pg&e’s participants’ webinar...webinar format •pg&e will not take questions during the...

81
PG&E’s Participants’ Webinar Distribution Investment Deferral Framework (DIDF) Request for Offers January 19, 2021

Upload: others

Post on 24-Feb-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

  • PG&E’s Participants’ Webinar

    Distribution Investment Deferral Framework

    (DIDF)

    Request for Offers

    January 19, 2021

  • Agenda

    Topics Presenter

    Introduction Sandy Burns

    Distribution Services Needed Mini Damodaran

    Solicitation Overview▪ Eligibility▪ Technology Neutral Pro-Forma ▪ Evaluation Methodology▪ Incrementality

    Michael Blaevoet

    Offer Submittal Process Michael Blaevoet

    Offer Form Michael Blaevoet

    Intermission

    Q&A Team

  • Webinar Format

    • PG&E will not take questions during the presentation. Please save all questions for the Q&A session.

    • Participants should email questions [email protected] during the presentation

    – Questions will be answered at the end of the webinar

    – PG&E might not address all questions during the Q&A portion of this webinar

    – After the webinar, PG&E will compile and post a Q&A document on PG&E’s DIDF RFO website, accessed via www.pge.com/2021didf

    • PG&E will post a list of attendees on PG&E’s website

    – If you do not want your name or the name of your company published, please send an email to [email protected] by January 21, 2021 at 5 PM (PPT)

    mailto:[email protected]://www.pge.com/2021didfmailto:[email protected]

  • Webinar Overview

    • This presentation is intended to provide a summary of the information and requirements set forth in the RFO materials

    • Participants should carefully review the DIDF Solicitation Protocol and all RFO materials, available on PG&E’s DIDF RFO website

    • To the extent that there are any inconsistencies between information provided in this presentation and the requirements in the RFO materials, the RFO materials published on PG&E’s website shall govern

  • Independent Evaluator (IE)

    • Primary role of the IE is to:

    • Monitor RFO processes to ensure fair and equal treatment of all Participants

    • Monitor evaluation processes to ensure PG&E has implemented methodology as described and that offers are treated consistently

    • Report on RFO process and proposed transactions to CPUC when filed for CPUC approval

    • The IE may review all Offer data and communications with Participants

    • DIDF RFO IE is Sedway Consulting. Contact is:

    Alan Taylor ([email protected])

    mailto:[email protected]

  • Communications and Website

    • RFO website provides everything you need to submit an Offer, including (but not limited to) the following:

    – RFO materials

    – Detailed instructions for submitting Offers(s) using Power Advocate and to the IE

    – Announcements, additional resources, and Q&A

    • All solicitation communications should be directed to: [email protected] with a copy to the Independent Evaluator at [email protected]

    mailto:[email protected]:[email protected]

  • 7

    DIDF Timeline

    Develop Assumptions & Scenarios

    Distribution Grid Needs Assessment

    (GNA) Report

    Distribution Deferral

    Opportunities Report (DDOR)

    Distribution Planning Advisory

    Group (DPAG)

    Seek Commission

    Approval Distribution

    Deferral Opportunities

    Competitive RFOs for DERs

    Implement Traditional

    Solution

    3

    Implement DER

    Solution

    3a

    5

    7

    62 4

    •For locations where

    DERs don’t meet RFO

    deferral screens,

    proceed with traditional

    solution

    Nov 15Sep –NovSep 1Jun 1

    PG&E received Commission approval on distribution deferral opportunities for competitive procurement on December 16, 2020

    1

    •Advice Letter (AL)

    submitted in

    November 2020

    •AL approved

    December 2020

  • 8

    DIDF RFO Schedule for Third Party Ownership Opportunities (Willow Pass, San Miguel, Calistoga, Ripon, Zamora, AND Greenbrae)

    Date/Time Event

    January 11, 2021 PG&E issued RFO

    January 19, 2021 Participants’ webinar

    February 20, 2021 at 1:00 PM (PPT)

    Deadline for Participants to submit Offers via Power Advocate

    February 21, 2021 Deadline for IE to receive a flash-drive of Offers

    March 5, 2021 Participants Notified of Eligibility for Shortlisted Offer Negotiations

    March 11, 2021 Participants notify PG&E whether they accept Shortlist status

    May 31, 2021 Negotiations complete

    June 14, 2021 Target Advice Letter filing with the CPUC

  • 9

    DIDF RFO Schedule for Third Party and Utility Ownership Opportunity (Blackwell Bank 1)

    Date/Time Event

    January 11, 2021 PG&E issued RFO

    April 15, 2021 PG&E issues detailed specifications and term sheet for IOU ownership

    April 20, 2021 Participants’ webinar

    June 14, 2021 at 1:00 PM (PPT)

    Deadline for Participants to submit Offers via Power Advocate

    June 15, 2021 Deadline for IE to receive a flash-drive of Offers

    July 23, 2021 Participants Notified of Eligibility for Shortlisted Offer Negotiations

    July 29, 2021 Participants notify PG&E whether they accept Shortlist status

    November 16, 2021 Negotiations complete

    December 16, 2021 Target Advice Letter filing with the CPUC

  • Distribution Services Need

  • DIDF Project Locations

    All data depicted in thisapplication is for PG&Einternal use only.Dissemination to any entityoutside of PG&E requires theapproval of Corporate Security.

