    STATEMENT SHOWING ACHIEVMENTS OF TELECOM UNIT OF MURI FORTHE MONTH OF OCTOBER 2010.

    1. At MURI to RMT UTS Channel 64kbps shifted from Ericssion MUX toWebfil MUX & also 64kbps modem shifted from M/W/Muri to TR/Muri

    during this month.

    2. At central panel 02 Nos. of new Railway Telephone connection provided(87452 & 87304) on 05.10.10.

    3. 6qd cable laid & back filling completed between JAA-THO (1Km) forpatching work on dated 12.10.10.

    4. 6qd cable laid & back filling completed between THO-MURI(1Km) forpatching work on dated 13.10.10.

    5. PA system installed at the following station:-

    a. BLNG on dated 20.10.10.b. HRBR on dated 21.10.10.c. MAEL on dated 22.10.10.d. JHMR on dated 23.10.10.e. TRAN on dated 24.10.10.f. HSNL on dated 25.10.10.

    g. JAA on dated 25.10.10 (JAA PA. System again newly installed dueto very poor wiring existed there, existing horns were not properlymatched and the repaired amplifier was not working properly).

    6. Emergency sockets repairing at the following kms :-

    a. GRE-HRBR = 02nos at km.no.381/23&376/31 on dated 22.10.10.

    b. JAA-KSX =01no at km.no.374/15 on dated 20.10.10.

    c. JHMR-LTMD =01no at km.no.313/4 on dated 20.10.10.d. SSIA-TRAN =01no at km.no.339/14 on dated 21.10.10.e. GDBR-CNI =03no at km.no.287/14,289/7&287/7 on dated

    25.10.10.

    Copy to Sr. DSTE/RNC & ADSTE/MURI information please.

    SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    2/18

    STATEMENT SHOWING THE PERFORMANCE OF AUTO ANNOUNCEMENTFOR THE MONTH OF OCTOBER 2010.

    SL.N

    O.

    Name of the

    circuit

    IN RIG

    HT

    REMARKS

    DATE TIME

    DATE TIME

    01 Autoannouncement

    No failurereported.

    Copy to Sr. DSTE/RNC & ADSTE/MURI information please.

    SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    3/18

    STATEMENT SHOWING THE PERFORMANCE OF BLOCK CIRCUIT FOR THEMONTH OF OCTOBER 2010.

    SL.No.

    Name ofthe circuit

    IN RIGHT REMARKS

    DATE TIME

    DATE TIME

    01 MURI-BLNG 27.09.10

    00.00

    27.09.10

    11.20

    Due to 60Mtrs switchboard cable cut &damaged at km.no.360/7-9.

    02 THIO-JAA 29.09.10

    17.51

    30.09.10

    09.25

    Due to 4qd cable cut &damaged at km. no.363/8.

    03 MURI-BLNG 12.10.10

    22.15

    19.10.10

    00.50

    160mtrs switch boardcable cut.

    04 RMT-BRKA 15.10.10

    07.00

    15.10.10

    14.45

    Due to cable cut.

    Copy to Sr. DSTE/RNC & ADSTE/MURI information please.

    SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    4/18

    STATEMENT SHOWING THE PERFORMANCE OF FOIS (TMS, RMS, CMS)FOR THE MONTH OF OCTOBER 2010.

    SL.No.

    Name of thecircuit

    IN RIGHT REMARKSDATE TIM

    E

    DATE TIM

    E01 MURI/LOCO

    CMS02.10.10

    02.15

    03.10.10

    12.00

    Modem shifted fromMURI/VHF to MURI/TR.

    02 MURI/LOCOCMS

    10.10.10

    16.20

    10.10.10

    17.15

    Modem reset.

    Copy to Sr. DSTE/RNC & ADSTE/MURI for information please.

    SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    5/18

    STATEMENT SHOWING THE PERFORMANCE OF OFC MUX FOR THEMONTH OF OCTOBER 2010.

    SL.No.

    Name of thestation

    IN RIGHT REMARKS

    DATE TIME

    DATE TIME

    01 GRE MUX 08.10.10

    13.38

    08.10.10

    18.40

    110Mtrs OFCCable joint atkm. no. 384/7-8

    02 JAA MUX 25.10.10

    08.00

    25.10.10

    08.15

    Webfil muxreset.

    Copy to Sr. DSTE/RNC & ADSTE/MURI for information please.

    SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    6/18

    STATEMENT SHOWING THE PERFPORMANCE OF 25W VHFCOMMUNICATION FOR THE MONTH OF OCTOBER 2010.

