Partial Wind Farm Repowering & Tax Credit Qualification

1

Complimentary Webinar November 10, 2016

DNV GL © 2016

Ungraded

07 November 2016

Today’s Speakers

2

Kevin Smith Keith Martin

Director, Asset Management &

Operating Services DNV GL

Partner Chadbourne & Parke

Victoria Richardson

Communications DNV GL

DNV GL © 2016

Ungraded

07 November 2016

Today’s Agenda

3

Welcome and Introduction

Partial Repowering & the Business Opportunity

Partial Repowering & Key Issues

Tax & Financial Considerations

Ask DNV GL and Chadbourne & Parke

DNV GL © 2016

Ungraded

07 November 2016 4

Partial Repowering & The Business Opportunity

DNV GL © 2016

Ungraded

07 November 2016

The Opportunity

Partial repower opportunity

– >1.5 MW or greater WTG capacity

– 10 year or older turbines

14% of turbines installed since 2000

May 2016, IRS guidance established criteria for operational project upgrades to re-qualify for PTCs

Investments must be 4x retained value

Calculations on a per turbine pad basis

Business case highly project and turbine specific

5

Projects since 2000:

68,090 MW

672 projects

37,710 turbines

Repower Opportunity:

8,657 MW

91 projects

5,420 turbines

Partial Wind Farm Repowering

DNV GL © 2016

Ungraded

07 November 2016 6

Partial Repowering & Key Issues

DNV GL © 2016

Ungraded

07 November 2016

What does partial repowering mean?

Scope depends on technical needs and meeting investment qualification threshold

Potential options include:

– Full nacelle and rotor replacement

– Replacement of rotor, various drivetrain & ancillary components, controls, & software

Tower and foundation likely to remain

Tower replacement conceivable but may not result in viable business case

20% rotor size increase ~ 10 - 20% energy increase

Larger rotors may result in loads exceeding tower and foundation capacity

7

Partial Wind Farm Repowering

DNV GL © 2016

Ungraded

07 November 2016

Site conditions and structural reliability

Partial repowering may result in some components operating 30 years or more

Careful analysis of site conditions and fatigue accumulation is critical

Structural reliability risk levels need to be agreed upon with Stakeholders

Risk mitigation could include: Type/Project Certification, 3rd party site specific design assessment

Pad locations in projects where turbines are ‘under-sited’ based on wind conditions or low availability are good repower targets

8

Partial Wind Farm Repowering

DNV GL © 2016

Ungraded

07 November 2016

Towers & Foundations

9

Towers

– Non destructive testing at key load points and welds

– Evaluation of harmonics

– Bolted interface compatibility & adapters

– Power cable compatibility

– Risk based inspections

Foundations

– New foundation loads must be calculated

– Foundations older than 10 years may not have been designed for fatigue

– Existing site and soil conditions

– Operating history of turbine for extreme events

– Refurbishment might be possible, but costly

Partial Wind Farm Repowering

DNV GL © 2016

Ungraded

07 November 2016

Energy Production

Energy assessments for repowering offer lower uncertainty compared to new project development.

– Up to 2-3% reduction in uncertainty of long term AEP

– Up to 4-7% increase in 1 year P99

– Historic operating data and wind data is a significant advantage

– Environmental and BOP loss factors are better quantified

– Grid curtailment and other interconnection issues are known or have been mitigated

– Topographic and wake effects are much better understood

10

Inter-turbine spacing will change which impacts loads and energy production

Load control software in new turbines may help keep loads within range, but could impact energy production

Sector management control maybe needed

Partial Wind Farm Repowering

DNV GL © 2016

Ungraded

07 November 2016

Balance of Plant

11

Partial Wind Farm Repowering

Turbine and/or plant capacity may change – investigate electrical BoP for potential limitations

Collection system capacity and remaining life evaluations:

– Pad transformers & related cables

– Medium voltage cables and overhead conductors

– Turbine grounding

Substation:

– Main power transformers

– Feeder circuit breakers

– Main breakers

– Reactive power compensation

– Surge arresters

DNV GL © 2016

Ungraded

07 November 2016

Environmental & Permitting

Avian and wildlife review – larger rotor swept area

Changes to FAA approvals – increased max tip heights

Sound, shadow, and other setbacks – larger rotors may trigger re-assessment need

Local or State permitting and review processes – evaluate impact of partial repowering for triggering new review process

12

Partial Wind Farm Repowering

DNV GL © 2016

Ungraded

07 November 2016

Contractual Consideration

New turbine supply & installation agreements

New warranties agreements and terms

Interconnection agreements – any key limitations or changes required?

