phos progress in ls1

4
PHOS progress in LS1 Alexander Vinogradov 11 August 2014

Upload: keilah

Post on 06-Feb-2016

31 views

Category:

Documents


0 download

DESCRIPTION

PHOS progress in LS1. Alexander Vinogradov 11 August 2014. Work done since 28.07.2014. See PHOS LS1 planning: https://twiki.cern.ch/twiki/pub/ALICE/PhosSRU/PHOS_LS1_schedule-20140513.pdf. Modules M2 and M3: - Transported to P2 July, 31. Module M1: - Lab test is over - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: PHOS progress in LS1

PHOS progress in LS1

Alexander Vinogradov 11 August 2014

Page 2: PHOS progress in LS1

Work done since 28.07.2014

See PHOS LS1 planning:https://twiki.cern.ch/twiki/pub/ALICE/PhosSRU/PHOS_LS1_schedule-20140513.pdf

• Modules M2 and M3:

- Transported to P2 July, 31

Page 3: PHOS progress in LS1

• Module M1: - Lab test is over https://twiki.cern.ch/twiki/pub/ALICE/PhosSRU/0802_Module1_Commissioning.pdf

- Moved to B-167 store area, need the air-tightness test (The test is planning for end of August, Yannick)

• Module M4: - Moved to testing area. - Readout test of opened module in progress.

• Cooling station: - Lab test is over. - Transported to P2 and installed to UX25 August,5:

Page 4: PHOS progress in LS1

Work at P2

• Cable trays installing in progress.

• Fixation trays production for ethernet cables in progress.

• Additional power cables laying for PHOS/DCAL STU modules in progress.

• LV cables from Patch panel to PHOS modules is planning nearest time.

Note:Updates on SRU/STU/TRU problems and common firmware development

for PHOS/EMCAL/DCAL to be discussed at 18.08.14