PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr. Victor Huo, President/CEO Can-China Real Capital Inc. 8500 Leslie Street, Suite 560 Markham, Ontario Prepared by: Andre Breberina P. Geo 35 Fairview Avenue Grimsby, On, L3M 3L4 T: 1 (905) 945-7019 F: 1 (905) 945-9735 e-mail: [email protected] Project Number 18161 January 27, 2019

Upload: others

Post on 20-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

PHASE I ENVIRONMENTAL SITE ASSESSMENT

157 CROSS AVENUE

OAKVILLE

JANUARY, 2019

Prepared for:Mr. Victor Huo,

President/CEO

Can-China Real Capital Inc.

8500 Leslie Street, Suite 560

Markham, Ontario

Prepared by:

Andre Breberina P. Geo

35 Fairview Avenue

Grimsby, On, L3M 3L4

T: 1 (905) 945-7019

F: 1 (905) 945-9735

e-mail: [email protected]

Project Number 18161

January 27, 2019

Page 2: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page ii

TABLE OF CONTENTS

1.0 EXECUTIVE SUMMARY………………………………………… 1

2.0 INTRODUCTION…………………………………………………… 3

(a) Phase I Property Information………………………………… 3

3.0 SCOPE OF INVESTIGATION…………………………………… 4

3.1 Purpose…………………………………………………………… 4

3.2 Scope and Methodology………………………………………… 4

3.3 Disclosure of Interest…………………………………………… 4

3.4 Limitations and Use of this Report…………………………….. 4

4.0 RECORDS REVIEW……………………………………………….. 6

(a) General…………………...……………………………………… 6

(i) Phase One Study Area Determination………………………… 6

(ii) First Developed Use Determination…...……………………... 6

(iii) Fire Insurance Plans……..…………………………………... 6

(iv) Chain of Title………………………………………………… 6

(v) Environmental Reports……………………………………….. 7

(b) Environmental Source Information…………………………… 8

(c) Physical Setting Sources……………………………………….. 9

(i) Aerial Photographs………………………………………….… 9

(ii) Topography, Hydrology and Geology……………………….. 9

(iii) Fill Materials………………………………………………… 10

(iv) Water Bodies and Areas of Natural Significance..…………… 10

(v) Well Records………………………………………………….. 10

(d) Site Operating Records………………………………………. 11

5.0 INTERVIEWS……………………………………………………… 13

6.0 SITE RECONNAISSANCE……………………………………... 15

(a) General Requirements…………………………………………… 15

(b) Specific Observations of the Phase One Property………………19

Page 3: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page ii

(c) Written Description of Investigation………………………….. 19

7.0 REVIEW AND EVALUATION OF INFORMATION..………….. 22

(i) Current and Past Uses ………………………………………… 22

(ii) Potentially Contaminating Activity …………………………. 22

(iii) Areas of Potential Environmental Concern …………………. 22

(iv) Rationale for APECs ……………………..…………………. 22

(v) Phase One Conceptual Model …………….…….……………. 23

8.0 CONCLUSIONS…………………………………………………….. 31

9.0 REFERENCES……………………………………………………… 32

10.0 APPENDICES……………………………………………………… 34

TABLES

Table 1: Site Information………………………………………………… 4

Table 2: Contact Information ……………………………………………. 4

Table 3: Property Use Directories, Site Use………………………………. 7

Table 4: Property Use Directories, Surrounding Properties………………. 8

Table 5: Interview Information………….………………….……………. 15

Table 6: Photographic Log ………………………………………………. 15

Table 7: Table of Current and Past Uses of the Phase One Property.……. 22

FIGURES

Figure 1 – Phase One Property ……………………….…………………... 26

Figure 2 – Buildings, Structures and Adjacent Property Uses..…………... 27

Figure 3 – Water Bodies and ANSIs…………………….………………... 28

Figure 4 – Conceptual Site Model – PCAs………………………………... 29

Figure 5 – Phase One Property ANSIs…………………………………….. 30

APPENDICIES

Appendix A – Surveys

Appendix B – Topographic Map

Appendix C – Aerial Photographs

Appendix D – Qualifications of Assessor

Page 4: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page ii

Page 5: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 1

1.0 EXECUTIVE SUMMARY

At the request of Mr. Victor Huo of Can-China Real Capital Inc. (the Client), a Phase I

Environmental Site Assessment (P1-ESA) was conducted on a property municipally known as

157 Cross Avenue in the Town of Oakville, Ontario (the Site).

The assessment was conducted in accordance with the requirements set out in Schedule D

Phase One Environmental Site Assessments of the Ministry of Environment’s O. Reg 511/09.

The procedure involved a records review, site reconnaissance, and interviews.

The Phase I Study Area (SA) was set at 250 m.

(i) Current and Past Uses

Year Name of Owner Description of Property Use Property Use Other Observations from Aerial

Photographs, Fire Insurance Plans, etc…

2017 -

Present

Can-China Real

Capital Inc.

Retail Lighting Store Commercial Title search, direct observation, interview

with current manager of store and ower

2002 - 2017 1532628 Ontario

Limited

Retail Lighting Store Commercial Title search, direct observation, interview

with current manager of store

1983 - 2002 Marlene A Beer Restaurant - Armadillos Commercial Title search, street directories, aerial

photographs

Restaurant - Pete and Marty’s Commercial Title search, street directories, aerial

photographs

1978 - 1983 Roshorn Limited

(formerly) D.L.

Fowles Development Limited

Restaurant - Chew Chinese Food

Emporium

Commercial Title search, street directories, aerial

photographs

Undeveloped Undeveloped Title search, street directories, aerial

photographs

The following PCA was identified on the Phase One Property:

PCA 1 – Road salt transported by vehicles onto the parking lot of the Phase One

Property on the adjacent property and is considered a PCA – Not Specified. PCA 1 is

considered to represent an APEC to the Phase One Property on the parking area and

laneways.

The following PCAs were identified in the Phase One Study Area:

PCA 2 – There is a ground mounted transformer situated on a below ground concrete

vault located trans-gradient to the Phase One Property on the adjacent property and is

considered a PCA#55 - Transformer Manufacturing, Processing and Use. The

underground utility corridor from the vault runs westward on the adjacent property,

and would direct any contamination due to leakage of transformer oil away from the

Phase One Property, and therefore PCA 2 is not considered to represent an APEC to

the Phase One Property.

PCA 3 – There are two nested ground mounted transformers situated on a below

ground concrete vault located trans-gradient to the Phase One Property on the adjacent

property and is considered a PCA#55 - Transformer Manufacturing, Processing and

Use The underground utility corridor from the vault runs westward on the adjacent

property, and would direct any contamination due to leakage of transformer oil away

Page 6: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 2

from the Phase One Property, and therefore PCA 3 not considered to represent an

APEC to the Phase One Property.

PCA 4 – There is a railroad track approximately 200 m southeast of and downgradient

of the Phase One Property and is considered a PCA #46 Rail Yards, Tracks and Spurs.

As PCA 4 is downgradient of the Phase One Property, it is not considered to represent

an APEC to the Phase One Property.

PCA 5 – There is an automotive repair shop at 142 Cross Avenue approximately 75 m

south and downgradient of the Phase One Property and is considered a PCA#27 –

Garages and Maintenance and Repair of Railcars, Marine Vehicles and Aviation

Vehicles. As PCA 5 is downgradient of the Phase One Property, it is not considered to

represent an APEC to the Phase One Property.

