pcm test: preliminary results seminar... · 2017-01-18 · – main and hom couplers test results...

42
pCM test: Preliminary results N.Solyak (on behalf LCLS-II team)

Upload: others

Post on 24-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

pCM test: Preliminary results

N.Solyak (on behalf LCLS-II team)

Page 2: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

Outline

• pCM chronology• Minimum acceptance tests

– MP, dark current, FE and radiation processing– Cavity processing, gradient and heat load measurements– CM Unit Testing– Main and HOM Couplers test results

• Extended Tests in Progress• Summary

1/17/2017"LCLS-II pCM test" at PIP-II meeting, January 17, 20172

Page 3: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

3"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

LCLS‐II Cryomodule design

Based on XFEL design with many modifications to meet LCLS‐II reqs

Baseline design: • 35 – 1.3GHz CMs (+1)• 2 – 3.9 GHz CMs (+1)

Energy upgrade +4 1.3GHz CMs

2 pCM are completed and under tests,  2 ‐ assembly

Page 4: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

4

CM details

"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

Page 5: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

pCM Chronology

– pCM delivered to CMTF ‐ 20 July– Installed into Cave – 24 July– Warm conditioning (1‐7) – 25 August– Cool down and first cold operation  (Min Tests) – Sept.

• pCM started cavity testing at 1.9K briefly under cold compressor mode.

• pCM cavity testing was completed at 2.1 K under warm pumping mode (Kinney pump) in October 2016

– Cryo shutdown for upgrade – November (for 2K operation)– Cool down to 2K and start Extended tests ‐ end December

"LCLS-II pCM test" at PIP-II meeting, January 17, 20175

E. Harms

Page 6: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

6

Line A, B and G Configuration

"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

Page 7: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

7

Cryogenic: Operating experience

"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

The CMTF Cryogenic system has two methods to achieve 2K operation:• Cryoplant Cold and Warm Vacuum Compressor (2K Refrig. mode, 500W capacity).   

Advs: JT heat exchanger in plant; Disadv: Min. CC flow, Less forgiving, • Cryoplant in Liquefier Mode with Kinney Vacuum Pump

Advs: More forgiving/flexible, Better turndown; Disadv: No JT HX high T

pCM Cryogenic Operating History– 2K Plant: Long recovery from CC trips (learning curve); Single cavity tests at 1.93K– 4.5K Plant and Kinney Vacuum Pumping

• Could only achieve 2.1K due to pressure drop and high flows resulting from the lack of a JT HX• Single cavity tests, coupler tests were performed in this mode

– Shutdown (Nov,2016):• Addressed Kinney header ∆P, added LN2 shield cooling to DB, changed CC drives, changed one control

valve, added thermal intercept to CM JT valve, added flow meter to Kinney discharge• Current mode at 2K. Some issues still open

– Apparent thermoacoustic oscillation (TAO) in CM JT valve• Added thermal intercept, investigating valve stem wiper

– High flow rates due to high JT valve inlet temperature (no JT HX and TAO)• Addressing TAO, investigating JT HX possibilities

– Liquid level stability in CM was challenging Jay Theilacker

Page 8: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

1/17/2017"LCLS-II pCM test" at PIP-II meeting, January 17, 20178

Coupler and cavity diagnostics

Cavities 1, 4, 5 and 8 have additional diagnostics inside HV‐ 4 T‐sensors, cell 1&5‐ 2 magnetic fluxgates

Magnetic shielding• 9 T‐sensors outside HV• Fluxgates 1,2,5,7,8,

Page 9: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

Minimum Acceptance Criteria - Production

"LCLS-II pCM test" at PIP-II meeting, January 17, 20179

✔✔

✔✔✔

✔✔

Beamline vacuum ~5E‐10, unbaked spools

pCM + FeedCap + EndCap ~13 W Static 2K64 W 2K dynamic of 128 MV 

Also specs for: • Q0 average > 2.5e10• Main coupler (FPC) 

‐ QL tuning range: 1.e7‐6.e7 • HOM coupler: 1W leak at 16MV/m• Frequency tuner 

slow/fast tuning range: 450kHz/500Hz 

Page 10: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

MP in HOM: heating response on HOM-can & HOM-feedthru

1/17/2017"LCLS-II pCM test" at PIP-II meeting, January 17, 201710

HOM can

HOM feedthru

HOM overheating due to MP (pulse)

Cav#1 Cav#5

• Sign of MP in HOM –overheating HOM can

•MP in cavities #1 & #5 @15MV/m (dwn HOM)

•After processing no MP in cav#1. Gradient improved to  17.2 MV/m, (19.6 MV/m in pulse mode).

