penspen subsea pipeline damage assessment and repair.ppt - subsea europe 2010.pdf · safety –...

21
1 Subsea Pipelines Anchor Damage Assessment and Repair A O i fM th d d Li it ti An Overview of Methods and Limitations With A Case Study From the BP CATS Pipeline Roland Palmer-Jones © Penspen Ltd 2010 [email protected] Penspen Integrity, UK SUBSEA EUROPE 2010 Paris Outline Challenges Safety – pressure reductions Assessment Stages Typical Damage Inspection Options/Limitations Assessment Methods/Limitations Repair Options © Penspen Ltd 2010 Case Study

Upload: vandieu

Post on 13-Apr-2018

219 views

Category:

Documents


3 download

TRANSCRIPT

1

Subsea PipelinesAnchor Damage Assessment and Repair

A O i f M th d d Li it tiAn Overview of Methods and Limitations With A Case Study From the BP CATS

Pipeline

Roland Palmer-Jones

© Penspen Ltd 2010

[email protected]

Penspen Integrity, UK

SUBSEA EUROPE 2010 Paris

Outline

Challenges Safety – pressure reductions

Assessment Stages

Typical Damage

Inspection Options/Limitations

Assessment Methods/Limitations

Repair Options

© Penspen Ltd 2010

Case Study

2

Pipeline Damage - Challenges

Ensure Safety

M i t i O ti Maintain Operation

Prevent Failure

Shutdown only if required

Select the Right Repair

Contain pressure

Support structure

Repair Quickly

Defect Identification, Measurement and Assessment

Emergency Repair System

© Penspen Ltd 2010

Repair Permanentlyg y p y

Safety!

Industry Practice - Reduce Pressure

Prevent Rupture1.2

h

Prevent time dependent failure

Will Pipe Collapse?

Bending

Ovalisation

Denting

External pressure

Can Pressure be Reduced?

0.2

0.4

0.6

0.8

1

Fai

lure

Str

ess/

Yie

ld S

tren

gth

leak

rupture

© Penspen Ltd 2010

Can Pressure be Reduced?

Hydrostatic head

Phase change

Even Basic Pressure Reduction Decision Requires Defect + Risk Assessment

0

0 1 2 3 4 5 6 7 8

Normalised Defect Length

3

Outline

Challenges

Safety – pressure reductions

A t StAssessment Stages Typical Damage

Inspection Options/Limitations

Assessment Methods/Limitations

Repair Options

© Penspen Ltd 2010

Case Study

Defect Assessment - Stages

Incident Reported

Preliminary assessment

ROV + Sonar Survey Secondary assessment

Detailed Diver/ROV Survey Main assessment

© Penspen Ltd 2010

4

Preliminary Assessment - Questions

Incident Reported

Shi i Ship reports snagging

ILI report indicates dent and gouge

Sonar/ROV survey indicates damage

Preliminary Assessment Questions

Should the pipeline be shutdown?

© Penspen Ltd 2010

Is a pressure reduction required?

Is it safe for a vessel to approach?

Will a repair be needed?

What type of repair is likely?

Preliminary Assessment - Data

Incident details

Location,

Ship speed,Ship speed,

Was anchor abandoned on Pipeline?

Did anchor chain break?

Leak?

Ship details

Tonnage,

Anchor size/weight,

Anchor chain weight/breaking strain.

Pipeline details

© Penspen Ltd 2010

Pipeline details

Diameter,

Wall thickness,

Material,

Coatings,

Depth of burial,

Operating pressure.

