picard ebook

Upload: thato-merapelo-pule

Post on 27-Feb-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 Picard eBook

    1/26

    PicardConsult LLCA leader in labor productivity measurement and analysis

    Labor Productivity

    Measurement and

    Analysis on

    Heavy Construction

    Projects

    PicardConsult LLC Next

    http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    2/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Our purpose is to help project management achieve their goal of completing

    their project as early, cost-effectively, and safely as possible.

    Dr. Hans Picard

    PicardConsult LLC

    Welcome!

    1Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    3/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Contents

    The Productivity Challenge 3

    The Opportunity 4

    The Approach: Measure Workforce Activity 5

    Key Performance Measures 6

    Where Are Labor Dollars Spent? 7

    Continuous Improvement 8

    Sample Results 9

    Best Practices (Part I) 10

    Best Practices (Part II) 11

    Summary 12

    Conclusions 13

    For More Information 14

    Click a chapter title to advance to that page

    2Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    4/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC 3

    The Productivity Challenge

    For decades, the trend of construction labor productivity

    has remained stagnant in comparison to all non-farm

    productivity (see the figure at right).

    The high costs associated with budget and schedule

    overruns in the heavy construction industry can often

    be traced to low worker productivity. Labor cost is less

    predictable and runs a greater chance of overruns thaneither equipment or material costs. As labor costs can

    amount to 50 percent or more of construction project

    costs, management of the work process presents the

    greatest opportunity to reduce project cost.

    Improving labor productivity results in reduced labor

    costs, faster job completion time, and direct savings

    at the bottom line. Conversely, cost overruns are the

    result of low productivity, more workers, and longer

    completion times.

    250.00%

    200.00%

    150.00%

    100.00%

    50.00%

    0.00%1969 1968 1972 1976 1980 1988 1992 1996 2000

    Construction & Non-Farm Labor Productivity Index (1964-2003)Constant $ of contracts/workhours of hourly workers Sources: US Dept. of Commerce, Bureau of Labor Statistics

    Construction Productivity Index

    (1964 = 100%)

    Non-Farm Productivity Index(1964 = 100%)

    In the last 40 years, construction productivity has

    lagged behind productivity in other industries.

    Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    5/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    The Opportunity

    Significant gains can be realized by enabling craft workers to become more efficient, and by enabling project managers

    and field supervision to execute effectively. Ignoring these potential gains represents a lost opportunity.

    The best way to improve labor productivity is to examine the work process from the workers perspective. How can

    assigned tasks be completed more easily, efficiently, and safely? The goals are to enable:

    Craft labor to spend maximum time workinginstead of walking or waiting

    Field management to provide all the tools, materials, and guidance when and where craft labor need them

    This approach serves craft labor as customers of the management system.

    4

    PicardConsult LLC worked with Dynegy on

    a successful project of continuous process

    improvement at the Baldwin Energy Complex in2010. This is an excerpt of a video on that project.

    Used by permission. See www.dynegy.comfor more

    information.

    t Click on the video to play a short video about Dynegys take on

    the opportunity to enhance efficiency in large construction projects.

    Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.dynegy.com/http://www.dynegy.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    6/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    The Approach: Measure Workforce Activity

    While typical project reports show progress and results compared to estimates, and are after the fact, they are usuallyproduced too late to provide timely information that can be used to adjust the work process. Useful data about the

    effectiveness of field management and contract labor productivity requires a system of data collection, storage,

    and information retrieval that measures and assesses the actual work process. To meet this need, PicardConsult LLC

    commissioned development of a contractor performance measurement system that was designed to meet these specific

    requirements. PicardConsult LLC then implemented this system on its construction and major maintenance outage projects.

    Not surprisingly, measurable differences were found between the labor productivity of various contractors and projects.

    A critical component of this system is daily measurement reports, which enable management to drill down and analyze the

    actual labor activities performed to a granular level. Using this near-real time information, management and supervision

    can take prompt corrective action, when required. Daily measurement provides the necessary insight into daily variation in

    the work process, as shown in the figure.