    Ripon

    ZamoraCalistoga

    Willow Pass

    `Greenbrae

    Blackwell

    San Miguel

    * CUSTOMER CONFIDENTIAL due to their peak loads violating the 15-15 customer privacy rule

    Candidate Deferral GNA Facility NameIn-Service

    Date

    WILLOW PASS BANK 1WILLOW PASS BANK 1 2023

    WILLOW PASS BANK 3 2023

    SAN MIGUEL BANK 2

    SAN MIGUEL BANK 1 2023

    SAN MIGUEL 1104 2023

    PASO ROBLES 1107 2023

    CALISTOGA BANK 1CALISTOGA BANK 1 2023

    CALISTOGA 1102 2023

    RIPON 1705 VIERRA 1707 2024

    ZAMORA BANK 1 ZAMORA BANK 1 2023

    GREENBRAE BANK 2* GREENBRAE BANK 2 2023

    BLACKWELL BANK 1 * BLACKWELL BANK 1 2023

  • WILLOW PASS DEFERRAL OPPORTUNITY

    Willow Pass Bank 1 and Willow Pass Bank 3

  • Technical and Operational Requirements

    • A combined need of at least 0.3 MW across Willow Pass feeders 1101 and 1102 is required• A combined need of at least 5.1 MW across Willow Pass feeders 2107 and 2108 is required

    Candidate Deferral

    Expected Performance and Technical Requirements

    GNA Facility NameIn-Service

    DateRequirement

    Real Time

    (RT) or Day

    Ahead (DA)

    Grid Need (MW)

    MonthDelivery

    DaysCalls/ Year

    HoursDuration (Hours)

    Willow Pass Bank 1

    WILLOW PASS BANK 1• Willow Pass 1101• Willow Pass 1102

    6/1/2023 A DA 0.3 6-8 Sat - Sun 82PM-8PM

    2

    WILLOW PASS BANK 3• Willow Pass 2107• Willow Pass 2108

    6/1/2023 B DA 5.1 6-9 Mon - Sun 1012PM-10PM

    6

  • Willow Pass Bank 1 and Feeders Location

    Overview

    • Equipment: Willow Pass Bank 1 – Feeders 1101 and 1102

    • Electrical Service:

    • 3-phase, 3.5 MVA bank with two 12.47 kV feeders

    Location

    Willow Pass Substation Bank 1, Contra Costa County

    All data depicted in thisapplication is for PG&Einternal use only.Dissemination to any entityoutside of PG&E requires theapproval of Corporate Security.

    Willow Pass

    Candidate Deferral GNA Facility NameIn-

    Service Date

    Grid Need (MW

    )

    Willow Pass Bank 1WILLOW PASS BANK 1 6/1/2023 0.3

    WILLOW PASS BANK 3 6/1/2023 5.1

  • DIDF Project Location: Willow Pass Bank 1

    Willow Pass Substation Bank 1 and Bank 3 Map

    Willow Pass Bank 1

    Willow Pass 1101

    Willow Pass 1102

    Willow Pass Bank 3

    Willow Pass 2107

    Willow Pass 2108

  • DIDF Project Location: Willow Pass Bank 1

    Willow Pass Substation Bank 1 Map

  • Willow Pass Bank 1

    Technical and Operational Requirements

    0

    2

    4

    6

    8

    10

    12

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    Load

    (MW

    )

    Hour

    Willow Pass Bank 1 – Hourly Load Profile

    June July August Facility Rating

    0.3 MW

    Candidate Deferral GNA Facility Name Requirement

    Real Time (RT) or

    Day Ahead (DA)

    Grid Need (MW)

    MonthDelivery

    DaysCalls/ Year

    HoursDuration (Hours)

    Willow Pass Bank 1WILLOW PASS BANK 1 A DA 0.3 6-8 Sat - Sun 8 2PM-8PM 2

    WILLOW PASS BANK 3 B DA 5.1 6-9 Mon-Sun 101 2PM-10PM 6

  • Customer Composition Served by Willow Pass

    Bank 1

    1 183

    2,674

    9

    Customer Count

    Agricultural Commercial/Industrial Residential Other

    0.0%

    18.5%

    81.5%

    0.0%

    Peak Day Load by Customer Class (%)

    Agricultural Commercial/Industrial Residential Other

    Customer Class Total Customer Count Peak Day Load (MW)

