pinch analysis technique to optimize heat exchanger

25
Heat Exchanger Network Design using Pinch Analysis Project Report

Upload: k-vivek-varkey

Post on 19-Jun-2015

476 views

Category:

Technology


16 download

DESCRIPTION

Report of the project which was assigned to me during internship at ONGC, Hazira Plant

TRANSCRIPT

Page 1: Pinch analysis technique to optimize heat exchanger

Heat Exchanger Network Design using Pinch Analysis

Project Report

Page 2: Pinch analysis technique to optimize heat exchanger

K Vivek VarkeyIIT Hyderabad

Submitted to the Training In-charge, ONGC Hazira, in partial fulfilment of Summer Technical Training, 2014.

Page 3: Pinch analysis technique to optimize heat exchanger

Acknowledgements:

We would like to thank our mentor for providing motivation and the required data in full detail, due to which the process was highly hassle-free. Also we would like to convey gratitude to the ONGC Hazira administration for arranging the training and allowing us to pursue this project.

Page 4: Pinch analysis technique to optimize heat exchanger

Introduction

Any process is an energy sink, demanding high amount of heat addition or removal, that ask for individual high costs, especially in a large process plant. A process may employ numerous heat exchangers to bring the process stream at required temperatures at the various stages. Operation of these all heat exchangers with their individual cooling utilities and heating utilities demand a high operating cost on a daily basis.It is hence beneficial to strategize the heat exchanger network layout so as to couple the hot and cold process streams, so that minimum heat duty is to be supplied or removed using the external utilities.

However design of an optimal heat exchanger network (HEN) so as to employ minimum operating costs keeping in mind the installation costs are also not out of proportion, is a complicated method. Hence several algorithms and famous approaches exist.This project employs the PINCH ANALYSIS of the energy flow to determine the optimal HEN structure for the CFU in the ONGC Hazira plant. The report does not deal with the derivation of the pinch technique, as several can be found in literature.The data are taken from the design report existing in the plant. The particular case deals with an inlet temperature of 33oC and inlet pressure of 93Kg/cm2.The heat duties are calculated in an ideal scenario, from the material balances, temperatures and enthalpy data taken from the web.

We deal with the 5 heat exchangers namely, E701, E702, E703, E705 and E706.E704 is not dealt with for reasons of unavailability of data.

Page 5: Pinch analysis technique to optimize heat exchanger

STRIPPER

LPG

Reflux Drum

Preheater

Off Gas Cooler

LPG Condenser

NGL Cooler

Reboiler

Feed

Off Gas to GSU

LPG to CW

Naptha to storage

Process Flow Diagram

Feed from Slug Catcher at 33oC and 93Kg/cm2

PFD shown only for elements associated with this project.

Vapour

Condensate

1

5

7

3

4

2

8

6

Page 6: Pinch analysis technique to optimize heat exchanger

Material Balance

Component 1 2 3 (liquid) 3(vapor) 4(liquid) 4(vapor) 5 6 7 8N2 0.02 0.01 0 0.01 0 0 0 0 0 0.02H2S 1.36 0.13 0.75 0.48 0 0 0 0 1.23 1.36CO2 40.46 7.15 12.11 21.2 0 0 0 0 33.31 40.46C1 266.56 72.14 40.82 153.6 0 0 0 0 194.42 266.56C2 68.51 7.5 34.02 26.99 0 0 0 0 61.01 68.51C3 90.32 4.76 68.18 17.38 12.69 45.56 58.25 0 27.31 32.07iC4 28.99 0.9 25.22 2.87 7.18 16.42 23.6 0 4.49 5.39nC4 45.74 1.13 41.21 3.4 13.32 25.95 39.16 0.11 5.34 6.47iC5 19.49 0.27 18.55 0.67 8.22 9.93 0.11 18.04 1.07 1.34nC5 22.4 0.26 21.54 0.6 10.14 11.04 0.01 21.17 0.96 1.22C6 32.03 0.18 31.54 0.31 19.39 11.95 0 31.34 0.51 0.69C7 38.59 0.11 38.35 0.13 28.22 10.03 0 38.25 0.23 0.34C8 47.64 0.07 47.51 0.06 39.45 8.02 0 47.47 0.1 0.17C9 25.29 0.02 25.26 0.01 22.58 2.67 0 25.25 0.02 0.04C10 15.5 0.01 15.49 0 14.5 0.99 0 15.49 0 0.01C11 17.73 0 17.73 0 17.02 0.71 0 17.73 0 0C12+ 7.96 0 7.96 0 7.77 0.19 0 7.96 0 0

All flows are in Kmol/hr.