PCA 6 – Historically, there has been a foundry until 1994 at 146 Cross Avenue south

of, and down gradient of the Phase One Property and is considered a PCA#32 – Iron

and Steel Manufacturing and Processing. As PCA 6 is downgradient of the Phase One

Property, it is not considered to represent an APEC to the Phase One Property.

PCA 7 – Historically, there has been an automotive repair shop at 142 Cross Avenue

approximately 75 m south and downgradient of the Phase One Property and is

considered a PCA#27 – Garages and Maintenance and Repair of Railcars, Marine

Vehicles and Aviation Vehicles, As PCA 7 is downgradient of the Phase One

Property, it is not considered to represent an APEC to the Phase One Property.

PCA 8 – Historically, there has been an autobody repair shop at 142 Cross Avenue

approximately 75 m south and downgradient of the Phase One Property and is

considered a PCA#10 – Commercial Autobody Shops. As PCA 8 is downgradient of

the Phase One Property, it is not considered to represent an APEC to the Phase One

Property.

PCA 9 – Historically, there has been a metal stamping shop at 142 Cross Avenue

approximately 75 m south and downgradient of the Phase One Property and is

considered a PCA#34 – Metal Fabrication. As PCA 9 is downgradient of the Phase

One Property, it is not considered to represent an APEC to the Phase One Property.

Road salt transported by vehicles onto the parking lot of the Phase One Property on the

adjacent property and is considered a PCA – Not Specified. PCA 1 is considered to represent

an APEC to the Phase One Property on the parking area and laneways. Road salt picked up by

vehicles on municipal roads may been transported onto the parking lot of the Phase One

Property where it may have leaked onto the parking pavement and leached into the soil below

resulting in sodium adsorption ratio impacts.

It is therefore a Phase II Environmental Site Assessment is required before a Record of Site

Condition can be submitted.

Page 7: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 3

2.0 INTRODUCTION

(a) Phase I Property Information

Table 1a: Site Information

Municipal Address 157 Cross Avenue, Oakville

Property Description (as per deed) “PT LT 14. CON3. TRAF SDS, PT 7-9. 20R5913.

Oakville. S/T 534539 S/T & T/W 589004”..

Property Identification Number (PIN) 24816-0048 (LT)

Assessment Roll Number 2401 030 010 02600 0000

Registered Owner Can-China Real Capital Inc.

Zoning MTC’ for Mid-town Transitional Commercial

Site Area/Shape Slightly irregular rectangular

Frontage 33.681 m on the northwest side of Cross Avenue

Depth 127.888 m.

Table 1b: Contact Information

Item Site Owner

Organization Can-China Real Capital Inc.

Contact Victor Huo

Title Owner

Address 8500 Leslie Street Suite 560, Markham ON. L3T 7M8

Canada

Phone 647-351-3688 ex 209

Table 1c: Client Information

Item Site Owner

Organization Can-China Real Capital Inc.

Contact Victor Huo

Title Owner

Address 8500 Leslie Street Suite 560, Markham ON. L3T 7M8

Canada

Phone 647-351-3688 ex 209

Page 8: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 4

3.0 SCOPE OF INVESTIGATION

3.1 Purpose

This P1-ESA was carried out in accordance with Part VII of the Ministry of Environment’s O.

Reg 511/09 and the requirements set out in Schedule D Phase One Environmental Site

Assessments .

The general objectives of the PI-ESA are:

• To develop a preliminary determination of the likelihood that one or more

contaminants have affected land or water on, in or under the phase one property.

• To determine the need for a phase two environmental site assessment

• To provide a basis for carrying out any phase two environmental assessment required.

• To provide adequate preliminary information about environmental conditions in the

land or water, in or under the phase one property for the conduct of a risk assessment

following completion of a phase two environmental site assessment.

3.2 Scope

The Phase I ESA scope of work included:

• A records review.

• Interviews.

• Site Reconnaissance.

• An evaluation of the information gathered from the records review, interviews, and the

site reconnaissance.

• A phase one conceptual site model

• Conclusions determining whether a phase two environmental site assessment is

required before a record of site condition can be submitted.

3.3 Disclosure of Interest

The author does not have any material interest, direct or indirect, in the Site or the Client.

Except for remuneration and information research fees received for the performance of this

assessment, the author will not receive any profit or specialized information from the Client

that would benefit the author.

3.4 Limitations and Use of this Report

The data reported and the findings, observations, and conclusions expressed in this report are

limited by the Scope of Work.

Page 9: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 5

The author has conducted this assessment in accordance with generally accepted professional

practices, as performed at the same or similar locations related to the nature of this assigned

work. The author’s services are not subject to any expressed or implied warranties

whatsoever.

The author has accepted information provided by third parties in good faith, but has not

completed independent evaluations as to the accuracy or completeness of such information,

and shall therefore not be responsible for any errors or omissions contained in such

information.

The Site inspection pertaining to this assessment, and associated findings, observations, and

opinions, are based solely on the Site conditions encountered at the time of the investigation.

Changes in conditions may occur after the completion of this investigation. The passage of

time, manifestation of latent conditions, or future events, may require further study, analysis

of data, and re-evaluation of the findings, observations, and conclusions in this report.

This report is provided as a measure of due diligence and to assess risks with respect to

environmental soil impairment, but it should not be considered as exhaustive or absolute in

coverage; no investigation can totally eliminate the possibility that environmental impairment

may exist at a site.

Regulatory requirements or their interpretations may be revised by the governing agencies,

resulting in future changes to the recommended works, or remediation needs.

The conclusions presented in this report are professional opinions based upon data and

conditions described herein. They are intended only for the purpose, site, and project

indicated. This report is not a definitive study of contamination at the site, and should not be

interpreted as such. A qualitative evaluation of soil conditions was not performed as part of

this investigation. No sampling or chemical analyses of structural materials or other

equipment, processes, or related media was performed in this study unless explicitly stated.

This report presents professional opinions and findings of a scientific and technical nature.

Because of the stated limitations, the findings, observations, opinions and conclusions

expressed by the author in this report are not, nor should not be, considered an opinion

concerning the compliance of any past or present owner of the site, with any Federal,

Provincial, or municipal law or regulation.

The report shall not be construed to offer legal opinion or representations as to the

requirements of, nor compliance with, environmental laws, rules, regulations or policies of

Federal, Provincial or local government agencies.

The author has prepared this report for the exclusive use of the Client. This report shall not be

used or relied upon by outside parties without the written consent of the author. Any use of

this report constitutes acceptance of the limits of liability that may apply to the author. Any

such liability extends only to the client of the author and not to any other parties who may

obtain the report.

If new information or conditions of concern are discovered during future work, including Site

assessments, excavations, borings, or other studies, the author should be requested to re-

evaluate the assessments and conclusions presented in this report and to provide amendments

as required.

Page 10: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 6

4.0 RECORDS REVIEW

(a) General

(i) Phase One Study Area Determination

The Phase I Study Area (SA) was set at 250 m. The general area beyond the study area is

rural and there was no evidence of significant sources of potential contamination within a

kilometer of the Site. Therefore, properties beyond 250 m of the site were not considered part

of the Phase I Study Area.

(ii) First Developed Use Determination

Based on review of: historic aerial photographs on file with the City of Oakville and the

Region of Halton dating back to 1954; and Might’s and Criss Cross Street Directories on file

with the Oakville Public Library, the Phase One Property was first developed 1981 as a

restaurant operating as Chew’s Chinese Food Emporium.

No development was identified prior to this period.

(iii) Fire Insurance Plans

Available fire insurance programs (FIP) at the Oakville Public Library were reviewed. No

FIPs with coverage for the area were identified.

