permi ng process flowchart for a federally-funded highway … · 2017-08-16 · for a highway...

1
Perming Process Flowchart for a Federally-Funded Highway Project in the U.S. State DOT/Project Sponsor STIP/TIP Project Preliminary Scoping Signicant Impacts? No Categorical Exclusion Impacts Uncertain Prepare Environmental Assessment (EA) Yes Publish Noce of Intent (NOI) to Prepare an Environmental Impact Statement (EIS) Idenfy and Consult with Relevant federal, State, local and tribal agencies NEPA Lead federal Agency CWA 404/ Rivers and Harbors Act Secon 10 CWA 401 Water Quality Cer�ficaon Apply to State/local/tribal Water Quality Authority Public Noce/ Comment Permit Evaluaon 401 Cer�ficaon Applicaon to USACE Endangered Fish/Wildlife Survey and Vericaon of Species Consult FWS/NOAA Hazardous Materials Site Assessment Submit Applicaon to State/EPA for RCRA Site ID No. Project involve hazardous waste? No Yes Site ID No. Issued Purpose/Need, Alternaves, Impacts, Studies, Preliminary Design Legally Required Analyses: I. Noise Noise Control Act of 1972 (42 USC 4901 – 4918) 23 USC 109(i)/23 CFR 772 II. Ecological Endangered Species Act (16 USC 1531 – 1544) Marine Mammal Protecon Act (16 USC 1361 – 1423h) Anadromous Fish Conservaon Act (16 USC 757a – 757f) Fish and Wildlife Coordinaon Act (16 USC 661 – 667d) Migratory Bird Treaty Act (16 USC 703 – 712) Magnuson-Stevens Fishery Conservaon and Management Act (16 USC 1801 – 1891d) Execuve Order 13751 (Safeguarding the Naonal Against Invasive Species) Bald and Golden Eagle Protecon Act (16 USC 668 – 668d) III. Historical and Cultural Resources and Parklands Naonal Historic Preservaon Act of 1966 (16 USC 470 et seq) Archaeological Resources Protecon Act (16 USC 470aa – 470mm) Archaeological and Historic Preservaon Act (16 USC 469 – 469c) Nave American Graves Protecon and Repatriaon Act (25 USC 3001 – 3013) Secon 4(f) of the DOT Act (49 USC 303/23 USC 138) Secon 6(f) of the Land and Water Conservaon Fund Act Execuve Order 11593 (Protecon and Enhancement of the Cultural Environment) IV. Water Resources and Wetlands Clean Water Act o Secon 401 (Cer�ficaon that discharges from project will comply with State water quality standards) o Secon 402 (Permit for discharge of wastewater or stormwater into waters of US) o Secon 403 (Permit for discharge into the ocean) o Secon 404 (Permit for discharge of dredged of fill material into waters of US) Coastal Barrier Resources Act (16 USC 3501 – 3510) Coastal Zone Management Act (16 USC 1451 – 1466) Safe Drinking Water Act (42 USC 300j – 300j-26) Rivers and Harbors Act (33 USC 403) Wild and Scenic Rivers Act (16 USC 1271 – 1287) Emergency Wetlands Resources Act (16 USC 3901 – 3921) Flood Disaster Protecon Act (42 USC 4001 – 4130) Execuve Order 11990, Protecon of Wetlands Execuve Order 11988, Floodplain Management V. Hazardous Materials Comprehensive Environmental Response, Compensaon and Liability Act (42 USC 9601 – 9675) Resource Conservaon and Recovery Act (42 USC 6901 – 6992k) VI. Air Quality Clean Air Act (42 USC 7401 – 7671q) VII. Social and Economic Farmland Protecon Policy Act (7 USC 4201 – 4209) American Indian Religious Freedom Act (42 USC 1996) Uniform Relocaon and Real Property Assistance Act (42 USC 4601 – 4655) Execuve Order 12898, Environmental Jusce Naonwide or Regional Permit? (45 Days) Yes Permit No Individu al Permit (120 Days) Will Acon Aect Species? No Nofy FWS/NOAA Public Noce (30 Day Comment Period) Public Interest Review/ Permit Evaluaon Permit 30-Day Public Comment Period Noce of Availability (NOA), Public Inspecon, Circulaon to Agencies Signicant Environmental Impact? No Finding of No Signicant Impact (FONSI) Yes May Aect but not likely to Adversely Aect May Adversely Aect Informal Consultaon with FWS/NOAA Prepare/Submit Biological Assessment