• In cav#5 gradient improved (MP still there) 

•HOM‐can sensors are more sensitive to MP than HOM‐feedthrough sensors

Page 11: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

MP in HOM of cavity#1 (zoom)

1/17/2017"LCLS-II pCM test" at PIP-II meeting, January 17, 201711

Gradient

RF power

HOM can Temp.

Radiation

MP starts at ~15MV/m 

HOM can T quickly goes up above threshold gradient

Processed in short  pulses (seconds) until T< 20K

After processing no MP up to max gradient

Radiation reduced after processing,Exist w/o MP

Before processing processing After

processing

Page 12: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

Field Emission and Dark Current / X-ray in cavity

12

X‐ray (mrem/hr)

RF power (W)

Dark CurrentPeak114nA

Peak20.5 nA

Peak34nA

• Cavity 2 & 3 tested,  but not plotted here.   No FE/ MP @16MV/m

•DC on cav#4 (pk 1&3) Processed away.

• X‐ray activity on cavities 5, 8; no DC

~16 MV/m

C7 C5 C6 C8 C1 C5

History plot

1/17/2017"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

Page 13: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

FE: Dark Current / X-ray on cav#4 before/after processing

1/17/2017"LCLS-II pCM test" at PIP-II meeting, January 17, 201713

FE processing

Cavity #4 processing

Dark current1nA/div

RF power

16MV/m

X‐ray

Pulse

 mod

e

Page 14: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

14

MP Processing (plot for CAV7)

"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

• CAV2 was limited at 16.8 MV/m due to MP (15.6 MV/m FE onset).RF pulsed processing improved the gradient to 19 MV/m in pulsed mode. Quench after 19 MV/m (as VTS). Ran 18.8 MV/m stably.

• CAV3: Processing has little effect (~2 hrs). Gradient stable at 17 MV/m.

• CAV4: Processing 30min , 40ms, 2Hz (radiation). Gradient >20 MV/m, parked to 19.2 MV/m CW, small FE at this gradient.

• CAV6: limited 16.3 MV/m due to MP (14.5 MV/mFE onset). RF pulsed processing improved the gradient to >17 MV/m (same onset).

• CAV7: quenched at 17.4 MV/m, after pulsed processing 40 ms 2Hz, cavity went to 20 MV/m without pulsed quench. Work at 19.4MV/m (below 50 mR/h)

Eacc

Eacc

Page 15: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

15

Cavity Limitations

Summary as of 2016‐10‐31  at 2.1K

Cavity Name

Eacc @<50mR/h [MV/m]

Max Gradient [MV/m] Gradient limitation

FE onset [MV/m] NOTE

1 TB9AES021 18.2 21.2 quench (cryo, admin limit) 14.6 Multipacting improved, <15min2 TB9AES019 18.8 19.0 quench 15.6 Multipacting improved, <15min

3 TB9AES026 17.2 17.3 Quench (Multipacting, cryo, no x‐ray) 17.3No improvement, ~2h, limited by cryogenics

4 TB9AES024 20.5 21.0 Quench (Multipacting, admin limit) 21.0 Multipacting improved, <30 min5 TB9AES028 14.2 14.9 Field Emission 13.96 TB9AES016 16.9 17.1 Quench (Multipacting, cryo) 14.5 Multipacting improved, <15 min7 TB9AES022 19.4 20.0 Quench (Multipacting, admin limit) 12.7 Multipacting improved, <15 min

8 TB9AES027 17.5 20.0 Quench (Multipacting, cryo) 20.0 Multipacting improved, <10 min,limited by vacuum interlock

TOTAL VOLTAGE 148.1 156.2 Average Eacc @FE onset  = 16.2

CAV3, CAV6 and CAV8 all exceeds specification. Additional RF processing at 2.0K may further improve cavity gradients.