    The focus on measuring work process performance

    provides a link between field managements

    decisions and productive or value-added labor.

    These highly visible links not only raise awareness,

    but speak loudly and clearly to indicate

    opportunities for improvement of the work

    process.

    90

    85

    80

    75

    7065

    60

    55

    50

    45

    40

    1/3/02 1/11/02 1/21/02 1/29/02 2/6/02 2/14/02 2/22/02 3/4/02 3/12/02 3/20/02 3/28/02

    Average 60.4%

    StdDev 5.2%

    DW% Near real-time measurement of direct work (productive

    labor utilization) enables adjustments to improve the

    work process.

    DW%isDirec

    tWorkPercent

    5Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    7/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Key Performance Measures

    The following key performance indices (KPIs), related to

    the utilization of the craft workforce, are critical to project

    success:

    Labor utilization:This is shown in the previous slide.

    It is the percent value-added, non-value-added, or

    wasted time.

    6Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    8/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Key Performance Measures

    The following key performance indices (KPIs), related to

    the utilization of the craft workforce, are critical to project

    success:

    Labor utilization:This is shown in the previous slide.

    It is the percent value-added, non-value-added, or

    wasted time.

    Field supervision effectiveness. This is the percentof the time that superintendents and foremen are

    available to their crews in work areas.

    6Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    9/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Key Performance Measures

    The following key performance indices (KPIs), related to

    the utilization of the craft workforce, are critical to project

    success:

    Labor utilization:This is shown in the previous slide.

    It is the percent value-added, non-value-added, or

    wasted time.

    Field supervision effectiveness. This is the percentof the time that superintendents and foremen are

    available to their crews in work areas.

    Craft accountability.This is categorized by trade. It

    is the percent of time craft labor are observed/not

    observed in their assigned work areas.

    6Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    10/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Where Are Labor Dollars Spent?

    Productive labor utilization is a major variable in construction labor productivity. Other important variables that effect laborproductivity are efficiency and quality of work, both of which are linked to craft skills and field supervisions expertise.

    Labor Productivity = Productive Labor Utilization x Efficiency x Quality of Work

    The metric Productive Labor Utilization brings to light an

    important variable of the labor productivity formula. With

    a given workforce, the greater the productive labor

    utilization, the less labor-hours are used to complete the

    project. Work is accomplished in less time and at lowercost, getting more done for less. PicardConsult LLC

    experience confirms that work process measurement

    and analysis improves results at relatively low cost.

    The figure shows an example result of productive labor

    utilization measurement. It shows the proportions of

    various labor activities observed and recorded at random

    intervals over an extended period of project execution.Many labor dollars are spent in non-productive activity

    due to various delays, interferences or roadblocks.

    There is, in fact, a hidden cost of labor: the unproductive

    labor dollars spent.

    Work expands to fill the time and spend the

    budgeted labor dollars available for its completion.

    Dr. Picards version of Parkinsons Law

    7Next | Back | Table of Contents

    Roll over this frame to find the

    total productive,

    indirect, and lost work...

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    11/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Continuous Improvement

    Eliminating the hidden cost of labor is a continuous

    process of gradual improvement. Awareness is raised

    through continuous assessment of the work process.

    Depending on the incentive offered, prompt action is

    taken to improve it.

    Labor productivity improves gradually as more labor-

    hours are spent in value-adding activities. Progressive

    labor-hour reduction is a natural result of an increasingly

    more efficient construction work process. This in turn

    results from the growing maturity of field management

    practices, as shown in the table.