(iv) Chain of Title

A chain of title was undertaken by Diane Harman LPS to the date of first development. The

results of search are summarized as follows:

CHAIN OF TITLE RE PIN 24816-0048 – from 1980 to date – 157 CROSS AVE.,

OAKVILLE (deeds only):

- 491914 Deed 14 Nov./78 The Flintkote Company of Canada Limited to D. L. Fowles

Development Limited;

- 557358 Articles of Amalgamation 14/05/82 D. L. Fowles… now Roshorn Limited;

- 589004 Grant 03/11/83 Roshorn Limited to Marlene A. Beer;

- HR135968 Transfer 2002/07/31 …Beer to 1532628 Ontario Limited;

- HR1471464 Transfer 2017/07/12 1532628… to Can-China Real Capital Inc.

Page 11: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 7

(v) Environmental Reports

A report entitled “PHASE I ENVIRONMENTAL SITE ASSESSMENT, 157 CROSS

AVENUE, OAKVILLE, APRIL, 2017” prepared by Andre Breberina P. Geo. was reviewed.

The findings of the report are summarized as follows:

“The Lighting Centre has been operating since about 2000. Previously the Site was used as a

restaurant operating as ‘Armadillo’s’ in the 1990s and ‘Peter and Marty’s’ in the 1980s.

There is a single storey concrete block with some wood cladding building on the Site. The

building had a slab on grade concrete floor with level asphalt roof over steel decking

supported by open webbed steel joists. The interior is used as a retail area and warehouse for

home lighting and has an office and washroom. Heating and cooling is from roof mounted

natural gas HVAC unit. There is municipal water and sanitary service to the Site.

No potentially contaminating activities were identified on the Site.

Properties located within the study area include historic foundry operation from 1971 to

2000, however this property is located downgradient to the Site and this activity is considered

not to be an area of potential environmental concern.

The Phase I ESA identified no areas of potential environmental concern were identified on the

Site or within the study area.”

No other environmental reports were identified or reported.

(vi) Other Reports Relating Potential Contamination or APEC on or under the Phase One

Property

Might’s and Criss Cross Street Directories on file with the Oakville Public Library were

reviewed for occupancies of the Site and properties in the study area in approximately five

year increments from dates of the most recent publication in 2000 to the earliest publication in

1965. The following occupancies for the Site were identified:

: Property Use Directories: Site Use

Address Year Occupant Activity

157 Cross Avenue <1982 No listings None

1982 - 1983 Chew’s Chinese Food Emporium Commercial – Restaurant

1984 - 1990 Peter and Marty’s Commercial – Restaurant

1995 – 2000 Armadillo’s Commercial – Restaurant

Within the study area, most of the historic listings consist of retail and office commercial uses

and residential uses. Five historic listings on two addresses in the study area were identified as

potentially contaminating activities, specifically:

Page 12: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 8

Property Use Directories, Surrounding Properties,

Address Direction from Site Years Occupant Activity

142 Cross Avenue

Across Cross Avenue South and approximately 40 m Downgradient of the Site

1971 - 1976 Wright CE Stampings Ltd. Industrial – metal stamping

1980 No Listing None

1985 - 2000 Noel’s Auto Service Commercial

1985 Cross Avenue Auto Body P&J Auto Body

Commercial Commercial

148 Cross Avenue

Across Cross Avenue Southeast and Downgradient of the Site

1971 – 1990 Titan/Witherpoon Foundry Industrial – Foundry

1995 - 2000 Bibby Waterworks Industrial – Foundry

As these properties with PCAs on them are hydrogeologically down gradient from the Phase

One Property, they are not considered areas of potential environmental concern to the Phase

One Property.

(b) Environmental Source Information

(i) National Pollutant Release Inventory (NPRI)

The NPRI data base searched for records in the study area. The phase one property was not

listed under the NPRI.

(ii) Ontario Inventory of PCB Storage Sites (October 1992)

A search of the Ontario Inventory of PCB Storage Sites (1992) did identify any properties in

the study area.

(iii) Certificates of Approval, Permits to Take Water, Certificates of Property Use and similar

instruments

No Certificates of Approval, Permits to Take Water, Certificates of Property Use or similar

instruments were identified on the Phase One Study or adjacent properties.

(iv) Inventory of Industrial Sites Producing or Using Coal Tar and Related Tars in Ontario

The MOE’s ‘Inventory of Industrial Sites Producing or Using Coal Tar or Related Tars in

Ontario, November, 1988’ was reviewed and no such facilities were identified within the Study

Area.

(v) Records concerning reported violations, prosecutions, or clean-up orders, past or present,

with respect to environmental regulations, pertaining to the Site.

There are no reported violations, prosecutions, or clean-up orders, past or present, with

respect to environmental regulations, pertaining to the Site.

(vi) Waste Management Records

Based on a review of the MOE’s HWIN, the phase one property and adjacent sites were not

identified as a waste generators or receivers.

Page 13: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 9

(vii) Reports submitted to the Ministry related to environmental conditions

There are no reported violations, prosecutions, or clean-up orders, past or present, with

respect to environmental regulations, pertaining to the Phase One Property or adjacent

properties.

(viii) Retail Fuel Storage Tanks maintained by the Technical Standards and Safety Authority

The Technical Standards and Safety Authority (TSSA), which maintains licenses of storage

tanks under the Gasoline Handling Act and the Fuel Safety Act, was contacted regarding

records of such tanks on the Phase One Property.

(ix) Notices and Instruments, including RSCs, posted in the Registry

No Notices and Instruments, including RSCs, posted in the Registry were identified on the

Phase One Property or adjacent properties.

(x) Areas of Natural and Scientific Interest (ANSIs)

The Ontario Ministry of Natural Resources ANSI map was reviewed and no ANSIs were

identified on the phase one property or within one kilometer of the property.

(xi) Waste Disposal Inventory

The MOE’s ‘Waste Disposal Site Inventory, June, 1988’ was reviewed and the Site. No such

sites were identified within phase one study area.

(xii) Town of Oakville’s Official Plan

The Official Plan was reviewed. In accordance with the Town of Oakville’s Official Plan, the

Site and local area are designated as ‘employment district’ land use.

No environmentally sensitive or hazard lands areas were found within the study area (Figure

5).

(xiii) Town of Oakville’s Zoning By-law

In accordance with the Town of Oakville’s zoning by- laws , the Site and local area are

designated as ‘MTC’ for Mid-town Transitional Commercial.

(c) Physical Setting Sources

(i) Aerial Photographs

An aerial photograph from 1954 at 1:15,840 scale from the Ministry of Natural Resources was

reviewed and is reproduced as Plate 1A. Aerial photographs from 1978, 1987 and 1994 at

1:5000 scale available at the Region of Halton Public Works Department were reviewed and

are reproduced as Plates 2A to 4A respectively. Satellite photographs from 1995, 1999, 2002,

Page 14: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 10

2006, 2008, 2010, 2012 and 2015 available from the Town of Oakville’s website were

reviewed and are reproduced as Plates 5A to 12A respectively.

The 1954 aerial photograph shows the Site and area as crop fields.

The 1979 aerial photograph shows the Site as undeveloped, but there is shopping mall to the

west, retail stores and offices to the northwest and northeast. Across the Cross Avenue to the

southeast and downgradient from the Site is foundry building.

The 1987 to 1999 aerial photographs show the Site developed in its current form. with the

current building on it and buildings to the east and west of the Site.

The 2002 to 2015 photographs show the Site in use and the surrounding properties as

developed in their current condition with the replacement of the foundry with Go transit

parking and redevelopment of the shopping mall to plaza format.

