors CSF’s
• CSU Phase Chart 40
![Page 41: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/41.jpg)
Choosing a CSU Team • Owner – Provides funding only, does not have any technical understanding or knowledge of the sport.
• CSU Manager
• Load Master/DZ Operations Lead
• Operations
• Pilot
• Skydivers
• Airport Staff • Fueling Station
• Air Traffic Control
• Choose Two CSF’s that you think will have the most impact on the DZ startup as it relates to the CSU team.
• Choose from the CSU planning model when each CSU team member is introduced and should start participating in the project. 41
![Page 42: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/42.jpg)
What CSU team member helped with defining the landing patterns?
42
![Page 43: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/43.jpg)
What team member has primary responsibility for this system?
43
![Page 44: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/44.jpg)
What team member thought of and installed the wheel guard?
44
![Page 45: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/45.jpg)
What CSU team members decided to modify the interior of the plane?
45
![Page 46: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/46.jpg)
System Based Focus • Areas
• Hangers, Runway, LZ • Systems
• Parachute, Airplane, Fueling Equipment
• Parachutes need assembly by a certified rigger
• Airplane arrives on a truck and needs assembly by a certified mechanic and all modifications inside the plane need to be made to accommodate jumpers.
• The Plane needs fuel and a runway to make the maiden flight.
• Choose Two CSF’s that you think will have the most impact on the DZ startup as it relates to Systems verse Areas.
• Choose from the CSU planning model when a shift to a System based focus should be initiated and in what other project phases a System focus is critical.
46
![Page 47: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/47.jpg)
This system has a AAD, Container, Main Parachute, and Reserve Parachute all of which need to be assembled by a certified rigger.
47
![Page 48: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/48.jpg)
Final assembly is almost complete for this system.
48
![Page 49: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/49.jpg)
System is complete and ready for Pre-commissioning
49
![Page 50: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/50.jpg)
Pre-Commissioning/Commissioning • Construction has turned over the project to the CSU team
• Detailed Pre-commissioning and Commissioning can start • Fuel Station
• Radio Communications
• Airplane (Factory Acceptance Testing) Instrument Calibrations
• Parachute riggers certifications of the rig
• Plane’s first flight
• Choose Two CSF’s that you think will have the most impact on the DZ startup as it relates to the Commissioning activities.
• Choose from the CSU planning model when the commissioning activities should be introduced.
50
![Page 51: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/51.jpg)
First Flight
51
![Page 52: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/52.jpg)
First use of Runway
52
![Page 53: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/53.jpg)
Initial Operations • Ready for Startup
• Startup of the DZ can begin
• Detailed Plane Loading Plan • Jumper exit plan is important, need to maintain plane balance • What are the upper wind speeds and directions
• Detailed Dive Flow Plan • Gear Safety Checks • What maneuvers are we going to perform, Star, Ring • What is the break away altitude • What is the opening altitude for the first jump, compared to other jumps
• What is the landing pattern • How do we communicate ground wind changes to pilot and jumpers
• How many jumps before Commercial Operation
• Choose Two CSF’s that you think will have the most impact on the DZ startup as it relates to the Initial Operation of the DZ.