    8

    MaturityLevel

    4

    3

    2

    1

    70% -80%

    60% - 70%

    50% - 60%

    40% - 50%

    ProductiveUtilization

    Progressive ConstructionWork Process Management

    Complete, planned work scopes; competitive estimates; just-in-timeleanmanpower scheduling; self-sufficientwork areas; trained, proactive fieldsupervision; craft briefings; project stakeholders fully aligned to targets;continuous improvement

    Customer-contractor joint planning and collaboration; labor productivity

    benchmarking, metrics and incentives; gain-sharing; buy-in by projectstakeholders; quick corrective action

    Labor productivity improvement is considered in pre-planning; most toolsand materials pre-staged; some improvements made during projectexecution

    Project is managed by the contract, just-in- case manpower; if problems,hire more; work process performance/productivity data not consideredrelevant

    Labor Productivity Linked with Management Practice

    Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    12/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Sample Results

    The figure shows how the productive labor utilizationincreased at a major midwestern power plant Clean

    Air project. The project installed selective catalytic

    reduction (SCR) for nitrogen oxides emission control,

    then flue gas desulfurization (FGD) scrubbers for

    sulfur oxides emission control. The project involved a

    workforce of over 200 crafts.

    A streamlined work process has minimal non-value-

    added activity, such as walking, or waste, such as

    waiting, and enables labor to complete tasks in less

    time. Comparing labor utilization over the course of

    the multi-year Clean Air construction project shows the

    share of direct labor cost that was productive. A relative

    labor dollar savings of 22 percent is made available

    through continuous improvement of the work process.

    Contractor Labor Use

    (proportions of monthly $1,093,625 labor spend)

    $1,000,000

    $800,000

    $600,000

    $400,000

    $200,000

    $02002 20072005 - 2006

    Productive $638,728 $828,321 $874,900Indirect $285,630 $144,866 $131,325

    Wasted $169,267 $120,438 $87,490

    Productive

    Indirect

    Wasted

    Productive work increased from 58% to 80% via adoption of

    this continuous improvement approach on a power Clean Air

    construction project.

    9

    58%

    76%

    80%

    Next | Back | Table of Contents

    How was this result achieved?

    Click to reveal the answer

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    13/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Sample Results

    The figure shows how the productive labor utilizationincreased at a major midwestern power plant Clean

    Air project. The project installed selective catalytic

    reduction (SCR) for nitrogen oxides emission control,

    then flue gas desulfurization (FGD) scrubbers for

    sulfur oxides emission control. The project involved a

    workforce of over 200 crafts.

    A streamlined work process has minimal non-value-

    added activity, such as walking, or waste, such as

    waiting, and enables labor to complete tasks in less

    time. Comparing labor utilization over the course of

    the multi-year Clean Air construction project shows the

    share of direct labor cost that was productive. A relative

    labor dollar savings of 22 percent is made available

    through continuous improvement of the work process.

    Contractor Labor Use

    (proportions of monthly $1,093,625 labor spend)

    $1,000,000

    $800,000

    $600,000

    $400,000

    $200,000

    $02002 20072005 - 2006

    Productive $638,728 $828,321 $874,900Indirect $285,630 $144,866 $131,325

    Wasted $169,267 $120,438 $87,490

    Productive

    Indirect

    Wasted

    Productive work increased from 58% to 80% via adoption of

    this continuous improvement approach on a power Clean Air

    construction project.

    9

    58%

    76%

    80%

    Next | Back | Table of Contents

    The following best practices promote a productive

    change in the construction work process.

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    14/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Best Practices (Part I)

    PicardConsult LLC suggests that project managers apply proven best practices to

    systematically improve project performance, project control, and labor productivity.

    Project management and contractors have some or substantial control over areas

    in which these practices can be used. Working together to implement these best

    practices can significantly reduce project cost and duration.

    Measure Labor Utilization.Collect data daily by random observation; analyze

    and report the data the same day.

    10Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    15/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Best Practices (Part I)

    PicardConsult LLC suggests that project managers apply proven best practices to

    systematically improve project performance, project control, and labor productivity.

    Project management and contractors have some or substantial control over areas

    in which these practices can be used. Working together to implement these best

    practices can significantly reduce project cost and duration.

    Measure Labor Utilization.Collect data daily by random observation; analyze

    and report the data the same day.

