part1 termination and damages
TRANSCRIPT
-
7/30/2019 Part1 Termination and Damages
1/49
TMH Copyright 2010 1
-
7/30/2019 Part1 Termination and Damages
2/49
TMH Copyright 2010
Chapter 13
T
ime and Place of Contract
Chapter 30 and 31
Termination and Damages
2
-
7/30/2019 Part1 Termination and Damages
3/49
TMH Copyright 2010
Case: Power Supply
A company was to supply power to its contractorfor a construction job. The company failed to
provide it. The contractor hired a generator set. Itcost the company 2 lakhs. The contractor isclaiming the money from the company.
3
-
7/30/2019 Part1 Termination and Damages
4/49
TMH Copyright 2010
Breach and Damages
On every breach of a term of a contract, thesuffering party has a right to compensation.
4
-
7/30/2019 Part1 Termination and Damages
5/49
TMH Copyright 2010
Car Service
Rohan booked a car on the internet from a carrental service to drop him from the MumbaiAirport to the city centre. The followings were the
terms of the contract:
1. Rohan would pay Rs. 500 through credit card atthe time of making of the contract.
5. The driver would be holding a 24 x 12 plasticplacard bearing the name and logo of the companyand the passenger. ..
5
-
7/30/2019 Part1 Termination and Damages
6/49
TMH Copyright 2010
cont 6. The company would provide an Inova air-
conditioned car.
7. The car would not have done more than 20,000Km.
10. The car seats would be in white cover.
11. The car would be fully fuelled beforereceiving the passenger.
6
-
7/30/2019 Part1 Termination and Damages
7/49
TMH Copyright 2010
cont 5. The driver would be holding a 24 x 12 plastic
placard bearing the name and logo of the companyand the passenger. ..
The driver was holding a big white sheet in hishand with the name of the passenger and the
company written in hand with drawing pen.
7
-
7/30/2019 Part1 Termination and Damages
8/49
TMH Copyright 2010
cont
6. The company would provide an Inova air-conditioned car.
The company sent Tata Indica instead. (TataIndica is a much smaller car)
8
-
7/30/2019 Part1 Termination and Damages
9/49
TMH Copyright 2010
Principles
Every contract has terms which constitute the coreof the contract. Other terms are subsidiary aspects.A term which is a part of the core of the contract iscalled condition and a subsidiary termwarranty.
For the breach of any term, condition or warranty,
the innocent party has a right to receivecompensation. However, on breach of a condition,
the innocent party gets the option to terminate the
contract.9
-
7/30/2019 Part1 Termination and Damages
10/49
TMH Copyright 2010
Principles
The innocent party can elect to continue with thecontract or terminate the contract.
Till the decision to terminate the contract iscommunicated (express or implied), both the
parties are bound by the terms of the contract.
10
-
7/30/2019 Part1 Termination and Damages
11/49
TMH Copyright 2010
Contract Clause
1. Rohan would pay Rs. 500 through credit card at the time of making of thecontract.
5. The driver would be holding a 24 x 12 plastic placard bearing the name and
logo of the company and the passenger. ..
6. The company would provide an Inova air-conditioned car.
7. The car would not have done more than 20, 000 Km.
10. The car seats would be in white cover. ..
11. The car would be fully fuelled before receiving the passenger.
18. All the terms of this contract are a condition of thecontract.
11
-
7/30/2019 Part1 Termination and Damages
12/49
TMH Copyright 2010
Termination clause
The Contract can be terminated in the following situations:
The Purchaser may terminate this contract in whole or
in part
(a) if the Supplier fails to deliver any or all of the
Goods within the period(s) specified in the Contract
(b) if the Supplier fails to perform any other
obligation(s) under the Contract.
12
-
7/30/2019 Part1 Termination and Damages
13/49
TMH Copyright 2010
Case: Union Eagle Ltd.
Time was of essence
If the Purchaser shall fail to comply with any ofthe terms and conditions of this Agreement theVendor may this Agreement
The purchaser was late by 10 minutes in tenderingthe money.
13
-
7/30/2019 Part1 Termination and Damages
14/49
TMH Copyright 2010
Case: Cochin Chemical Ltd.
Kerala Government was to advance money 2.5lakhs the Company and the Company was tomortgage its assets in favour of the Government.
Over the next five months the Company was tosupply goods at the prevailing price and balanceout the money given to it.
The Kerala Government failed to pay the money.The Company, however, arranged to supply thegoods.