• Choose from the CSU planning model when the CSU team should start thinking about the initial operations 53
![Page 54: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/54.jpg)
Safety meeting before going to the plane
54
![Page 55: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/55.jpg)
Instructions on plane loading and plane exits
55
![Page 56: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/56.jpg)
Plane loaded and ready for take off
56
![Page 57: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/57.jpg)
Jumpers out at 12,000 Ft AGL
57
![Page 58: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/58.jpg)
Landing pattern established on final approach
58
![Page 59: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/59.jpg)
Safe Landing the first jump was a success
59
![Page 60: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/60.jpg)
Initial operations were successful, ready to move into the Performance Testing phase of the project
60
![Page 61: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/61.jpg)
Breakout Session (10 minutes)
• Choosing CSU Team Answers • CSF #4 CSU Team Capability • CSF #1 Alignment among Owner PM, Operations, CSU Engineering and
Construction • Owner Phase: Concept Development & Feasibility • CSU Manager Phase: FEED • Operations Phase: Detailed Design • Airport Staff Phase: Construction
• System Based Focus Answers • CSF # 12 Systems-Focus in Detailed Design • Phase: Detailed Design • CSF # 15 Transition to Systems-Based Management • Phase: Construction 61
![Page 62: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/62.jpg)
Breakout Session (10 minutes)
• Pre-Commissioning & Commissioning Answers • CSF #13 Definition of Check-Sheets and Procedures
• Phase: Detailed Design
• CSF #3 Collaborative Approach to Construction-CSU Turnover
• Phase: Construction
• Initial Operation • CSF #1 Alignment among Owner PM, Operations, CSU Engineering and
Construction
• Phase: Concept Development & Feasibility
• CSF # 10 Adequate Funding for CSU
• Phase: Detailed Design 62
![Page 63: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/63.jpg)
Agenda Session 4
• Power Plant Overview
• Power Plant System Startup
• Break Out Group Objectives
• Discuss Group Answers
63
![Page 64: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/64.jpg)
Power Plant Overview
•3 Major Areas
•Generator
• Turbine
•Boiler
• Boiler Overview Presentation
64
![Page 65: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/65.jpg)
Power Plant System Start-up
•Project Objective
• Safely Commission Boiler Water Circulation System
• Boiler Water Circulation Pump
• BWCP Presentation
65
![Page 66: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/66.jpg)
Power Plant System Start-up
•Break Out Group #1 Objectives
• Factory Acceptance Test (Pump & Motor)
• Reference CSF #5, 4 items required for adequate check sheet criteria prior to accepting from factory
• In which project phase should this be addressed?
66
![Page 67: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/67.jpg)
Power Plant System Start-up
•Break Out Group #2 Objectives
• Specific Milestone Acceptance Criteria and Deliverables from CSU Team
• Reference CSF #13, 4 items required for functional checkouts prior to commissioning system
• In which project phase should this be addressed?
67
![Page 68: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/68.jpg)
Power Plant System Start-up
•Break Out Group #3 Objectives
• Issues with installing new BWCP on Brownfield Projects
• Reference CSF #6, identify 4 areas of opportunity with existing plant facilities
• In which project phase should this be addressed?
68
![Page 69: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/69.jpg)
Power Plant System Start-up
•Break Out Group #4 Objectives • Issues with incorrect drawings from design
engineering • Reference CSF #16, what actions should be taken if
drawings are incorrect from Design Engineering i.e. P&IDs, Piping Isometrics, Electrical Single Lines etc.
• Who is responsible for making corrections to incorrect drawings from Design Engineering?
• In which project phase should this be addressed?
69
![Page 70: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/70.jpg)
Group Discussion
• My Answers
• Group #1 - 4 items required for adequate check sheet criteria prior to accepting from factory? • Installation Manual
• PM Procedure
• Bill of Material
• Factory Operational tests
• In what phase? Construction
70
![Page 71: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/71.jpg)
Group Discussion
• My Answers
• Group #2 - 4 items required for functional checkouts prior to commissioning system? • Motor Test Report
• Pump/Motor Alignment Report
• As built Drawings
• System Specific Commissioning Procedure
• In what phase? Checkout and Commissioning
71
![Page 72: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/72.jpg)
Group Discussion
• My Answers
• Group #3 - 4 areas of opportunity with existing plant facilities • System Isolation
• Up-to-date drawings of existing plant systems
• Personnel training
• Additional Spare Parts
• In what phase? Front End Engineering (FEED)
72
![Page 73: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/73.jpg)
Group Discussion
• My Answers • Group #4 – What actions should be taken if drawings are incorrect from
Design Engineering? • Design Engineering should be notified and any “field” modifications should be
approved by Design Engineering before being constructed or commissioned. Once approved, “As-built” drawings should be developed by “field” personnel and submitted to Design Engineering so that the corrections can be properly documented.
• Who is responsible for making the corrections to the incorrect drawings from Design Engineering? • Any “ field” personnel that finds the discrepancy and gets approval from Design
Engineering
• In what phase? Construction and Checkout and Commissioning
73
![Page 74: Planning for Start-Up - SCOAR · The focus of design is commonly on equipment and individual technical disciplines, rather than on systems. A systems-focus during design, involving](https://reader034.vdocuments.us/reader034/viewer/2022042310/5ed825070fa3e705ec0deb08/html5/thumbnails/74.jpg)
Questions
74