Visual analysis of the photos do not indicate other structures or other activities or features

(tank farms, pits, lagoons, etc.) on the Site, or on adjoining properties, that would be of

environmental concern. There are no former watercourses or depressions identified on the

Site.

(ii) Topography, Hydrology and Geology

A 1961 topographic map available at the Oakville Public Library was reviewed and presented

as figure 6. The map shows the shopping mall to the west, retail store to the northwest, and

across the Cross Avenue to the southeast and downgradient from the Site is foundry building.

A topographic map from the Ministry of Natural Resources and Forestry website was

obtained and is presented as Figure 7. The map shows that elevations range across the Site

from just over 104 m at the back of the Site to about 102 m at the front of the Site.

The site is level with no water courses. Surface runoff drains to the municipal storm drain

system.

The general topography slopes to the southeast toward Lake Ontario. The Sixteen Mile Creek

meanders approximately 300 m to the east and south of the Phase One Property and the valley

drops sharply by about 20 m. Groundwater is inferred to be influenced by the local

topography and flow in southeasterly direction.

Ontario Geological Survey (OGS) maps, “Surficial Geology of Greater Toronto and Oak

Ridges Moraine Area, Southern Ontario” available on the Ministry of Natural Resources

website were reviewed. The Site is situated on a deposit of glaciolucustrine silts and clays of

generally low permeability and the underlying bedrock was identified as paleozoic shale

bedrock of the Queenston Formation consisting of shale, siltstone, minor limestone and

sandstone.

A review of “The Physiography of Southern Ontario” places the Site on a physiographic unit

known as the Iroquois Plain. Which is lowland bordering Lake Ontario that was inundated in

the late Pleistocene by Lake Iroquois. Soils in this area consist of a clayey-silt till (Halton

Till).

Page 15: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 11

No geotechnical or geological reports were on file with the owner.

(iii) Fill Materials

Other than a gravel sub-base for the asphalt apron in the rear lane way and parking pad, no

other extraneous fill was observed or suspected during the Site reconnaissance of from other

sources.

(iv) Water Bodies and Areas of Natural Significance

No water bodies and areas of natural significance were identified in the Study Area.

(v) Well Records

The Ontario Well Records data base was searched and the following well records were

identified in the study area:

- One well record from 2009 of a monitoring was identified on 214 Cross Avenue to the

south. The soil log reported a shale till beneath 1’ of granular fill to 11’ followed by

shale with limestone layers to 20’. Depth to groundwater was not reported.

- One well record from 2012 of six overburden and six bedrock monitoring were

identified on 177 and 185 Cross Avenue and 580 Argus St to the east. The soil logs

reported soils below the surface asphalt and sub-base fill to consist of clay to silt to

depths of between 2.7 m and 4.0 m followed by shale with limestone layers to 5.1’.

Depth to groundwater in the overburden wells was reported to between 2.0 m and 3.5

m. Depth to groundwater in the bedrock wells was reported to between 4.5 m and 5.1

m.

- Three well records from 2011 of three overburden monitoring were identified on 177

586 Argus St to the east. The soil logs reported soils below the surface asphalt and

sub-base fill to consist of silt and sand to 11’. Depth to groundwater was not reported.

- One well record from 2004 of a monitoring was identified on 217 Cross Avenue to the

south. The soil log reported soils of silt and sand to 2.4 m followed by shale with

limestone layers to 5.1m’. Depth to groundwater was not reported.

(d) Site Operating Records

(i) Regulatory Information and Permits

There are no reported violations, prosecutions, or clean-up orders, past or present, with

respect to environmental regulations, pertaining to the Site.

(ii) Material Safety Data Sheets (MSDS)

There were no MSDS for the operation.

Page 16: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 12

(iii) Site Utility Drawings

None reported.

(iv) Inventory of Chemicals and Their Usage

Chemicals on Site generally consisted of small quantity containers of household type cleaners.

(v) Inventory of Underground and Aboveground Storage Tanks

No above-ground or underground storage tanks were observed currently, or reported

previously, on the Site.

(vi) Environmental Reporting Data

No monitoring was reported as being conducted.

(vii) Waste Management Records

Currently wastes and recyclables are placed curbside for municipal pick-up.

(viii) Process, Production and Maintenance Records

There are no process, production or maintenance records.

(ix) Spills Reporting Records

No spills have been reported to occur during the current occupancy/operations.

(x) Emergency Response or Contingency Plan

None reported.

(xi) Environmental Audit Reports

None were identified or reported to exist for the present of previous operation.

(xii) Site Plans

A 1982 site plan of the Phase One Property was provided in the Client. The plan identifies the

property limits and the existing building footprint. The survey reports the area of the Phase

One Property to be 0.3699 ha. No features of environmental concern were identified.

A 2017 Survey of the Phase One Property was provided in the Client. The plan identifies the

property limits and the existing building footprint. Topographic points on the plan show the

Site is generally level and dips gently from the northwest at 104.38 masl. to the southeast at

102.27 masl.

The plan shows a single ground mounted and two nested ground mounted transformers on the

adjacent property to the northwest, all situated on below ground concrete vaults. The

underground utility corridors from the vaults run westward on the adjacent property, and

would direct any contamination due to leakage of transformer oil away from the Phase One

Property, and therefore the Transformers are not considered to represent APECs to the Phase

One Property.

Page 17: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 13

5.0 INTERVIEWS

General Information

Table 3: Interview Information

Date and Time 18/11/14

Method In person

Interviewee Mr. George

Title Manager of Lighting Centre

Reason for Selection Manager of Lighting Centre for last 18 years

Interview Information

Phase One Property

(1) Structures

1. Structures

(i) Description of structure and other improvements – There is a one storey wood

and concrete block building on the Site. There is small wood storage shed

behind the building in side a wood fence compound.

(ii) Below ground structures – There are no below ground structures on the Phase

One Property.

(iii) Tanks - There are no known tanks on the Phase One Property.

(iv) Potable water sources – The Site is on municipal water supply

2. Underground utilities

Natural gas, water and sanitary services come to the building but the locations are

unknown.

3. Building Interior(s)

(i) Exit and entry points – There are man doors at the front and southwest side of

the building and service doors rear of the building.

(ii) Existing and former heating systems – The building is currently heated by a

natural gas fired by a roof mounted HVAC unit.

(iii) Cooling systems – The building is currently cooled by a natural gas fired by a

roof mounted HVAC unit.

(iv) Current and former drains, sumps and pits –No current or former drains, sumps

or pits were noted other than those to the washrooms or former kitchens, the

latter of which have been capped and sealed.

(v) Unidentified substances – none noted

(vi) Stains and corrosion – none noted

Page 18: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 14

4. Other features

(i) Wells – none noted

(ii) Sewage works – The Phase One Property is on municipal sanitary service

(iii) Ground surfaces – The area of the Phase One Property outside the footprint of

the building is paved over with asphalt with a lane way from in front and

behind the building.

(iv) Current or former rail lines – No current or former rail lines were noted

(2) Exterior

(a) Areas of stained soil, vegetation or pavement – No stained areas were noted on the

ground cover.

(b) Stressed vegetation – There was no stressed vegetation observed.

(c) Areas of fill – Other than a gravel sub-base for the asphalt apron in the rear lane

way and parking pad, no other extraneous fill was observed or suspected during

the Site reconnaissance of from other sources.

(d) Potentially contaminating activity – No PCAs observed around the exterior.

(e) Unidentified substances – None noted.

