pakistan private limitedto engineers who, rather than blindly following the codes of practice, seek...
TRANSCRIPT
Pakistan Private Limited
Prestressed Concrete | Structural Engineering
Company Brochure
STRONGHOLD PRESTRESSING SYSTEM
STRONGHOLD PAKISTAN
Specialist Sub-Contractor of Prestressing Works
And Structural Rehabilitation
TECHNICAL AND SERVICES BROCHURE
To engineers who, rather than blindly following the codes
of practice, seek to apply the laws of nature.
T. Y. Lin, 1955.
1
Table of Contents
1. COMPANY HISTORY ........................................................................................................................ 3
2. OUR SERVICES .................................................................................................................................. 7
3. PRESTRESSING PRODUCTS ............................................................................................................ 8
4. PRESTRESSING EQUIPMENT ........................................................................................................ 12
4.1. Hydraulic Jacks ............................................................................................................................ 12
4.2. Hydraulic Pumps ......................................................................................................................... 15
4.3. Grouting Machines ...................................................................................................................... 16
4.4. Ancillary Equipment .................................................................................................................... 17
5. PROJECTS – PRESTRESSING WORKS .......................................................................................... 18
6. STRESSING & GROUTING PROCEDURE – GENERAL METHOD STATEMENT.................... 30
6.1. Fixing Anchorage ......................................................................................................................... 30
6.2. Fixing Ducts & Threading of Cable ............................................................................................ 30
6.3. Stressing of Cable ....................................................................................................................... 31
6.4. Grouting ...................................................................................................................................... 34
7. END BLOCK RECESS AND CLEARANCES .................................................................................. 35
8. SELECTION TABLES – TENDON, TRUMPET, JACK AND SHEATH ........................................ 36
9. TRUMPET & ANCHOR BLOCK- DESIGN DATA DIMENSIONS ............................................... 40
9.1. Standard Cast Trumpet ............................................................................................................... 40
9.2. Fabricated Trumpet .................................................................................................................... 41
9.3. Rib Cast Trumpet ......................................................................................................................... 42
10. DEAD ANCHORAGE - DESIGN DATA DIMENSIONS ................................................................ 44
10.1. Semi-Bonded Dead Anchorage ................................................................................................... 44
10.2. X Dead Anchorage ....................................................................................................................... 44
11. PRESTRESSING IN BUILDINGS ................................................................................................... 44
12. BUILDING PT – ANCHORAGE DATA TABLES ........................................................................... 47
12.1. Bonded System: .......................................................................................................................... 47
12.2. Unbonded System: ...................................................................................................................... 48
13. GROUND ANCHOR ......................................................................................................................... 49
14. REHABILITATION – HEAVY LIFTING........................................................................................ 50
15. LIFTING EQUIPMENT .................................................................................................................... 51
16. PROJECTS – REHABILITATION .................................................................................................... 52
17. PROJECTS – BEARING REPLACEMENT ...................................................................................... 57
Appendix A – Design Notes
Appendix B – Selective List of PT Projects
2
Ebro River Bridge – Spain
Completed: 1979
Consultants: Fernandez Casado S.A
PT Contractor: CTT Stronghold S.A
Prestressing System: Stronghold Multi-Strand
Stays: 35 Pairs of Stronghold Cable
3
1. COMPANY HISTORY
Stronghold Pakistan was established in 1985 as a licensee of CTT Stronghold SA, a
renowned Spanish company that has now been integrated into the VSL Group – a member
of Bouygues Construction.
The company founder Tahir Karamat who holds Masters degree in Structural Engineering
from the Massachusetts Institute of Technology (MIT), and is in the post-tensioning field
since the 1960’s, pioneered the use of multi-strand post-tensioning system in the country
with local manufacturing of anchorages under a license agreement with CTT Stronghold
with the founding of Stronghold Pakistan. Under his leadership, the company grew rapidly
within the early years of its founding and became market leader in the post-tensioning field.
The company enjoyed near monopoly for over twenty years with almost 100% of the post-
tensioning market with us in Pakistan.