"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

Page 16: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

16

MP issue. Summary and lessons learned

Multipacting Determination• Consistent gradient limit (almost all cavities)• No or very low radiation (except CAV5 FE)• Quench field can be conditioned• No electron signals in FPC• Two cavities experienced HOM can heating

- One processed away (CAV1), One still present (CAV5 with high FE)• VTS experience was similarPossible Causes of MP in pCM• Non baked beam line components that release H2• Long period (5-6 month) of cavity filled with N2• Coupler outgassing after exposed to air brieflyMultipacting Mitigation• RF pulse conditioning (Successful in FNAL pCM)• Warm up and pump longer time • No coupler conditioning

"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

Page 17: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

17

Gradient and Q0 after MP Processing – in progress

*Usable Gradient: demonstrated to stably run CW, FE < 50 mR/h, no dark current

**Fast cooldown from 45K, >40 g/sec, extrapolated from 2.11K

***Also limited by administrative limit ~20MV/m

"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

Genfa/Elvin

Page 18: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

18"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

JLAB result

Page 19: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

19

Field Emission

0.1

1

10

100

1000

0 5 10 15 20 25

Rad [m

R/h]

Eacc [MV/m]

CAV1 Rad#2

CAV2 Rad#N

CAV3 No Rad

CAV4 No Rad

CAV5 Rad#6

CAV6 Rad#6

CAV7 Rad#6

CAV8 No Rad

Average Eacc@FE‐onset >16 MV/m

"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

Arrays of rad. detectors along the CM and ends.

Page 20: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

20

Cryomodule Unit Testing (in progress)

All cavities powered to nominal gradient (#5 @12MV/m)All 3 magnet coils powered to 10A‐nominalRan continuously for ~45minLow radiation < 34 mR/h (not phase synchronized)No detectable dark current

Vacc = 128 MV (spec)

"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

(10A spec)

Endurance test (10hrs) expected later this week

Page 21: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

21

Unit heat load test at 16MV/m @2K (preliminary)

"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

HeaterAll cavities @16MV/m, except cav5 ‐ 12 MV/m (Vacc = 128MV)

Heat calibration at 50WΔM = 5 [g/s];

Dynamic heat load ~70 W    (~9W/cav)  <Q0> ~ 3.e10

Next steps– long unit test (>10hrs)

Page 22: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

22

Heat Load Measurement - Static

Measured at 4K; Total ~ 13 W.( pCM + FeedCap + EndCap)Will be repeated at 2K. Courtesy of R. Wang

"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

Mass flow

He Liquid level

JT‐valve

Page 23: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

23"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

Spec < 5mG

Page 24: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

24

Fast Cool Down

"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

>40 g/s 32 g/s

Cavitydelta T(K)

delta T(K)

CAV1 3.8 3CAV4 5.6 2CAV5 8.3 5CAV8 4.7 2.5

Fast cool down in a cryomodule demonstrated

pCM Test Review January 11, 2017

Slow cooldown to be tested

Page 25: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

25

HOM and FP performance at FNAL pCM

AUTHOR - CM PRR Sep.13-14 2016

Cavity HOM1 Qext

HOM2 Qext

Field Probe Qext

HOM1 Power @16MV/m (W)

HOM2 Power @16MV/m (W)

TB9AES021 1.6e13 5.0e13 2.04e12 0.017 0.005TB9AES019 3.8e13 1.1e12 8.26e11 0.007 0.248TB9AES026 3.0e12 6.5e12 7.48e11 0.091 0.042TB9AES024 4.5e13 2.7e12 7.40e11 0.006 0.101TB9AES028 5.0e11 2.4e12 4.61e11 0.545 0.114TB9AES016 8.1e11 2.6e12 1.07e12 0.336 0.105TB9AES022 1.8e13 1.3e12 5.48e11 0.015 0.210TB9AES027 6.8e11 1.4e12 1.60e12 0.401 0.195

Specification: HOM Qext > 2.7e11 and 1 W maximumAll have < 1W @ 16MV/m At 20 MV/m, P_HOM ~ 1.56 W specification. 