    SL.NO.

    Name of thestation

    IN

    RIGHT REMARKS

    DAT

    E

    TIM

    E

    DAT

    E

    TIME

    01. 25 Watt VHFSET

    No failure during thismonth.

    Copy to Sr. DSTE/RNC & ADSTE/MURI information please.

    SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    7/18

    STATEMENT SHOWING THE PERFORMANCE OF GATE PHONES FOR THEMONTH OF OCTOBER 2010.

    SL.NO.

    Name of the Gate& km. no.

    IN RIGHT

    REMARKS

    DATE TIME

    DATE TIME

    01 Kushi gate atkm.no.3443/6between ILU-TRAN

    No failure reported.

    02 Pacharu gate at km.no. 365/11 betweenBLNG-SND

    No failure reported.

    03 Shukla gate at km.no. 369/8 betweenBLNG-HRBR

    No failure reported.

    04 Noadih gate at km.no. 370/15 betweenBLNG-HRBR

    No failure reported.

    05 JHMR-GDBR Gate atKm.No.301/7

    No failure reported.

    06 BRKP-GRE Gate atKm.No.390/15

    No failure reported.

    07 JAA-KSX Gate atkm.no.368/3

    No failure reported.

    Copy to Sr. DSTE/RNC & ADSTE/MURI information please. SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    8/18

    STATEMENT SHOWING THE PERFORMANCE OF P.A.SYSTEM FOR THEMONTH OF OCTOBER 2010

    SL.NO.

    Name of thecircuit

    IN RIGHT REMARKS.DATE TIM

    EDATE TIM

    E

    01 THO-PASYSTEM

    No failurereport.

    02 JAA-PA SYSTEM 17.10.1020.10.1024.10.10

    13.0007.0009.00

    19.10.1023.10.1025.10.10

    18.4511.3018.20

    AmplifierDefective.Amplifierdefective.Amplifierdefective.

    03 MURI-DY.SS PASYSTEM

    AmplifierDefective.

    04 GRE-PA SYSTEM 22.09.10

    13.10

    02.10.10

    13.00

    AmplifierDefective.

    05 BRKP-PASYSTEM

    No failurereport.

    06 RMT-PASYSTEM

    No failurereport.

    07 SSIA-PASYSTEM

    No failurereport.

    08 TUL-PA SYSTEM No failurereport.

    09 LTMD-PASYSTEM

    27.09.10

    05.30

    28.09.10

    10.30

    Line wire break.

    10 GDBR-PA

    SYSTEM

    No failure

    report.

    Copy to Sr. DSTE/RNC & ADSTE/MURI for information please.

    SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    9/18

    STATEMENT SHOWING THE PERFORMANCE OF CONTROL PHONES FORTHE MONTH OF OCTOBER 2010.

    SL.NO

    Name of thecircuit

    IN RIGHT Remarks.

    DATE TIM

    E

    DATE TIME

    01 TPC.BRKA/TSS 13.10.06

    22.00

    0+5+0 cabledefective.