    Agricultural 1 0.00

    Commercial/Industrial 183 1.64

    Residential 2,674 7.23

    Other 9 0.00

    Total 2,867 8.87

  • Load by Customer Class – Willow Pass Bank 1

    (Peak Load Day – August 15th, 2019)

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

    MW

    Hour

    Peak Day Hourly Load Profile by Customer Type

    Agricultural Commercial/Industrial Residential Other

  • Willow Pass Bank 1 DER Overview

    Historical 2019 Forecast

    Observed Peak Load

    (MW)

    Installed DERs

    Year(Need vs

    Peak)

    Peak Load (1 in 10 Year) (MW)

    Incremental DER Growth

    Solar PV (MW)

    Storage (MW)

    PV (MW)

    ES (MW) EE (MW) DR (MW) EV (MW)

    8.87 0.94 0.022020 10.11 0.26 0.004 0.07 0.00 0.00

    2020 10.11 0.26 0.004 0.07 0.00 0.00

  • Willow Pass Bank 3

    Technical and Operational Requirements

    0

    5

    10

    15

    20

    25

    30

    35

    40

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    Load

    (MW

    )

    Hour

    Willow Pass Bank 3 – Hourly Load Profile

    June July August September Facility Rating

    5.1 MW

    Candidate Deferral GNA Facility Name Requirement

    Real

    Time

    (RT) or

    Day

    Ahead

    (DA)

    Grid

    Need

    (MW)

    MonthDelivery

    Days

    Calls/

    YearHours

    Duration

    (Hours)

    Willow Pass Bank 1

    WILLOW PASS BANK 1 A DA 0.3 6-8 Sat - Sun 8 2PM-8PM 2

    WILLOW PASS BANK 3 B DA 5.1 6-9 Mon – Sun 101 2PM-10PM 6

  • SAN MIGUEL DEFERRAL OPPORTUNITY

    San Miguel Bank 1, San Miguel 1104, and Paso Robles 1107

  • Technical and Operational Requirements

    • A combined need of at least 3.5 MW across San Miguel feeders 1104, 1105, 1106 and 1107 is required• At least 1.0 MW of the 3.5 MW must be sourced at San Miguel feeder 1104• 0.6 MW must be sourced at Paso Robles 1107

    Candidate Deferral

    Expected Performance and Technical Requirements

    GNA Facility NameIn-Service

    DateRequirement

    Real Time

    (RT) or Day

    Ahead (DA)

    Grid Need (MW)

    MonthDelivery

    DaysCalls/ Year

    HoursDuratio

    n (Hours)

    San Miguel Bank 2

    SAN MIGUEL BANK 1• San Miguel 1104• San Miguel 1105• San Miguel 1106• San Miguel 1107

    5/1/2023 A1 DA 1.3 Jun-Sep Mon - Sun 122 6AM-11PM 5

    5/1/2023 A2 DA 2.2 Jun-Sep Mon - Sun 122 6AM-11PM 10

    SAN MIGUEL 1104 5/1/2023 B DA 1.0 Jun-Sep Mon - Fri 66 5PM-10PM 4

    PASO ROBLES 1107 5/1/2023 C DA 0.6 Jul-Sep Mon - Fri 21 3PM-9PM 4

  • San Miguel Bank 1 and Feeders Location

    Overview

    • Equipment: San Miguel Bank 1 – Feeders 1104, 1105, 1106, and 1107

    • Electrical Service:

    • 3-phase, 16 MVA bank with four 12.47 kV feeders

    Location

    San Miguel substation Bank 1, San Luis Obispo County

    All data depicted in thisapplication is for PG&Einternal use only.Dissemination to any entityoutside of PG&E requires theapproval of Corporate Security.

    San

    Miguel

    Candidate Deferral GNA Facility NameIn-Service

    Date

    Grid Need (MW)

    San Miguel Bank 2

    SAN MIGUEL BANK 1 5/1/2023 3.5

    SAN MIGUEL 1104 5/1/2023 1.0

    PASO ROBLES 1107 5/1/2023 0.6

  • San Miguel Bank 1 – Hourly Load ProfileFlat, baseload profile – Energy storage will not be able to charge from the constrained location to meet

    the grid need (i.e., would need a separate energy source)

    Technical and Operational Requirements

    0

    5

    10

    15

    20

    25

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    Load

    (MW

    )

    Hour

    San Miguel Bank 1

    June July August September Facility Rating

    Candidate Deferral

    GNA Facility NameDistribution

    Service Required

    RequirementReal Time

    (RT) or Day Ahead (DA)

    Grid Need Grid

    Need Unit

    MonthDelivery

    DaysCalls/ Year

    HoursDuratio

    n (Hours)