(3) Enhanced Investigation Items

(a) Operations – The building is used as retail lighting store for the last 18 years,

and includes showroom, storage area, office and washroom.

(b) Hazardous materials on site – Other than small quantity household cleaners

none were noted.

(c) Products manufactured – None conducted

(d) By-products and wastes – None generated other than dry packaging wastes

(e) Raw materials – None

(f) Location and contents of drums, totes and bins – There is one bin for solid

non-hazardous waste located behind the building serviced by a private waste

hauler.

(g) Oil/water separators – None

(h) Equipment maintenance, fluid and waste storage areas – There are currently no

equipment maintenance, fluid or waste storage areas. Spills – none noted or

reported.

(i) Liquid discharge points – None

(j) Hydraulic lift equipment – None

Phase One Study Area

(a) Potentially contaminating activities – None that he was aware of.

(b) Water bodies – None noted or reported.

(c) Areas of natural significance – None noted or reported.

Page 19: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 15

6.0 SITE RECONNAISSANCE

(a) General Requirements

Table 4a: Site Reconnaissance Information

Date and Time 18/11/14

Weather Conditions Cool and Overcast

Length of time of Reconnaissance 90 minutes

Facility operating (Y/N) Y

Name and Qualifications of Assessor Andre Breberina BES. P.Geo. QP. (see Appendix D)

Table 4b: Photographic Log

Photograph Orientation Description

Northwest Front of Site

Northeast Southwest side of building

Page 20: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 16

Southeast Rear of building.

Northwest Back of Phase One Property,

northwest of building

Southwest Northeast side of building.

Page 21: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 17

Typical showroom view

Typical store room view.

Office

Page 22: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 18

Washrrom

Electrical Room

Storage shed behind building.

Page 23: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 19

(b) Specific Observations of the Phase I Property and Investigation Description

Phase One Property

(1) Structures

1. Structures

(i) Description of structure and other improvements – There is a one storey wood

and concrete block building on the Site. There is small wood storage shed

behind the building in side a wood fence compound.

(ii) Below ground structures – There are no below ground structures on the Phase

One Property.

(iii) Tanks - There are no known tanks on the Phase One Property.

(iv) Potable water sources – The Site is on municipal water supply

2. Underground utilities

Natural gas, water and sanitary services come to the building but the locations are

unknown.

3. Building Interior(s)

(i) Exit and entry points – There are man doors at the front and southwest side of

the building and service doors rear of the building.

(ii) Existing and former heating systems – The building is currently heated by a

natural gas fired by a roof mounted HVAC unit.

(iii) Cooling systems – The building is currently cooled by a natural gas fired by a

roof mounted HVAC unit.

(iv) Current and former drains, sumps and pits –No current or former drains, sumps

or pits were noted other than those to the washrooms or former kitchens, the

latter of which have been capped and sealed.

(v) Unidentified substances – none noted

(vi) Stains and corrosion – none noted

4. Other features

(v) Wells – none noted

(vi) Sewage works – The Phase One Property is on municipal sanitary service

(vii) Ground surfaces – The area of the Phase One Property outside the footprint of

the building is paved over with asphalt with a lane way from in front and

behind the building.

(viii) Current or former rail lines – No current or former rail lines were noted

Page 24: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 20

(2) Exterior

(a) Areas of stained soil, vegetation or pavement – No stained areas were noted on the

ground cover.

(b) Stressed vegetation – There was no stressed vegetation observed.

(c) Areas of fill – Other than a gravel sub-base for the asphalt apron in the rear lane

way and parking pad, no other extraneous fill was observed or suspected during

the Site reconnaissance of from other sources.

(d) Potentially contaminating activity – No PCAs observed around the exterior.

(e) Unidentified substances – None noted.

(3) Enhanced Investigation Items

(a) Operations – The building is used as retail lighting store for the last 18 years, and

includes showroom, storage area, office and washroom.

(b) Hazardous materials on site – Other than small quantity household cleaners none

were noted.

(c) Products manufactured – None conducted

(d) By-products and wastes – None generated other than dry packaging wastes

(e) Raw materials – None

(f) Location and contents of drums, totes and bins – There is one bin for solid non-

hazardous waste located behind the building serviced by a private waste hauler.

(g) Oil/water separators – None

(h) Equipment maintenance, fluid and waste storage areas – There are currently no

equipment maintenance, fluid or waste storage areas. Spills – none noted or

reported.

(i) Liquid discharge points – None

(j) Hydraulic lift equipment – None

Phase One Study Area

(a) Potentially contaminating activities –Within the study area the following

potentially contaminating activities (PCAs) were identified: 1) a railroad track

approximately 200 m southeast and downgradient of the Phase One Property –

PCA 46 Rail Yards, Tracks and Spurs; and, 2) an automotive repair shop

approximately 75 m south and downgradient of the Phase One Property – PCA 27

Garages and Maintenance and Repair of Railcars, Marine Vehicles and Aviation

Vehicles.

(b) Water bodies – None noted or reported.

(c) Areas of natural significance – None noted or reported.

Page 25: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 21

7.0 REVIEW AND EVALUATION OF INFORMATION

(i) Current and Past Uses

Year Name of Owner Description of Property Use Property Use Other Observations from Aerial

Photographs, Fire Insurance Plans, etc…

2017 - Present

Can-China Real Capital Inc.

Retail Lighting Store Commercial Title search, direct observation, interview with current manager of store and ower

2002 - 2017 1532628 Ontario

Limited

Retail Lighting Store Commercial Title search, direct observation, interview

with current manager of store

1983 - 2002 Marlene A Beer Restaurant - Armadillos Commercial Title search, street directories, aerial photographs

Restaurant - Pete and Marty’s Commercial Title search, street directories, aerial

photographs

1978 - 1983 Roshorn Limited

(formerly) D.L.

Fowles Development Limited

Restaurant - Chew Chinese Food

Emporium

Commercial Title search, street directories, aerial

photographs

Undeveloped Undeveloped Title search, street directories, aerial

photographs

(ii) Potentially Contaminating Activity (PCAs)

The following PCA was identified on the Phase One Property:

PCA 1 – Road salt transported by vehicles onto the parking lot of the Phase One

Property on the adjacent property and is considered a PCA – Not Specified. PCA 1 is

considered to represent an APEC to the Phase One Property on the parking area and

laneways.

The following PCAs were identified in the Phase One Study Area:

PCA 2 – There is a ground mounted transformer situated on a below ground concrete

vault located trans-gradient to the Phase One Property on the adjacent property and is

considered a PCA#55 - Transformer Manufacturing, Processing and Use. The

underground utility corridor from the vault runs westward on the adjacent property,

and would direct any contamination due to leakage of transformer oil away from the

Phase One Property, and therefore PCA 2 is not considered to represent an APEC to

the Phase One Property.

PCA 3 – There are two nested ground mounted transformers situated on a below

ground concrete vault located trans-gradient to the Phase One Property on the adjacent

property and is considered a PCA#55 - Transformer Manufacturing, Processing and

Use The underground utility corridor from the vault runs westward on the adjacent

property, and would direct any contamination due to leakage of transformer oil away

from the Phase One Property, and therefore PCA 3 not considered to represent an

APEC to the Phase One Property.

PCA 4 – There is a railroad track approximately 200 m southeast of and downgradient

of the Phase One Property and is considered a PCA #46 Rail Yards, Tracks and Spurs.

Page 26: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 22

As PCA 4 is downgradient of the Phase One Property, it is not considered to represent

an APEC to the Phase One Property.

