PHOS progress in LS1. Alexander Vinogradov 11 August 2014. Work done since 28.07.2014. See PHOS LS1 planning: https://twiki.cern.ch/twiki/pub/ALICE/PhosSRU/PHOS_LS1_schedule-20140513.pdf. Modules M2 and M3: - Transported to P2 July, 31. Module M1: - Lab test is over - PowerPoint PPT PresentationTRANSCRIPT
PHOS progress in LS1
Alexander Vinogradov 11 August 2014
Work done since 28.07.2014
See PHOS LS1 planning:https://twiki.cern.ch/twiki/pub/ALICE/PhosSRU/PHOS_LS1_schedule-20140513.pdf
• Modules M2 and M3:
- Transported to P2 July, 31
• Module M1: - Lab test is over https://twiki.cern.ch/twiki/pub/ALICE/PhosSRU/0802_Module1_Commissioning.pdf
- Moved to B-167 store area, need the air-tightness test (The test is planning for end of August, Yannick)
• Module M4: - Moved to testing area. - Readout test of opened module in progress.
• Cooling station: - Lab test is over. - Transported to P2 and installed to UX25 August,5:
Work at P2
• Cable trays installing in progress.
• Fixation trays production for ethernet cables in progress.
• Additional power cables laying for PHOS/DCAL STU modules in progress.
• LV cables from Patch panel to PHOS modules is planning nearest time.
•
Note:Updates on SRU/STU/TRU problems and common firmware development
for PHOS/EMCAL/DCAL to be discussed at 18.08.14