Tuner side Coupler side

Page 26: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

HOM performance: Effect of RF losses in HOM cable

1/18/2017Presenter | Presentation Title26

•HOM power heat cable  heating of HOM antenna & FT  antenna quench•Expected HOM power from 0.3mA beam < 5W, system designed for 10 W.•Cav#8 HOM1 cable (coupler side) powered at 2GHz up to 5W, full reflection Ptot=10W

HOM FT

HOM1 can

Beam tube

Gradient 16MV/m

Test Summary•No antenna/FT overheating

•FT static T=5.3K (<50mW from cable)

•RF power in cable 5.1W; ΔTFT< 0.9K. ‐ Same ΔTFT for 16MV/m

•Temp of HOM can & beampipe is not sensitive to cable heating; ΔT<0.04K

•At 16MV/m: ΔTHOMcan~0.3K; ΔTbeampipe~ 0.4K (FPC power & Eacc)

Page 27: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

Main coupler tests in pCM

1/18/2017Presenter | Presentation Title27

• Room temp. power processing (couplers #1 thru #7): 2.5 to 4 kW• Coupler #8 was processed at 4kW with cavity OFF‐resonance (2.1K)  • All couplers are tested at cold, P= 3.5 kW & 3.2 kW (~12‐20 hrs)

‐ QL =1.e7 (tuned to low Qext for low cavity gradient )‐ Cavity gradient 10‐12 MV/m‐ All couplers in pCM are TTF3 modified (different from production)

• Coupler #4 was retested at 2K (13hrs). From other couplers data are taken from cavity Q0 measurement runs (0.9 kW and 1.6kW)

Page 28: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

1/17/2017"LCLS-II pCM test" at PIP-II meeting, January 17, 201728

Page 29: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

1/17/2017"LCLS-II pCM test" at PIP-II meeting, January 17, 201729

Interlock=200K Interlock=250K

Page 30: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

Extended test of the main coupler #4 (2K)

1/18/2017Presenter | Presentation Title30

• Power 3.2kW• Duration ~13hrs

• TCT100 = 208 K

• Consistent with 2.1K result

RF power =3.2kW

Gradient=11.510 MV/m

TCT100

Page 31: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

Summary of coupler heating 

• Different thermal intercept configuration in HTS

Coupler#4

50K 5K

Page 32: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

1/17/2017"LCLS-II pCM test" at PIP-II meeting, January 17, 201732

pCM

pCM

pCM

No air cooling in pCM

Page 33: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

HOM coupler: static and dynamic heating

1/18/2017Presenter | Presentation Title33

Conclusion from pCMmeasurements and simulation:

• Static heat load to 2K < 0.15 W‐ FPC  ~ 50mW‐ HOM+FP cables < 100mW

• Dynamic heatload (2K) < 1.2 W‐ bellow < 150mW @16MV/m‐ FPC @3.5kW < 1W

HOM‐can HOM‐can

HOM‐feedthruHOM‐feedthru

Acnetname Location cavity Note

#1 #2 #3 #4 #5 #6 #7 #8CT116 CavBeamTube (coupler) 2.51 2.38 2.29 2.38 2.63 2.32 2.38 2.81CT121 HOMcan(coupler) 2.41 2.34 2.26 2.31 2.30 2.25 2.31 2.87CT120 HOMfeedthru (coupler) 6.43 5.35 5.02 5.29 4.97 5.28 5.90 5.30 Heatedby2.5mcable

CT117 CavBeamTube (tuner) 5.01 5.47 2.85 2.84 10.73 4.64 2.71 2.35CT119 HOMcan (tuner) 2.68 2.24 2.31 2.24 2.83 2.38 2.20 2.22CT118 HOMfeedthru (Tuner) 4.30 4.59 4.43 4.05 3.96 4.04 4.26 4.35 Heatedby3mcable

Static temperatures (no RF power)

Page 34: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

FPC&HOM Couplers 2K Heat Load (CTS/COMSOL analysis of pCM)

