permanent ground anchors(volume 2).pdf

Post on 05-Jul-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    1/322

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    2/322

    Technical Report Documentation1. Report No. 2. Government Accerr~on No. 3. Rec,p*.nt’s Catoloq No.

    FHWA-DP-90-068-003

    4. Title and Subtitl. 5. Report Date

    Pope

    1

    DP-68 - Permanent Ground Anchors

    Volume 2, Field DemonstrationProject Summaries

    7. Author’s)

    Richard S. Cheney

    April 1990

    6. Pdorm~n g Orqamzotoon CodeHHO-420. Parformenq Organization Report NO.

    9. Performing Organexation Name and Address

    HHO-30/HHO-4010. work unit No. (TRA IS)

    Federal Highway Administration400 Seventh Street. SW.FJashington, D.C. 20590

    -is sponsoring Agw wy Name and b.ddr*,*

    HHO-40

    11. Contract or Grant No.

    13. Type of Report and Pwod Covered,

    Final ReportFederal Highway Administration

    400 Seventh Street, SW.Washington, D.C. 20590IS. Supplwn~ntary Not-

    FHWA: Theodore Ferragut

    1 14. Sponsoring Agency Cod*

    16. AbstractGround anchors, often called tiebacks, are structural elements which receive theirsupport in soil or rock and act to retain earth masses and/or appl ied structuralloads. The Federal Highway Administration recognized that the use of permanentground anchors in highway cut sections could affect substantial benefits in botheconomy and safety. The specific purpose of the permanent ground anchor demonstra-tion project was to introduce the concept of permanent ground anchor use intoAmerican construction practice. A manual numbered FHWA-DP-68-1R and titled"Permanent Ground Anchors" was prepared and several thousand copies distributed tohighway engineers. Permanent ground anchors on several projects were monitored tovalidate the concepts addressed in FHWA-DP-68-1R. This report summarizes theresults of both the field monitoring and the history of the permanent ground anchordemonstration project.

    17. Key Words 18. Distribution Statement

    Permanent ground anchors, tiebacks, No restriction - NTISanchors, anchor specifications, anchortest projects, anchor acceptance criteria,anchor test procedures

    19. Security Clorsif. (of this report) 20. Security Clossif. (of this page) 21. No. of Pago. 22. Pric*

    Form DOT F 1700.7 (8-72) Reproduction of completed page authorized

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    3/322

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    4/322

    REPORT TITLE

    1 Report of Field Performance Permanent Tieback Wall,Atlanta, Georgia

    2 Performance of Two Instrumented, Permanent Post-Grouted Tiebacks, Baltimore, Maryland

    3 Permanent Tieback Anchors in Cohesive SoilDemonstration Site, Seattle, Washington

    4 Performance Monitoring of a Highway Tieback Wall,Carroll County, Kentucky

    5 Permanent Ground Anchors for Lateral Support ofBridge End Slopes, Anchorage, Alaska

    6 Retention System Monitoring, Lima, Ohio

    ii

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    5/322

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    6/322

    REPORT NO. 1

    REPORT OF FIELD PERFORMANCEPERMANENT TIEBACK WALL

    DEMONSTRATION SITEI-75 - ATLANTA, GEORGIA

    GEORGIA DEPARTMENT OF TRANSPORTATIONbY

    LAW/GEOCONSULT INTERNATIONAL

    PROJECT PEI-75-2(41)MAY 1985

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    7/322

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    8/322

    SECTION Page

    1 INTRODUCTION........................................4

    2 PROJECT DESCRIPTION ................................ .

    Design Method ................................ ...6Construction Method ............................ .Subsurface Conditions .......................... .

    INSTRUMENTATION PLAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..g

    Background ..................................... .

    Description .................................... .LOAD TESTING PROCEDURE . . . . . . . . . . . . . . . . . . . . . . . . . . ..ll

    TEST RESULTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...13

    Load Test: Load Displacement . . . . . . . . . . . . . . . . . . ...13Load Test: Displacement and Load Distribution

    in Bonded Zone.......................14Load Test: Comparison between Load Cell and

    and Hydraulic Jack . . . . . . . . . . . . . . .19Long-term: Load at Anchor Head . . . . . . . . . . . . . . . . ...19

    Long-term: Displacements . . . . . . . . . . . . . . . . . . . . . . . . .20Long-term: Displacements and Distributionin Bonded Zone.......................22

    DISCUSSION OF WALL PERFORMANCE . . . . . . . . . . . . . . . . . ...24

    INSTRUMENTATION RECOMMENDATIONS . . . . . . . . . . . . . . . . ...26

    CONCLUSIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...30

    Instrumentation Results ......................... ..3 0Wall Performance .................................. 30Safe Design Loads ............................... ..3 1

    APPENDICES

    Appendix A - Tables and FiguresAppendix B - Dunnicliff Recommendations for Instrumentation

    l-i

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    9/322

    LIST OF TABLES AND FIGURES CONTAINEDIN APPENDIX A

    TABLES

    TABLE I - Summary of InstrumentationTABLE II - Summary of Acceptance Criteria Creep TestingTABLE III - Apparent Modulus of Unbonded Tendon Length Determined

    During Load TestsTABLE IV - ,Summary of Anchor Performance

    FIGURES

    FIGURE 1 -FIGURE 2-3 -FIGURE 4 -FIGURE 5 -FIGURE 6-15 -FIGURE 16 -FIGURE 17-18 -

    FIGURE 19-22 -FIGURE 23 -

    FIGURE 24 -

    FIGURE 25-30 -

    FIGURE 31-35 -FIGURE 36-37 -FIGURE 38-40 -FIGURE 41-42, -

    . . . .FIGURE 43 -

    FIGURE 44 -

    FIGURE 45-46 -

    .

    Plan and Profile Permanent Tieback WallPermanent Tieback Wall InstrumentationSchematic of Primary Instrumented Tieback AnchorCross Section of Instrumented Tieback AnchorLoad Displacement Curve - Load TestCreep Curves From Performance TestsComparison of Wire Telltale Versus Rod TelltaleDuring Load TestRelative Deformation in Bond Zone - Load TestHypothetical Load Transfer Diagrams and CalculatedTotal Elongation of Bonded ZoneLoad Distribution in Bonded Zone Assuming Slippageof Wire #l and Short Rod Telltale AnchorsComparison of Load Cell and Hydraulic Jack DuringLoad TestsLong Term Load VariationHorizontal Deflection Behind Permanent Tieback wallInclinometer Deflection Versus TimeComparison of Inclinometer Top Movement Survey. . . . . . . . . . . . . . . . . . Data Versus Inclinometer DataSummary of Maximum Horizontal and Vertical SurveyMeasurementsHorizontal and Vertical Survey Deflections VersusWall HeightLong Term Relative Deflection in Bonded Zone

    l-ii

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    10/322

    1. INTRODUCTION

    The Georgia Department of Transportation (Georgia DOT) ispresently conducting an extensive refurbishing program on theinterstate highways that pass through Atlanta's urban environment.An important element of this program is the implementation of manynew innovations in design and construction in cooperation with theFederal Highway Administration (FHYWA) to develop a modern andeconomical interstate system, One such innovation involved thedesign and construction of a permanent tieback retaining wallusing ground anchors in lieu of a conventional design using acantilevered wall in front of a temporary excavation supportsystem.

    The permanent tieback wall design and construction projectpresented in this report was funded through the FHWA's

    Demonstration Projects Program to "promote and accelerate theadoption of new research results and innovative planning,engineering, and construction practices." The overall objectiveof this demonstration project was to instrument and monitor thelong-term performance of the wall in order to evaluate the designand construction procedures for future Georgia DOT and FHWA-fundedhighway construction projects. This report describes theinstrumentation plan used to monitor the wall and the groundanchors, the testing procedure,during

    the test results of data gatheredthe first eight months of monitoring, and presents

    conclusions and recommendations. It is the intent of the GeorgiaDOT and the FHWA to monitor the wall's performance over a threeyear period.

    To accomplish the project objective,developed

    a comprehensive work plan wasto verify the wall design assumptions and construction

    methods and to collect and interpret long-termThe project scope included the following tasks:

    performance data.

    Task A. Measure deflection of the wall face to an accuracyof 0.1 inches.

    Task B. Measure deflection of the wall and ground with

    slope indicators in the unbonded length of thetieback and beyond the bonded length..

    Task C. Measure load variations in the tieback tendonswithin the unbonded and bonded lengths at specifiedstations along the wall.

    Task D. Measure other variables which are deemed necessaryfor the evaluation of the wall's performance.

    This demonstration project is one of many that the FHWA has fundedas part of its efforts to transfer technology into useful

    processes, products and programs. This report presents results of

    l-l

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    11/322

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    12/322

    calculations. No water pressure loading was assumed to act on theretaining wall since groundwater levels were deeper thanexcavation levels. Also, drainage fabric was to be installedbehind the concrete facing to carry away any groundwater thatmight collect behind the wall.

    Tieback loads were calculated using a structural computer programand were checked by hand calculations. Both methods consisted ofsumming forces and moments and checking for equilibrium. Onelevel of tiebacks was included in the lower portion of the wall,while the remaining portion of the wall included two levels.Design tieback loads ranged from 57 kips (in the lowest portion ofthe wall) to 138 kips. In cases where the design load in atieback was not achieved during field proof testing, therequirement for an additional tieback was also calculated bysumming moments and forces.

    The soldier piles were designed as simply supported steel beamswhere two or more tiebacks were installed on the soldier pile.Both final configuration and critical construction sequenceloadings were examined. The latter calculations were made forintermediate excavation levels to check for maximum moments in thepiles occurring during construction rather than at the deepestexcavation levels.

    Construction Method

    The method of construction used in this tieback wall involvedseveral components and sequences. The wall consisted of soldierpiles, timber lagging, ground anchors and concrete face panels.First, 30 inch diameter holes were augered from the ground surfaceto design depths ranging from seven to nine feet below theproposed bottom of the wall. Soldier piles were inserted into theholes. The piles were located on eight or nine foot centersapproximately 15 inches behind the proposed wall face.