Prepare/Submit Biological Assessment Formal Consultaon with FWS/NOAA (90 days) Leer of Concurrence FWS/NOAA Issue Biological Opinion (45 Days) Concur? Yes No Jeopardy Opinion? No “Incidental Take” Statement with reasonable and prudent measures Yes “Incidental Take” Statement with reasonable and prudent alternaves to project CWA 402/403 Naonal Polluon Discharge Eliminaon System Develop Stormwater Polluon Prevenon Plan Submit a Noce of Intent to relevant State/local/tribal authority Prepare and submit permit applicaon to relevant authority 30-Day Public Comment Period Permit Issued Floodplain Development Project in Floodplain? No Yes Study Impacts and Alternaves Submit Permit Applicaon to State/local/tribal authority Public Noce/Comment Analyze Floodplain Impacts Issue Permit Begin Scoping Prepare DraEIS (DEIS): Purpose/Need, Alternaves, Impacts, Studies, Preliminary Design Idenfy federal, State, local, and tribal cooperang agencies and invite parcipaon File with EPA, Publish NOA, Circulate to Agencies 45-Day Public Comment Period and Public Hearing Prepare Final EIS (FEIS): Respond to Comments, Addional Studies, Preferred Alternave, Migaon File with EPA, Publish NOA, Circulate to Agencies Aer 30 days, Issue Record of Decision (ROD) Migratory Birds/Eagles Survey/Study Impact Nests? Yes No Apply to FWS for Take Permit Marine Mammals Impact Marine Mammals? Survey/Study No Yes Apply to FWS/NOAA for Take Authorizaon Public Comment (30-60 days) Coastal Zone Consistency Determinaon Acvity inside the coastal zone? Yes No Prepare and submit consistency cer�ficaon to relevant State/tribal agency Public noce and comment period Consistency Determinaon (6 months)? Concur Nonconcur Appeal to Secretary of Commerce Public Noce and Comment Public Noce of Decision Permit Issued Permit Issued Historical Property/ Secon 106 Determine Area of Impact, idenfy historic properes, evaluate for Naonal Register eligibility, public and local gov consultaon Consult Tribe/THPO if historic property on tribal land or involves tribal signicance Submit to SHPO/THPO/Tribe for concurrence Concur? No – Resolve Objecon Assess Adverse Eects Adverse Eects? No and SHPO/THPO Concur -> Process Complete Yes Nofy SHPO/THPO and Resolve Adverse Eects with Project Spulaons Execute MOA with ACHP SHPO, THPO and other consulng pares 4(f) for Historic Properes, Public Parks and Rec Areas, and Wildlife Refuges Use/ Construcve Use? Must Implement Reasonable and Prudent Avoidance Alternave 6(f) - Parkland acquired with funds from the LWCF Evaluate Avoidance Alternaves Idenfy Comparable Replacement Property Obtain NPS Approval for Conversion Archaeological Resources On federal or Tribal land? No Yes Apply to Applicable Fed Land Managing Agency for Permit ARPA Permit Issued Secon 9 Bridge Permit Submit Applicaon to USCG USCG Publishes Noce and Requests Public Comments (30 Days) USCG Navigaon Determinaon Bridge Permit Issued Aeronaucal Determinaon for projects near airports or involving structures/cranes over 200’ Submit Applicaon to FAA Public Noce of an Aeronaucal Study FAA Aeronaucal Determinaon Permit Issued *Not all of these permits and approvals are required for all infrastructure projects. Approvals necessary for a highway project, and the complexity of the analysis, are dependent on context and locaon of the project. *Flowchart is just federal permits/approvals and does not include state and local permits/approvals. Addionally, the administraon of some federal laws represented in this owchart are delegated to state and/or local governments. *Projects processed as a categorical exclusion under Na�onal Environmental Policy Act (NEPA) may require addional permit approvals. *Dierent approvals by federal agencies could require addional analysis and approval under NEPA by the perming agency. .