    San Miguel Bank 2

    SAN MIGUEL BANK 1 Capacity A DA 3.5 MW 6-9 Mon - Sun 122 6AM-11PM 10

    SAN MIGUEL 1104 Capacity B DA 1.0 MW 6-9 Mon - Fri 66 5PM-10PM 4

    PASO ROBLES 1107 Capacity C DA 0.6 MW 7-9 Mon - Fri 21 3PM-9PM 4

    1.3 MW

    2.2 MW

  • San Miguel Bank 1 Options

    • Option 1: Requirement A

    • Requirement A: 3.5 MW, 10 hours

    • Option 2: Requirements A1 and A2

    • Requirement A1: 1.3 MW, 5 hours

    • Requirement A2: 2.2 MW, 10 hours

    • Both Requirement A1 and Requirement A2 must be met in order to meet the cumulative 3.5 MW grid need

  • San Miguel 1104 – Peak Day, Hourly Load Profile

    Technical and Operational Requirements

    0

    2

    4

    6

    8

    10

    12

    14

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Lo

    ad (M

    W)

    Hour

    San Miguel 1104

    June July August September Facility Rating

    1 MW

    Candidate Deferral

    GNA Facility NameDistribution

    Service Required

    RequirementReal Time (RT) or Day Ahead

    (DA)Grid Need

    Grid Need Unit

    MonthDelivery

    DaysCalls/ Year

    HoursDuratio

    n (Hours)

    San Miguel Bank 2

    SAN MIGUEL BANK 1 Capacity A DA 3.5 MW 6-9 Mon - Sun 122 6AM-11PM 10

    SAN MIGUEL 1104 Capacity B DA 1.0 MW 6-9 Mon - Fri 66 5PM-10PM 4

    PASO ROBLES 1107 Capacity C DA 0.6 MW 7-9 Mon - Fri 21 3PM-9PM 4

  • Paso Robles – Peak Day Hourly Load Profile

    Technical and Operational Requirements

    0

    2

    4

    6

    8

    10

    12

    14

    16

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Lo

    ad (M

    W)

    Hour

    Paso Robles 1107

    July August September Facility Rating

    0.6 MW

    Candidate Deferral

    GNA Facility NameDistribution

    Service Required

    RequirementReal Time (RT) or Day Ahead

    (DA)Grid Need

    Grid Need Unit

    MonthDelivery

    DaysCalls/ Year

    HoursDuration (Hours)

    San Miguel Bank 2

    SAN MIGUEL BANK 1 Capacity A DA 3.5 MW 6-9 Mon - Sun 122 6AM-11PM 10

    SAN MIGUEL 1104 Capacity B DA 1.0 MW 6-9 Mon - Fri 66 5PM-10PM 4

    PASO ROBLES 1107 Capacity C DA 0.6 MW 7-9 Mon - Fri 21 3PM-9PM 4

  • CALISTOGA DEFERRAL OPPORTUNITY

    Calistoga Bank 1 and Calistoga 1102

  • Technical and Operational Requirements

    Candidate Deferral

    Expected Performance and Technical Requirements

    GNA Facility NameIn-

    Service Date

    Requirement

    Real Time

    (RT) or Day

    Ahead (DA)

    Grid Need (MW)

    MonthDelivery

    DaysCalls/ Year

    HoursDuration (Hours)

    Calistoga Bank 1

    CALISTOGA BANK 1

    • Calistoga 1101• Calistoga 1102

    5/1/2023 A DA 1.3 6-9Mon –

    Sun40 2PM-6PM 3

    CALISTOGA 1102

    5/1/2023 B1 DA 2.0 6-9Mon –

    Sun122 12PM-9PM 5

    5/1/2023 B2 DA 1.0 6-9Mon –

    Sun122 12PM-9PM 8

    • A combined need of at least 1.3 MW across Calistoga feeders 1101 and 1102 is required• 3.0 MW must be sourced at Calistoga feeder 1102

  • Calistoga Bank 1 and Feeders Location Overview

    • Equipment: Calistoga Bank 1 – Feeders 1101 and 1102

    • Electrical Service:

    • 3-phase, 7 MVA bank with two 12.47 kV feeders

    Location

    Calistoga substation Bank 1, Napa County

    All data depicted in thisapplication is for PG&Einternal use only.Dissemination to any entityoutside of PG&E requires theapproval of Corporate Security.

    Calistoga

    Candidate Deferral GNA Facility NameIn-Service

    Date

    Grid Need (MW)

    Calistoga Bank 1CALISTOGA BANK 1 5/1/2023 1.3

    CALISTOGA 1102 5/1/2023 3.0

  • Technical and Operational Requirements

    • Calistoga Bank 1 – Peak Day, Hourly Load Profile• Potential red flag – Interconnection in the area may be costly and challenging due to protection and operational issues. PG&E will

    continue to assess the issue.