    The structural members used for the soldier piles were doublebeams (ranging from W12 x 26 to W18 x 46 sections) joined withsteel plates. Concrete (3000 psi strength) was placed around thepiles from the bottom of the hole to the proposed ground line.Lean concrete was placed above the proposed ground line. As earthin front of the piles was excavated, the lagging was installedbetween the piles bearing against the steel beam flanges. Atdesigned locations and angles, approximately 6 inch diameter holeswere drilled between the two joined beams through the leanconcrete and into the soil for placement of the ground anchors.Casing was placed as the hole was advanced to allow insertion ofthe anchor. The ground anchors were stranded tendonsapproximately 50 feet long placed at angles from 20 to 30 degreesfrom the horizontal. Each tendon consisted of from two to fivestrands with each strand made up of seven wires. The majority oftendons in the higher portions of the wall had either four or five

    strands. The five strand tendon had an approximate diameter of

    1-3

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    13/322

    0.6 inches and total cross-sectional area of 1.075 square inches.In the unbonded portion of the tendon, a grease filled plasticsheath covered each strand. A corrugated plastic sheath wasfitted around the entire tendon in both the unbonded and bondedzone. Grout was injected through the casing as the casing waswithdrawn from the hole. The grout eventu,ally filled boththeannular space between the tendon and the corrugated tube, and thecorrugated tube and the ground. Grout pressures of approximately70 pounds per square inch were utilized. Grout pressures weremeasured with gages located at both the drill head and grout pumpto ensure that the pressure was maintained.

    After curing of the grout, the anchors were load-tested and posttensioned to a predetermined load. The load test procedure isdescribed in detail in Section 4. In some cases, an anchor wouldnot hold the predetermined design load. In these cases, theanchor was assigned a "safe" load based on the load test results.

    The designer would then assess whether this reduced load capacitywas sufficient. If not, an additional anchor was installed.Additional anchors were required at the northern instrumentationsection (Piles 65, 66, and 67).

    The process of lagging installation and anchor installation wasrepeated until the excavation in front of the wall was complete.The final sequence was to install strips of drainage fabric alongthe lagging and cast concrete face panels over the piles, laggingand tieback retaining system. The concrete face panels wereattached to the soldier piles by a series of studs welded to thesoldier piles and embedded in the cast-in-place concrete.

    Subsurface Conditions

    Subsurface conditions at the site were determined by boringsperformed by the Georgia DOT. The over-burdened soils weredescribed as "medium dense to dense yellowish-brown and pinkishmicaceous sandy silts." The micaceous nature of the site soilswas of interest because of its potential effect on anchor capacityand particularly long-term creep. The residual soils in thePiedmont geologic province are typically micaceous due to theirderivation from parent geneses and sects. Mica content has beenestimated (Sowers, 1963) in the Southern Piedmont areatypically range from 5 to 25 percent. Quantification of soil rnikzcontent is not commonly performed; therefore, it was not includedby Georgia DOT as part of their investigation.

    Standard Penetration Test resistances ranged from 11 blows perfoot to 60 blows with no penetration. These values generallyincreased with depth. However, harder and softer layers werefrequently encountered in interbedded fashion. Groundwater wasencountered approximately 40 feet below the ground surface. Thedepth to hard rock varies from 45 to 65 feet.

    During construction, thin black, iron-manganese coated zones wereobserved. These zones are common in the Southern Piedmont and are

    l-4

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    14/322

    locally termed "slickensides," but are actually unrelated tofaulting (St. John, et al, 1969).

    3. INSTRUMENTATION PLAN

    Backaround

    The instrumentation of the permanent tieback wall consists ofseveral mon‘itoring devices. The instrumentation plan wasrecommended by Mr. John Dunncliff and is appended to this report.Table I briefly presents all monitoring devices, including typeand source of instruments and their primary purpose within theprogram. A discussion of the instrument plan is contained in thefollowing paragraphs.

    A significant change resulted early in the instrumentation programwhen stranded tendons were selected over the initially planned baranchors. Strain gages were initially planned to measure strain atdesignated locations within the bonded zone and thus allowcalculation of load transfer. However, it was not deemed feasibleto mount strain gages to the tendon strands. Thus, wiretelltales, with a custom-fitted fixation to the strand, were usedto measure deformation within the bonded zone.

    Description

    Two monitoring stations spaced approximately 135 feet apart alongthe wall were selected to monitor the wall performance in higherportions of the wall (Figures 2 and 3). At each monitoringstation, two production anchors (upper and lower) on a single pileline were designated for "primary" instrumentation. Theproduction anchor on the piles on both sides of the "primary"anchor was designated for "secondary" instrumentation. Theinstrumentation for two secondary anchors was destroyed duringconstruction (discussed in Section 7). Thus, a total of fourprimary and six secondary anchors were instrumented.

    Instrumentation for the primary instrumented anchors included: apermanent load cell; short and long rod telltales; and

    five wiretelltales. This arrangement is shown in Figure 4 . The five wiretelltales were fixed approximately 7.5 feet apart from the top tothe bottom of the bonded zone (Instrument Positions 1 through 5).The short rod telltale was fixed at the top of the bond zone(Instrument Position 1). The long rod telltale was fixed at thebottom of the bond zone (Instrument Position 5). Rod and wiretelltales were attached to the same tendon strand. A basicassumption in application of the wire and rod telltales was thatall strands within the anchors behaved similarly and thatinstrumentation of one strand would predict the behavior of theentire anchor.

    l-5

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    15/322

    The secondary instrumented anchors had only one rod telltale fixedto one of the five strands at Position 1. The load cell mountedat the anchor head during load testing was not left in placepermanently.

    In addition to the anchor instrumentation, each monitoring stationincluded three inclinometers. One inclinometer was placed in apipe which was welded to the soldier pile for the primary anchors(Piles 51 and 68). The other two inclinometers were locatedapproximately 10 and 50 feet behind the wall.

    Extensive horizontal and vertical survey data all along thepermanent tieback wall was provided by the Georgia DOT. Surveypoints were established on the wall top and face. Ground surveypoints were also established at several distances (10 and 30 feet)behind the wall. Points 50 feet behind the wall were included fora limited portion of the wall. Movement of the inclinometer tops

    was also measured. Horizontal survey was performed by electronicdistance measurement from points across the existing interstate.Vertical survey was performed by routine level measurements.

    Each instrument was given a code for identification. This code ispresented below.

    w - XY - z

    where W = Instrument Type

    RT = Rod telltale

    WT = Wire telltale

    LC = Load cell

    SI = Slope inclinometer

    x = Soldier Pile NumberSee Figures 2 and 3

    1 = Anchor Locations

    U= Upper Row or L = Lower Row

    z = Instrument Position Desiqnation

    See Figure 4

    4. LOAD TESTING PROCEDURE

    All project anchors were subjected to a load test duringinstallation. The load tests were either a "proof test" or a

    l-6

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    16/322

    "performance test". All anchors were to be loaded to 150 percentof their design load. Incremental cycling of load was part of theperformance load testing. Anchors were loaded with a center-pullhydraulic jack with an electric pump. Displacement of the loadinghead was measured with a dial gage attached to a tripod set on theground.

    The acceptance criteria for the anchors was based on the movementof the anchor head (measured by the dial gage) during load testingand creep movement at the maximum test load. An anchor wasacceptable if:

    A. The total elastic movement obtained exceeded 80 percentof the theoretical elastic elongation of the free lengthand was less than the theoretical elastic elongation ofthe free length plus 50 percent of the bond length.

    B. The creep movement did not exceed 0.080 inches during asingle log-time cycle (five to 50 minutes forperformance testing, and one-half to five minutes forproof testing) regardless of tendon length and load.

    Anchors which met the above acceptance criteria were unloaded andlocked-off at 115 percent of design load. The additional 15percent of load was included to account for load losses due tolock-off (wedge setting) and potential long-term creep losses.Anchors which did not meet the above criteria were redesigned.This typically involved assuming a new design load equal to 67percent of the maximum safe load determined during the load test.The anchor was unloaded and locked-off at 115 percent of the "new"design load.

    Both anchors which met the original criteria and redesignedanchors were actually unloaded to below the design load and thenreloaded to the lock-off load. This is because the jack pressure(which determines load) is considered to be more accurate inloading than in unloading. Thus, by loading up to the lock-offload, a more accurate reading is obtained.

    Several d-ifferences in the load test procedures were utilized forthe instrumented anchors (primary and secondary). A 150-ton and a300-ton capacity hydraulic jack was utilized for loading thesecondary anchors and primary anchors, respectively. The primaryanchors required a larger jack because the center hole in the 150-ton jack was not large enough to accommodate the instrumentationand the anchor. In addition to the jack load reading, a load cellwas used to monitor the anchor loads. For this reason, it was notnecessary to unload and reload the anchors to obtain an accuratelock-off load. A different loading sequence occurred at fouranchor locations. At anchor locations 52-upper, 67-upper and 67-lower the anchors were unloaded to the seating load (alignmentload) and then loaded back to the lock-off load. At anchor

    location 66-lower, the load was cycled (loaded and unloaded) at

    l-7

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    17/322

    approximately 50 percent of design load and cycled again at 150percent of design load. Some details of the load testing at eachof the instrumented anchors are shown on Figures 6 through 15(Load Displacement Curve - Load Test).

    5. TEST RESULTS

    Test results presented and discussed within the following sectionare divided into those obtained during load testing of anchors andthose obtained during the long-term (approximately eight months)monitoring program.

    Load Test: ,Load-Displacement

    Loads applied during load testing of both primary and secondary

    anchors were measured with both the jack pressure gage and loadcell. However, the load data presented within this section weremeasured with the load cell because it is generally considered tobe more accurate. Displacements of the anchor head were measuredwith a dial gage which read displacement independent of anchormovement. Plots of load versus head displacement are shown inFigures 6 through 15. The acceptance criteria (A) discussed inthe Section 4 are also shown on these figures. The free and bondlengths used for determination of the acceptance criteria areshown on Figures 6 through 15. Some results of the load testshave been included in Table IV, Summary of Anchor Performance.