Stronghold pioneered local production of trumpets, anchor blocks and sheaths for its multi-
strand market. In our state-of-the-art production facility, we have developed innovative
methods of production that have led to cost competitiveness of our products while
maintaining highest industry standards meeting all relevant code requirements and
specifications.
Stronghold introduced the incremental launching method (ILM) of bridge construction in
Pakistan. As a joint venture partner with CTT, we helped Daewoo Engineering and
Construction Co to construct six long span box girder bridges using ILM on the Lahore-
Islamabad Motorway Project, a 375 KM dual carriage motorway – the first project of its
kind in the country. We locally fabricated steel nose, formwork and some other items that
were required for launching the bridges to completion. The project was successfully
completed within the set budget and time. The steel nose used in the project was later
exported after modification carried out by us for launching a few other bridges in Portugal.
Pakistan Motorway- Two ILM bridges over River Soan at Chakri – 1x40m+7x50m+1x40m
spans
4
Motorway Project- Lifting and pushing equipment for an ILM bridge during launching.
On the Lahore-Islamabad Motorway Project Stronghold provided all post-tensioning
related supplies and services single-handedly for all of its over 150 bridges to Daewoo. In
fact, Stronghold has already been involved in over 10,000 bridges completed to date in
Pakistan where our products and services have been used. Live and dead anchorages, and
couplers for cable up to 37/0.5″ and 31/0.6" locally produced by Stronghold have been
delivered successfully in these projects. In addition, the company has also supplied a large
number of imported elastomeric bearings, pot bearings, and modular expansion joints
capable of accommodating up to 510mm of movement.
Star Coupler produced by Stronghold Pakistan for the Motorway Project
Test in Barcelona of fabricated Star Coupler produced by Stronghold Pakistan – Test showing
broken strands with no distress to coupler.
5
Throughout our history, we have been at the forefront of providing prestressing services
and supplies on almost all major projects completed across Pakistan. From the mega metro
projects like the Lahore Metro and Green Line to power projects like the Gulpur Hydro
Power in AJ&K, Stronghold has been a key sub-contractor for the prestressing works, and
in most cases delivered all prestressing related services and supplies on the given projects.
New Khairabad Bridge Attock
Stronghold has successfully completed a range of projects requiring different methods of
bridge construction – construction with pre-tensioned girders, post-tensioned cast-in-situ,
segmental balanced cantilever method etc. For example, in the New Khairabad Bridge
both segmental as well as conventional cast-in-situ construction method was employed. All
the post-tensioning services and supplies were rendered by Stronghold.
Khushal Garh Bridge over River Indus
6
Bridge Over River Indus, Islamabad – Peshawar Motorway
Stronghold has made several contributions
to rehabilitation projects in Pakistan. We are
the first local company to carryout external
tensioning to strengthen an existing bridge
super-structure.
Ghazi Ghat Bridge – External post-
tensioning of cable in the deck recess.
We have also successfully completed a number of projects where we have lifted bridge
decks for bearing replacements with our locally developed flat jacks. In some cases we have
lifted bridge super-structure directly through the girders. In these projects diaphragms that
are generally employed for lifting were found under-capacity for jacking the decks.
Chiniot Bridge – Three lifting jacks with
lifting capacity of 70 Metric Tons each placed
under bridge girder with over all height of
only 45 mm.
Lastly, Stronghold has been pivotal in the development of the post-tensioning industry in
Pakistan. From the production of PT supplies to providing stressing and grouting services,
a number of companies in operation in this line are founded by former employees of
Stronghold. While we take pride in our role as seen by many as an institution, we look
forward to continuing with our ambition in the development of new sectors with introducing
latest technologies to the construction industry in Pakistan.
7
2. OUR SERVICES
We offer a range of services that include the following:
• Stressing and grouting of post-tensioned structures e.g. bridges, buildings, dams, etc.
