PEOPLESOFT ROAD MAP PROJECT ���THE WAY FORWARD
Phase 1 CSS/ HCM Split – Cut over plan
Agenda Outage Window and Timeline Impacted Systems Refreshments Communication Approach / Plan Business Validation Expectations Back Out Plan Post Go-Live
2
Outage Window The CSS/HCM/FMS Oracle PeopleSoft applications and associated MyBGSU self-service applications will be unavailable from 6:00 p.m. on Friday July 18 until 6:00 p.m. Saturday July 19 in order to complete the planned split
6PM 6PM
3
Cutover Weekend - Timeline Friday, 7/18/2014
Noon – Check Point Meeting – Go/No Go for the weekend 5:00 p.m. – 1 hour announcement 6:00 p.m. – All systems down 6:00 p.m. to 3:00 a.m. – Technical Activities (9 hours)
Saturday, 7/19/2014 3:00 a.m. – “Split” activities completed
Production Verification to begin
6:00 a.m. - ITS Connectivity Validation 8:00 a.m. – Business Verification of HCM, CSS, FMS only 10:00 a.m. – Check Point – Go/No Go 10:30 a.m. – Noon – Business Verification Controlled release of interfaces (Point of No Return) Noon – All systems up End of Outage Communication
4
Impacted Systems (1 of 2) The following Systems will be unavailable from Friday July 18th at 6PM until Saturday July 19th at 6PM.
• Account Registration • Admissions - UAS • All Self Service Links • Bookstore Class List • CashNet** • DARWin - Degree Audit -
Faculty • Directory Search • Enrollment Verification • Falcons Purch • Financial Aid Awards
• Financial Aid Eligibility • Financial Aid Web Apps • Financial ODS • Grad Contracting/GA
Stipends • Holds • Housing Application
Status • IR ODS • Learning Communities • OIM
• OnBase • PeopleSoft CSS/HCM • PeopleSoft FMS • Portal Bio Demo • Public Class Search • Resource25 • Schedule Planner • StarRez • Student Health Insurance • To Do Checklist
5
*Note: Time Collection Devices will be available for swipes **Note: Will be available for payment processing, will not update the PeopleSoft CSS System until after the outage
Impacted Systems (Continued)
• Academic Software Request Database
• Accudemia • CEE Contracting • CMA Program Creator • College of Technology
Co-Op Request Form • Degree Audit • Econ Experiments Web
App • GSWOutline • HRLeaveBank • Lab Staff • LDAP Groups • Mail Form • Motor Vehicle
Registration Statement • Pharos Reports
• PNC Refund • Summer Contracts • Transfer Credit • Translation Services
Request • Vendor Bid • Wireless Guest Accounts • ZiggyPoints
The following Systems will be unavailable on Saturday July 19th from 1AM until 2 AM
6
Refreshments
Breakfast will be provided for Saturday morning activities. Lunch will be provided during the business validation efforts. Please contact project management for any dietary limitations.
7
Before anything else, preparation is the key to success.
~Alexander Graham Bell
Communication Approach Cut Over Weekend Command Center
• Hayes Hall 203 • Conference Bridge – live communication 877-820-7831 PIN#354522 • WebEx Information: https://bgsu.webex.com/bgsu
ü Meeting #: 640 314 187 ü Password: CHESS
• Listserv created – [email protected] • Key resources will be onsite during outage • Central Point of Coordination & Communication • Delays past 30 minutes in planned schedule will be communicated
8
Communication Plan
9
Message Timing Audience Method
Approval to move into cutover weekend 7/10 & 7/18
Functional Leads & Steering Committee In Person
1 Hour Until Outage 7/18 5PM Campus Campus Wide E-mail
Outage Update 7/18 10PM Project Team Listserv
End of Day activities are complete and system is ready for scheduled validation
7/19 3AM Project Team Listserv
Go / No-Go Call 7/19 10AM Project Team Call / In-Person
Systems are available 7/19 2PM Campus Campus Wide E-mail
Business Validation • 8AM Start Time • Production validation and verification • On site to avoid connectivity issues and speed resolution • Two parts divided by a Go/No-Go call at
• 10AM • 877-820-7831 PIN#354522
• Representation from each area will need to be available during communication window
• Point of contact will be needed for escalations • Functional Leads to work with Rich Kasch to provide progress updates
10
Back Out Plan Should an irreversible error occur on the cut over weekend, the project team has developed a back out plan. Highlights of this plan are:
• Dynamic, based on progress of cut-over • Point of no return identified • Duration of back out tasks have been captured to insure outage
window is not impacted
11
Post Go Live Support Week 1 – 7/21 to 7/25
• Issue Management will be “all hands”
• Central Contact: Rich Kasch ext. 2-7749 [email protected]
• Issue Management Call 3:30-4PM, 877-820-7831 PIN#354522
Week 2 7/28 to 8/1 • Production support model followed • Normal Contact
TSC ext. 20999 [email protected]
12
Questions and Answers