    0

    5

    10

    15

    20

    25

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    Load

    (MW

    )

    Hour

    Calistoga Bank 1

    June July August September Facility Rating

    1.3 MW

    Candidate Deferral GNA Facility Name RequirementReal Time

    (RT) or Day Ahead (DA)

    Grid Need (MW)

    MonthDelivery

    DaysCalls/ Year

    HoursDuration (Hours)

    Calistoga Bank 1CALISTOGA BANK 1 A DA 1.3 6-9 Mon – Sun 40 2PM-6PM 3

    CALISTOGA 1102 B DA 3.0 6-9 Mon – Sun 122 12PM-9PM 8

  • • Calistoga 1102 – Peak Day, Hourly Load Profile

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    Load

    (MW

    )

    Hour

    Calistoga 1102

    June July August September Facility Rating

    2 MW

    Candidate Deferral GNA Facility Name Requirement

    Real Time (RT) or Day

    Ahead (DA)

    Grid Need (MW)

    MonthDelivery

    DaysCalls/ Year

    HoursDuration (Hours)

    Calistoga Bank 1CALISTOGA BANK 1 A DA 1.3 6-9 Mon – Sun 40 2PM-6PM 3

    CALISTOGA 1102 B DA 3.0 6-9 Mon – Sun 122 12PM-9PM 8

    Technical and Operational Requirements

    1 MW

  • Calistoga 1102 Options

    • Option 1: Requirement B• Requirement B: 3 MW, 8 hours

    • Option 2: Requirements B1 and B2• Requirement B1: 2 MW, 5 hours

    • Requirement B2: 1 MW, 8 hours

    • Both Requirement B1 and Requirement B2 must be met in order to meet the cumulative 3.0 MW grid need

  • RIPON DEFERRAL OPPORTUNITY

    Vierra 1707

  • Vierra 1707 Feeder Location Overview

    • Equipment: Vierra Feeder 1707 (Bank 2)

    • Electrical Service:

    • 17 kV feeder

    Location

    Ripon Substation Bank 1, San Joaquin County

    All data depicted in thisapplication is for PG&Einternal use only.Dissemination to any entityoutside of PG&E requires theapproval of Corporate Security.

    Ripon`

    Candidate Deferral

    GNA Facility Name

    In-Service

    Date

    Grid Need (MW)

    Ripon 1705 VIERRA 1707 4/30/2024 3.7

  • 0

    5

    10

    15

    20

    25

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    Load

    (MW

    )

    Hour

    Vierra 1707

    June July August September Facility Rating

    3.7 MW

    Technical and Operational Requirements

    • Vierra 1707 – Peak Day, Hourly Load Profile

    Candidate Deferral GNA Facility Name RequirementReal Time

    (RT) or Day Ahead (DA)

    Grid Need (MW)

    MonthDelivery

    DaysCalls/ Year

    HoursDuration (Hours)

    Ripon 1705 VIERRA 1707 A DA 3.7 6-9 Mon – Sun 102 3PM-10PM 5

  • ZAMORA DEFERRAL OPPORTUNITY

    Zamora Bank 1

  • Zamora Bank 1 and Feeders Location Overview

    • Equipment: Zamora Bank 1 – Feeders 1105 and 1106

    • Electrical Service:

    • 3-phase, 10.5 MVA bank with two 12.47 kV feeders

    Location

    Zamora Substation Bank 2, Yolo County

    All data depicted in thisapplication is for PG&Einternal use only.Dissemination to any entityoutside of PG&E requires theapproval of Corporate Security.

    Zamora

    Candidate Deferral

    GNA Facility Name

    In-Service Date

    Grid Need

    (MW)

    Zamora 1108 ZAMORA BANK 1 5/1/2023 1.1

  • Technical and Operational Requirements

    • Zamora Bank 1 – Peak Day, Hourly Load Profile• Flat, baseload profile – Energy storage will not be able to charge from the constrained location to meet the grid

    need (i.e., would need a separate energy source)

    0

    2

    4

    6

    8

    10

    12

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    Load

    (MW

    )

    Hour

    Hourly Load Forecast - Peak Year (2020)

    May June July August Facility Rating

    1 MW

    Candidate Deferral GNA Facility NameIn-Service

    Date

    Real Time (RT) or

    Day Ahead (DA)

    Grid Need (MW)

    MonthDelivery

    DaysCalls/ Year

    HoursDuration (Hours)

    Zamora 1108 ZAMORA BANK 1 5/1/2023 DA 1.1 6-7 Mon - Fri 45 6AM-10PM 14

  • Customer Composition Served by Zamora Bank 1

    194

    87

    230

    2

    Customer Count

    Agricultural Commercial/Industrial Residential Other

    82.6%

    14.3%

    3.0%

    Peak Day Load by Customer Class (%)

    Agricultural Commercial/Industrial Residential Other

    Customer Class Total Customer Count Peak Day Load (MW)

    Agricultural 194 6.60

    Commercial/Industrial 87 1.14

    Residential 230 0.24

    Other 2 0.00

    Total 513 7.99

  • DIDF Project Locations

    All data depicted in thisapplication is for PG&Einternal use only.Dissemination to any entityoutside of PG&E requires theapproval of Corporate Security.