• Supply and installation of post-tensioning sheaths and anchorage set – wedges, trumpets and
anchor blocks
• Stressing of pre-tensioned structures including cable installation
• Stressing and grouting of ground anchors
• Design and consulting services for temporary structures e.g. pre-tensioning yard
• Structural rehabilitation and heavy load lifting
• Supply of imported ground anchors, bridge bearings and expansion joints
We are a strong team with many of our staff with 25 plus years of diversified experience
gained on major infrastructure projects. Given our large staff strength and equipment
inventory we are by far the biggest company in Pakistan offering prestressing services and
are capable of handling multiple projects simultaneously anywhere across the country.
Post-tensioning 31/0.6″ Cable – DHA Karachi. Pre-tensioning Mono-Strand – Gulpur Hydro Power Project, AJ&K.
Stressing in progress – Karachi Green Line. Deck lifting – Bridge on Islamabad Muree
Highway undergoing rehabilitation
8
3. PRESTRESSING PRODUCTS
We offer the following products for mono-strand and multi-strand applications.
1. Trumpets
2. Anchor Blocks
3. Couplers
4. Wedges
5. Sheaths both flattened and round
6. Ground Anchors
Some of our product samples are shown below.
Trumpet and Anchor Block for post-tensioned slabs and other multistrand flat cable
applications.
Trumpet and Anchor Block for post-tensioned multistrand cable applications.
9
Coupler for multi-strand cable Imported wedges for 0.5″ and 0.6″strand
Flat sheath for post-tensioned slab cable Round sheath for multi-strand cable
We manufacture our products under strict quality control program in our facility in Karachi
and Lahore that has a combined working space of over 20,000 square feet. We regularly
get our raw material tested in nationally recognized laboratories like the University of
Engineering and Technology Lahore, Peoples Steel Mills Karachi, Delta Laboratories
Karachi etc. All our products satisfy relevant requirements of major international codes and
standards such as the AASHTO and EN., and have been successfully used since 1985 in
over 10,000 bridges to date across Pakistan.
10
11
12
4. PRESTRESSING EQUIPMENT
Our prestressing equipment includes hydraulic jacks, pumps, grouting machines and some
ancillary equipment. Prestressing jack ranges from mono-strand jacks that are typically used
in post-tensioned slabs and in pre-tensioning applications to multistrand jacks that are
generally employed for post-tensioning in bridges and other heavy civil structures.
4.1. Hydraulic Jacks
We have a large selection of hydraulic jacks to stress a range of different cable sizes. Our
jacks possess the universal ability to stress any form of cable composed of wires or strands
that is individually anchored by means of wedges. Whatever the pattern or angular
disposition assumed by the cable, Stronghold jacks can stress a given strand with only 30cm
of end projection irrespective of the strand orientation.
Stronghold jacks are designed to seat wedges forcibly by means of hydraulic lock-off that
ensures uniform draw-in when transferring load to the cable. The draw-in limit for the
Stronghold system is 7mm.
Operating sequence of Stronghold Jack
Locate temporary bearing plate over anchor
plate. Position indexing template on
projecting end of cable and advance the Jack.
In this position the cable is ready for stressing
with all its elements separately and
simultaneously gripped by the Jack’s internal
wedges
The cable is extended to specified load and
elongation.
The anchorage wedges are advanced by the
template which also seats them forcibly,
under pressure from the Jack’s lock-off
mechanism.
The Jack is retracted, automatically releasing
the stressing wedges. It is then removed from
the cable end.
13
Mono-Strand Alevin Jacks:
A range of mono-stressing jacks of different strokes and force range has been developed
and thoroughly tested, incorporating the Stronghold features of front-gripping and hydraulic
lock-off. These jacks have multiple applications such as in prestressing yards, for
ground/rock anchors, circular stressing of plastic-coated unbonded strands, etc. The
following details relate only to the post-tensioning applications of the Alevin jacks which
are commonly used in conjunction with the Stronghold multi-stressing equipment.
Multi-Strand Jacks:
Stronghold system was officially
launched in 1974 at the FIP Convention in
New York, USA. It was among the
leading few systems in the world at the
time that was developed for multi-strand
prestressing. Since its launch it has been
incorporated in innumerable projects
world-wide with many notable structures
including cable-stay bridges being built on
the Stronghold system.