5

Preliminary Assessment - Approach

Calculate Damage Resistance

Dent Depth vs Impact Energy

3

2 De-burial vs Ship kinetic energy

Bending vs Ship kinetic energy

Calculate Available Energy for Damage

Anchor + chain weight and velocity

Concrete crushing

Local denting

Ed

2100 m p

OD

© Penspen Ltd 2010

Local denting

Ship mass and velocity

Pipeline de-burial

Global deformation/bending

Preliminary Assessment - Potential Conclusions

Significant damage not credible (Small ship + Large pipeline)pipeline)

No immediate pressure reduction

Proceed with ROV survey

Review repair readiness

Significant damage possible (Large ship + Large pipeline)

Reduce pressure

Mobilise emergency repair system (grouted sleeve)

© Penspen Ltd 2010

Mobilise emergency repair system (grouted sleeve)

Proceed with ROV

Significant damage likely (Large ship + Small pipeline)

Shutdown or significantly reduce pressure

Mobilise emergency repair (mechanical connectors)

Proceed with ROV

6

ROV + Sonar Survey

Initial survey to:

Confirm location

Provide general visual information

ROV

Video survey

De-burial

Displacement

Coating state

Evidence of denting

Evidence of gouging

Currents

© Penspen Ltd 2010

Cu e ts

Sediment/silt

Basic measurements

CP stab – identify bare metal

Sonar

Displacement

Seabed scars

Secondary Assessment- Questions

Should the pipeline be shutdown?shutdown?

Is a pressure reduction required?

Is it safe for divers?

Can the anchor be safely removed?

Can excavation / exposure be carried out?

© Penspen Ltd 2010

carried out?

Can the coating be removed?

Will a repair be needed?

What type of repair is likely?

7

Secondary Assessment

‘Global’ Stress analysis of snagging/displacement to

l t t diti

Tension

B di Bending

As-laid Pipeline

Displaced Pipeline

evaluate stress condition

Span assessment

Stability

Identify ‘likely’ local damage type:

Plain dent

Dent on weld

CompressionBending Bending

Direction of Anchor Impact & Drag

Axial defect (fixed width, 20mm), axial compression, internal pressure (55 bar) DNV

-2701.0mm Defect Depth2.0mm3.0mm

© Penspen Ltd 2010

Dent on weld

Dent plus gouge

Gouge only

Calculate critical damage sizes

Identifies measurements required

-260

-250

-240

-230

-220

-210

0 100 200 300 400 500 600 700 800 900 1000

Axial Defect Length 2c (mm)

'saf

e' a

llow

ab

le t

ota

l axi

al c

om

pre

ssi

on

(M

Pa

)

4.0mm5.0mm6.0mm7.0mm8.0mm

Diver Survey

Excavate

Remove coating

D t il d i l i ti Detailed visual inspection

Geometric inspection

Magnetic Particle Inspection

Ultrasonic inspection

© Penspen Ltd 2010

Ultrasonic inspection

8

Final Assessment- Questions

Should the pipeline be shutdown?

Is a pressure reduction required?

Will a repair be needed?

What type of repair?

© Penspen Ltd 2010

Final Assessment

Assess local damage

Burst pressure

Oil Pipeline Pressure history

800

1000

1200

1400

ure

(p

si)

Burst pressure

Fatigue life

Operational restrictions

Basis of assessment Industry guidance/experience

FEA

0

200

400

600

22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr

Time

Pre

ssu

© Penspen Ltd 2010

Include effects of displacement

Damage behaviour and failure mechanism Repair performance requirements

9

Outline

Challenges

Safety – pressure reductions

Assessment Stages Assessment Stages

Typical Damage

Inspection Options/Limitations

Assessment Methods/LimitationsR i O ti

© Penspen Ltd 2010

Repair Options

Case Study

Typical (Possible) Damage

Rupture

Gouge

Displacement

Plain Dent

Dent Plus Displacement

© Penspen Ltd 2010

Dent on Weld

Dent and Gouge

Kinked Dent

10

Inspection Options and Limitations

Sonar Survey

ROV

Vi l Visual

Position

CP

Diver Visual

Calliper

© Penspen Ltd 2010

Straight edge

MPI

UT

Laser scanning

Assessment Options and Limitations

Gouge – NG18

Displacement – FEA or Beam Theory (strain limits) dd

tdd

c

c

f

11

1

Theory (strain limits)