    Displacement of the long and short rod telltales and wiretelltales. #l and #5 for the primary anchors are also shown onFigures 6 through 9. The long rod telltale and wire telltale #5measure displacement of the pulling head with respect to theanchor bottom. As may be seen only minor differences existbetween the dial gage and long rod telltale readings for primaryAnchors 51-upper, 51-lower, and 66-lower. This indicates that thebottoms of these anchors showed no or very little movement duringthe load test. Anchor 66-upper (Figure 8) indicates a differenceof approximately 0.1 inches between the dial gage and the long rodor wire #5 telltale. Thus, a displacement of this amount of theanchor bottom may have resulted during load testing.

    The modulus of elasticity of the unbonded length can be determinedduring the load test for the primary and secondary anchors bycomparison of load versus elongation of the unbonded length. Thiselongation is measured with the short rod telltale, or wire #l,both of which are anchored at the interface between the unbondedand bonded zones. Modulus values determined in this manner arepresented in Table III. The ,reported manufacturer's modulus was28.5 x lo6 pounds per square ,inch. As may be seen in that table,the calculated modulus values during loading are considerably lessthan the manufacturer's modulus. A potential explanation for thisdifference in slippage of the rod and wire telltale anchors

    l-8

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    18/322

    relative to the tendon, causing the telltales to overestimateelongation. The slippage could be caused by the tendonout" of the grout

    '*breakingwith the telltale anchors restrained by the

    grout. The \possibility of slippage cannot be discounted, despitea soft material which was placed immediately in front of thetelltale anchors (around the tubes containing the rods or

    designed to alleviate this problem.

    wires)

    As discussed later, anevaluation of load transfer data tends to supportof slippage of these telltale anchors.

    the hypothesis

    As discussed previously, five and 50 minute creep tests wereperformed at the maximum test load for the secondary and primaryanchors, respectively.in Table II.

    The results of these tests are presented

    We have also utilized the creep test data to make a preliminaryassessment of creep potential. For this assessment, we have useda procedure presented in the report "Permanent Ground Anchors:Soletanche Design Criteria," dated September 1982 (Report No.FHWA/RD-81/150). This procedure involves the performance ofseveral "design load tests" prior to the installation ofproduction anchors. In these tests, the anchor load is held forone hour at different increasing load levels. These "design loadtests" were not performed as part of either the design orconstruction of the permanent tieback wall. However, we haveutilized the, results from 50 minute creep tests performed both forthe primary instrumentation anchorstesting for selected production anchors.

    and as part of performanceThis data is plotted

    (Figure 16) in a manner similar to that suggested in theSoletanche Report. The data appears to generally suggest that the"critical creep tension" was not reached during these tests.

    Load Test: Displacement and Load Distribution in Bonded Zone

    Displacement along the bonded anchor zones of the four primaryanchors was measured using a series of five wire telltales. Thespacing between the wire telltales,approximately 7.5 feet.

    as shown in Figure 4, was

    bondedDisplacement at the sop and bottom of the

    zone was also measured with the short andtelltales which were attached at the

    long rod

    strand assame place on the tendon

    the wire telltales #l and #5,

    comparison of the short rod versus

    respectively.

    versus wire #5, wire #l, and the long rotis shown in Figures 17 and 18 (Appendix A) for thefour primary anchors. Because the rod and wire telltale are fixedat the same locationapproximately

    on the tendon strand, they should measureequal deflection (that is, approximately zero

    relative deflection on Figures 17 and 18).agreement (less than 0.05 inch relative deflection)

    Relatively goodwas obtained

    for Anchors 51-upper, 66-upper,rod, only).

    and 51-lower (wire #l versus shortLesser agreement was obtained for Anchor 86-lower

    (0.05 to 0.10 inch relative deflection) and Anchor 51-lower, wire#5 versus long rod (0.10 to 0.15 inch relative deflection). Forboth Anchors 51-lower and 66-lower we have also shown relative

    l-9

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    19/322

    deflection of the long rod versus dial gage, which should beapproximately equal if no deflection occurs at the bottom of thebonded zone. Good agreement between the dial gage and long rodwas obtained for Anchor 51-lower, thus indicating that wire #5overestimated deflection. In Anchor 88-lower, the dial gage wasgreater than the long rod which could indicate either displacementat the bottom of the bonded zone or relative instrument accuracy.Wire #5 deflection exceeded dial gage deflection, which probablyindicates. that wire #5 overestimated deflection.

    The displacement measured by each wire telltale with respect towire telltale #l (relative deformation) during load testing isshown on Figures 19 through 22. The difference between wiretelltale curves at a given load represents the relativedeformation between points. Example: the difference betweencurves 2-l j and 3-l represents the relative displacement betweenpoints 2 and 3). Positive relative deformations between any twopoints (2-1, 3-1, 3-2, etc.) represents elongation of that segmentof the tendon. The displacement of the long rod telltale withrespect to the short rod telltale is also shown on these figures.

    The relative deformations within the bonded zone must meet twocriteria which are based on two closely related assumptions.These criteria and their related assumptions are:

    A. Relative deformation (elongation) should increase withincreased distance between points (the 3-l differenceshould be greater than the 2-l difference, etc.)assuming that the tendon is in tension. The wire 5-ldifference long rod-short difference(whichever is izre %?rect) should form tEzdupper boundof the plots shown on Figures 19 through 22.

    B. The elongation of adjacent equal length segments mustdecrease moving down the tendon. That is, the wire 2-ldifference must be greater than the wire 3-2 difference(3-2 = 3-l minus 2-l), etc. This assumes that tensionin the tendon decreases with increased distance from thetop of the bond zone.

    The relative deformations presented in Figures 19 through 22 may

    be examined utilizing these two criteria. Anchor 51-lower, withthe displacements measured by wire #3, #4, and #5 all exceedingthe long rod displacement, will be excluded from thisconsideration. Examination based on data for the remaining threeanchors (Figures 19, 21, and 22) yields the following generalpoints:

    A. The wire 2-l difference is less than the wire 3-ldifference (Criterion I) in all three cases (includingAnchor 66-upper for which the wire 2-l difference wasnegative). However, the wire 2-l difference is lessthan the wire 3-2 difference (3-2 = 3-l minus 2-l) in

    all three cases, which is contrary to Criterion II.

    l-10

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    20/322

    B In two of three anchors (88-upper and 66-lower) the wire3-l difference is less than the wire 4-l difference(Criterion I). In both cases, the wire 4-3 differenceis less than the wire 4-3 difference (Criterion II).

    c. The wire 4-l difference is less than the wire 5-ldifference in Anchorwire 3-l difference) 51-upper (and also less than theand close to the wire 5-ldifference in Anchors 66-upper and 66-lower. Ingeneral, deformations in this portion of the bonded zoneappear to be in the range of the data accuracy.it appears difficult to

    Thus,resolve deformations in this

    portion of the bonded zone.

    In summary, the wire 2-l difference appears too small in allcases, while the validity of the remaining data appears mixed. Apotential reason for this apparent underestimation of the 2-lrelative deformation (elongation) is slippage of the wire #l (and

    short rod) telltale anchorage.slippage could As discussed previously, thiscause an overestimation of elongation of theunbonded length and, thus, an underestimation of elongation of thebonded zone (particularly the upper 7.5 feet of the bondedwhen wire #l is compared to wire #2).

    zone,

    anchors,Slippage of the telltale

    caused by the grout restraining free movement of thetelltale anchor along with the tendon, appears more likely atPoint #l than at the other telltale anchorage points. This isbecause higher tensions and displacements occur in this portion ofthe tendon than in deeper portions of the bonded zone.tensions

    The higherand displacements increase the possibility that the bond

    between the tendon and the grout could be broken and thus thatrelative displacement between the two could occur.the grout within the unbonded zone (free length) is

    In addition,not stressed

    by the tendon and thus acts to restrain the outward movement ofgrout in the upper portion of the bonded zone.

    The amount of possible slippage of the wire #l and short rodtelltale anchors can be estimated by making the assumption thattelltale anchor slippage is the only cause of difference betweenthe apparently underestimated modulus values determined during theload test and the manufacturer's modulus. the differencebetween

    Thus,the elongation compatible with the manufacturer's modulus

    and the elongation measured by wire #l (or the short rod) couldapproximately equal the amount of slippage. The amount ofestimated slippage increases with load and isapproximately

    increasing0.3 inches at maximum loads. If the wire #l and

    short rod readings are corrected for the estimatedthe wire differences (2-1,

    slippage, all3-1, 4-1, 5-1, and the long rod-short

    rod) plotted on Figures 19 through 22 would be moved to thewith respect to the ordinate.

    right

    The purpose of deflection measurements within the bonded zone wasto provide an indirect calculation of load transfer.of slippage of

    The questionthe wire #l and short rod telltale anchor

    l-11

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    21/322

    significantly effects the results of this calculation. Thiseffect will be further discussed below. First, however, we willdiscuss the manner in which load transfer is estimated fromrelative deflections within the bonded zone.

    Elongation of a segment of the tendon is a function of strains

    along that segment length.of The elongation equals thestrain integrationplot).

    versus length (the area under the strain versus lengthThus,

    withinelongation is directly related to the average strain

    that segment. Stress (and load) are directly related tostrain at any point along the tendon (Hooke's Law). Thus, theshape of load versus length plot must be directly related to theshape of the strain versus length plot, and average load directlyrelated to, average strain. Further, the average load within asegment, as 'a measure of the area under the load distributioncurve, is directly related to the elongation of the segment, andcan be calculated from that elongation. The simplifyingassumption that strains and loads change linearly within a segmentallows positioning the calculated average load at the mid-point ofthe segment. The change in load from one point in the tendon toanother point is the load transfer between those points.