    02 TPC/TC.RWP 13.11.07

    12.00

    4 QD cable faulty.

    03 KSX CNL atMURI/N/O/Cabin

    26.09.10

    08.00

    26.09.10

    21.30 DTMF cardchanged.

    04 KSX CNL at KSX 27.09.10

    11.00

    07.09.10

    12.00 Telephonechanged.

    04 BRKA CNL at BRKA 20.09.10

    16.15

    28.09.10

    17.30 Buzzer changed.

    05 KSX CNL at KSX 28.09.1

    0

    14.2

    0

    28.09.1

    0

    16.30 DTMF card TX

    wire break.06 RC at TRAN/SSP 28.09.1

    017.00

    29.09.10

    10.10 RC equipmentfaulty.

    07 MURI/TSS/RC 28.09.10

    17.30

    28.09.10

    19.30 Cable Pairchanged.

    08 RC at TRAN/SSP 24.09.10

    16.30

    01.10.10

    12.00 RC equipmentfaulty.

    09 KSX CNL atMURI/N/O/Cabin

    01.10.10

    06.40

    01.10.10

    15.30 DTMF cardchanged.

    10 KSX CNL at KSX 01.10.10

    20.50

    01.10.10

    22.25 TX gainadjustment.

    11 RC at TRAN/SSP 23.09.1

    0

    11.4

    0

    02.10.1

    0

    13.00 Cable Pair

    changed.12 KSX CNL at KSX 02.10.1

    017.00

    03.10.10

    01.00 Telephone & cardchanged.

    13 KSX CNL at THO 03.10.10

    06.30

    03.10.10

    01.00 Card changed.

    14 RC at BRKP/TSS 03.10.10

    17.30

    03.10.10

    23.45 Automaticallyright.

    15 TPC CNL at BRKA 19.09.10

    12.05

    04.10.10

    23.00 Cable Pairchanged.

    16 BRKA CNL at ILU 04.10.10

    16.20

    05.10.10

    21.25 DTMF Card wirebreak.

    17 BRKA CNL atMURI/LOCO

    01.10.10

    14.00

    07.10.10

    15.30 Charger changed.

    18 TPC CNL atMURI/TSS

    18.09.10

    10.00

    08.10.10

    09.30 Cable defective.

    19 KSX CNL atMURI/ENQ

    29.09.10

    11.30

    08.10.10

    17.00 Card changed.

    20 TPC CNL atMURI/TSS

    09.10.10

    11.35

    39.10.10

    13.00 Wire loose.

    21 RC at MURI/TSS 09.10.1 15.0 09.10.1 18.00 RC equipment

  • 7/31/2019 Pcdo Fo Achivments

    10/18

    0 0 0 faulty.22 BRKA CNL at BRKA 10.10.1

    009.32

    10.10.10

    15.50 MUX Card reset.

    23 BRKA CNL atMURI/LOCO

    11.10.10

    22.00

    12.10.10

    10.30 Fuse burnt.

    24 RC at TUL/TSS 15.10.10

    18.00

    16.10.10

    10.15 RC equipmentfaulty.

    25 BRKA CNL at GDBR 18.10.10

    17.00

    19.10.10

    12.00 Card changed.

    26 KSX CNL at KSX 22.10.10

    12.30

    22.10.10

    17.00 TX Gain adjust.

    Copy to Sr. DSTE/RNC & ADSTE/MURI for information please.

    SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    11/18

    STATEMENT SHOWING THE PERFORMANCE OF RADIO PATCH AND E1PATCHING FOR THE MONTH OF OCTOBER 2010.

    Sl.

    No.

    Name of the circuit Date of

    testing

    Reading

    Recorded

    Remarks/Tested by

    DATE TME Testingpoint

    Hatia

    01 Hatia- RMT BSNL E1patch

    21.10.10

    08.00 Tested by Hatia/CNLTestroom-H.B.Singhand Muri Testroom-Nitu Devi found ok.

    02 Hatia- KSX MW Radiopatch

    13.10.10

    10.10 Tested by Hatia/CNLTestroom-H.B.Singhand Muri Testroom-Nitu Devi found ok.

    -do- 20.10.10

    13.15 Tested by Hatia/CNLTestroom-H.B.Singhand Muri Testroom-Nitu Devi found ok.

    03 Hatia- JAA E1Protection

    21.10.10

    08.15 Tested by Hatia/CNLTestroom-H.B.Singhand Muri Testroom-Nitu Devi found ok.

    04 Hatia- CNI E1Protection

    21.10.10

    08.30 Tested by Hatia/CNLTestroom-H.B.Singhand Muri Testroom-Nitu Devi found ok.

    05 Hatia- BRKA E1patch

    21.10.10

    09.00 Tested by Hatia/CNLTestroom-H.B.Singhand Muri Testroom-Nitu Devi found ok.

    Copy to Sr. DSTE/RNC & ADSTE/MURI information please.SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    12/18

    STATEMENT SHOWING THE PERFORMANCE OF AUTO TELEPHONES FORTHE MONTH OF OCTOBER 2010.

    SL.NO

    TELENOS.

    IN RIGHT REMARKS

    DATE TIME DATE TIME

    01 87373 24.09.

    10

    11.2

    0

    26.09.1

    0

    09.00 O/H break.

    02 87368 24.09.10

    16.00

    26.09.10

    09.30 Cable pair changed.

    03 87446 26.09.10

    08.20

    28.09.10

    09.00 Wire break.

    04 87363 28.09.10

    08.00

    28.09.10

    09.10 Cable pair changed.

    05 87406 29.09.10

    07.00

    04.10.10

    21.0 MUX Problem.

    06 87427 29.09.10

    23.15

    30.09.10

    11.00 Noise.

    07 87430 24.09.10

    10.00

    01.10.10

    05.00 Hand cord changed.

    08 87315 29.09.10

    11.40

    02.10.10

    08.00 O/H break.

    10 87352 02.10.10

    06.30

    02.10.10

    08.45 Cable pair changed

    11 87373 28.09.10

    16.00

    04.10.10

    13.00 Wire break.

    12 87465 02.10.10

    09.30

    04.10.10

    10.20 Line cord changed.

    13 87374 03.10.10

    12.00

    04.10.10

    10.20 O/H break.

    14 87404 04.10.10

    13.30

    04.10.10

    17.25 Cable pair changed

    15 87424 28.10.