    Ripon

    ZamoraCalistoga

    Willow Pass

    `Greenbrae

    Blackwell

    San Miguel

    * CUSTOMER CONFIDENTIAL due to their peak loads violating the 15-15 customer privacy rule

    Candidate Deferral GNA Facility NameIn-Service

    Date

    WILLOW PASS BANK 1WILLOW PASS BANK 1 2023

    WILLOW PASS BANK 3 2023

    SAN MIGUEL BANK 2

    SAN MIGUEL BANK 1 2023

    SAN MIGUEL 1104 2023

    PASO ROBLES 1107 2023

    CALISTOGA BANK 1CALISTOGA BANK 1 2023

    CALISTOGA 1102 2023

    RIPON 1705 VIERRA 1707 2024

    ZAMORA BANK 1 ZAMORA BANK 1 2023

    GREENBRAE BANK 2* GREENBRAE BANK 2 2023

    BLACKWELL BANK 1 * BLACKWELL BANK 1 2023

  • Solicitation Overview

  • RFO Design (1/4)

    Product Attributes

    Product • PG&E is purchasing distribution capacity only, for either generation or load▪ No RA, energy, ancillary services, RECs, other attributes

    Dispatch • Day-Ahead

    Delivery • Monthly Range (e.g. June – August) • Hourly Range (e.g. 2PM – 8PM) • Hours Duration during the range (e.g. 3 hours between 2 PM and 8 PM)

    Delivery Term • PG&E is looking for 6 or 7 Delivery Terms

    Online Date • Beginning in 2023 or 2024

    Project Size • PG&E is looking to procure a minimum of 25.4 MW across all deferral opportunity locations

  • RFO Design (2/4)

    • Offers– Offers cannot exceed 200% of the grid need MW amount and cannot be less than 0.5 MW, unless where

    the grid need is less than 0.5 MW the grid need acts as the minimum allowable offer size. – Participants should indicate whether their Offer pricing may be applied to project sizes above or below

    the project size specified in the offer. This range will allow PG&E to facilitate combinations of Offers to satisfy grid needs, potential grid load need changes due to an updated load forecast, or potential procurement of a buffer to address load forecasting uncertainty. PG&E encourages Participants to submit Offers that are flexible to the greatest extent possible.

    – There are no limits on the number of offers Participants may submit.– To the extent that a Participant is able to, each Participant is encouraged to submit at least one Offer

    that addresses the entire combined need at each Grid Need Location.

    • Project eligibility

    – DERs: Renewable or non-renewable distributed generation, energy storage, energy efficiency, demand response, permanent load shift, electric vehicles

    – Projects may be either in-front-of-the-meter or behind-the-meter

    – Projects may be dispatchable or non-dispatchable

    – Participants may offer one resource or an aggregation

  • RFO Design (3/4)

    • Measurement and verification

    – Participants must submit a measurement and verification plan with their offers

    – Behind the meter Projects using a baseline methodology may require a customized approach

    • Interconnection

    – Project must connect to specified lines/feeders

    – No specific interconnection milestone required, but Participants must demonstrate they can meet the online date

    • Double payments/double counting

    – Projects must be fully or partially incremental to PG&E’s programs, tariffs, and solicitations

    – Participants must submit Appendix B Section 5 of the RFO materials to demonstrate how their Offer is incremental

    – Energy efficiency Participants may choose to have their Offer evaluated for incrementality on a project-specific basis or having their Offer evaluated based on a pre-specified overlap factor of 10%

    – All other resources must go through the project-specific review process

  • RFO Design (4/4)

    Resources can be: Examples

    Fully Incremental Not already sourced through another program, tariff, solicitation

    • Add-on’s to existing DERs, such as the addition of dispatchable storage to an existing PV resource

    • New programs;• EE Technology not included in Portfolio

    Partially Incremental

    Partially sourced through another program, tariff, solicitation

    Enhanced uptake of DER over base

    Not Incremental Wholly sourced through another program, tariff, solicitation

    Rooftop PV compensated under NEM without enhancement;Existing DG or ES compensated under SGIP without enhancement;EE or DR portfolio resources without enhancement

    Participants must demonstrate how Projects are incremental:

  • Technology Neutral Pro Forma (TNPF) Overview

  • Transaction

    • Product: Distribution Services in accordance with Operating Parameters

    −Decrease load or increase generation during specified hours−Sellers are free to monetize other revenue streams −Seller is free to operate the resource how it wants outside of the Delivery Days

    • Seller commits to provide Product at Contract Quantities

    −Seller may sell excess amount of Product from Project to third parties

    −Seller may sell other attributes of the Project to third parties

    • Sellers will be instructed on whether they are required to provide distribution capacity by 8 am day-ahead

    −Project may be dispatched at the Buyer’s discretion up to the Contract Capacity

    −Seller will provide PG&E with real-time visibility into DER performance

    −Sellers are required to install a communications system and equipment for PG&E to be able to remotely monitor Project status on an aggregate and individual unit basis