PCA 5 – There is an automotive repair shop at 142 Cross Avenue approximately 75 m

south and downgradient of the Phase One Property and is considered a PCA#27 –

Garages and Maintenance and Repair of Railcars, Marine Vehicles and Aviation

Vehicles. As PCA 5 is downgradient of the Phase One Property, it is not considered to

represent an APEC to the Phase One Property.

PCA 6 – Historically, there has been a foundry until 1994 at 146 Cross Avenue south

of, and down gradient of the Phase One Property and is considered a PCA#32 – Iron

and Steel Manufacturing and Processing. As PCA 6 is downgradient of the Phase One

Property, it is not considered to represent an APEC to the Phase One Property.

PCA 7 – Historically, there has been an automotive repair shop at 142 Cross Avenue

approximately 75 m south and downgradient of the Phase One Property and is

considered a PCA#27 – Garages and Maintenance and Repair of Railcars, Marine

Vehicles and Aviation Vehicles, As PCA 7 is downgradient of the Phase One

Property, it is not considered to represent an APEC to the Phase One Property.

PCA 8 – Historically, there has been an autobody repair shop at 142 Cross Avenue

approximately 75 m south and downgradient of the Phase One Property and is

considered a PCA#10 – Commercial Autobody Shops. As PCA 8 is downgradient of

the Phase One Property, it is not considered to represent an APEC to the Phase One

Property.

PCA 9 – Historically, there has been a metal stamping shop at 142 Cross Avenue

approximately 75 m south and downgradient of the Phase One Property and is

considered a PCA#34 – Metal Fabrication. As PCA 9 is downgradient of the Phase

One Property, it is not considered to represent an APEC to the Phase One Property.

(iii) Areas of Potential Environment Concern

PCA 1 is considered to represent an APEC to the Phase One Property to soil below the

parking area and laneways.

(iv) Rationale for APECs :

Road salt picked up by vehicles on municipal roads may been transported onto the

parking lot of the Phase One Property where it may have leaked onto the parking

pavement and leached into the soil below.

(v) Phase I Conceptual Site Model

i) Areas where potentially contaminating activity (PCA) has occurred:

Page 27: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 23

PCA 1 – Road salt transported by vehicles onto the parking lot of the Phase One

Property on the adjacent property and is considered a PCA – Not Specified. PCA 1

is considered to represent an APEC to the Phase One Property on the parking area

and laneways.

The following PCAs were identified in the Phase One Study Area:

PCA 2 – There is a ground mounted transformer situated on a below ground

concrete vault located trans-gradient to the Phase One Property on the adjacent

property and is considered a PCA#55 - Transformer Manufacturing, Processing

and Use. The underground utility corridor from the vault runs westward on the

adjacent property, and would direct any contamination due to leakage of

transformer oil away from the Phase One Property, and therefore PCA 2 is not

considered to represent an APEC to the Phase One Property.

PCA 3 – There are two nested ground mounted transformers situated on a below

ground concrete vault located trans-gradient to the Phase One Property on the

adjacent property and is considered a PCA#55 - Transformer Manufacturing,

Processing and Use The underground utility corridor from the vault runs westward

on the adjacent property, and would direct any contamination due to leakage of

transformer oil away from the Phase One Property, and therefore PCA 3 not

considered to represent an APEC to the Phase One Property.

PCA 4 – There is a railroad track approximately 200 m southeast of and

downgradient of the Phase One Property and is considered a PCA#46 Rail Yards,

Tracks and Spurs. As PCA 4 is downgradient of the Phase One Property, it is not

considered to represent an APEC to the Phase One Property.

PCA 5 – There is an automotive repair shop at 142 Cross Avenue approximately

75 m south and downgradient of the Phase One Property and is considered a

PCA#27 – Garages and Maintenance and Repair of Railcars, Marine Vehicles and

Aviation Vehicles. As PCA 5 is downgradient of the Phase One Property, it is not

considered to represent an APEC to the Phase One Property.

PCA 6 – Historically, there has been a foundry until 1994 at 146 Cross Avenue

south of, and down gradient of the Phase One Property and is considered a

PCA#32 – Iron and Steel Manufacturing and Processing. As PCA 6 is

downgradient of the Phase One Property, it is not considered to represent an APEC

to the Phase One Property.

PCA 7 – Historically, there has been an automotive repair shop at 142 Cross

Avenue approximately 75 m south and downgradient of the Phase One Property

and is considered a PCA#27 – Garages and Maintenance and Repair of Railcars,

Marine Vehicles and Aviation Vehicles, As PCA 7 is downgradient of the Phase

One Property, it is not considered to represent an APEC to the Phase One

Property.

Page 28: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 24

PCA 8 – Historically, there has been an autobody repair shop at 142 Cross Avenue

approximately 75 m south and downgradient of the Phase One Property and is

considered a PCA#10 – Commercial Autobody Shops. As PCA 8 is downgradient

of the Phase One Property, it is not considered to represent an APEC to the Phase

One Property.

PCA 9 – Historically, there has been a metal stamping shop at 142 Cross Avenue

approximately 75 m south and downgradient of the Phase One Property and is

considered a PCA#34 – Metal Fabrication. As PCA 9 is downgradient of the Phase

One Property, it is not considered to represent an APEC to the Phase One

Property.

ii) Contaminants of Potential Concern – Sodium Adsorption Ratio (SAR) to the soil

iii) Underground Utilities - Underground utilities on the phase one property have not been

identified, except for an Oakville Hydro Utility Corridor identified on the 2017

Survey which runs from the front of the Phase One Property along the northwest

side of the property.

iv) Geological and Hydrogeological Conditions – The general topography slopes to the

southeast toward Lake Ontario. The Sixteen Mile Creek meanders approximately

300 m to the east and south of the Phase One Property and the valley drops sharply

by about 20 m. Groundwater is inferred to be influenced by the local topography

and flow in southeasterly direction.

Ontario Geological Survey (OGS) maps, “Surficial Geology of Greater Toronto

and Oak Ridges Moraine Area, Southern Ontario” available on the Ministry of

Natural Resources website were reviewed. The Site is situated on a deposit of

glaciolucustrine silts and clays of generally low permeability and the underlying

bedrock was identified as paleozoic shale bedrock of the Queenston Formation

consisting of shale, siltstone, minor limestone and sandstone.

A review of “The Physiography of Southern Ontario” places the Site on a

physiographic unit known as the Iroquois Plain. Which is lowland bordering Lake

Ontario that was inundated in the late Pleistocene by Lake Iroquois. Soils in this

area consist of a clayey-silt till (Halton Till).

Based on borehole logs from the Ontario Well Records in the Study Area,

overburden consists of clay with some silt, and silt and sands to depths of between

2.4 m and 4.0 m followed by shale with limestone layers to 5.1’. Depth to

groundwater in the overburden wells was reported to between 2.0 m and 3.5 m.

Depth to groundwater in the bedrock wells was reported to between 4.5 m and 5.1

Page 29: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 25

m. The site is level with no water courses. Surface runoff drains to the municipal

storm drain system.

The general topography slopes to the southeast toward Lake Ontario. The Sixteen

Mile Creek meanders approximately 300 m to the east and south of the Phase One

Property and the valley drops sharply by about 20 m. Groundwater is inferred to be

influenced by the local topography and flow in southeasterly direction.

v) Uncertainty or Absence of Information – Geologic conditions to the Phase One

Property were not identified, however, geologic information on several properties

in the Phase One study area were reasonably consistent and conditions on the

Phase One Property would be expected to be similar in terms of soil types,

stratigraphy and depts to bedrock and groundwater.