Plain Dent – Empirical limits, strain assessment, EPRG fatigue model

Dent Plus Displacement – No proven methods

Dent on Weld – EPRG fatigue model

Mt1

2

501000

10

1292.4

sA

U

KN

© Penspen Ltd 2010

Dent and Gouge – EPRG model

Kinked Dent – No Proven method

2

1

2

02

012

1 )ln(exp

22.10

2

8.11

5.1expcos

2

K

KC

R

D

t

RY

R

DY

Ad

E vf

11

Offshore Pipeline Repair Options

Grinding

Clamps / Sleeves

Section Replacement Connectors

Hyperbaric welding

Recovery to

© Penspen Ltd 2010

Recovery to surface

Outline

Challenges

Safety – pressure reductions

Assessment Stages Assessment Stages

Typical Damage

Inspection Options/Limitations

Assessment Methods/Limitations

Repair Options

© Penspen Ltd 2010

Case Study

12

Grind repair

Area to be removed

Pipe

Cracking

Hardened layer

© Penspen Ltd 2010

Clamps / Sleeves

© Penspen Ltd 2010

13

Section Replacement

© Penspen Ltd 2010

Outline

Challenges

Safety – pressure reductions

Assessment Stages Assessment Stages

Typical Damage

Inspection Options/Limitations

Assessment Methods/Limitations

Repair Options

© Penspen Ltd 2010

Case Study

14

Central Area Transmission System (CATS)

© Penspen Ltd 2010

Details of the Incident

Late evening on 25th June 2007 a large crude tanker which had been anchored to the north of the CATS Pipeline for a period of time awaiting entry to Teessport Harbour, began to drag its anchor in deteriorating weather

At approx. 2330 the vessel reported that it had “snagged” its anchor on a pipeline to the south east of its original position

After around 10 minutes the vessel was able to free itself from the pipeline and move off to the south

Harbour Authority reported incident to CATS Terminal staff

BP Emergency Response Plans instigated & investigation

© Penspen Ltd 2010

commenced

Incident has been fully investigated by Marine Accident Investigation Branch & the report has recently been published (Report No. 3/2008 at www.maib.gov.uk)

15

Anchor Damage – Case Study

25th June 2007 - A ship was in difficulty in bad weather.

O f it h hit th 36”

Anchor Weight – circa 14t

One of its anchors hit the 36” pipeline and lifted it from under the seabed

Harbour Authority reported

© Penspen Ltd 2010

Harbour Authority reported incident to CATS Terminal staff

BP Emergency Response Plans instigated & investigation commenced

Initial Assessment

No evidence of rupture

No evidence of leak

Potentially severe damage

Small pressure reduction imposed

Pressure controlled

© Penspen Ltd 2010

Anchor weight and velocity – approx. 15 mm dent (1,7%)

Gouging? Displacement? Bending?

16

ROV Survey

Initial reports showed concrete damage, bending,damage, bending, gouging, and denting

© Penspen Ltd 2010

Secondary Assessment

Apparently severe damage

Dent gouge calculations indicate failure pressure below design for credible combinations.

P d ti i d

© Penspen Ltd 2010

Pressure reduction required

Review repair options

17

Investigation of Repair options

BP Project Team established & dedicated to the repair.

Do nothing or dress defect, assess and leave

following repair options reviewed in parallel with inspection activities

© Penspen Ltd 2010

Wet weld, metal build up

Deploy existing BP clamp / identify alternatives across the globe

Replace section with subsea connectors

Replace section with hyperbaric welds

Lift pipe and re-lay section with lay barge and tie-in

Re-lay new section with lay barge and tie-in

Detailed Inspection / Work Program

1. Pipeline depressurisation (in controlled stages from 113 barg to 54 barg) to enable safe diver access

2. Diverless excavation of pipeline and further ROV inspection2. Diverless excavation of pipeline and further ROV inspection

3. Final excavation of pipe spool (approx. 20m)

4. Concrete & Coal Tar Coating removal (approx. 14m)

5. Detailed Diver Inspection- Close visual inspection

- Out of Straightness survey

- Ovality Survey

- Taut Wire

© Penspen Ltd 2010

- Magnetic Particle Inspection (welds & defect areas)