14
-
7/30/2019 Part1 Termination and Damages
15/49
TMH Copyright 2010
cont The company claimed damages. The Government
contested that the government receiving the goodswas contingent on it advancing the money.
15
-
7/30/2019 Part1 Termination and Damages
16/49
TMH Copyright 2010
Supreme Court
Breach of contract by one party does notautomatically terminate the obligation under thecontract; the injured party has the option either totreat the contract as still in existence, or to regardhimself as discharged. If he does not accept thedischarge, he may insist on performance. Itcannot, therefore, be said that by refusing to
advance the loan which the State had undertakento advance, the obligation to purchase groundnutcake from the Company came to an end.
16
-
7/30/2019 Part1 Termination and Damages
17/49
TMH Copyright 2010
Defective ATM
Sun Bank placed order on Ewan Engineering Ltd.for supplying it three ATM Machines. Under thecontract, it had already paid 50% of the price. It
was to pay another 30% on the first of the monthand Ewan Engineering Ltd. was to supply themachines on 15th of the month.
Sun Bank was only the third bank to buy thatmodel of ATM. It got report from the other two
buyers that the machine had several defects indesign and manufacturing.
17
-
7/30/2019 Part1 Termination and Damages
18/49
TMH Copyright 2010
cont Sun bank, citing that the machine delivered to
others was defective and the company coulddeliver them only defective machine, refused to
pay 30% of the 1st of the month and demandedback the 50% contract value paid to them inadvance.
18
-
7/30/2019 Part1 Termination and Damages
19/49
TMH Copyright 2010
Car Service
The car company called Rohan on his cell phonewhen he was checking in at Delhi for his Mumbaiflight. The company told him that they would not
be able to supply the car as their drivers had goneon strike. Rohan replied, That is your problemnot mine. I booked a car 20 days in advance andyou have to provide it.
Rohan in the arrival lounge paid for a pre-paidtaxi. On exiting, Rohan saw a driver holding thecompanys placard bearing his name.
19
-
7/30/2019 Part1 Termination and Damages
20/49
TMH Copyright 2010
Anticipatory Breach
An advance notice of intended breach of condition
is called anticipatory breach. The other party can
elect to accept it. In this case, the contract will beterminated and the innocent party can claim
damages.
A party can reject an anticipatory breach. In this
case, the contract subsists and both the parties are
bound by its terms.
20
-
7/30/2019 Part1 Termination and Damages
21/49
TMH Copyright 2010
Damages
21
-
7/30/2019 Part1 Termination and Damages
22/49
TMH Copyright 2010
Case: Carriage of Computers
Sudip contracted to transport computercomponents from Mumbai to Bangalore, forPrakash, for a consideration of Rs 2 lakh. On theappointed time, Sudip did not turn up. Prakashfound Akash to do the work for him. However, theconsignment got delayed by two days.
22
-
7/30/2019 Part1 Termination and Damages
23/49
TMH Copyright 2010
Consequential Losses
As a consequence of breach, several eventsunfold.
All business contracts contain clauses exemptingthem from consequential losses.
23
-
7/30/2019 Part1 Termination and Damages
24/49
TMH Copyright 2010
Specific Performance
As a remedy, should the party be forced to what
he has contracted to do?
Specific performance is awarded in rare case. In
most case, a monetary equivalent is provided to
compensate the party for the breach of the
contract.
24
-
7/30/2019 Part1 Termination and Damages
25/49
TMH Copyright 2010
Principle for Compensation
... such money compensation as will put him in theposition in which he would have been but for thebreach... In working out the compensation you
should as nearly as possible get at that sum ofmoney which will put the party ...in the same
position as he would have been in if he had notsustained the wrong.
25
-
7/30/2019 Part1 Termination and Damages
26/49
TMH Copyright 2010
Huxley
the law relating to damages for breach ofcontract has developed almost exclusively in a
commercial context, these criteria normally
proceed on the assumption that each contracting
party's interest in the bargain was purely
commercial and that the loss resulting from a
breach of contract is measurable in purely
economic terms.
As a result, the courts award loss of profit as a
damages.26
-
7/30/2019 Part1 Termination and Damages
27/49
TMH Copyright 2010
Contract Act: Compensation
73. Compensation for loss or damage caused by
breach of contract.- When a contract has been
broken, the party who suffers by such breach is
entitled to receive, from the party who has brokenthe contract, compensation for any loss or damage
caused to him thereby, which naturally arose in
the usual course of things from such breach, or
which the parties knew, when they made thecontract, to be likely to result from the breach of
it.