    As discussed previously the question of slippage of the wire #land short rod telltale anchors significant affects our calculationof load transfer. Thus, the two possible outcomes of the questionlead to two separate lines of reasoning, which are developedseparately below:

    A. Assumption of No Telltale Anchor Slippaqe: If we assumethat slippage of the wire #l and short rod telltaleanchors has not occurred, then the wire 2-1 differencesbecome too small compared to the wire 3-2 differences(Criterion II). Thus, both these wire differencesappear in question and it appears impossible to utilizethem to calculate average loads and load transfer in theupper 15 feet of the bonded zone. However, if slippagehas not occurred, then a good estimate of overall bondzone elongation appears possible utilizing the wire 5-lor long rod-short rod difference. This data issupported by the previously discussed agreement betweenthe short rod versus wire #l, and the long rod versuswire #5. A significant result of the previousdiscussion on calculation of load transfer is thatelongation of the entire bonded zone (or any segment ofthe bonded zone) is directly proportional to the areaunder the load distribution curve. Thus, although it isnot possible to calculate average loads within segmentsof the bonded zone, it may be possible to derive generaltrends in the load distribution. Anchors Sl-upper and66-lower both showed approximate 0.6 inch bonded zoneelongation at 150 kips above the seating load. Thus,Part A of Figure 23 shows three hypothetical loaddistribution diagrams with elongation of the entire

    1-12

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    22/322

    bonded zone equal to 0.6 inches. Examination of thesediagrams shows that significant load transfer must occurwithin the first two segments of the bonded zone toresult in 0.6 inches of elongation. Lesser loadtransfer rates in this portion of the bonded zone wouldresult in increased area under the curve and thusincreased bonded zone elongation.

    B. Assumption of Telltale Anchor Slippaae: If we assumethat slippage of the wire #l and short rod telltales hasoccurred,through 22

    then the wire difference curves on Figures 19are shifted to the right, as discussed

    previously. As stated, we may calculate the amount ofslippage based on the manufacturer's modulus and use itto correct the wire #l data, This increases the wire 2-1 difference, but does not affect the relativedifferences between the other curves (the wire 3-2, 4-3,

    and 5-4 differences). The overall elongation of thebond zone (the wire 5-l or long rod-short roddifference) is, of course, also increased. The maximumslippage, as previously discussed, is estimated to beapproximately 0.3 inches. Adding this amount to the 0.6inches discussed previously for Anchors 51-upper and 66-lower, yields a total bond zone elongation ofapproximately 0.9 inches. Part B of Figure 23 showshypothetical load distribution diagrams with elongationof the entire bonded zone equal to 0.9 inches. Inaddition, we may use the adjusted wire 2-l differenceand the other wire differences to calculate averagesegmental loads and thus derive a load distribution plotwhich is based on the slippage assumption. This hasbeen performed for Anchors 66-upper and 66-lower. Afteradjustment of the data from all four anchors for assumedslippage, we judge the data from these two anchors to bemore reasonable than the other two primary anchors.Load distribution plots for these two anchors are shownon Figure 24. Load distribution for selected loadingincrements are shown. At each load increment we haveplotted calculated average load within bonded zonesegments. We have also shown smoothed loaddistribution curve which meets thz criteria, statedpreviously,related

    that area under the curve must be directlyto elongation of the entire bonded zone. These

    curves intersect the ordinate of the plots at the loadcell reading, which is assumed to equal load at the topof'the bonded zone. The calculated averageloads

    segmentaland the smoothed load distribution curve are both

    based on deflection data which begins at theload.

    seatingThus, these loads must be added to assumed load

    distribution at the seating load. This assumeddistribution is shown on the plots.

    In summary, our estimate of load distribution within thebonded zone is significantly affected by the question of

    1-13

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    23/322

    slippage of the wire #l and short rod telltale anchors.The assumption of no slippage results in our inabilityto utilize the wire differences to estimate loads, andresults in relatively high load transfers within theupper portions of the bonded zone (based on totalelongation of the bonded zone). The assumption ofanchor slippage is based on the low modulus valuescalculated for the unbonded zone during the load test.Application of the estimated slippage makes the wiredifferences appear more reasonable and allowscalculation of average segmental loads. Load transferb&sed on the anchor slippage assumption appear morereasonable than that based on the no slippageassumption. Thus, there appears to exist several pointssupporting the slippage assumption. However, we do notfeel that it is possible to decide conclusively betweenthese two assumptions and associated results. Futureprojects might provide insight into this question,

    Load Test: Comparison between Load Cell and Hvdraulic Jack

    Figures 25 through 30 show jack load reading divided by load cellreading versus load cell reading during load testing for primaryand secondary anchors. The load cell reading was chosen for theabscissa because it is assumed to be more accurate that the jackload reading. As may be seen the jack load reading in almost allcases is greater than or equal to the load cell during loading andless than the load cell during unloading. The load as measured bythe jack has an apparent accuracy of + 5 to 10 percent. Thisagrees with most published data which generally

    cite off-centerloading and end effects as probable cause of inaccuracy.

    Lonq term: Load at Anchor Head

    Long-term variation in load at the anchor head was measured on theprimary anchors with load cells and short rod telltales (telltaleload cells), and on the secondary anchors with only short rodtelltales.

    The functioning of the short rod telltale as a load indicator isas follows. (A sketch and description are also contained in

    Figure 3 of the appended instrumentation plan. The short rodtelltale measures displacements between the top of the bonded zoneand the anchor head. Thus, the short rod telltale measureschanges in length of the unbonded anchor strand. These changes inlength can be converted into load changes (via Hooke's Law) withinthe unbonded zone. It is assumed that no load transfer occurswithin this unbonded zone. Thus, these load changes are alsoindicative of load changes at the anchor head. Because the wiretelltale -#l also measures changes in length of the unbonded zone,it can be used as a telltale load cell in a similar manner. Theunbonded length in the final lock-off position (the lengthutilized in the telltale load cell calculations) is less than the

    1-14

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    24/322

    unbonded length during the load test. This is because a portionof tendon was cut off during the lock-off. This reduction inlength was typically 4 to 5 feet.

    Utilization of Hooke's Law, as discussed above, requiresassumption of a modulus of elasticity

    w lAs discussed

    previously, modulus values of the unbonded length determinedduring load testing were significantly less than the reportedmanufacturer's modulus and may have been caused by slippage ofwire #l and short rod telltale anchors. For this reason, it wasdecided to use the manufacturer's modulus.

    Long-term load variation at the anchor head is shown for theprimary anchors on Figures 31 and 32. Load change measured by theload cell and calculated by both the rod and wire telltale loadcells are shown. As may be seen, there is good agreement in threeof four primary anchors between the loads changes measured with

    the load cell and those calculated from the rod telltale. Thisagreement tends to support the decision to use the manufacturer'smodulus in the telltale load cell calculations. The differencebetween the load indicators in Anchor 51-lower cannot beexplained. Based on the comparisons, it appears that the shortrod telltale is a relatively reliable indicator of long-term loadchange. Figures 33 through 35 show load variations in the sixsecondary anchors as measured with the rod telltale load cell.Measurement of long-term load change for both primary andsecondary anchors was begun after setting wedges to lock-off theanchor into final configuration.

    Approximately eight months of load variation data has beencollected for all ten instrumented anchors. Seven of the anchorshave shown approximately 5 kips or less variation from their lock-off condition (Anchors 50-upper, 51-upper, 51-lower, 52-upperper, 65-upper, 65-lower, and 66-upper). Of the remaining threeanchors, two have shown increase in load of approximately 10 kips(Anchors 66-lower and 67-lower) while Anchor 67-upper has shown adecrease in load of approximately 15 kips. The load changes aftereight months have been added to the seating loads, and are shownin Table IV. We have also attempted to estimate the long-termload loss (creep) in anchors. These results are also shown inTable IV. These estimated creep values should be consideredpreliminary and should be reevaluated when additional long-termdata is available.

    Lonu-term: Displacements

    Three inclinometers (SI) are located behind each instrumentedstation (Piles 50-52 and 65-67). The Number 1 inclinometers wereinstalled in a steel pipe welded to Piles 51 and 66. The Number 2and 3 inclinometers are located in the soil approximately 10 and50 feet behind the retaining wall, respectively. The horizontalinclinometer deflections observed atconstruction are shown in Figures 36 and 37.

    different stages of

    1-15

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    25/322

    The inclinometer casings were extended approximately 10 feet belowthe bottoms of the soldier piles as shown in Figures 36 and 37.As may be seen by examination ofthose figures,

    the inclinometer profiles on

    casings.fixity was not exactly achieved at the base of the

    The amount of base deviation was small and the effect onthe overall readings appears negligible. Thisconfirmed by horizontal survey of the

    is generallyinclinometer

    Comparisonscasing tops.

    in Figuresof survey data versus inclinometer top data are shown

    41 and 42.determine

    The procedure of "check sums" was used toinclinometer accuracy. This confirmed that the

    inclinometers were providing reliable data.

    The maximum',horizontal retaining wall movement measuredinclinometers

    by thewas about 3/4 inches toward the excavation. The

    magnitude of the horizontal movements 10 feet behind the wall(Number 2 inclinometers) are similar

    wall; however,to that of the retaining

    the vertical distribution of the movement is

    somewhat different. Somewhat greater deflection occurred inInclinometer SI-66-2 than in Inclinometer SI-66-1. The deflectionof Inclinometer SI-51-3 (approximately 50 feet behind the wall)was not significant. However,40 feet behind the wall)

    Inclinometer Sl-66-3 (approximatelymeasured approximately 0.4 inches

    deflection.

    Figures 38 through 40 show inclinometer deflection at given depthsversus time. As may be seen, movement continued to occur afterthe excavation was complete but appears to betime, especially over the last three months.

    slowing down with

    Extensive horizontal and vertical survey data was provided by theGeorgia DOT. Survey points were established on the wallface six feet below the top of

    top andthe wall.

    established on the wallAll survey points

    topuseful long-term

    were destroyed prior to yieldinginformation. Ground survey points were also

    established,at several distances (10, 30 and 50 feet) behind thewall. As 'discussed above,also measured.

    movement of the inclinometer tops wasMaximum horizontal and vertical deflections are

    shown in plan view on Figure 43. Maximum horizontal and verticaldeflections as a function of wall height are plotted in Figure 44.