34 1/18/2017Andrei Lunin | LCLS-II CM01 Cavity Thermal Analysis

T‐map (QFPC = 1.2 W)

Temperature Profile along the 5K Tube

QFPC = 1.2 W

QFPC = 0.8 W

QFPC = 0.4 W

QFPC = 0.2 W

QFPC = 0.05 W

QFPC = 0.1 W

Static heat load

Dynamic heat load

P=55 mW@10MV/m

A.LuninTotal 2K  Heat Loads  from FPC & HOM Couplers in the LCLS‐II pCM(based on T‐meas: FPC/HOM/BP)

Page 35: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

35

Summary and Lessons Learned

Procurement CM Final Review, May 12-14, 2015

• Coupler warm conditioning may causes cavity surface contamination (hydrogen) MP

• Coupler has acceptable 2K heat load (<1W @ 3.5kW), even at relatively high temperature of the 50K/5K intercepts (~200K/20K). Spec 150K @50K

• small Q0 degradation due to FPC overheating (very preliminary, to be tested in pCM extended tests).

• FPC thermal intercept design is improved in production CMs, incl. JLAB pCM. (next slide)

• Antenna heating changes QL ~7 % (16MV/m) at ~10 hrs timescale

Page 36: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

Thermal intercept improvements in production CM (vs. pCM)

1/18/2017Presenter | Presentation Title36

• Use XFEL FPC design  (vs.TTF3 in pCM). Better AL can ‐flange thermal contact

• Thermal strap is connected close to 50K pipe (vs. 50K shield‐see thermal analysis) Better thermal contact between braid and 

copper extension (flat surfaces) JLAB pCM already has this feature

pCM: Thermal analysis – R.Fischer/ANL

zoom

5K th

ermal

Intercep

t50K thermal

intercep

t

pCM

Production CM

120K110K

55K150K

Page 37: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

Other systems

– Magnet consists of conduction-cooled Quadrupole and Horizontal & Vertical correctors

• All coils able to achieve 20 A without quenching• Deguassing ramps demonstrated

"LCLS-II pCM test" at PIP-II meeting, January 17, 201737

– CMTS1 commissioning in parallel with first tests– Other measurements/testing

• Tuners• Low Level RF • Thermometry• Interlocks

Page 38: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

FNAL pCM Vibration, microphonics (microphonics team)

1/17/2017"LCLS-II pCM test" at PIP-II meeting, January 17, 201738

• RMS vibration levels are up to 100 Hz or more (spec 10Hz peak)

• significant variation in time, amplitude, frequency and space.

• Some frequency lines correlate well with output massflow. Cryogenic noise is most likely candidate.

JLAB data is coming. Changes in design is under discussion (PRR; Test results workshop)

Page 39: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

JLAB first microphonics measurements (T.Powers)

Peak to peak value is 96 Hz, rms value is 10.4 Hz‐rms

Preliminary result: CAV3 has 70 Hz pp and CAV4 has 20 Hz pp"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

39

Page 40: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

Summary

– pCM testing at Fermilab has advanced from minimum acceptance to extended testing• Cryomodule exceeds total voltage specification• Cryomodule exceeds heatload specification• Magnet specs are demonstrated• Radiation acceptable, no dark current measurement until

microphonics is suppressed to below 10Hz.– Great progress in ability to test CM’s at CMTS1

• more to do• likely take 2 more test cycles to reach stride

– Schedule not out of line with original estimates – Staffing, test tools require additional thought and discussion– Once both pCM’s (FNAL and JLAB) are tested it would be

beneficial to regroup and compare both results and processes

40"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

Page 41: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

41"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

• Thanks all LCLS-II team for excellent job and good results.

• Many slides are borrowed from FNAL team presentation at LCLS-II pCMtest result workshop, (JLAB, January 11-13, 2017. Thank you) and Cryomodule PRR.

Page 42: pCM test: Preliminary results seminar... · 2017-01-18 · – Main and HOM Couplers test results ... •X‐ray activity on ... • Warm up and pump longer time • No coupler conditioning

42"LCLS-II pCM test" at PIP-II meeting, January 17, 2017

Thank you for your attention