27
-
7/30/2019 Part1 Termination and Damages
28/49
TMH Copyright 2010
cont
Such compensation is not to be given for
any remote and indirect loss or damage
sustained by reason of the breach.
28
-
7/30/2019 Part1 Termination and Damages
29/49
TMH Copyright 2010
Case: Carriage of Computers
Raman contracted to transport computercomponents from Mumbai to Bangalore, forPrakash, for a consideration of Rs 2 lakh. It wasagreed that in the case of a breach of contract,
Raman would pay damages worth Rs 50,000. Howmuch should Raman be made to pay in thefollowing different situations:
1. The actual damage came out to be Rs 60,000.
2. The actual damage was Rs. 10,000.
3. There was no damage to Prakash.
29
-
7/30/2019 Part1 Termination and Damages
30/49
TMH Copyright 2010
Contract Act: Liquidated Damages
74. Compensation for breach of contract where
penalty stipulated for.- When a contract has been
broken, if a sum is named in the contract as the amount
to be paid in case of such breach, or if the contract
contains any other stipulation by way of penalty, the
party complaining of the breach is entitled,
30
-
7/30/2019 Part1 Termination and Damages
31/49
TMH Copyright 2010
cont
...whether or not actual damage or loss is
proved to have been caused thereby, to
receive from the party who has broken thecontract, reasonable compensation not
exceeding the amount so named or, as the
case may be, the penalty stipulated for.
31
-
7/30/2019 Part1 Termination and Damages
32/49
TMH Copyright 2010
Remoteness of Damage
1. If the parties have provided on the
consequences of breach, by mentioning the
consequences or the amount, the stipulation wouldapply. For example, a courier company may
provide that it is not responsible for any losses
caused due to late delivery of the consignment.
32
-
7/30/2019 Part1 Termination and Damages
33/49
TMH Copyright 2010
cont
2. If the contract has not provided, the only
thing we can go with is impliedly, what is
agreed between the parties?
33
-
7/30/2019 Part1 Termination and Damages
34/49
TMH Copyright 2010
Supreme Court: Compensation
The Indian courts have adopted the judgement in
the Hadley case. The Supreme Court stated the
principle for awarding compensation thus:
... such money compensation as will put him in
the position in which he would have been but
for the breach... In working out the
compensation you should as nearly as possible
get at that sum of money which will put the
party
34
-
7/30/2019 Part1 Termination and Damages
35/49
TMH Copyright 2010
cont
...in the same position as he would have beenin if he had not sustained the wrong.... the rulelaid down as to measure of damage is the same,
namely, the party in breach must makecompensation in respect of the directconsequences flowing from the breach and notin respect of loss or damage indirectly or
remotely caused, which is also the rule inEnglish common law.
35
-
7/30/2019 Part1 Termination and Damages
36/49
TMH Copyright 2010
Case: Dwarka Das v. State of MP
Dwarka Das is the contractor and State of MPemployer. The total value of the contract was Rupees
two lakhs. The Superintending Engineer is alleged to
have obstructed the progress of the work. As a result,
the work could not be completed within the timeschedule. Following this, the State of Madhya Pradesh
terminated the contract. Dwarka Das moved the court
claiming that this was breach of contract and loss of
profit at the rate of 10% of the value of the project,amounting to Rs. 20,000, as damages for breach of
contract. The Supreme Court emphasised loss of profit
as the basis for claiming damages. The court ruled:
36
-
7/30/2019 Part1 Termination and Damages
37/49
TMH Copyright 2010
cont
The appellant (Contractor) had never claimed Rs. 20,000/-
on account of alleged actual loss suffered by him. He had
preferred his claim on the ground that had he carried out
the contract he would have earned profit of 10% on Rs. 2
lacs which was the value of the contract. damages can
be claimed by a contractor where the government is proved
to have committed breach by improperly rescinding the
contract and for estimating the amount of damages, Court
should make a broad evaluation instead of going intominute details. the contractor is entitled to claim the
damages for loss of profit which he expected to earn by
undertaking the works contract.
37
-
7/30/2019 Part1 Termination and Damages
38/49
TMH Copyright 2010
Maula Bux v. Union of India
It is true that in every case of breach of contractthe person aggrieved by the breach is not requiredto prove actual loss or damage suffered by him
before he can claim a decree and the Court iscompetent to award reasonable compensation incase of breach even if no actual damage is provedto have been suffered in consequence of the
breach of contract. But the expression "whether or
not actual damage or loss is proved to have beencaused thereby" is intended to cover differentclasses of contracts which come before the Courts.