  • Payment and Delivered Energy

    • Compensation:

    – Fixed price ($/kW-month)

    – Variable price ($/kWh) for dispatchable resources when called upon to provide Distribution Services

    • Fixed compensation is dependent on delivery of services when called:

    Contract Capacity * Contract Price * Ratio Delivered Services when called * Delivered Services Adjustment

    Delivered Services Delivered services adjustment

    ≥0.90 and ≤ 1.00 1.0

    ≥0.80 and < 0.90 0.5

    ≥0.75 and < 0.80 0

    < 0.75 Delivered Services Adjustment – .75

    (Seller will pay PG&E)

  • Project Site and Customers

    • Sellers are solely responsible for acquiring Customers

    • Sellers may remove or replace Sites/Customers, provided that changes are in accordance with safety provisions

    • Seller must provide PG&E a list of Customers and satisfy incrementality criteria prior to Initial Delivery Date

    – Changes to initial Customer list must continue to satisfy incrementality criteria

    • Seller’s marketing materials that reference PG&E are subject to written approval by PG&E

    • Seller is responsible for all marketing activities, provided that PG&E may negotiate specified type of assistance

  • Performance Assurance

    Performance Assurance

    • “Project Development Security” is due to PG&E within five (5) business days following CPUC approval of the agreement and must be in the form of a letter of credit or cash and in the following amounts:

    – $40/kW for all new resources

    – $25/kW for existing resources

    • “Delivery Term Security” is due to PG&E before the Initial Delivery Date and will be held by PG&E throughout the delivery term

    – $40/kW

    – Seller may apply Project Development Security toward the Delivery Term Security

    Damage Payment/Termination Payment

    • In an event of default, defaulting party will owe non-defaulting party an amount equal to the performance assurance

  • Conditions Precedent

    • If CPUC Approval has not occurred on or before 180 days from the date on which PG&E files the agreement with the CPUC, then either party may terminate the agreement

    • Initial Delivery Date shall not occur until Seller:

    – Has constructed the Project and provided certification from an independent engineer that Project is commercially operable and constructed in accordance with the safety requirements

    – Has passed an initial Performance Test demonstrating that the Project is capable of delivering Distribution Service

    – Has provided PG&E with a list of Sites and Customers and PG&E has verified that such Sites/Customers are incremental

    – Has provided Delivery Term Security

  • Events of Default and Early Termination

    Events of Default

    • Failure to meet two Critical Milestones

    • Failure to meet Initial Delivery Date

    • Monthly Distribution Services Factor averages less than 80% for any calendar year

    • Results of Performance Test shows that the Project provides less than 85% of Contract Capacity

    Early Termination

    • Seller may terminate contract early if interconnection study results are not received or if they indicate interconnection costs are beyond a prespecified threshold.

    • Early termination must be exercised within 120 days after execution.

    • Seller subject to reduced damage payment.

  • Evaluation Methodology

  • Evaluation Criteria: Least Cost, Best Fit

    • Quantitative Factors

    – Benefits (Distribution Deferral Value)

    – Fixed and Variable Costs– Contract payments

    – Administrative costs

    • Qualitative Factors

    – Project Viability– Interconnection

    – Site Control Assessment

    – Developer Experience

    – Technology Viability

    – Ability to provide full need

    – Renewable vs. non-renewable

    – Technology, Counterparty Concentration

    – Supply Chain Responsibility

    – Safety

  • The distribution deferral values represent the net present value of deferring the annual revenue requirement associated with the traditional distribution investment.

    • Deferral Values:

    – Willow Pass Bank 1: $7,427,414

    – San Miguel Bank 2: $4,904,489

    – Calistoga Bank 1: $2,746,193

    – Ripon 1705: $1,429,249

    – Zamora 1108: $460,959

    – Greenbrae Bank 2: $2,252,417

    – Blackwell Bank 1: $2,307,478

    Distribution Deferral Values

  • Offer Submittal Process

  • Offer Submittal

    • Offers must be submitted via the online platform at Power Advocate. Only accepted registrants are permitted to submit Offers.

    Register through Power Advocate at: https://www.poweradvocate.com/pR.do?okey=111578&pubEvent=true

    – PG&E strongly encourages you to register well in advance of Offer due dates of February 19, 2021 at 1 PM (PPT) for third-party only offers and June 14, 2021 at 1 PM (PPT) for Blackwell.

    • Offer materials must also be physically delivered to the IE on a USB flash drive, no later than February 20, 2021 for third party only offers and June 15, 2021 for Blackwell at the following address:

    Sedway Consulting, Inc. 821 15th Street

    Boulder, CO 80302

    • PG&E will only consider Offers that, as of the submittal deadline, are complete and conforming Offers.

    https://www.poweradvocate.com/pR.do?okey=111578&pubEvent=true

  • Required Offer Submission Forms

    Offer package must be in the format as specified in the DIDF RFO Protocol.