Page 7: Pinch analysis technique to optimize heat exchanger

Cp values for the required components

Page 8: Pinch analysis technique to optimize heat exchanger

The values of the components in the CFU unit is obtained. Following which the respective mole fraction in each stream is also obtained. These two data are used simultaneously and the weighted mean is to obtained the overall specific heat value.

Cp values for the required components

Page 9: Pinch analysis technique to optimize heat exchanger

PROCEDURE

The method used is called Temperature Interval Method of Pinch Analysis

1. The Cp value obtained is multiplied by the flow rate to obtain the heat capacity flow rate (C).

2. Now we create the following table for the further calculation.

The approach temperature is taken to be 10 degree Celsius. This is subtracted from both the inlet and outlet temperatures of the hot stream for the purpose of calculation, so as to obtain the pinch where the net heat exchange is supposed to be 0. this is put in is Tout* and Tin* in the tables.

Page 10: Pinch analysis technique to optimize heat exchanger

E-702 (Stipper Reboiler) C2

Assumptions:• Stripper reboiler operates at constant 156oC, and main heat consumption is to cause phase change.• Stripper column bottoms is saturated liquid and the outlet composition is same as the feed to the LPG column.• Heat duty is calculated by determining the amount of latent heat required.

T = 156ocM = 344 Kmol/hrQ = - 959.03 KW

E-703 (LPG Condenser) H1

Assumptions:• Constant operation temperature of 43oC• Feed is saturated vapour from the LPG column top and outlest stream is saturated liquid.• Heat duty is calculated from the latent heat calculations.

T = 43oCM = 121.13 Kmol/hrQ = + 627.55 KW

Page 11: Pinch analysis technique to optimize heat exchanger

E-705 (NGL Cooler) H2 Assumptions:• The inlet and outlet temperatures are respectively 175oC and 45oC.• The composition is known from the mass balance.• No phase change.

Tf = 45oCTi = 175oCCp = .244 KJ/mol KM = 222.81 Kmol/hr

M*Cp = 15.10 KW/KQ = + 1963.0 KW

Page 12: Pinch analysis technique to optimize heat exchanger

E-706 (Off Gas Cooler) H3

Assumptions:• Inlet and outlet temperatures are respectively 125oC and 40oC.• No phase change.• Composition is given in the material balance.

Tf = 40oCTi = 125oCCp = 0.044 KJ/mol KM = 424.65 Kmol/hr

M*Cp = 5.20 KW/KQ = + 442 KW

Hence summing all the enthalpy requirements of the streams we get,C1+C2+H1+H2+H3 = + 1801.52 KW

Hence the Q min, req is + 1801.52 KW that must the removed somewhere in the process using cooling utilities

Page 13: Pinch analysis technique to optimize heat exchanger

PROCEDURE

3. Now we draw a diagram where we label the adjusted temperatures in order from coldest to hottest and we draw arrows to designate streams overlapping these temperature intervals.

Page 14: Pinch analysis technique to optimize heat exchanger

PROCEDURE

4. Now for each interval in the previously drawn figure we find the enthalpy of each intervals. This is obtained by adding the heat capacity flow rates ( for hot streams it is considered positive and negative for the cold stream ). This is then multiplied by the temperature interval for which we are calculating and the values are written right next to the respective intervals in the figure labelled under Q.

5. These values are then added cumulatively from the top to the bottom ( higher temperature to colder temperature ). The obtained data is then written in a new column Qres.

6. The least value in the Qres column is called the pinch value and the temperature of that interval is called the pinch temperature.7. The pinch value is then added from the beginning of the values in Qres. It is observed that it becomes 0 at the pinch point.8. The pinch value is the hot utility added and the final value obtained ( in this case 2005.55 ) becomes the cold utility required.

Page 15: Pinch analysis technique to optimize heat exchanger

Hence we determine our pinch temperature as 115oC for the Cold streams and 125oC for the Hot streams.

Also MER (minimum energy requirement) targets:• Qhot utility = -204.43 KW (to be added by steam)• Qcold utility = 2005.55 KW (to be removed by cooling water)

As per the method the hot utility can only be used above pinch, and cold utility can only be used below pinch.

Before we start coupling a hot stream with a cold stream we should keep one thing in mind. Let the specific heat flow rate of the hot stream be Ch and that of the cold stream be Cc . If we are trying to couple in the hot side of the pinch it has to be made sure that Cc > Ch of the respective streams. Similarly when we are trying to couple in the cold side of pinch it should be taken care that Ch > Cc . Otherwise the stream coupling will become infeasible.

In the next page we draw a pinch decomposition of the streams and determine an optimal heat exchanger network.