G-800 Stronghold Jack
CTT Project – Barrios de Luna Bridge, Spain. Stronghold Stays used.
14
CTT Projects – Weirton-Steubenville Bridge, USA and Water Towers, Kuwait.
Stronghold multi-strand system has been developed for a range of jacks that are capable of
delivering a maximum jacking force ranging from 60 metric tonnes to 1600 metric tonnes.
These jacks are classified as G series jacks and labelled as G-60 to G-1600 respectively.
Their dimensional details are provided in Table 4-1.
Table 4-1: Jack dimensional details
Note: From time to time, we update our equipment inventory based on the market needs.
Therefore, in addition to our Stronghold jacks we also carry stressing equipment from other
vendors that are custom made and compatible with our Stronghold system. Accordingly, we
are in a position to take on any prestressing related work without requiring any third party
assistance/equipment.
15
De-tensioning Jacks:
De-tensioning jacks are employed in pre-tensioning
applications when the strands projecting beyond the
precast section that has attained its desired concrete
strength have to be de-tensioned. Our inventory includes
such jacks with de-tensioning capability upto 1000 metric
tonnes and 300mm stroke.
De-tensioning jack in operation during casting of pre-tensioned bridge girders
4.2. Hydraulic Pumps
Stronghold pump Type-B are the commonly used pumps to operate the Stronghold pre-
stressing jacks. These pumps operate at high pressure for stressing and low pressure for
retracting. A double control valve separates stressing and lock-off operations, the latter
being preset before delivery. A manual relief valve enables pressure to be gradually reduced,
so ensuring uniform transfer of jacking force to the tendon. A large capacity oil tank is
incorporated fitted with a tubular indicator gauge. The pump is mounted on a pair of wheels
for maximum mobility.
Table 4-2: Type-B Pumps – Capacity
16
4.3. Grouting Machines
Stronghold grouting machines MX-5 and MX-7 are the two models for grouting
applications with different capabilities.
Model MX-5
It is the most commonly used model and
weighs 770 lb. (350 Kg) when empty. It
has two chassis wheels plus a front caster
for greater mobility over irregular ground.
A second caster is mounted for towing the
machine horizontally. Two vertically
mounted pans of 3.17 cu. ft. (90 litres)
capacity each ensure continuous mixing
and delivery to the pump. This has a triple
worm drive for pumping the grout
continuously to the point of injection. The
MX-5 will develop a maximum pressure
of 220 Psi(1.52 MPa) and a maximum
delivery of 53 cu.ft. (1500 litres) per hour.
Model MX-7
The MX-7 is an electrically driven high pressure grout injection machine incorporating two
horizontally mounted independent mixing pans of 9.36 cu. ft. (265 litres) capacity to ensure
continuous delivery. The machine will develop a maximum pressure of 234 psi (1.61 MPa)
when displacing an optimum grout output of 2.74 cu. ft (76 litres) per minute. Overall
dimensions are 2.23m x 0.87m x 1.5m.
17
4.4. Ancillary Equipment
Some ancillary equipment comes in handy to facilitate the execution of prestressing
operations. Among such equipment includes strand pushing machines.
Stronghold Pushing Machines:
There are alternative ways to fabricate cable of which pushing individual strands of precise
length is the most practical. Strands may be threaded into sheathing cast into concrete or
before the sheathing is installed. Electrically motorized machines are most common but
restricted in performance to relatively short cable of limited curvature.
Hydraulically operated machines are required for every long cable or cable with reverse
curves, when the speed can be varied and threading reversed if necessary. In either case a
thimble end of the strand to avoid snagging with the sheath wall or binding with other
strands. Although mechanical threading is generally used for cable made in-situ, the method
is limited when duct lengths or number of strands are excessive or subject to multiple
curvature. In all other circumstances mechanical threading is undoubtedly more simple and
economical.
18
5. PROJECTS – PRESTRESSING WORKS
In the following section some of the projects completed by Stronghold are presented.