Offtake agreements – min/max limits, term, rates, etc.

O&M agreements – changes due to new turbines, parts, responsibilities, etc.

Build-out/shared facilities agreements

13

Partial Wind Farm Repowering

DNV GL © 2016

Ungraded

07 November 2016 14

Tax & Financial Considerations

DNV GL © 2016

Ungraded

07 November 2016

Tax Credits

A wind farm owner may be able to qualify for another 10 years of production tax credits on a project by repowering. Whether tax credits can be claimed requires a two-part calculation.

15

Tax Credit Qualifications

DNV GL © 2016

Ungraded

07 November 2016

Tax Credits

First, the repowering effort must be considered underway by the end of this year to qualify for tax credits at the full rate. If it gets underway in any of the next three years, it will qualify for tax credits at a reduced rate: 80% for repowerings starting in 2017, 60% in 2018 and 40% in 2019.

16

Tax Credit Qualifications

DNV GL © 2016

Ungraded

07 November 2016

Tax & Financial Considerations

In order for construction to be considered underway, one of two things must happen. The wind farm owner with must "incur" at least 5% of the total repowering cost or else it must start "physical work of a significant nature" by the construction-start deadline.

17

Tax Credit Qualifications

DNV GL © 2016

Ungraded

07 November 2016

Tax & Financial Considerations

Costs are not "incurred" merely by spending money. Costs are incurred as equipment that will be used in the repowering is delivered, with one exception. The exception is that a payment this year counts as a 2016 incurred cost if the equipment is delivered within 3 1/2 months after the payment.

– Method of accounting

– Binding contract

18

Tax Credit Qualifications

DNV GL © 2016

Ungraded

07 November 2016

Tax & Financial Considerations

Most wind companies sign a "PTC components" contract. Buy equipment whose next stop will be the project site rather than components that have to return to the factory for further assembly. Delivery can be at the factory. Avoid vendor financing. Most companies incur at least 7% in case of cost overruns.

– Guaranteed debt

– Project schedule

19

Tax Credit Qualifications

DNV GL © 2016

Ungraded

07 November 2016

Tax & Financial Considerations

Physical work means physical work at the site or on equipment at the factory. It is harder to raise tax equity on projects that rely on the physical work test. The more physical work before the deadline, the better.

20

Tax Credit Qualifications

DNV GL © 2016

Ungraded

07 November 2016

Repowering Calculations

Repowering requires two calculations. The second calculation is application of the "80-20 test" to each separate turbine, pad and tower to see whether the repowering will be extensive enough to lead to construction of a new "facility." Each turbine, pad and tower is analyzed like a separate power plant.

21

Tax Credit Qualifications

DNV GL © 2016

Ungraded

07 November 2016

Financial Considerations

You must spend on the repowering of each "facility" at least four times the value of the used components retained from the original facility. The IRS prefers the depreciated replacement cost method to value the used components. That means determining their cost new and then adjusting for wear and tear and any technological obsolescence.

22

Tax Credit Qualifications

DNV GL © 2016

Ungraded

07 November 2016

Securing Production Tax Credits

Ideally, the repowering should be about more than just renewing tax credits: for example, increasing the generating capacity or electricity output. However, the law in this area goes back to 1962 and 1994 revenue rulings. Production tax credits can be claimed on the electricity output from a new facility.

– Computational issues

– Appraisal issues

23

Tax Credit Qualifications

DNV GL © 2016

Ungraded

07 November 2016

Q&A: Ask our Speakers

24

Kevin Smith Keith Martin

Director, Asset Management &

Operating Services DNV GL

Partner Chadbourne & Parke

DNV GL © 2016

Ungraded

07 November 2016

SAFER, SMARTER, GREENER

www.dnvgl.com

Thank you!