Upload: others

Post on 11-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Permi ng Process Flowchart for a Federally-Funded Highway … · 2017-08-16 · for a highway project, and the complexity of the analysis, are dependent on context and loca on of

Permi�ng Process Flowchart for a Federally-Funded Highway

Project in the U.S.

State DOT/Project

Sponsor

STIP/TIP

Project

Preliminary Scoping

Significant Impacts? No

Categorical Exclusion

Impacts Uncertain

Prepare Environmental

Assessment (EA)

Yes

Publish No�ce of Intent (NOI) to Prepare an

Environmental Impact Statement (EIS)

Iden�fy and Consult with Relevant federal, State, local and tribal agencies

NEPA Lead federal Agency

CWA 404/ Rivers and Harbors Act Sec�on 10

CWA 401 Water Quality Cer�fica�on

Apply to State/local/tribal Water Quality Authority

Public No�ce/

Comment

Permit Evalua�on

401 Cer�fica�on

Applica�on to USACE

Endangered Fish/Wildlife

Survey and Verifica�on of Species

Consult FWS/NOAA

Hazardous Materials

Site Assessment

Submit Applica�on to State/EPA for RCRA Site ID No.

Project involve hazardous waste?

No

Yes

Site ID No. Issued

Purpose/Need, Alterna�ves,

Impacts, Studies, Preliminary Design

Legally Required Analyses:

I. Noise • Noise Control Act of 1972 (42 USC 4901 – 4918) • 23 USC 109(i)/23 CFR 772

II. Ecological • Endangered Species Act (16 USC 1531 – 1544) • Marine Mammal Protec�on Act (16 USC 1361 – 1423h) • Anadromous Fish Conserva�on Act (16 USC 757a – 757f) • Fish and Wildlife Coordina�on Act (16 USC 661 – 667d) • Migratory Bird Treaty Act (16 USC 703 – 712) • Magnuson-Stevens Fishery Conserva�on and Management Act (16 USC 1801 – 1891d) • Execu�ve Order 13751 (Safeguarding the Na�onal Against Invasive Species) • Bald and Golden Eagle Protec�on Act (16 USC 668 – 668d)

III. Historical and Cultural Resources and Parklands • Na�onal Historic Preserva�on Act of 1966 (16 USC 470 et seq) • Archaeological Resources Protec�on Act (16 USC 470aa – 470mm) • Archaeological and Historic Preserva�on Act (16 USC 469 – 469c) • Na�ve American Graves Protec�on and Repatria�on Act (25 USC 3001 – 3013) • Sec�on 4(f) of the DOT Act (49 USC 303/23 USC 138) • Sec�on 6(f) of the Land and Water Conserva�on Fund Act • Execu�ve Order 11593 (Protec�on and Enhancement of the Cultural Environment)

IV. Water Resources and Wetlands • Clean Water Act

o Sec�on 401 (Cer�fica�on that discharges from project will comply with State water quality standards) o Sec�on 402 (Permit for discharge of wastewater or stormwater into waters of US) o Sec�on 403 (Permit for discharge into the ocean) o Sec�on 404 (Permit for discharge of dredged of fill material into waters of US)

• Coastal Barrier Resources Act (16 USC 3501 – 3510) • Coastal Zone Management Act (16 USC 1451 – 1466) • Safe Drinking Water Act (42 USC 300j – 300j-26) • Rivers and Harbors Act (33 USC 403) • Wild and Scenic Rivers Act (16 USC 1271 – 1287) • Emergency Wetlands Resources Act (16 USC 3901 – 3921) • Flood Disaster Protec�on Act (42 USC 4001 – 4130) • Execu�ve Order 11990, Protec�on of Wetlands • Execu�ve Order 11988, Floodplain Management

V. Hazardous Materials • Comprehensive Environmental Response, Compensa�on and Liability Act (42 USC 9601 – 9675) • Resource Conserva�on and Recovery Act (42 USC 6901 – 6992k)

VI. Air Quality • Clean Air Act (42 USC 7401 – 7671q)

VII. Social and Economic • Farmland Protec�on Policy Act (7 USC 4201 – 4209) • American Indian Religious Freedom Act (42 USC 1996) • Uniform Reloca�on and Real Property Assistance Act (42 USC 4601 – 4655) • Execu�ve Order 12898, Environmental Jus�ce

Na�onwide or Regional Permit?

(45 Days)

Yes Permit No

Individual Permit

(120 Days)

Will Ac�on Affect

Species?

No

No�fy FWS/NOAA

Public No�ce (30 Day

Comment Period)

Public Interest Review/ Permit

Evalua�on

Permit

30-Day Public Comment Period

No�ce of Availability (NOA), Public Inspec�on, Circula�on to Agencies

Significant Environmental

Impact?