    Survey points on the wall face generally indicated an inwardmovement during the time anchors were stressed. This inwardmovement ranged from approximately 0.03 to 0.07 feet (0.4 to 0.8inches). Outward movement was referenced frommaximum inward movement and

    the point ofwas a maximum of

    inches).0.10 feet (1.2

    Ground survey points 10 feet and 30 feet behind the wallface showed a maximum outward horizontal deflection of 0.11 feet(1.3 inches) and 0.09 feet (0.8 inches), respectively.seen in Figure 44,

    As may bea good correlation apparently exists between

    wall height and surveyed outward deflections of both the piles(measured from the point of maximum inward deflection) and groundpoints. Examination of the survey data appears to indicate that

    wall movement has stabilized.

    1-16

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    26/322

    Downward deflections of the surveyed pile monitor points indicateda downward maximum deflection ofinch).

    approximately 0.08 feet (1.0As may be seen in Figure 44 these deflections were erratic

    with respect to wall height. The pile settlement was probablycaused by the downward component of tieback orloads.

    earth pressureGround survey points 10 feet and 30 feet behind the wall

    showed a maximum settlement of 0.07 feet (0.8 inch) and 0.02 feet(0.2 inch), respectively. As may be seen in Figure 44 a goodcorrelation apparently exists betweenground settlements.

    wall height and surveyedSurveyed vertical ground deflections averaged

    approximately 50 percent of horizontal deflections.

    Maximum horizontal wall movements measured by the inclinometersand by survey were approximately 0.8 inches and 1.2 inches,respectively. These correspond to approximately 0.2 percent and0.3 percent of wall height, respectively. Goldberg, Jaworski andGordon (1976) reported a range of horizontal movements of 0.1percent and 0.8 percent of wall height for tieback walls in sandand gravel. Experience with standard cantilever retaining wallsin the Atlanta area indicates that development of the active earthpressure case requires a horizontal wall movement of approximately0.3 to 0.6 percent of wall height.the permanent tieback wall are in the

    In our opinion, movements of

    associatedrange of

    withthose generally

    the active earth pressure condition for soils inthe Atlanta.area.

    One purpose of the survey data was to determine whether or not theinstrumented sections were typical of the rest of the wall.Examination of Figure 43 and 44 appears to indicate that they weretypical of the higher portion of the wall.

    Lonq-term: Displacements and Load Distribution in Bonded Zone

    The wire #5 and long rod telltales measure relative deformationsbetween the anchor head and the bottom of the bonded zonethe entire anchor).

    (i.e.Examination of the long term data indicates

    elongations of the anchor ranging from 0.05 to 0.20 inches. Thisis compared to outward movements of the wall and anchor head, ofapproximately 3/4 inch. Thus, as the wall deformed theentire anchor

    outward,(including the bonded zone) also moved outward

    approximately l/2 to 3/4 inch. Inclinometer SI-66-3 was locatednear the bottom of the anchors (seeapproximately 0.4 inches of deflection.

    Figure 37) and measuredThus, movement of the

    bottom of the anchors may be related to overall movement of thesoil mass rather than displacement of the bonded zone in relationto the surrounding soil.

    Overall elongation of the entire anchor,#5 and long rod telltale,

    as measured by the wireconsists of unbonded length deformation

    (indicative of load in the anchor) and bonded length deformation(indicative of load transfer within the bonded zone). Figures 45and 46 show long-term relative displacement within the bonded zone

    1-17

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    27/322

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    28/322

    the general outward movement in the wall and anchor. A second isthat the pile moved inward due either to stressing of theintermediate anchor, or possibly a redistribution of load towardthe bottom of the wall (as reflected in increased load in Anchor67-lower). However, the second possibility is not supported byeither Anchor 65-upper or 66-upper both of which had an

    intermediate' anchor below them. In addition, Anchor 66-lowerexperienced a load increase similar to that of Anchor 67-lowerwithout a decrease in load in Anchor 66-lower.

    An intermediate level of tiebacks was required at the northerninstrumentation section (piles 65, 66, and 67) because of failureof the upper level of anchors to achieved proposed design loads.The design loads for these intermediate anchors were calculated inthe same manner as the original design loads, including the actualload for the upper level of anchors. Thus, while long-term loadchange data is not available for the intermediate anchors, itappears that the conclusions within this section wallperformance and the relation to wall design are also appl?:able tothis case.

    7. INSTRUMENTATION RECOMMENDATIONS

    The instrumentation on this project has generally provided theintended information. While some problems have surfaced, theseare to be expected in an instrumentation program for which therewas little precedent. The successful implementation of theprogram required intensive coordination between ourselves,

    theinstrumentation consultant, the tieback contractor, the instrumentsuppliers, and the overseeing agencies.the instrumentation

    The customized design ofnecessitated many iterations between these

    parties. The need for this coordination cannot be overemphasized.The ability to select and procure the proper instrumentation on a"preferred sole source" basis was critical to the successes of theprogram. If similar instrumentation is planned on future projectswe recommend that theservices

    work be performed under a professionalcontract rather than be subjected to bid as part of the

    construction contract.

    The evaluation of instrument performance must be judged based onexperience during instrument installation, proof testing of thetieback, -and long term behavior. The performance ofinstrument

    specifictypes are discussed below with recommendations for

    future consideration.

    Load Cells: The load cells have performed well and theirreliability and durability have been excellent. The load cellshad spherical bearings at their ends to increase accuracy. Thesebearings made difficult alignment of the cell, as well asalignment of the loading jack and chair. used forload testing,

    The equipmentwhen mounted, cantilevered approximately four feet

    1-19

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    29/322

    beyond the retaining wall and therefore induced a moment at thespherical bearing location. Methods to stabilize the assemblyduring testing included very high alignment loads, supporting thejack with an overhead crane, and bolting the assembly to thesoldier pile with long threaded rods and nuts. A convenientmethod of assembly was never developed. Future considerations tohandle this problem could be: omission of the spherical bearings;or a "chair" similar to the one used for the jack which could bemodified to support the load cell also. Bracing from the soldierpile and/or the ground below could be used for additional support.

    Connection of the wire leads to the load cell was inconvenient.On future projects each of the load cells should have apermanently installed lead wire with environmental connectors.

    Rod Telltales: Installation of the rod telltales was generallystraight forward. For the short rod telltale on two of theintended secondary anchors it was impossible to insert the rodthrough the tube to the telltale anchor. The rod for one telltalecould be inserted only a short distance, presumably because grouthad entered the tube either at the telltale anchor connection, ata break in the tube, or at the top cap. In remaininginstallations this top cap was glued in place and cut off aftergrouting. The rod for the second unsuccessful telltale could beinserted almost to the telltale anchor. It was concluded that thetube had be come disconnected from the telltale anchor at theirthreaded connection. This connection could be improved in futureinstallations by providing a longer threaded section.

    Twisting of the tendon and attached rod and wire telltales wasrecognized as a potential problem prior to initiation of theinstrumen-tation program. This twist is believed to be a majorcause of the problems when interpreting aspects of the wire androd telltale data. After attachment of the telltales andplacement of the tendon in the anchor hole, there was no way tomaintain alignment of the instruments during grouting. As thegrout was pumped, the casing was twisted and pulled. Difficultyin inserting the rod into the rod telltale sleeve is believed tobe evidence of significant twist. However the actual degree ofrotation experienced by the telltales and tendon is unknown. Webelieve there is no way to alleviate this problem in future

    installations involving stranded tendons.As discussed previously slippage may have occurred at theconnection between the short rod telltale and the tendon. Thispossibility was recognized during the design phase, andsubstantial precautions were taken, including machining the baseof the anchor to match the tendon spiral, gluing the two surfacestogether, double-banding around the anchor and tendon, using ahigh tension banding system, and placing a soft material in frontof the telltale anchors. Improvements should be sought in futureinstallations, but space limitations may prevent a solution to theproblem. As a minimum, the telltale anchors could be notched,

    l-20

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    30/322

    where the steel bands hold it to the strand, to improve mechanicalinteraction between them. Three bands, instead of two, would makethe shear strength of the telltale anchor-strand connectiontighter. Additional soft material placed in front of the anchorcould help. alleviate the forces causing slippage. However,slippage may be impossible to prevent, particularly in the upper

    portion of the bonded zone where high loads in the tendon createthe greatest possibility for differential movement between thetendon and grout.

    The telltale load cell (short rod telltale) has, in three of fourcases, compared well with data from the load cell in providinglong-term load change data, Thus, the telltale load cell appearsto be a relatively reliable indicator of long term load change.In the one case where disparity exists it is not possible todetermine which is correct, although it would be generally assumedthat the load cell is more accurate. Where space within theanchor allows, two telltale load cells attached to differentstrands could provide redundancy in future installations.Wire Telltales: The wire telltales were used to measuredeformation and thus estimate load transfer within the bond zone.The wire telltales gave more problems than the otherinstrumentation both in terms of installation, reading, andperformance. In comparisons between rod and wire telltale data,good agreement was achieved in some cases while in other cases thewire telltales appears to have overestimated deflection. Severalof the other wire telltales appear to have yielded unreasonableinformation.

    Small collars attached to the top of the wire telltales allowedthe indicator to grip the telltale. The system was identical to aproven multi-point wire extensometer system which has performedwell on other projects. However, when the range of the indicatorwas exceeded, it was necessary to move these collars. Because thewires were relatively stiff, they crimped easily during placementof the collars and made this operation difficult to performproperly. It is possible that some of the collarsslipped during the

    may haveload test and long term readings. In future

    installations, an improved method of collar attachment should bedevised. Alternately,

    with the indicator,

    by use of spacers or shims in conjunction

    it might be possible to eliminate the need forcollar relocation.

    The Peter Smith Mark I indicator used to read the wire telltalesperformed poorly. An increased reading range would help alleviatethe problem discussed above.tensioning load be transmitted

    The indicator also required that thethrough the micrometer used to

    measure deflection. Thus, the tensioning load was significantlylimited by the strength of the micrometer threads. An instrumentwith a larger range ofreading accuracy,

    tensioning loads would provide greater

    wiresby allowing a check on the functioning of the

    to be performed by a comparison of readings made at low and

    1-21

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    31/322

    high tensions. This multi-tension check was part of the originalinstrumentation proposal. The inability to perform these multi-tension checks reduced the reliability of the wire telltale dataon this project. Such checks should be included as part of futurewire telltale instrumentation.