    10

    11.0

    0

    05.10.1

    0

    11.00 Cable pair changed

    16 87381 04.10.10

    07.30

    05.10.10

    10.00 O/H break.

    17 87333 05.10.10

    06.20

    05.10.10

    10.00 Cable pair changed

    18 87407 03.10.10

    17.30

    05.10.10

    18.00 MUX Problem.

    19 87466 04.10.10

    16.20

    05.10.10

    21.25 Cable Burnt.

    20 87315 06.10.10

    09.40

    06.10.10

    17.00 Telephone Changed.

    21 87333 06.10.10

    10.00

    06.10.10

    15.00 Link short.

    22 87476 04.10.10

    09.30

    07.10.10

    10.30 O/H/ Break.

    23 87390 07.10.10

    13.00

    07.10.10

    17.00 CT.BOX wire break.

    24 87341 05.10.10

    18.45

    08.10.10

    08.40 Wire break

    25 87350 07.10.10

    09.40

    08.10.10

    09.00 O/H break.

    27 87351 07.10. 09.4 08.10.1 09.10 Wire break

  • 7/31/2019 Pcdo Fo Achivments

    13/18

    10 0 0

    28 87323 27.09.10

    16.00

    09.10.10

    11.30 Telephone Changed.

    29 87324 09.10.10

    10.10

    12.10.10

    08.30 Cable pair changed

    30 87420 12.10.

    10

    10.0

    0

    12.10.1

    0

    13.00 Wire break

    31 87373 12.10.10

    10.00

    13.10.10

    09.20 Cable pair changed

    32 87342 12.10.10

    10.00

    13.10.10

    10.10 Cord changed.

    33 87331 12.10.10

    10.00

    13.10.10

    09.40 Telephone Changed.

    34 87352 13.10.10

    05.00

    13.10.10

    09.00 Wire Break.

    35 87401 15.10.10

    11.00

    17.10.10

    10.30 Telephone Changed.

    36 87398 09.10.10

    20.00

    18.10.10

    09.30 Wire Break.

    37 87302 18.10.10

    15.00

    19.10.10

    18.30 Cable pair changed.

    38 87376 18.10.10

    18.00

    19.10.10

    10.30 Cable pair changed.

    39 87490 20.10.10

    11.00

    20.10.10

    17.00 Wire Break.

    40 87396 20.10.10

    07.30

    22.10.10

    08.40 O/H/ Break.

    41 87362 22.10.10

    07.30

    22.10.10

    09.35 Wire Break.

    42 87373 22.10.10

    09.30

    22.10.10

    10.30 Cable pair changed.

    43 87485 20.10.

    10

    113.

    30

    23.10.1

    0

    16.20 Wire Break.

    44 87307 23.10.10

    18.30

    24.10.10

    11.30 Wire Break.

    Copy to Sr. DSTE/RNC & ADSTE/MURI for information please.SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    14/18

    STATEMENT SHOWING THE POSITION OF BSNL PHONE UPTO 25TH OFTHE MONTH OF OCTOBER 2010.

    SL.NO.

    Name of theBSNL phone

    IN RIGHT Remarks

    DATE TIME DATE

    TIME

    01 RMT Working properly.02 MAEL Working properly.03 BRKP 24.07.1

    019.30 Not Working .

    04 GRE Working properly.05 HRBR 30.10.0

    612.00 Very feeble signal &

    disconnected due tonon payment.

    06 BLNG 11.10.05

    13.00 No signal at BLNGstation & disconnecteddue to non since

    30.10.0607 MURI/SS Working properly.08 MURI/ENQ Working properly.091011

    MURI T/ROOMMURI EXCH.IMURI EXCH.II

    Working properly.Working Properly.Working Properly.

    12 ADSTE/MURI Working properly.13 ILU Working properly.14 TRAN No BSNL connection.15 SSIA 16.06.1

    015.00 Not Working,

    16 TUL 01.04.1

    0

    14.00 Not Working due to

    very week signal.17 LTMD Working properly.18 JHMR Working properly.19 GDBR Working properly.20 THO Nonpayment.21 JAA Working properly.