- Ultrasonic Inspection (welds & defect areas) – automated and manual

18

Inspection Results

• 1.5m vertical displacement

• 4.5m horizontal displacement

• Damage over a 4m length in middle• Damage over a 4m length in middle of spool

• 2 Dents within a larger deformed area

© Penspen Ltd 2010

2 Dents within a larger deformed area

• 31mm and 25mm max. depth (3.4%D)

• 2 Protrusions of max. 15mm

• Weld deformed

• No weld defects / cracking

• No gouging

Final Defect Assessment

Defects were assessed using the Pipeline Defect Assessment Manual (PDAM)

Limitations: No method for combined No method for combined

dent and external load. Limited test data for large

diameter offshore pipelines.

FEA of displacement. FEA of dented area EPRG dent fatigue Terminal Inlet Pressure (Previous 12 Months)

123

125

© Penspen Ltd 2010

105

107

109

111

113

115

117

119

121

Time

Pre

ssu

re (

bar

)

19

Results of Defect Assessment

Analysis Findings: No reduction in static strength of pipeline

Fatigue life of pipeline reduced by dents on weld

Repair Decision: Existing sleeve would not fit (too short and pipe bent)

Structural, cement grouted sleeve repair selected to provide reinforcement of dented area

© Penspen Ltd 2010

How long did it take?

Incident occurred - 25 June

Initial survey complete – 30 June

Pipeline shutdown – 1 July Pipeline shutdown 1 July

Pipe depressurised and safe to dive – 18 July

Detailed inspection complete – 28 July

Go ahead for sleeve fabrication – 29 July

Sleeve Fabrication / Fit-Up Trials complete - 17 August

Diving Support Vessel on location - 18 August

Pipeline recommissioning commenced - 24 August

© Penspen Ltd 2010

p g g

Delivery of on-spec gas - 1 Sept

Rock dump complete – 2 Oct

20

Cross-industry support to release vessels during peak summerperiod – both from operators and contractors

Fantastic support & dedication from key contractors with whomBP already had long term relationships Technip Acergy RBG

Critical Success Factors

BP already had long term relationships – Technip, Acergy, RBG,JP Kenny, Penspen/APA, Jee, Foundocean, Subsea 7 andothers

Rapid mobilization of dedicated project team from BP &contractors

Existing relations with BP global experts simplified assuranceprocesses

Clear accountabilities within Project Team – Pipeline Integrity,Subsea Activities Terminal Ops Sleeve Fabrication JV and

© Penspen Ltd 2010

Subsea Activities, Terminal Ops, Sleeve Fabrication, JV andReputation Management

Strong engagement with regulators from Day 1

HIGH QUALITY, PERMANENT PIPELINE REPAIR SAFELY IMPLEMENTED IN LESS THAN 3

MONTHS

Summary

There are stages to damage assessment

Uncertainties at each stage

Data changes

Need to use all available data

Specialist skills/experience needed

Contingency plans/repairs may not be appropriate

Proven methods for assessment may not be available

Caution is needed

© Penspen Ltd 2010

21

Repair Management

Pipeline operator

Vessel operator

Diving contractor

ROV operator ROV operator

NDT contractor

Defect specialists

Welding

Re-commissioning

Subsea designer

Verification agency/consultant

Equipment suppliers Pipe handling

© Penspen Ltd 2010

Pipe handling

Concrete removal

Pipe cutting

Clamp or connectors

Welding habitat

Isolation tools

De-watering pigs

Regulator

REPAIR: Caution.

Some wise words on repair*: ‘Do no harm!’

A bad repair can makeA bad repair can make matters worse.

Repairs need careful engineering, at least as much as a new construction.

Do not act in haste.

A repair is often not a good time to try something new.

© Penspen Ltd 2010

g

There is less experience with a new procedure, compared to tried and tested designs. Surprises may occur with uncertainty and incompletely planned engineering

*A C Palmer, R King, ‘Subsea Pipeline Engineering’, Penwell. 2004.