No

Finding of No Significant Impact (FONSI)

Yes

May Affect but not likely to Adversely Affect

May Adversely Affect

Informal Consulta�on with

FWS/NOAA

Prepare/Submit Biological

Assessment

Prepare/Submit Biological

Assessment

Formal Consulta�on with FWS/NOAA (90 days)

Le�er of Concurrence

FWS/NOAA Issue Biological Opinion

(45 Days)

Concur?

Yes No

Jeopardy Opinion?

No

“Incidental Take” Statement with reasonable and prudent measures

Yes “Incidental Take” Statement with

reasonable and prudent alterna�ves to project

CWA 402/403 Na�onal Pollu�on Discharge Elimina�on System

Develop Stormwater Pollu�on Preven�on Plan

Submit a No�ce of Intent to relevant State/local/tribal authority

Prepare and submit permit applica�on to relevant authority

30-Day Public Comment Period

Permit Issued

Floodplain Development

Project in Floodplain?

No

Yes Study Impacts and

Alterna�ves

Submit Permit Applica�on to

State/local/tribal authority

Public No�ce/Comment

Analyze Floodplain

Impacts

Issue Permit

Begin Scoping

Prepare Dra� EIS (DEIS): Purpose/Need,

Alterna�ves, Impacts, Studies, Preliminary Design

Iden�fy federal, State, local, and tribal

coopera�ng agencies and invite par�cipa�on

File with EPA, Publish NOA, Circulate to Agencies

45-Day Public Comment Period

and Public Hearing

Prepare Final EIS (FEIS): Respond to Comments,

Addi�onal Studies, Preferred Alterna�ve, Mi�ga�on

File with EPA, Publish NOA, Circulate to Agencies

A�er 30 days, Issue Record of Decision (ROD)

Migratory Birds/Eagles

Survey/Study

Impact Nests?

Yes No

Apply to FWS for Take Permit

Marine Mammals

Impact Marine

Mammals?

Survey/Study

No Yes

Apply to FWS/NOAA for Take Authoriza�on

Public Comment

(30-60 days)

Coastal Zone Consistency Determina�on

Ac�vity inside the coastal zone?

Yes No

Prepare and submit consistency cer�fica�on to relevant State/tribal agency

Public no�ce and comment period

Consistency Determina�on

(6 months)?

Concur Nonconcur

Appeal to Secretary of Commerce

Public No�ce and Comment

Public No�ce of Decision

Permit Issued

Permit Issued

Historical Property/ Sec�on 106

Determine Area of Impact, iden�fy historic proper�es,

evaluate for Na�onal Register eligibility, public

and local gov consulta�on

Consult Tribe/THPO if historic property on tribal land or involves tribal significance

Submit to SHPO/THPO/Tribe for concurrence

Concur? No – Resolve Objec�on

Assess Adverse Effects

Adverse Effects?

No and SHPO/THPO Concur -> Process Complete

Yes

No�fy SHPO/THPO and Resolve Adverse Effects with Project S�pula�ons

Execute MOA with ACHP SHPO, THPO and other

consul�ng par�es

4(f) for Historic Proper�es, Public Parks and Rec Areas,

and Wildlife Refuges

Use/ Construc�ve

Use?

Must Implement Reasonable and Prudent Avoidance Alterna�ve

6(f) - Parkland acquired with funds from the LWCF

Evaluate Avoidance Alterna�ves

Iden�fy Comparable Replacement Property

Obtain NPS Approval for Conversion

Archaeological Resources

On federal or Tribal land? No

Yes

Apply to Applicable Fed Land Managing Agency for Permit

ARPA Permit Issued

Sec�on 9 Bridge Permit

Submit Applica�on to USCG

USCG Publishes No�ce and Requests Public Comments

(30 Days)

USCG Naviga�on

Determina�on

Bridge Permit Issued

Aeronau�cal Determina�on for projects near airports or involving

structures/cranes over 200’

Submit Applica�on to FAA

Public No�ce of an Aeronau�cal Study

FAA Aeronau�cal

Determina�on

Permit Issued

*Not all of these permits and approvals are required for all infrastructure projects. Approvals necessary for a highway project, and the complexity of the analysis, are dependent on context and loca�on of the project.

*Flowchart is just federal permits/approvals and does not include state and local permits/approvals. Addi�onally, the administra�on of some federal laws represented in this flowchart are delegated to state and/or local governments.

*Projects processed as a categorical exclusion under Na�onal Environmental Policy Act (NEPA) may require addi�onal permit approvals.

*Different approvals by federal agencies could require addi�onal analysis and approval under NEPAby the permi�ng agency..