While Stronghold has been involved in providing prestressing services and supplies in
over 10,000 bridges to date, a selective list of our projects is included in Appendix-B.
PAKISTAN GULPUR HYDRO POWER PROJECT-AJ&K
This project is about construction of a 102-megawatt run-of-the-river hydropower plant. It
is located on the Poonch River that is approximately 167 kilometers south-east from
Islamabad and 28 kilometers upstream of the Mangla Dam Reservoir.
The project General Contractor, a joint venture between two Korean companies – Daelim
Industrial Co., Ltd and Lotte Engineering Construction Co. Ltd., contracted Stronghold as
a subcontractor for all prestressing related works on this project. Further, Stronghold was
also contracted to provide complete design for the pre-tensioning yard that was set-up at the
construction site to fabricate box girders for a bridge that spans over the weir walls.
A view of the project site during construction – Weir walls and pretensioning yard visible
19
Pretensioning yard with two girder lines designed by Stronghold.
In total 66 box girders were fabricated successfully with all pre-tensioning works completed by Stronghold. Each cycle produced 6 girders with turn around time of about 3 days per cycle.
During pre-tensioning operation – consultants with stronghold team present verifying
the stressing works
All prestensioned girders after being launched to their respective positions on the wier walls
were transversely post-tensioned by Stronghold. Special anchor blocks were also designed
and fabricated by Stronghold for this application.
20
Weir wall cable – Dead anchorage being prepared by Stronghold technician.
The weir walls were post-tensioned with 20/0.6″ cables that were embedded with dead
anchorages at one end while the live ends were anchored in a specially designed end block
in the weir wall that itself was heavily post-tensioned in the vertical and the horizontal
planes. In total, 756 cables were prepared for the 7 weir walls. Though the PT design of the
weir walls were based on the DSI System, the stressing and grouting works were carried out
by Stronghold.
Preparation in progress for post-tensioning the main cable of the weir walls .
21
KARACHI METROBUS PROJECT
The Karachi Metrobus is the largest of the bus rapid transit project in the country with a
total length of 112.9 km. The Metrobus comprises of five different bus lines namely the
Green Line, Orange Line, Blue Line, Yellow Line and Red Line with Green Line being the
biggest and the latest edition to the Metrobus system.
Stronghold provided all prestressing
supplies excluding strands, and stressing
and grouting services for the entire
Metrobus Project.
The elevated bridge sections across the
project were constructed using box-girder
as well as I-girder sections. Prestressing
cable from 10/0.5 to 37/0.5 were used.
Given the large number of bridges with
different span configuration in this
project, both single end and double end
prestressing has been carried out in the
bridge girders.
Stressing was carried out with 420 tons to
800 tons jacks with Type B2 pumps while
grouting was completed using Stronghold
MX-5 grouting machine.
22
LAHORE METRO BUS PROJECT
As a major project constructed in Lahore,
and the first one of its kind in Pakistan, the
rapid bus transit project was planned in
several stages. The first stage stretching
over 27 km from Shahdara to Gajumata
was constructed by M/S Saadullah Khan
Brothers.
For this major segment of the project
Stronghold provided all post-tensioning
material supplies excluding strands, and
carried out stressing and grouting.
Stronghold G-300 and G-400 jacks were
used for carrying out stressing with Type
B2 pumps. The girders had spans upto
30m and were stressed with 10/0.6″ cable.
The project was inaugurated in 2014. It
was planned in 2011 by local authorities
in conjunction with Turkish experts as it
was modelled after projects like the
Istanbul Metrobus System.
23
LYARI EXPRESSWAY KARACHI
One of the major projects of its kind in
Pakistan, Lyari Expressway is a 38 km
long freeway constructed along Lyari
River in Karachi. It by-passes the city’s
busy corridor starting from Sohrab Goth
and ending at Mauripur.
The expressway has multiple elevated
segments with simple and continuous span
post-tensioning from 25m to 80m.
I-girders and box girders utilizing cable
from 8/0.5″ to 24/0.5″ were used in the
construction of the elevated bridge
segments.