    As discussed previously, slippage of the wire and rod telltaleanchors may have also contributed to instrument error, and themeasures recommended earlier for rod telltale anchors should alsobe adopted for wire telltale anchors. Where space within theanchor allows, we recommend additional telltales close to the topof the bonded zone. These would provide additional referencepoints should the question arise of slippage of the first telltalein the bonded zone. In addition, higher tensile loads exist inthis zone than deeper in the anchor. This creates greater tendonelongations which are easier to detect amidst the normal datavariation.

    An assumption common to both the wire and rod telltales is thatdeformations measured in one strand are representative of theentire tendon. General long term agreement in the telltale loadcell (short rod telltale) with respect to the load cell tend tosupport the assumption. Instrumentation of duplicate strands,which would provide insight into this assumption, is typicallylimited because of space limitation.

    The success of the use of wire telltales on a stranded tendon toestimate load transfer within the bonded zone on this project isin question because of possible anchor slippage. In addition,certain inaccuracies exist in the remainder of the data. Theproblem of tendon twist during the pulling of casing may be thecause of these inaccuracies. In that case, the problem of twistmay be impossible to overcome. However, the implementation of theimprovements suggested within this section should improve the dataquality and could yield more successful results.

    Inclinometers: The inclinometers appear to have providedconsistent and reliable information. Although examination of thedata indicates that base fixity was not quite obtained, thedeviations were small and do not appear to have caused significanterror in deflection measurements.

    Survey: Survey appears to have provided the reliable dataanticipated from this proven instrumentation technique. Thesurvey points were installed, read and reported by the Georgia DOTcrews. Thus, credit for success should belong to them. As shouldbe expected, many points on the top of the wall were destroyedbefore significant data could be obtained.

    Lonq-Term Readinas: We recommend continued long-term readings ofload cells, short and long rod telltales, inclinometers, andsurvey points. Long-term reading of wire telltales #l and #5should also be considered to provide redundancy for the rod

    l-22

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    32/322

    telltales. If this is performed, readings for wire telltales #2,#3, and #4 could also be continued and might provide informationconcerning long-term redistribution of load transfer within the

    ,bonded zone.

    8. CONCLUSIONS

    The following are our primary conclusions concerning the permanenttieback retaining wall, Georgia DOT Project P.E. l-75-02 (41).

    Instrumentation Results

    Conclusions which may be drawn from the test data are summarizedin the following points:

    1. During the load test, the bottoms ofinstrumented anchors showed little or no movement.

    the primaryEstimation ofmodulus values for the anchor free length may have been affected

    by slippage of the short rod and wire #l telltale anchors.

    2. The question of telltale anchor slippage during the loadtest also affects the estimation of load transfer within thebonded zone. If slippage did not occur,transfer appears to have occurred in

    relatively high load

    bondedthe upper portion of the

    zone. If slippage did occur, estimated load transferappears more reasonable.

    3. Comparison of jack pressure gage loads with load cellresults indicates that jack gage overestimates load during loadingand underestimates load during unloading. Load as measured by thejack has an apparent accuracy of + 5 to 10 percent.

    4. Significant variation in load at the anchor head has notoccurred for seven of the ten instrumented anchors. Two of theother anchors have gained load (approximately 10 kips) while onehas lost load (approximately 15 kips).

    5. Most of the measured wall deflection occurred within oneto two months after excavation.

    that deflection has stabilized.

    Long-term measurements indicate

    The magnitude of both horizontaland vertical deflections appear to be related to wall height, andare well within the range of past experience.

    6. The anchors'approximately

    bonded zones were displaced a distance ofl/2 to 3/4 inch during outward deflection of the

    wall and anchor head. result of overallsoil deformation.

    This appears to be theSome load redistribution within the bonded zone

    occurred during this displacement.

    l-23

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    33/322

    Wall Performance

    Based on the results of the load testing and long-term load anddisplacement performance monitoring to date, it appears that thepermanent tieback wall is performing satisfactorily. Theassumptions and procedures used to design the wall and theconstruction methods used to accomplish the design also appearsatisfactory. Thus, it can be stated that the permanent tiebackretaining wall system is a suitable design and constructionalternative for future highway construction in similar soils inthe State of Georgia and in the southeastern United States.

    It is recognized that one of the major concerns of owner-agenciesis the anchor permanency against long-term corrosion and/or creep;or: "What is the design life of the anchor wall?" This concerncan be addressed by relating the past 25-40 years of experience inthe use of permanent tieback walls to the design, installation andtesting procedures used in this project.

    The design life of anchor permanency can be ensured throughestablishing the technical feasibility for a permanent tiebackwall for the specific site, an evaluation of the risk by theowners based on the feasibility study, the pre-qualification ofdesigners and contractors, the selection of tieback type includingstate-of-the-art corrosion protection, and the establishment ofload testing acceptance criteria and long-term monitoring.

    To estimate the design life of this particular permanent anchorwall, one must evaluate the short-term load holding capacity ofthe anchors,

    the long-term load holding behavior which is eightmonths to date, and consider the design and constructionprocedures. The test results presented in this report indicatethat the wall is behaving as designed. The design andconstruction was carried out by qualified professionals, and thecorrosion protection system selected and installed is assumed tobe providing the long-term corrosion performance for which it wasdesigned. Therefore, the life expectancy of this permanenttieback wall can be estimated to be comparable to a reinforcedconcrete structure designed and constructed with similarprofessional care.

    Safe Desian LoadsUltimate capacity of the instrumented anchors is shown in TableIV. Ultimate loads obtained on this project typically ranged fromfour to five kips/foot of bond length. Anchor loads for thesubject wall were reduced from these ultimate loads by use of asafety factor. The data for the instrumented anchors and overallwall system indicate that under similar subsurface andconstruction conditions, preliminary safe design loads on otherprojects could be derived from these ultimate loads and a similarsafety factor. Of course, actual loads must be confirmed withload testing.

    l-24

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    34/322

    INSTRUMENT TYPE

    Inclinometer

    Load Cell

    Wire Telltales

    TABLE I

    SUMMARY OF INSTRUMENTATION

    MANUFACTURER

    Slope Indicator, Co.

    Brewer EngineeringLaboratories, Inc.

    Geokon, Inc.

    PARAMETERMEASURED

    Horizontal deforma-tions of wall faceand retained soil

    Load in anchor

    Load distributionin anchor bond zone

    EQUIPMENT (MAJOR PARTS)

    . Inclinometer system withDigitilt sensor, LCDindicator, 2.75" o.d.

    plastic casing installedusing grout backfill.

    . 225-kip capacity with BLR120 Indicator Box, anddigital readout, bearing--washers and sphericalbearing plates. Gage andcalibrated pull bar tore-establish zero readingat any time.

    s/s wire type 16 G.A.1 l/4" oil-filled nylon

    tube around each wire. 5/8" grooved s/s anchor

    attached to the strandusing clamps and epoxy

    . 3/4" pvc pipe on the axisof the entire anchor withslots for grout entry andnylon tube entry.

    . Peter Smith Mark I exten-someter readout. %

    . Readings made using a ' 'dchair attached to the 3anchor head. l-lx

    P

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    35/322

    TARLE I (can't.)

    SUMMARY OF INSTRUMENTATION

    INSTRUMENT TYPE MANUFACTURER PARAMETER EQUIPMENT (MAJOR PARTS)MEASURED

    Rod Telltales Geokon, Inc. Load chanqe in .anchor

    Provides dataredundancy in bond .zone

    .

    .

    r

    +10 Survey

    .

    Flush-coupled l/4" s/srod within an oil-

    filled PVCpipe.Anchors same as wiretelltalel-7/8" s/s referenceplate required on theanchor head.s/s chair for in-situcalibrationmicrometer for readout

    Provided by Georgia Horizontal and . Electronic distanceDOT vertical defor- meter (EDM) for horizon-

    mation of wall zontal deflectionsface and top of . conventional levelingretained soil techniques.

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    36/322

    TABLE II

    SUMMARY OF ACCEPTANCE CRITERIACREEP TESTING

    INSTRUMENTED ANCHORS

    ANCHORCreep/Cycle LENGTH OF TEST

    (inches) (minutes)

    51 upper 0.00351 lower 0.02066 upper 0.00166 lower 0.00267 upper 0.00867 lower 0.01765 upper 0.02965 lower 0.00952 upper 0.01350 upper 0.008

    The creep per log cycle computed by:

    d2 - dlcreep/cycle =

    5”:5

    505

    10

    lo"55

    d - deflectionT- time

    1-A-3

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    37/322

    TABLE III

    APPARENT MODULUS OF UNBONDED TENDON LENGTH

    DETERMINED DURING LOAD TESTS

    Short Rod Telltale Data Wire Telltale #I DataE Loading E Unloading E Loading E Unloading

    PRIMARYANCHORS

    (Psi) (Psi) (psi> (Psi)

    51-lower 21.4~106 30.7~106 21.9x106 29.2x106

    51-upper 22.4~106 26.3~106 22.4~106 29.5x106

    66-lower 22.7~106 28.9x106 26.3~106 27.3~106

    66-upper 19.3x106 30.6~106 20.0~106 29.8x106

    SECONDARYANCHORS

    67-lower 23.9x106 25.7~106

    67-upper 24.0~106 23.9x106

    52-upper 24.2~106 25.2~106

    50-upper 19.3x106 36.2~106

    65-lower 22.4~106 32.8~106

    65upper 26.2~106 30.49106

    l-A-4

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    38/322

    TABLE IV

    SUMMARY OF INSTRUMENTED ANCHOR PERFORMANCE

    LOAD AFTER LOAD AFTER CREEPBOND ULTIMATE LOAD DESIGN SETTING EIGHT KIPS PER

    LENGTH ~XIPSPER LOAD WEDGES MONTHS LOGANCHOR (FEET) (KIPS) FOOT (KIPS) (KIPS) (KIPS) CYCLE

    51-u

    51-L

    66-U

    66-L

    50-u

    52-u

    65-U

    65-L

    67-U

    67-L

    32 189.9*

    35

    32

    35

    33

    33

    32

    35 147.2

    32

    35

    188.0

    131.9*

    155.0

    190.5

    201.7

    114.2*

    130.2*

    158.7

    5.9 132.6** 128.4 132.9 tt

    5.4 125.3 126.0 126.0 3.9

    4.1 91.8** 94.1 92.3 tt

    4.4 104.1 99.9 108.9 0.5

    5.8 129.7 147.6t 145.6 1.9

    6.1 138.8 154.6.t 152.4 3.4

    3.6 78.4** 83.0 79.3 tt

    4.2 98.0 94.7 94.1 0

    4.1 91.1** 94.2 79.2 0.7

    4.5 105.8 106.1 117.3 ttt

    NOTES:

    Grout pressure of approximately 70 psi used on all anchors

    * Approached acceptance criteria before reaching predeterminedultimate load; other anchors achieved predetermined loadwithout approaching criteria.