Underground utilities on the phase one property have not been identified, except

for an Oakville Hydro Utility Corridor identified on the 2017 Survey which runs

from the front of the Phase One Property along the northwest side of the property.

Underground utility corridors could act a preferential pathways for salt transport.

Page 30: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 26

Page 31: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 27

Page 32: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 28

Page 33: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 29

Page 34: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 30

Page 35: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 31

8.0 CONCLUSIONS

Road salt transported by vehicles onto the parking lot of the Phase One Property on the

adjacent property and is considered a PCA – Not Specified. PCA 1 is considered to represent

an APEC to the Phase One Property on the parking area and laneways. Road salt picked up by

vehicles on municipal roads may been transported onto the parking lot of the Phase One

Property where it may have leaked onto the parking pavement and leached into the soil below

resulting in sodium adsorption ratio impacts.

It is therefore a Phase II Environmental Site Assessment is required before a Record of Site

Condition can be submitted.

We trust that this report will accommodate your requirements. If you have any questions or

comments, please contact the undersigned.

The gathering of information, evaluation of the information and conclusions and

recommendations made in this Phase I ESA have conducted by, or supervised by, the

undersigned QP.

Andre Breberina P.Geo

Page 36: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 32

Page 37: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 33

9.0 REFERENCES

Association of Professional Geoscientists of Ontario, April 2011, “Guidance for

Envrionmental Site Assessments under Ontario Regulation 153/04 (as amended)”

Breberina, A., “Phase I Environmental Site Assessment, 157 Cross Avenue, Oakville, April

12, 2017”

CSA, 2001.’Phase I Environmental Site Assessment’. CSA Publication Z768-01.

Chapman, L.J., and D.F. Putnam, 1951. “The Physiography of Southern Ontario”. Toronto:

University of Toronto Press.

Environment Canada, “National Pollutant Release Inventory (NPRI)” www.ec.gc.ca

Hazardous Waste Information Network (HWIN, 1986 – 2005) www.hwin.ca

Natural Heritage Information System, www.nhic.gov.on.ca

Ontario’s Environmental Registry, www.ebr.gov.on.ca

Ontario Geological Survey “Palezoic Geology of Southern Ontario” www.mndm.gov.on.ca

Ontario Geological Survey “Surficial Geology of Southern Ontario” www.mndm.gov.on.ca

Ontario Ministry of Environment, June 1988, “Waste Site Disposal Inventory.”

Ontario Ministry of Environment, November 1988, “Inventory of Industrial Sites Producing

or Using Coal Tar or Related Tars in Ontario”.

Ontario Ministry of Environment, 1991, “Ontario Inventory of PCB Storage Sites (October

1991)”

Ontario Ministry of Environment, June 1996, “Guidelines for Use on Contaminated Sites in

Ontario.”

Ontario Ministry of Environment, December, 1996, “Guidance on Sampling and Analytical

Methods for Use on Contaminated Sites in Ontario.”

Ontario Ministry of Environment July, 2011 “Soil, Sediment and Groundwater Standards for

Use in Accordance Part XV.1 of the Environmental Protection Act”

Ontario Ministry of Environment, June, 2011, Guide for Completing Phase One

Environmental Site Assessments Under Ontario Regulation 153/04

Ontario Ministry of Environment, July 1, 2011, Ontario Regulation 153/04 as amended by

Ontario Regulation 511/09. Environmental Protection Act, R.S.O. 1990, Part XV.1

Page 38: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 18161 Page 34

Town of Oakville’s Official Plan www.oakville.ca

Town of Oakville’s Zoning By-Laws www.oakville.ca

Page 39: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Can-China Real Capital Inc. Andre Breberina P.Geo Phase I Environmental Site Assessment 157 Cross Avenue Oakville, Ontario January 27, 2019 CONFIDENTIAL

. Project Number 14031 Page 28

10.0 APPENDICIES

Appendix A – Surveys

1982 Survey

2017 Survey

Page 40: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr
Page 41: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr
Page 42: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Appendix B – Topographic Maps

Page 43: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Site

Page 44: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

APPENDIX C

AERIAL PHOTOGRAPHS

Plate 1A – 1954 Aerial Photograph

Plate 2A – 1979 Aerial Photograph

Plate 3A – 1987 Aerial Photograph

Plate 4A – 1994 Aerial Photograph

Plate 5A – 1995 Aerial Photograph

Plate 6A – 1999 Aerial Photograph

Plate 7A – 2002 Aerial Photograph

Plate 8A – 2006 Aerial Photograph

Plate 9A – 2008 Aerial Photograph

Plate 10A – 2010 Aerial Photograph

Plate 11A – 2012 Aerial Photograph

Plate 12A – 2015 Aerial Photograph

Page 45: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

1954 Aerial Photograph

Site

Page 46: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

SITE

1979 Aerial Photograph

Site

1987 Aerial Photograph

Page 47: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Site

Site

1994 Aerial Photograph

1995 Satellite Photograph

Page 48: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Site

Site

2002 Satellite Photograph

1999 Satellite Photograph

Page 49: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Site

2008 Satellite Photograph

Site

2006 Satellite Photograph

Page 50: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

2010 Satellite Photograph

2012 Satellite Photograph

Site

Site

Page 51: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

2015 Satellite Photograph

Site

Page 52: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Appendix D – Qualifications of Assessor

Page 53: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Qualifications of Assessor

Andre Breberina B.E.S. P. Geo. Q.P*. Environmental Geoscientist *Qualified Person (Ontario Ministry of Environment O. Reg 153/04) (E&O Insured)

Expertise:

▪ Project development and management. ▪ Environmental Site Assessments – Phase 1 and 2. ▪ Site remediation and Brownfield re-development project design and management. ▪ Aboveground and underground storage tank decommissioning. ▪ Emergency Spill Response assessment, management and abatement. ▪ Waste Transfer Station, Waste Management System Waste Processing Site

Certificates of Approval submissions, including design and operations, environmental management systems and training.

▪ Waste Audits and Minimization/Diversion Programs. Client support involving:

▪ Regulatory compliance, complaints and orders. ▪ Records of Site Condition. ▪ Applications for Certificates of Approval. ▪ Property acquisitions, divestitures, leasing and finance. ▪ Stakeholder peer reviews. ▪ Baseline studies for due diligence, environmental management systems and strategic

planning. ▪ Site/operation EMS procedures and training. ▪ Expert testimony at Ontario Municipal Board hearing and at Provincial Courts in

litigation matters. Sector involvement:

▪ Federal, Provincial and Municipal governments and agencies ▪ Chemical processors and storage facilities ▪ Paint manufacturers and warehousing ▪ Printing and photochemical facilities ▪ Plastics processors ▪ Steel producers ▪ Metal fabricating, plating and warehousing sites ▪ Textile processing ▪ Aggregate producers ▪ Automotive manufacturers, dealerships, service and body repair shops ▪ Trucking companies, service depots and dealerships ▪ Gasoline stations and other private petroleum outlets ▪ Airport, seaport and rail road operations ▪ Salvage, recycling, waste disposal, composting facilities and transfer sites ▪ Public and private utility companies ▪ Federal, provincial and municipal facilities ▪ Hospitals and other health care facilities ▪ Educational institutions and school boards ▪ Retail and other commercial sites ▪ Developers and holding companies ▪ Residential houses and apartments

Teaching and Training Experience

Page 54: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

▪ Lecturer - Solid Waste and Hazardous Materials Management Course as part of the Environmental Engineering Diploma Program at Mohawk College, Hamilton, from 1998 to 2009.