    Create Lean, Self-Sufficient Work Areas and Point-of-Use Logistics. Maximize

    craft productive activity by eliminating the need to travel away from the

    workface or wait for foreman support, supplies, tools, or information.

    10Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    16/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Best Practices (Part I)

    PicardConsult LLC suggests that project managers apply proven best practices to

    systematically improve project performance, project control, and labor productivity.

    Project management and contractors have some or substantial control over areas

    in which these practices can be used. Working together to implement these best

    practices can significantly reduce project cost and duration.

    Measure Labor Utilization.Collect data daily by random observation; analyze

    and report the data the same day.

    Create Lean, Self-Sufficient Work Areas and Point-of-Use Logistics. Maximize

    craft productive activity by eliminating the need to travel away from the

    workface or wait for foreman support, supplies, tools, or information.

    Constantly Balance Crew Size with Actual Workload. Use just-in-time staffing

    to provide just the right numbers of crafts on the job to achieve a target

    productive level of labor utilization.

    10Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    17/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Best Practices (Part I)

    PicardConsult LLC suggests that project managers apply proven best practices to

    systematically improve project performance, project control, and labor productivity.

    Project management and contractors have some or substantial control over areas

    in which these practices can be used. Working together to implement these best

    practices can significantly reduce project cost and duration.

    Measure Labor Utilization.Collect data daily by random observation; analyze

    and report the data the same day.

    Create Lean, Self-Sufficient Work Areas and Point-of-Use Logistics. Maximize

    craft productive activity by eliminating the need to travel away from the

    workface or wait for foreman support, supplies, tools, or information.

    Constantly Balance Crew Size with Actual Workload. Use just-in-time staffing

    to provide just the right numbers of crafts on the job to achieve a target

    productive level of labor utilization.

    Provide Foremen with 1-3 day Look-ahead Schedules.This enables foremento anticipate roadblocks that could cause delays. This should also include plan

    B tasks when scheduled tasks cannot be performed.

    10Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    18/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Best Practices (Part II)

    Maximize Foremen Availability to Crews

    in Work Areas.The figure shows that higher

    foreman availability translates into higher

    productivity. Locate foremans desks in the work

    area and equip crafts with two-way radios to

    obtain tools and materials, thus maximizing

    foreman workface time.

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    65.0% 70.0% 75.0% 80.0% 85.0% 90.0%

    FMAv

    DW

    R

    2

    = 0.4324

    Direct Work vs Foreman AvailablityFGD Projects 2006 - 2007

    11Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    19/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Best Practices (Part II)

    Maximize Foremen Availability to Crews

    in Work Areas.The figure shows that higher

    foreman availability translates into higher

    productivity. Locate foremans desks in the work

    area and equip crafts with two-way radios to

    obtain tools and materials, thus maximizing

    foreman workface time.

    Institute Continuous Improvement. Set

    realistic yet demanding targets; raise the bar on

    each succeeding project to drive continuous

    improvement.

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    65.0% 70.0% 75.0% 80.0% 85.0% 90.0%

    FMAv

    DW

    R

    2

    = 0.4324

    Direct Work vs Foreman AvailablityFGD Projects 2006 - 2007

    11Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    20/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Best Practices (Part II)

    Maximize Foremen Availability to Crews

    in Work Areas.The figure shows that higher

    foreman availability translates into higher

    productivity. Locate foremans desks in the work

    area and equip crafts with two-way radios to

    obtain tools and materials, thus maximizing

    foreman workface time.

    Institute Continuous Improvement. Set

    realistic yet demanding targets; raise the bar on

    each succeeding project to drive continuous

    improvement.

    Management Support Essential. Contractually

    establish a cooperative relationship in which the

    results of improvement benefit the contractor,

    crafts, and owner.