    ** New design load based on results of load test.

    t Lock-off Load (load after setting wedges not determined)

    tt bad variation judged too erratic for accurate creep de-termination.

    ttt Anchor gained load.

    l-A-5

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    39/322

    -N

    ATLANTACOCA COLA

    1

    BOTTLINGCOMPANY

    l-75 CONSTRU CTION -ILIMITS TIEBACK WALL

    PLAN ‘INSTRUMENTATIONSTATIONS

    CANTILEVER WALL PERMANENT TIEBACK WALL

    ELE”IN FT. TOP OF WALL 9

    960

    920-I L BOT TOM OF WALL(LAGGING & FACING)

    PROFILE

    FIGURE 1 -PLAN AND PROFILE OF PERPAAN ENT TIEBAC K WALL

    l-A-6

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    40/322

    8

    51

    -N

    LEGEND CURB LINE. PERMANENT TIEBACK ANCHOR

    . PRIMARY INSTRUMENTED ANCHOR (PA)

    ,$ SECONDARY INSTRUMENTED ANCHOR ,SA)

    7 a SLOPE INCLINO METER (SI)

    WILLIAMS STREET /

    SI I

    8

    7 I

    :SOLDIER PILE CURB LINE

    b-;

    SI ?I

    II II II

    4II -

    PLAN(TIMBER LAGGING NO T SHOWN)

    ::jj SOLDIER

    -L; PILE _/

    3 CONCRETEFACING

    ELEVATION NOT E: LOWER SECONDARY ANCHOR

    (TIMBER LAGGING NO T SHOWN)

    INSTRUM ENTATION (PILES 50

    & 52 DESTROYED)

    FIGURE 2 - PEFWANENT TIEBACK WALL INSTRUMENTATION

    l-A-7

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    41/322

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    42/322

    INCLINOMETERCASING

    (SI) -T--

    LONG RODTELLTALE

    WIRETELLTALE

    SOLDIER PILE

    >I(/ JyQ

    SHORT ROD /TELLTALE A

    I

    (RT) u ‘GROUT/LEGEND

    0 INSTRUMENT POSITION DESIGNATION L WIRE\TFI I l-AI F---. , .--(WT)

    NOTE:

    ANCHOR IS SHOWN IN FINAL LOCK-OFFCONDITION.

    FIGURE 4 - SCHEMATIC OF PRIMARY INSTRUMENTED TIEBAC K ANCHOR

    l-A-9

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    43/322

    WIRE TELLTALE

    ) )-PVC PIPE

    i?nn TFI I TAI FCORRUGATEDPLASTIC PIPE

    FlGUR: 5 - CROSS SECTION OF INSTRUMENTED TIEBACK ANCHOR

    1-A-10

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    44/322

    I,...“R--.

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    45/322

    50 MlNUTti0 MlNUTtiCREEP TEST--\REEP TEST--

    WIRE TELLTALE

    145.6 KIPS

    ACCEPTANCECRITERIA

    WIRE TELLTALE #5

    NOTE:

    AFTER SETTING WEDGESLOAD= 126.0 KIPS

    FIGURE 7;- LOAD DlSPLACElZIiENT CURVE LOAD TEST

    PILE 51. LOWER ANCHOR- -I_-FREE LENGTH (LOAD TES T) = 19.6 FT .

    BOND LENGTH = 34.6 FT .

    ------

    I -- -- - _ , -- -- . . .- -, -- -- -- ,

    I.6 I .n 2.0 2.2

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    46/322

    150

    14;

    123

    i 100Y

    :

    2 80

    50

    40

    20

    / 5 MINUTE/

    //WIRE TELLYLE #I\

    CREEP TEST

    SHORT ROD TELLTALE

    - LVI.V VT””/

    DIAL GAGE

    /’

    WIRE TELLTA LE #5

    ‘TANCE CRITERIA

    TELLTALE

    SEATING LOAD = 31.6 KIPS

    // PILE 66. UPPER ANCHOR

    FREE LENGTH (LOAD TEST ) = 22.6 FT

    BOND LENGTH = 31.7 FT.

    102.5 KIPS

    NOTE:

    AFTER SETTING WEDGES

    LOAD= 94.1 KIPS

    0 9.2 0.4 0.6 0.9 1 .o 1.2 1.4 I .6 1.6

    DEFLECTION, INCHES

    FIGURE 8 LOAD DISPLACEMENT CURVE - LOAD TEST

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    47/322

    50 MINUTECREEP TEST CREEP TEST

    120 SHORT ROD TELLTALE

    100

    In WIRE TELLTALE X5iij2 ACCEPTANCE

    Ii 00CRlTERlA -;y/ /s$fi Ly R&;LLT AL,

    ./

    60. /' -'/ NOTES:A F T E R S E T T I N G WEDGESLOAD=99.9 KIPS (a STRANDS

    ONLY

    UNLOADING AND RELOADING

    FOR WIRES #l AND #5ARENOT INCLUDED

    PILE 66, LOWER ANCHOR7. ,

    kFREE LENGTH (LOAD TES T) = 19.1 FT .

    SEATING LOAD = 10.0 KIPS BOND LENGTH =34.4 F T.

    0 I 1 --- , I I I 1 10 0.2 0.4 0. 6 0.6 I.0 1.2 I .b I .6 1.6 2.0

    DEFLECTION, INCHES

    KIPS

    FIGURE 9 LOAD DISPLACEMENT CURVE - LOAD TEST

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    48/322

    \

    \ara111

    a

    Li‘3\

    a.N

    W. .(u

    d.N

    N.N

    0. .N

    co. .

    lnwow

    ‘, IuZ

    *Z‘, 0

    iz

    iiJ

    NLL

    ‘, wcl

    0_

    m.0

    W_0

    *0

    N_

    0

    -0

    SdlN 6 avo71-A-15

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    49/322

    \ i\ 0

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    50/322

    N

    0

    c3d

    5

    W6

    Pd

    Nd

    0

    .O

    I I I I

    z iti0 0 0W P .O

    N m

    SdlM * avow1-A-17

    N

    W

    -I

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    51/322

    \

    a

    \h \ a

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    52/322

    r*

    a \W L

    rW

    a

    0 0P 0N 0ID q

    Sdl>l ' avoi1-A-19

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    53/322

    200

    180

    160

    140

    120

    PO

    60

    40

    20

    0

    10 MINUTECREEP TEST-

    1SHORT ROD TELLTALE

    /

    -SEATING LOAD = 5.0 KIPSNOTE : UNLOADING AND RELOADING ACCORDING TO

    DIAL GAGE ARE NOT INCLUDED FOR CLARI TY.,

    I I I I I I I I I I I I I I0 G.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4 2.6 2.8

    DEFLECTION , INCHES

    FIGURE 15-LOAD DISPLACEMENT CURVE - LOAD TEST

    PILE 67 , LOWER ANCHOR

    FREE LENGTH (LOAD TEST ) = 19.7

    BOND LENGTH=JS.O FT.

    /

    :RI

    NOTE:AFTER SE TTIN G WEDGES LOAD 106.1 KIPS

    A

    FT.

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    54/322

    LOG TIME (MINUTES)

    ; 40

    g 30

    w0 20f

    10

    1

    0

    00 o/-----o

    /- --

    000 O O

    I I I50

    I100

    1150 200 250

    LOAD , KIPS

    LEGEND:

    20 ANCHOR NUMBER

    (13oh) LOAD, KIPS

    FOR FURTHER INFORMATIONON THE FORM AND INTERPRE -TAT ION OF THE DATA PRE-

    SENTED IN THIS FIGURE,PLEASE REFER TO REPORTNO. FHWA RD-61/150,PAGES 91-95

    FIGURE lEj- CREEP CURVES FROM PERFORMANCE TES TS

    1-A-21

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    55/322

    19c

    160

    16C

    14c

    120

    60

    60.