▪ Lecturer - Youth Enviro-Entrepenuers Program. Human Resources Canada, Canadian Environmental Industry Association, Niagara College and the Business Advisory Centre, Hamilton,1995

▪ Trainer to private environmental contractors and waste management operators of O. Reg 347, TGDA, waste manifesting, sampling and monitoring procedures, EMS record keeping, hazardous materials handling procedures, level A to D personnel protection equipment use and maintenance, spills and emergency response procedures.

Education, Professional Development and Certifications

▪ Bachelor of Environmental Studies (Honours), University of Waterloo. Waterloo, 1983 ▪ Environmental Legislative Compliance Program, Mohawk College, Hamilton, 1992 ▪ Environmental Chemistry, Mohawk College, Hamilton, 1993 ▪ Benthic Marco Invertebrate Survey, McMaster University, Hamilton 1995 ▪ WHMIS Certificate, Team-1Environmental Services Inc., Hamilton 1996 ▪ Confined Space Entry/Rescue Certificate, Team-1 Environmental Services Inc., 1997 ▪ Tanker Truck Roll-over Specialist, Oil Spill Control Services, Toronto, 1997 ▪ Explosives Recognition and Forensic Documentation, RSP International Inc,

Mississauga, 1998 ▪ TDGA and Waste Manifesting Inc., Talon Environmental Inc., Hamilton, 1998 ▪ Air Emission Summary and Dispersion Modeling Workshop, Ontario Ministry of

Environment, Toronto, 1999 ▪ Radiation Safety Certification, Ontario Power Generation Corp., Pickering Nuclear

Station, Pickering, 1999 ▪ Shoreline Clean-up Assessment, Team-1 Environmental Services Inc. Hamilton,

1999 ▪ Open Water Oil Spill Marine Containment, Eastern Canada Spills Response Corp.,

Sarnia, 1999 ▪ International SCUBA Certifications – Open Water, Advanced, Scuba Rescue and

DAN Oxygen Provider, American and Canadian Underwater Council ▪ First Aid Certification and CPR (current), Canadian Red Cross ▪ Canadian Coast Guard accredited Watercraft Operator Certificate, Watercraft

Rescue and Training Centre, Hamilton, 2000 ▪ Technical Standards and Safety Authority Licensed PM2 and PM3 Petroleum

Mechanic ▪ ISO 14001 Internal Auditor, Quality Management Institute, Mississauga, 2002 ▪ Environmental Sampling, National Contaminated Sites Training Program,

Environment Canada, 2002 ▪ Hazmat Technician Certificate, Team 1 Environmental Services Inc. 2003

Professional Associations

▪ Association of Professional Geoscientists of Ontario – Practicing Member ▪ Canadian Council of Professional Geoscientists

Page 55: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

Professional Profile

Andre Breberina has over 25 years experience in environmental consulting in Ontario and has provided professional services to address environmental concerns for clients in private and public sectors. Prior to his own private practice, Mr. Breberina worked with Trow Inc. where he performed materials testing, geotechnical investigations and QA/QC programs on construction projects. Mr. Breberina later worked with Hydrology Consultants Inc. where he conducted field work for the Environmental Impact Assessment for the Halton Region Landfill Study and CN Rail Lands decommissioning for the Skydome (now Rogers Centre) site.

Environmental Site Assessments: Phase I and Phase II Environmental Site Assessments have been conducted on a wide range of property types from undeveloped land to industrial parks throughout southern and central Ontario. Phase II Environmental Site Assessments have involved a variety of non-intrusive and intrusive investigation and sampling techniques of various media on site, and off-site as required, to identify: chemicals of concern, their presence and concentrations, migration pathways, extent of contamination, actual and potential receptors, the risk to the receptors and recommendations for mitigation and/or remedial action. Investigations have included to not only surface and sub-surface conditions but also hazardous materials in buildings. Site Remediation and Brownfield Re-development: Site remediation work has included problem identification, conceptualization of remedial options with risks and costs, consultation with client to determine preferred remedial option, finalization and implementation of work plan, arranging necessary sub-contractor and support services, project management and quality control and regulatory compliance assurance to the target clean-up level. Upon completion of remedial work, Records of Site Conditions are filed, if requested, or as required under regulations for Brownfields to be-redeveloped to an active use. Remediated sites have included problems with a range of contaminants including petroleum products, solvents, (LNAPLs and DNAPLs), heavy metals and other organics, pesticides and fertilizers and leachate control. Remedial methods have included: extraction and disposal, ex-situ treatment, in-situ treatment pump and treat methods and bioremedial methods. Brownfield re-developments projects have included taking former rail lands, gas stations and industrial sites to high density residential land uses and health care facilities. Aboveground and Underground Tank Management: Tanks and tank farms have been assessed to determine if decommissioning is warranted by virtue of actual or potential leakage or regulation. Recommendations were made and implemented to bring tanks to regulatory requirements and/or leak and spill mitigation measures were undertaken that met or exceed standards. During the decommissioning of tanks by qualified contractors, either through voluntary removal or as required under regulation, environmental assessments were conducted of soil and groundwater conditions to determine if, remedial action plan and/or a containment management plan was required. Remedial action plans and/or containment management plans were developed and implement through to completion in accordance with regulatory compliance. The scope of tanks assessed ranged from residential fuel oil tanks to industrial/commercial tank farms. Emergency Spill Response: Consulting services were provided for emergency spills response teams for last 15 years throughout Ontario to assess the nature and extent of spills, develop emergency responses on site with team personnel in the unique situations where S.O.Ps did not apply, identification of primary and secondary hazards, conducted sampling of various media to assess impact from spills, assessed the extent of emergency clean-up and recommendations for further assessment

Page 56: PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS … planning/da-16147301-phase1es… · PHASE I ENVIRONMENTAL SITE ASSESSMENT 157 CROSS AVENUE OAKVILLE JANUARY, 2019 Prepared for:Mr

and remediation. Reports were written detailing the cause and nature of the spill, work undertaken to contain and clean up the spill and the results of the clean-up efforts. The reports were submitted to clients, insurance companies and regulatory authorities who relied upon them in the event prosecutions were undertaken. Emergency response situations included: tanker truck roll-overs, chemical tanker car train derailments, marine spills, chemical and industrial fires. Also, on behalf of Team 1 Environmental Services Inc. Mr. Breberina designed, assembled and operated mobile laboratory consisting of a converted 34’ mobile home fitted with PID/GC, FID/GC, ECD/GC, FTIR and IR scanners, meteorological station and support equipment to provide emergency analytical services at spill sites. Waste Management: A cost accounting of a municipal blue box Material Recovery Facility’s operation was conducted to improve handling and operations procedures. Waste Audits and Waste Minimization programs in accordance with O. Reg 102/94 and 103/94 were conducted for industrial and commercial operations and school boards. Certificates of Approval for solid waste and hazardous waste Waste Transfer Stations and Waste Management Systems have been prepared and submitted on behalf of clients. Preparation for the client included design and operations details, containment design, handling and storage procedures, contingency measures, record management and training requirements based on regulatory requirements, best practices and ISO 14001 practices, as well as financial assurance calculations and public consultation. Since 2002, consulting services have been provided to commercial composting operation that have included: routine monitoring of ground and surface waters to assess potential off-site impacts as required under their Certificate of Approval, annual assessment of spray irrigation field to control leachate as required under their Certificate of Approval, repair of existing and setting of new monitoring wells, sampling and assessment compost in compliance with Certificate of Approval and MOE Guidelines, and, as requested, addressed specific compliance and operational issues through training, monitoring operational procedures.