paul l. shank p.e., c.m. chief engineer bwi marshall airport maryland transportation builders and...
TRANSCRIPT
PAUL L. SHANK P.E., C.M.CHIEF ENGINEER BWI MARSHALL AIRPORT
MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION
WHERE WE ARE – WHERE WE ARE GOINGNOVEMBER 20,
2013
RSA IMPROVEMENTS, PMP & STANDARDS PROGRAM
PROGRAM YEAR 2013TASK CONTRACT VALUE MBE
1Runway 15R-33L Standards Compliance Earthwork Project
$21,800,000 25%
2Runway 15R Deicing Pad Pavement Rehab. And Stnds. Compliance
$14,169,000 30%
3 Low Maintenance Grassing Test Plots
$133,000 25%
4 General Aviation Pavement Rehabilitation
$994,000 20%
5RSA Program Environmental Stream Restoration Project
$2,079,000 26%
6Runway 15L-33R Runway Safety Area Improvements
$4,960,000 20%
7Runway 15R-33L RSA, PMP and Standards Compliance Project
$83,235,000 20%
8Runway 10-28 and 15R-33L Obstruction Clearing Project
$413,000 4%
9* Runway 15R-33L NAVAIDS Project
$5,409,000 13%
*Graphic location same as Task 7
15R 33L EARTHWORK
CONTRACT VALUE: $ 21,756,470
Contract Completes – Summer 2014
MBE: 25%
PROJECT OVERVIEW:
Clearing and grubbing. Storm drain installation. Box culvert installation. Sanitary sewer and underground fire hydrant relocation. Mass earthwork, grading and retaining wall.
RUNWAY 15R DEICINGCONTRACT VALUE: $ 14,168,409
Contract Completes – November 2013
MBE: 30%
PROJECT OVERVIEW:
Removal of existing pavement. Installation of new glycol drainage infrastructure, lighting, diversion vaults. New concrete pavement and pavement markings.
ENVIRONMENTAL STREAM RESTORATION
CONTRACT VALUE: $ 2,078,771
Contract Completes – July 2014
MBE: 26%
PROJECT OVERVIEW:
Grading of stream channels and placement of fill.
Construction of in-stream structures. Removal of invasive vegetation and plantings.
RUNWAY 15L 33R RSA
CONTRACT VALUE: $ 4,959,398
Contract Completes – Spring 2014
MBE – 14%
PROJECT OVERVIEW:
New vehicle service road and airfield equipment access road. Drainage pipe, box culvert and structure installation. Preparation of site and infrastructure for future relocation of existing NAVAIDS.
CONTRACT VALUE: $ 83,235,000
Proposed Schedule – September 2013 to April 2015
PROJECT OVERVIEW:
Comprehensive Pavement Rehabilitation. Runway Safety Area Grading and Improvements. NAVAID Relocations and Infrastructure Improvements. Runway and Taxiway Lighting Improvements. Taxiway Realignments. Runway Incursion Prevention Elements.
RUNWAY 15R 33L RSA
PROGRAM YEAR 2014-2015
2014-2015 PROGRAM ELEMENTS
6Runway 10-28 Navaids & Runway 28 Displacement
15A
New T/W “Uniform” & T/W “Uniform 1” And South Portion De-ice Pad
15BRunway 4-22 Conversion To Taxiway “Papa”
15CNew Taxiway Construction (EB-75)
15DOld Taxiway “Delta” Demolition
PROGRAM VALUE 75-100M
15D
15B
15C
15A
6
10
EXISTING TERMINAL - 2012
SECURITY CHECKPOINTS IN THE
THROAT OF THE CONCOURSES
RESTRICT EGRESS/ EVACUATION CAPACITY
CORRIDOR WIDTH IN ORIGINAL
PORTIONS OF CONCOURSES INADEQUATE
11
LONG TERM TERMINAL PLAN UPPER LEVEL PLAN
NEW CHECKPOINTS
BETWEEN CONCOURSES BEHIND SECURITY
CONNECTORS ALLOW FOR LOAD BALANCING
AND CONNECTING FLIGHTS
12
LONG TERM TERMINAL PLAN PHASING PLAN
CONCOURSE D ORIGINALLY FIRST
BECAUSE DEFICIENCIES WERE
GREATER DUE TO THE NUMBER OF GATES
SERVED.
SWA / AIRTRAN MERGER AND CONSOLIDATION ON
CONCOURSES A/B/C SHIFTED PRIORITIES TO
BC CONNECTOR
A B
C
E
13
CONCOURSE C WIDENING
B/C CONNECTOR
BC CONNECTOR PROGRAM TWO CONSTRUCTION PROJECTS
14
BC CONNECTOR FINAL UPPER LEVEL PLAN
9 LANE CHECKPOIN
T
BC CONNECTORCONTRACT VALUE: $ 43,937,000
MBE: 20%
PROJECT OVERVIEW:
Secure passenger corridor connecting Concourse B and C. Nine (9) Lane Security Checkpoint. Observation Deck improvements. Concessions and Office Spaces.
BC CONNECTOR
NEW BC SECURITY CHECKPOINT
NEW BC CONNECTOR
CONCOURSE C WIDENING
CONTRACT VALUE: $ 28,799,512
Completion Date – January 2013
MBE: 31%
PROJECT OVERVIEW:
Renovate Concourse C to include larger passenger hold rooms and a wider corridor and exit.
New passenger boarding bridges. New baggage handling system. New public restrooms. Modify mechanical & electrical systems.
DE CONNECTOR
CONTRACT VALUE: $ 75-100M
Proposed Design Schedule: September 2013- September 2014
Proposed Construction Schedule: January 2015- November 2016
DE CONNECTOR
DE CONNECTOR ARRIVAL LEVEL PLAN
DE CONNECTOR DEPATURE LEVEL PLAN
NEW DE SECURITY CHECKPOINT
DE SECURITY CHECKPOINT VIEW FROM TERMINAL D
DE SECURITY CHECKPOINT VIEW FROM TERMINAL E
DE CONNECTOR
DE CONNECTOR
VIDEO OF PROJECT OVERVIEW:
BWI CONFORM.wmv
*Program
**Advertised
***BidsDue
****Bid Opening
Contract Number & Title Proposed Date Project Value
MAA-CO-13-020Parking Access and Revenue Control System (PARCS)
***May 2013 $8M-$11M
MAA-CO-14-0012015 Airfield Capacity Enhancement Project
**April 2014 $80M
MAA-CO-14-005International Building Expansion
**December 2013 $7M
MAA-CO-14-007Comprehensive Interior/Exterior Modification 2014
**November 2013 $25M
MAA-CO-14-008Long Term Parking Lot B Pavement Rehabilitation
**November 2013 $1.7M
MAA-CO-14-009Pedestrian Walkway from CRCF to the East Tenant Lot *October 2013 $.5M
MAA-CO-14-010Public Parking Area Pavement Rehabilitation **November 2013 $1M
MAA-CO-14-011Central Terminal Third Floor Elevator Upgrades **November 2013 $.5M
MAA-CO-14-012Air Cargo Drive Pavement Rehabilitation *February 2014 $1.7M