    40,

    20.

    o-

    PILE 51 , UPPER ANCHOR

    WIRE 5 - I

    LONG ROD 4

    74---0.1 0 +0.05 +0.1RELATIVE DEFORM ATION, INCHES

    1 -ROD

    PILE 51, LC

    WIRE 1 -

    SHORT ROD\

    1 I I 1-0.2 -0.15 -0.1 -0.05

    IER ANCHOR

    \

    II-WIRE 5 -\ LONG ROD\

    I

    \

    LONG ROD -DIAL GAGE

    I

    I

    4

    I

    I 1 ,

    +0.05 +0.1 +0.15 *0.2

    RELATIVE DEFORM ATION. INCHES

    I

    -t

    -4

    -2

    190

    160

    160

    140

    120

    22IO0 _

    2

    s

    30

    $0

    0

    0

    IFIGURE 17- COMPARISON OF WIRE TELLTALE VERSUS ROD TELLTALE

    DURING LOAD TEST1-A-22

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    56/322

    163

    140

    120

    100

    60

    40

    20

    0

    PILE 66, UPPER ANCHOR

    1 -

    ROD

    I-0.1 -0.05 0 +0.05 +0.1

    RELATIVE DEFORM ATION, INCHES

    PILE 66, LOWER ANCHOR

    t\t1itI.

    tLONG ROD- .DIAL GAGE

    1

    RE 1 -

    RT ROD

    WIRE 5 -LONG ROD

    ----I--0.1 -0.05 0 +0.05 +0.1RELATIVE DEFORM ATION, INCHES

    L

    .I60

    ‘140

    ,120

    60

    40

    20

    0

    FIGURE IS-COMPARISON OF WIRE TEL LTAL E VERSUS ROD TELL TALE

    DURING LOAD TES T

    1-A-23

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    57/322

    190

    180 1

    -160

    L-WIRE 2-1

    /WIRE 3-l

    7

    L LONG ROD - SHORT ROD

    LOAD

    WIRE 5-f

    0I 1 I I I I

    0 0.11

    0.2 u.3 0.4 0.5 0.6 0.7

    RELATIVE DEFORMATION . INCHES

    FIGURE 19 - RELATIVE DEFORMATION IN BONDZONE - LOAD TEST

    l-A-24

    PILE 51 - UPPER ANCHORLOAD TEST

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    58/322

    180

    160

    140

    120

    8C

    60

    4

    /iI

    i\

    i

    t:L- WIRE 2-1

    i

    i

    i /’ k- WIRE 4-1

    LONG ROD -SHORT ROD-

    7

    i

    //

    I IIi

    I:

    4II

    :

    - 11.4 KIP SEATING LOAD

    WIRE 5-l

    P

    PILE 51 - LOWER ANCHORLOAD TEST

    0 0.1 0.2 0.3 0.4 0.5 0.6RELATIVE DEFORMATION , INCHES

    FIGURE 20 - RELATIVE DEFORMATION INBOND ZONE - LOAD TEST

    l-A-25

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    59/322

    ‘L LONG ROD - SHO RT ROD

    NOTE:

    WIRE COMBlNATlON 2-l MEASUR EMENTS

    GIVE NEGATIVE DEFLECTIONS.

    - NEGATIVE VALUES IN THISRANGE NOT SHOWN

    t 3t.6 KIP SEATING LOAD

    PILE 66 - UPPER ANCHORLOAD TEST

    4-T----.2 0.3 0.4 0.5RELATIVE DEFORMATION ,INCHES

    FIGURE 21 . RELATIVE DEFORMATION IN BOND ZONE - LOAD TEST

    1-A-26

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    60/322

    16C

    140

    120

    1 oc

    kr

    2

    Ii

    80

    6C

    I-

    t-

    I-

    3-

    0-l1

    Dc

    I I I I I\ 0.1 012 0.3 04 0.5 0.6

    RELATIVE DEFORMATION INCHES

    i WIRE 3-f I

    -WIRE 4-1

    FIGURE 22- RELATIVE DEFORMATION IN BOND ZONE - LOAD TEST

    1-A-27

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    61/322

    B O T T O M

    7.5 FT. ; I ,,,‘,“,“,‘,-/- 7.5 FT . _ 1 _OF ANCHOR

    7.5 FT.

    NOTE:

    LOAD S IN ADDITION TO SEATING LOAD. LOAD IN FREE

    LENGTH ASSUMED = 150 KIPS [ABOVE SEATING LOAD)

    TOTA L CALCULATED ELONGATIONOF BONDED ZONE=O .BO IN.

    TOTA L CALCULATED ELONGATIONOF BONDED ZONE = 0.60 IN.

    LEGEND

    @ -INSTRUMENT POSITIO N DESIGNATION (SEE FIGURE n)

    AL -CALCULATED ELONGAT ION OF SEGMEN T OF BONDEDZONE (INCHES)

    B O T T O MOF ANCHOR

    TOTA L CALCULATED ELONGATIONOF BONDED ZONE = 0.90 IN.

    TOT AL CALCULATED ELONGATIONTOTA L CALCULATED ELONGATIONOF BONDED ZONE = 0.90 IN.

    OF BONDED ZONE = 0.60 IN.

    A. HYPOT HETICA L LOAD TRANSFER DIAGRAMS WITH CALCULATEDTOT AL BONDED ZONE ELONGATION = 0.60 INCH

    6. HYPOT HETICA L LOAD TRANSFER DIAGRAMS WITH CALCULATEDTOT AL BONDED ZONE ELONGATION = 0.90 INCH

    FIGURE 23 - HYPOTH ETICAL LOAD TRANSFER DIAGRAMS AND CALCUL ATED TOTAL ELONGATION OF BONDED ZONE

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    62/322

    FREE 7.5 FT.BOTTOM OF

    _ 7.5 FT. ANCHORLENGTH

    ANCHOR 66-UPPER

    LEGEND:

    0 -.- LOAD CELi=79.4 KIPS

    ISO-

    1 oo-

    ::

    z

    li

    tiso-

    O(

    LOAD CELL= 109.4 KIPS

    LOAD CELL-131.9 KIPS

    ANCHOR 66-LOWER

    LEGEND:

    0 -.- LOAD CELL179.7 KIPS

    A------ LOAD CELL-1 19.9 KIPS

    a-..-- LOAD CELL=139.3 KIPS

    NOT E: POINT S REPRSENT CALCULATED AVERAGE LOAD WITHIN 7.5 FT . SEGMENTS

    BASED ON RELATIVE DEFLECTIONS AS MEASURED BY WIRE TELLTALESAND ADJUSTED FOR ASSUMED SLIPPAGE OF WIRE +l

    CURVES REPRESENT LOAD DISTRIBUTIO NS FOR WHICH CALCULATED BONDEDZONE ELONGAT ION IS EQUAL TO THE MEASURED ELONGATIO N ADJUSTEDFOR ASSUMED SLIPPAGE OF WIRE trl

    ‘DlsTRlBuTl0~ AT SEATING LOAD is ASSUMED

    FIGURE 24 - LOAD DISTRIBUTION IN BONDED ZONE (LOAD T EST ) ~SsuitiiNG SLIPPAGE

    OF WIRE * 1 AND SHORT ROD TELLTA LE ANCHORS

    1-A-23

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    63/322

    115-

    110-

    d00

    ‘i 105 -

    siOWJV

    yu2a0

    0 0-3J 100

    PILE 50

    1 SOtJACK

    LOAD TEST

    95-

    90 I I I 10 50 100 150 200

    LOAD CELL, KIPS

    LEGEND:

    -0 LOADING

    3UPPER

    -.A UNLOADING

    FIGURE 25~OWl ‘ARISON OF LOAD CELL AND HYDRAULIC JACK

    DURING LOAD TEST

    1-A-30

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    64/322

    115

    110

    105

    100

    95

    90

    PILE 51

    300tJACK

    LOAD TEST

    0 50 100 150 200

    LOAD CELL, KIPS

    LEGEND:

    -0 LOADING

    3UPPER

    -)4 UNLOADING

    4 L3ADINGLOWER

    -.4 UNLOADING

    FIGi;RE 26SO RPARISOIJ OF LOAD CELL AND HYDRAULIC JACK

    DURING LOAD TETT

    1-h-31

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    65/322

    -*-,-.y--

    .-’ PILE 521 SOtJACKLOAD TEST

    90 I I I0

    150 100 150 200

    LOAD CELL. KIPS

    LEGEND:

    ___O LOADING

    3

    UPPER--4 UNLOADING

    FIG’,rRE 27COQl ‘ARISON OF LOAD CELL AND HYDRAULIC JACK

    DURING LOAD TEST

    1-A-32

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    66/322

    11:

    11c

    105

    100

    95

    90

    PILE 65

    1 SOtJACK

    LOAD TEST

    I I I50 100

    I150 200

    LOAD CELL 8 KIPS

    LEGEND:

    0 LOADING

    -. 4 UNLOADING 3UPPER

    a LOADING

    -.A 3

    LOWER

    UNLOADING

    FIGURE 28COV’/IPARlSON OF LOAD CELL AND HYDRAULIC JACK

    DURING LOAD TEST

    1-A-33

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    67/322

    115

    110

    8

    j;

    ,“i 105

    OW

    ;::

    i;

    100

    95

    90

    PILE 66

    \ 300tJACK

    +

    LOAD TEST

    0 50 100 150

    LOAD CELL. KIPS

    200

    LEGEND:

    ,-O LOADING

    f

    UPPER--.d UNLOADING

    d LOADING

    3

    LOWER-.- UNLOADING

    FIGURE 29S:OMPA.RISON OF LOAD CELL AND HYDRACLIC JA3K

    CURING ‘-OAD TECT

    l-A-34

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    68/322

    105

    0 0

    PILE 67

    1 SOtJACK

    LOAD TEST

    LOAD CELL, KIPS

    LEGEND:

    4 LOADINGUPPER

    -.a UNLOADING

    -I LOADING LOWER

    FlGC RE 30COMDARISON OF LOAD CELL AND HYDRAULIC JACK

    DZRiNG LOAD TEST

    1-A-35

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    69/322

    PILE 51 , UPPER ANCHOR

    LOWERANCHOR

    STRESSED1

    LOAD CEL>. 4*.

    I I lllll//‘I I-----l

    100 300 1000DAYS

    \NOTE: AFTER SETTING WEDGES ,

    /i\

    LOAD= 128.4 KIPS5

    J

    \\L

    PILE 51 , LOWER ANCHOR

    SHORT RODHORT ROD TELLTALEELLTALE

    NOTE: AFTER SETTING WEDGES ,

    LOAD=1 26.1 KIPS

    FIGURE 31 . LONG TERM LOAD VARIATION

    l-A-36

  • 8/16/2019 Permanent Ground Anchors(Volume 2).pdf

    70/322

    INTERMEDIATEANCHOR

    STRESSED

    I LOWER

    +10

    1 1ANCHOR

    PILE 66 . UPPER ANCHOR STRESSED

    i-

    WIRE NO.1

    TIME , DAYS

    NOTE: AFTER SETTING WEDGES ,

    LOAD=94.1 KIPS

    PILE 66 , LOWER ANCHOR

    WIRE NO.1

    LOAD CELL

    SHORT