All stressing and grouting services and
prestressing supplies other than strands
were provided by Stronghold. In addition,
66 pot bearings were also provided by
Stronghold in this project.
24
MULTAN METRO PROJECT
The project involved construction of a 18.5 km long dedicated bus route with some
segments totaling 12.5 km being constructed above grade. Cast-in-situ box girder section
were used in the construction of the 12.5 km long above grade segment.
About 70% of post-
tensioning related work
and supplies other than
strands for this project
were delivered by
Stronghold.
The bridge segments had
27-30m spans that were
constructed with box
girder sections. For post-
tensioning 18/0.6″ and
21/0.6″ cable were
employed. Single-end
prestressing was carried
out with 500 ton jacks.
The project was funded
by the Government of
Punjab.
It’s construction began in May 2015 and the project was
completed with metro services being commenced in
January 2017.
25
ZERO POINT INTERCHANGE ISLAMABAD
Considered as the largest of its kind in the
country, Zero Point Interchange is located
in Islamabad at the intersection of
Kashmir Highway and Faisal Avenue.
It was constructed by Maqbool Associates
(Pvt) Limited at a project cost of about
PKR 4 Billion.
All prestressing services and supplies
excluding strands for the interchange were
provided by Stronghold in this project.
In addition Stronghold also provided
stressing and grouting services for
imported VSL ground anchors – 3/0.6″ to
7/0.6″. Ground anchoring was carried out
for soil stabilization around an existing
monument.
26
KPT FLYOVER KARACHI
KPT flyover bridge is located at a busy
intersection connecting traffic travelling
on M.T Khan Road, Jinnah Bridge and
PIDC Bridge.
The bridge was built at a cost of about
PKR. 73 million. It has 21 spans in total
with spans in the range of 30-35m. The
superstructure was constructed using cast-
in-situ box girder sections with
prestressing cable upto 24/0.5.
PT design on this project was based on the
CCL System. However, given the
complexity of this project, Stronghold was
contracted by relevant authorities in
taking a lead role of handling PT related
issues and getting all post-tensioning work
executed under its supervision. In
addition, Stronghold was also contracted
in providing post-tensioning sheaths on
this project.
In Pakistan, this was one of the first few bridges that were built as a multi-level structure.
Further, the nature of road layout where multiple merging and exiting ramps are provided
at the bridge was a unique element of this flyover interchange.
27
RATHOA HARYAM BRIDGE MIRPUR- AJ&K
The longest bridge in AJ&K, the Rathoa
Haryam Bridge is nearly 5 km long that is
constructed across the reservoir channel of
Mangla Dam. It connects the city of
Mirpur with Islamgarh.
Stronghold provided all post-tensioning
supplies except for strands and carried out
all stressing and grouting on this project.
The bridge was constructed by a Chinese
construction firm - Xinjiang Beixin Road
& Bridge Construction Co., Ltd. It has 40-
45m long spans that are prestressed using
10/0.5″ to 14/0.5″ cable s with Stronghold
G-400 jacks.
Transverse prestressing in the bridge deck
slab and diaphragms was also carried out
on this project by Stronghold with 4/0.5″
cables.
28
Bridge Over Chenab,
Talibwala
I-Girder Bridge
18 Spans of 46 M.
Contractor:
Ghulam Rasul& CO.
Malir River Bridge
N-5 Sec 1.
I-Girder Bridge
13 Spans of 24.7 M
Contractor:
J & P (Overseas)
Bridge Over Indus,
Hyderabad
I-Girder Bridge
18 Spans of 46 M.
Contractor:
Sachal Eng. Works
Kech Bridge Turbat
I-Girder Bridge
30 Spans of 15.1 M.
Contractor:
Saadullah Khan & Brothers
29
Bridge Over River
Indus Connecting
Larkana – Khairpur.
I-Girder Bridge
26 Spans of 46.8m
Contractor:
Sachal Eng. Works.
Bahria Town Bridge at
Abdullah Shah Ghazi,
Karachi.