Page 16: Pinch analysis technique to optimize heat exchanger

PROOF

Let us assume a counter current pair of hot and cold stream.Thi and Tho are respectively the inlet and outlet temperature of the hot stream.Tci and Tco are respectively the inlet and outlet temperature of the cold stream.∆T1 and ∆T2 are respectively the difference between hot inlet and cold inlet and hot inlet and cold outlet.Q is the energy exchanged

Ch Cc are respectively the specific heat flow rates for the hot and cold streams.

Page 17: Pinch analysis technique to optimize heat exchanger

PROOF

Q = Ch * [ Thi - Tho ] Q = Cc * [ Tco - Tci ]

After rearranging we get,

Thi - Tho = Q/Ch Tco - Tci = Q/Cc

now we subtract the equations to get

∆T2 - ∆T1 = Q*[Cc - Ch ]/Cc Ch

Page 18: Pinch analysis technique to optimize heat exchanger

PROOF

HOT SIDE OF THE PINCH

∆T1 = ∆TMIN

Hence, ∆T2 = ∆Tmin + Q*[Cc - Ch ]/Cc Ch now, ∆T2 has to be greater than ∆Tmin hence, Cc > Ch COLD SIDE OF THE PINCH

∆T2 = ∆T min Hence, ∆T1 = ∆Tmin - Q*[Cc - Ch ]/Cc Ch

now ∆T1 has to be greater than ∆Tmin

hence, Ch > Ch

Page 19: Pinch analysis technique to optimize heat exchanger

In the next page we draw a pinch decomposition of the streams and determine an optimal heat exchanger network.

Page 20: Pinch analysis technique to optimize heat exchanger

H1

H2

H3

C1

C2

175 125

156156

125 45

125

43

43 33

40

43

PINCH

H=204.03

H=755

H=272

H= 627.55

H=936

H=442

Heating Utility

Heat Exchanger

Cooling Utility

Heat loads of Exchangers mentioned are in KW.Temperature is in Celsius

Above pinch Below pinch

Page 21: Pinch analysis technique to optimize heat exchanger

The above the diagram can be explained by taking an example from the actual streams.

So in the hot side of the pinch we see a hot stream E-705 going from 175˚C to 125 ˚C with a heat capacity flow rate of 15.1 KW/K. this would give out a heat of

15.1*[175-125] KW = 755 KW

Now, when we couple this hot stream with a cold stream , E-702, this 755 KW of energy can be utilised by the cold stream which actually requires energy of 959.03 KW. For the excess 204.03 KW, that is required for the cold stream, we provide it with a hot utility of the same amount.

Similarly we obtain the other hot and cold utilities required.

Page 22: Pinch analysis technique to optimize heat exchanger

Results and Discussions:The exchanger network drawn allows for the MER targets . The streams are coupled and utilities are distributed keeping in mind the temperature interval of 10, and the subsequent corollary that heating utilities can only be used above pinch and cooling utilities can only be used below pinch.

The main purpose of this design is to allow for energy recycle, a term synonymous with the modern era and the global challenges we face. Though in this process it is not significant, some processes can self sustain themselves, that is we can achieve all temperature targets using very little external utilities. This leads to economic benefits and environmental benefits. The temperature interval method and pinch analysis as shown here can be utilised for all processes for energy recycle. The CFU here is only one example.

The project has several assumptions of ideality and some figures are rounded off to allow for smooth calculations. Hence for application of the process, this is a rough schematic, more accurate measurements, considerations and calculations are required. Also installation costs and restrictions must be considered when determining heat exchanger area.

As per the calculation shown, • 204.03 kW hot utilities• 2005.55 kW cold utilities is required.

Page 23: Pinch analysis technique to optimize heat exchanger

Results and Discussions:

Current energy requirement

Heating utilities

QE-701 + QE-702

= 27.2*[33-43] + [-959.03]= 1231.03 kW

Cooling utilities

QE-7.03 + QE-705 + QE-706

= 627.55 + 15.1*[175-45] + 5.2*[125-40] = 3032.55 kW Therefore the energy that can be saved in terms of percentage :- • 83.4% for heating utilities• 33.8% for cooling utilities

Page 24: Pinch analysis technique to optimize heat exchanger

Comments:

Upon supervision by the mentor the following drawbacks were observed :-

1. The NGL cooler is not always in functioning. It is used generally only during abnormal functioning of C-702

2. In this project it was taken into assumption that everything in reboiler vaporised at 100%. However, this is not the case.

3. E-704 was not used in the calculation.

Page 25: Pinch analysis technique to optimize heat exchanger

References:

www.engineeringtoolbox.xomwww.wikipedia.comwww.cheresources.com

Process and Product Design (Seeder)Nptel open courseware