38
-
7/30/2019 Part1 Termination and Damages
39/49
TMH Copyright 2010
cont
In case of breach of some contracts it may be
impossible for the Court to assess compensation
arising from breach, while in other casescompensation can be calculated in accordance
with established rules. Where the Court is unable
to assess the compensation, the sum named by the
parties if it be regarded as a genuine pre-estimatemay be taken into consideration as the measure of
reasonable compensation,
39
-
7/30/2019 Part1 Termination and Damages
40/49
TMH Copyright 2010
cont
but not if the sum named is in the nature of a
penalty. Where loss in terms of money can
be determined, the party claimingcompensation must prove the loss suffered
by him.
40
-
7/30/2019 Part1 Termination and Damages
41/49
-
7/30/2019 Part1 Termination and Damages
42/49
TMH Copyright 2010
ONGC v. SAW Pipes Ltd.
Through a tender, SAW got in a contract with theONGC to supply it casing pipes for offshore oilexploration and maintenance. Due to strike in Italy,from where SAW was procuring the pipes, the
pipes could not be delivered on time. The contracthad a liquidated damages clause which stipulatedthat damages, at the rate of 1% of the contract price
per week, would be payable. There was no dispute
on this amount. The arbitrator, however, did notallow damages as it was not proved that the ONGChad indeed suffered damages. The case came beforethe Supreme Court.
42
-
7/30/2019 Part1 Termination and Damages
43/49
TMH Copyright 2010
Judgement: Supreme Court
when a contract has been broken, the party whosuffers by such breach is entitled to receivecompensation for any loss which naturally arise inthe usual course of things from such breach. These
sections further contemplate that if parties knewwhen they made the contract that a particular lossis likely to result from such breach, they can agreefor payment of such compensation. In such a case,
there may not be any necessity of leading evidencefor proving damages, unless the Court arrives atthe conclusion that no loss is likely to occur
because of such breach.
43
-
7/30/2019 Part1 Termination and Damages
44/49
TMH Copyright 2010
cont
Further, in case where Court arrives at the conclusionthat the term contemplating damages is by way ofpenalty, the Court may grant reasonable compensationnot exceeding the amount so named in the contract on
proof of damages. However, when the terms of the
contract are clear and unambiguous then its meaningis to be gathered only from the words used therein. Ina case where agreement is executed by experts in thefield, it would be difficult to hold that the intention of
the parties was different from the language usedtherein. In such a case, it is for the party who contendsthat stipulated amount is not reasonable compensation,to prove the same.
44
-
7/30/2019 Part1 Termination and Damages
45/49
TMH Copyright 2010
Judgement: Supreme Court
if the parties have pre-estimated such loss after clearunderstanding, it would be totally unjustified to arriveat the conclusion that party who has committed breachof the contract is not liable to pay compensation. It
would be against the specific provisions of Sections73 and 74 of the Indian Contract Act. There wasnothing on record that compensation contemplated bythe parties was in any way unreasonable. It has beenspecifically mentioned that it was an agreed genuine
pre-estimate of damages duly agreed by the parties. Itwas also mentioned that the liquidated damages arenot by way of penalty.
45
-
7/30/2019 Part1 Termination and Damages
46/49
TMH Copyright 2010
Judgement: Supreme Court
The Supreme Court, in summary, mentioned thefollowing principles:
(1) Terms of the contract are required to be taken
into consideration before arriving at the
conclusion whether the party claiming damages is
entitled to the same;
46
-
7/30/2019 Part1 Termination and Damages
47/49
TMH Copyright 2010
cont
(2) If the terms are clear and unambiguousstipulating the liquidated damages in case of the
breach of the contract unless it is held that such
estimate of damages/compensation isunreasonable or is by way of penalty, party whohas committed the breach is required to paysuch compensation and that is what is provided
in Section 73 of the Contract Act.
47
-
7/30/2019 Part1 Termination and Damages
48/49
TMH Copyright 2010
cont
(3) Section 74 is to be read along with Section73 and, therefore, in every case of breach ofcontract, the person aggrieved by the breach is
not required to prove actual loss or damagesuffered by him before he can claim a decree.The Court is competent to award reasonablecompensation in case of breach even if no
actual damage is proved to have been sufferedin consequences of the breach of a contract.
48
-
7/30/2019 Part1 Termination and Damages
49/49
cont
(4) ... it would be impossible for the Court toassess the compensation arising from breachand if the compensation contemplated is not by
way of penalty or unreasonable, Court canaward the same if it is genuine pre-estimate bythe parties as the measure of reasonablecompensation.
49