    • Introductory Letter. Format: PDF

    • Fully Completed Offer Form (Appendix A1 and/or A2). Format: MS Excel

    • Supplemental RFO Appendix Document (Appendix B). Format: PDF

    • Note that in order to receive Greenbrae offer form an NDA (Appendix C) is required

    Note: Incomplete documentation will require additional communication to resolve any issues.

  • Offer Form

  • Offer Form Documents

    • Appendix A1– Offer Form for the Willow Pass, San Miguel, Calistoga, Ripon, and Zamora

    deferral opportunities

    • Appendix A2– Offer Form for Greenbrae which includes confidential load information

    – In order to receive this offer form, please submit a completed and executed NDA (Appendix C)

  • Offer Form Structure

    • Instructions• Create Offer• Select Deferral Opportunity• Select Grid Need Location• Offer Info• Participant Information• Attestations• Project Information• Pricing• Offer Size Flexibility• Offer Exclusivity• Offer Generation/Load Profile• Supply Chain Responsibility• File Name

  • Offer Form – Instructions

    • Be sure to ENABLE MACROS when opening the offer form.

    • Instruction tab provides clear directions on completing the offer form.

    • Please make sure you save and submit the form in Microsoft Excel “.xlsb” format. No other formats will be accepted.

  • Offer Form – Instructions (continued)

    • All fields with an orange background must be filled in. As they are filled in, they will change to green and be considered complete.

    • Data cannot be entered directly into grayed out fields. They are either for informational purposes or referenced elsewhere in the offer form.

  • Offer Form – Create Offer

    Participants can submit offers for a grid need location by selecting the “Create Offer” button in the “CreateInitialOffer” tab. More than one offer may be submitted for each deferral opportunity in your offer package. Only one offer can be created per offer form.

  • Offer Form – Select Deferral Location

    1. Select from one of the drop-down lists for the Deferral Opportunity you would like to make an offer for.

  • Offer Form – Select Offer Location

    1. Input the MW amount for the location at which you would like to make an offer.

    2. Click the radio button to right of the grid option for the offer you would like to create.

    3. Once chosen, click on the “Create” button to begin entering offer information.

  • Offer Form – Offer Info

    This is a vertical offer form. All offer information will start at the top and work down in a single column.

  • Offer Form – Participant Info

  • Offer Form – Project Information

    1. Choose Technology Type

    2. EE Only: Select appropriate incrementality evaluation option: Project-specific basis (Custom) or Pre-specified Overlap (10% overlap factor)

    3. Demand Response or Load Shift: Specify hours you anticipate on reducing load

    4. Some Technology Types will require a Generation or Load Profile to be entered on the “MW_Profile” Tab

  • Offer Form – Pricing

    Variable Pricing Not Applicable if following Technology Types Chosen:• Front of the Meter – Renewable Distributed Generation (Non-

    dispatchable)• Behind the Meter – Energy Efficiency• Behind the Meter – Permanent Load Shift

    Year 1 $ Pricing is Only Applicable to Behind the Meter – Energy Efficiency

  • Offer Form – Offer Range

    Specify if your offer price can be applied to a MW range outside of the drop-down list selection made for the offer.

    Enter a maximum or minimum MW amount that can be applied to your offer.

  • Offer Form – Offer Exclusivity

    Provide additional information about the exclusivity of each offer relative to other offers that you may be submitting.

    Specify if your offer is exclusive of other offers

  • Offer Form – Attestations

    All participants must adhere to theattestations listed in the offer form to remain a qualified and eligible participant.

  • Offer Form – Generation/Load Profile

    For front-of-the-meter renewable distributed generation (non-dispatchable), behind-the-meter energy efficiency, behind-the-meter electric vehicles (non-dispatchable) or behind-the-meter permanent load shift offers, provide the generation or load data stated in MW by hour and month.

    If applicable, enter the Annual Degradation value for your project.

  • Offer Form – Supply Chain Responsibility

    Fill out all fields in this tab. Once all of the required fields are populated, the message at the top of the tab will change to “Complete”

  • Offer Form – File Name

    VERY IMPORTANT! Please follow instructions carefully.

    Generate File Name

    Then click “Save This File”

  • Offer Form - Key Takeaways

    • Enable macros in the Excel file.

    • Submit a single offer form for each offer that you wish to submit for all grid need locations.

    • Only one offer for a grid need location can be made in each Offer Form.

    • Ensure the file name is the same as the pre-populated Offer ID.

    • Pay attention to “Units” i.e. kW vs MW.

    • Be sure all fields are filled in completely.

    All required input fields should be green for the offer form to be considered complete, not orange.

    • Data contained in Offer Forms must be consistent with contract values

  • Intermission

    Participants should email questions [email protected]

    mailto:[email protected]

  • Q & A