    Copy to Sr. DSTE/RNC & ADSTE/MURI for information please.SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    15/18

    STATEMENT SHOWING THE PERFORMANCE OF PRS/UTS FOR THEMONTH OF OCTOBER 2010.

    Name of theStation

    IN RIGHT REMARKS.DATE TIME DATE TIME

    PRS/MURI No Failure Reported.1. NKM Link -DO-2. JAA Link -DO-

    PRS/RMT No Failure Reported.1. RLY Link 09.10.

    1009.30 09.10.

    1017.00 RLY Link problem.

    2. BSNLLink

    -DO-

    PRS/RWP No Failure Reported.1. BSNL

    Link09.10.10

    13.45 09.10.10

    13.40 Link failure.

    PRS/JAA No Failure Reported.

    1. MURILink -DO-

    2. KSX Link -DO-

    PRS SSIA No Failure Reported.1. MURI

    Link-DO-

    2. TUL Link -DO-PRS TUL No Failure Reported.

    1. MURILink

    -DO-

    2. SINI Link -DO-UTS/MURI 09.10.

    10

    04.20 09.10.

    10

    05.00 Modem reset.

    1. NKM Link -DO-2. JAA Link -DO-

    UTS/RMT No Failure Reported.

    1. RLY Link -DO-2. BSNL

    Link02.10.10

    17.30 02.10.10

    23.00 BSNL Link failure.

    UTS/JAA No Failure Reported.1. MURI

    Link-DO-

    2. KSX Link -DO-

    UTS/SSIA No failure reported.1. Muri Link 17.10.

    1022.35 17.10.

    1023.10 Modem reset.

    2. TUL Link -DO-UTS/TUL 28.09.

    1016.00 29.09.

    1008.00 Link problem.

    1. SSIA Link -DO-

    2. SINI Link -DO-

  • 7/31/2019 Pcdo Fo Achivments

    16/18

    UTS/BLNG No failure reported.UTS/HSNL No failure reported.UTS/TRAN Modem reset.

    Copy to Sr. DSTE/RNC & ADSTE/MURI for information please.SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    17/18

    STATEMENT SHOWING THE EMERGENCY SOCKETS LYING DEFECTIVETILL 25TH OF THE MONTH OF OCTOBER 2010.

    SL.NO.

    Name ofthesection

    Totalsocket

    KM.NO.

    IN REMARKS

    DATE TIME

    01 BRKP-GRE 08 388/16 21.09.10

    21.50 Socket missing.

    02 JHMR-LTMD

    10 304/11 11.10.10

    13.45 D/Cable cut.

    03 JAA-KSX 13 374/15 20.10.10

    16.00 Socket damage.

    04 GRE-HRBR 09 381/1 24.10.10

    14.30 NO LOOP.

    -DO- 09 380/1 24.10.10

    14.30 NO LOOP.

    Copy to Sr. DSTE/RNC & ADSTE/MURI for information please.SE/T/MURI

  • 7/31/2019 Pcdo Fo Achivments

    18/18

    STATEMENT SHOWING THE EMERGENCY SOCKETS TESTING REPORTFOR THE MONTH OF OCTOBER 2010.

    SLNo.

    Section TotalNo.

    Date oftesting

    Number ofsocket

    tested

    Numberof socketsmissing /

    defective

    Remarks

    01 CNI-GDBR 09 23.10.10

    09 02 Joint tested by H.D.Singh with TRD staff.

    02 GDBR-JHMR

    10 23.10.10

    10 00 Joint tested by N.C.Mahato with TRDstaff.

    03 JHMR-LTMD

    10 11.10.10

    10 02 Joint tested byRaman Lohra with

    TRD staff.04 TUL-SSIA 07 11.10.1

    007 00 Joint tested by P.C.

    Sarkar with TRDstaff.

    05 SSIA-TRAN 11 12.10.10

    11 01 Joint tested byH.D.Singh with TRDstaff.

    06 MURI-BLNG

    10 14.10.10

    10 00 Tested by R. Lohra.

    -DO- 10 21.10.10

    10 01 Joint tested by B.D.Muchi with TRD staff.

    07 HRBR-GRE 09 14.10.10

    09 03 Tested by B.D.Muchi.

    -do- 09 24.10.10

    09 02 Joint tested by P.C.Sarkar with TRD

    staff.08 MAEL-RMT 13 21.10.10

    02 00 Tested by A. Mura.

    Copy to Sr. DSTE/RNC & ADSTE/MURI for information please.SE/T/MURI