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    65.0% 70.0% 75.0% 80.0% 85.0% 90.0%

    FMAv

    DW

    R

    2

    = 0.4324

    Direct Work vs Foreman AvailablityFGD Projects 2006 - 2007

    11Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    21/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Summary

    To promote labor productivity on heavy construction projectsand save time and money, improve the work process. Use best

    practices based on these approaches:

    Approach construction project execution as a production

    work process

    Distinguish what craft activities add value to the work

    process, and what activity is unproductive or wasteful

    Define needed improvement areas to increase efficiency of

    the work process

    Institute continuous improvement of the work process

    12Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    22/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Summary

    To promote labor productivity on heavy construction projectsand save time and money, improve the work process. Use best

    practices based on these approaches:

    Approach construction project execution as a production

    work process

    Distinguish what craft activities add value to the work

    process, and what activity is unproductive or wasteful

    Define needed improvement areas to increase efficiency of

    the work process

    Institute continuous improvement of the work process

    Collect real-time labor utilization data at the points where

    the work is done

    Use statistical methods to analyze the level and variation of labor performance

    Identify and quantify labor productivity constraints and areas of opportunity

    Determine the lean workforce size, in balance with actual workloads

    12Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    23/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Summary

    To promote labor productivity on heavy construction projectsand save time and money, improve the work process. Use best

    practices based on these approaches:

    Approach construction project execution as a production

    work process

    Distinguish what craft activities add value to the work

    process, and what activity is unproductive or wasteful

    Define needed improvement areas to increase efficiency of

    the work process

    Institute continuous improvement of the work process

    Collect real-time labor utilization data at the points where

    the work is done

    Use statistical methods to analyze the level and variation of labor performance

    Identify and quantify labor productivity constraints and areas of opportunity

    Determine the lean workforce size, in balance with actual workloads

    Introduce new visibility and accountability in project performance management and field supervision

    Provide daily contractor/craft reports and trend labor utilization data

    Monitor productive labor utilization against estimate-independent benchmarks

    Present real-time data that enables project managers and field supervision to proactively address problems

    12Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    24/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    Conclusions

    13

    With relatively little, but consistent effort, construction projects can be

    completed using less labor than conventionally estimated by minimizing

    wasted resources and maximizing benefits in the process.

    Dr. Hans Picard

    PicardConsult LLC

    Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    25/26

    PicardConsult LLC A leader in labor productivity measurement and analysis

    PicardConsult LLC

    About PicardConsult LLC

    PicardConsult LLC is a leader in labor productivity measurement and analysis. With its

    robust Work Process Analytics Deming/Six Sigma-based technology, PicardConsult

    LLC provides clients real-time craft and foreman utilization metrics to support timely,

    fact-based decision making. Productivity improves as the utilization of the craft

    workforce and the effectiveness of trades foremen improves.

    Quantifying and reducing non-productive craft activity, such as excessive waiting

    or walking, which is often associated with heavy engineering construction and

    maintenance, boosts productivity and can generate labor cost savings of 20 to 30

    percent, or more, through continuous process improvement.

    PicardConsult LLC has established a reputation of delivering results for more than 30

    years by assisting managers to do more with less. Picard Consult LLC offers on-site

    training in data collection, treatment, analysis, and reporting.

    Clients include Kansas City Power & Light, Tennessee Valley Authority (T VA), The

    Southern Companies, Cinergy/Duke Energy, Dynegy Midwest, Corn Products

    International, and Cameco Corporation.

    PicardConsult LLC is led by Dr. Hans Picard, Mine Eng., ScD Metallurgy, MBA.

    14Next | Back | Table of Contents

    http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/http://www.picardconsult.com/
  • 7/25/2019 Picard eBook

    26/26

    PicardConsult LLCA leader in labor productivitymeasurement and analysis

    For More Information

    For more information, contact

    PicardConsult LLC

    PO Box 1046

    Tryon, NC 28782 USA

    828-859-3129 office

    828-859-3169 fax

    [email protected]

    PicardConsult.com

    Back | Table of Contents

    mailto:info%40picardconsult.com?subject=Inquiry%20from%20eBookhttp://www.picardconsult.com/http://www.picardconsult.com/mailto:info%40picardconsult.com?subject=Inquiry%20from%20eBook