Cast-in-Situ Box Girder
8 Spans, 26-40m
Contractor:AA Quality
Builder
Thallair Bridge Over
River Poonch, Kotli
AJ&K
Segmental Construction
2 spans, 68m
Contractor:
ZK&Associates
Jhirk-Mulla Katiar
Bridge Over River
Indus
I-Girder Bridge
36 Spans of 49.6m
Contractor: Kainat
Enterprises
30
6. STRESSING & GROUTING PROCEDURE – GENERAL
METHOD STATEMENT
6.1. Fixing Anchorage
Anchorage comprises of three components – trumpet, anchor block, and wedges. The first step in
anchorage fixing is trumpet installation.
Trumpet is buried in the concrete section at each end of the girder where cable have to be anchored.
It is fixed on to the end plate of the shuttering at a desired angle given on the relevant drawings.
For fixing the trumpet two diagonally located holes in the trumpet base plate are provided that are
used for fixing the trumpet onto the shuttering before concreting. A soft board packing is placed
between the trumpet and the shuttering to prevent any laitance from going into the anchorage.
The installation of the block and the wedges are carried out after cable installation has been
completed. These are discussed in the following section.
6.2. Fixing Ducts & Threading of Cable
The duct shall be laid to the lines indicated on the drawing and shall be securely fixed in position
with binding wires using either onto special chairs or to stirrups. The distance between supports
should not be more than a meter.
Joints between duct and anchorage shall be adequately and securely taped using waterproof plastic
tape to prevent the ingress of laitance from the concrete. If HDPE is used as ducting the desired
length is obtained by connecting different pieces of the HDPE using sockets which are welded to
the two pieces with the help of a special HDPE welding machine which ensures a complete leak
proof joint.
The duct shall be carefully inspected immediately prior to concreting in order to ensure that the
alignment is correct, the joint secure, and the duct undamaged and unblocked.
The cable are made by cutting the required number of strands using a high-speed disc cutter. Length
of cable shall be worked out as per the given cable profile plus a minimum 60 cm. Where our
supplementary jacks are used for cable greater than 24/0.5 a minimum of 100 cm shall be added
instead of 60 cm. Cable shall be tied with binding wire or tape every meter or so depending on the
cable size. Threading of cable can be done manually by either pushing them from one end or by
using a pulling sock. As an alternate strand pushing machine can also be used. The strand pushing
machine, main features of which are given in this brochure, pushes one strand at a time. The tip of
the strand is covered with a steel cap like a thimble so that it does not damage the duct and each
strand is pushed through the ducting from one end of the cable to the other and once the given
strand reaches its desired location it is cut off from the coil .
31
During cutting of strand special care has to be exercised to ensure that the direction of the rotation
of the disc cutter is the same as the lay of the strand. If the strand is cut in the opposite direction
the wires of the strand will open up during cutting.
6.3. Stressing of Cable
1. PREPARATION OF CABLE.
Once the concrete has attained the requisite strength for transferring the pre-stressing load on to the
girder, the cable that have already been cut to desired length are prepared. At each end of the girder
beyond the trumpet the cables are projected a minimum of 30 cm. In some cases where our
supplementary jacks are used for cable greater than 24/0.5 a 50 cm projection is required. The
cable must be cleaned first by using a compressor to remove any muck etc from the duct. It shall
be moved manually or with a chain pulley too and fro a few times to ensure that there is no blockage
due to concrete or laitance.
2. THREADING OF ANCHOR BLOCKS AND FIXING OF WEDGES.
The anchor block which has a number of
conical holes depending on the size of the
cable to be stressed shall be threaded on to
the projecting strands. For example, for 10,
11, or 12 strand cable a block having 12 holes
shall be used. Similarly, for 8, 9 strand cable
a block with 9 holes shall be used, for 6 and
7 strand cable a block with 7 holes shall be
used and so on and so forth.
After the blocks have been threaded at the
two ends of the tendon, the two piece wedges
are threaded on the individual strand and
tapped lightly so that these are seated
securely within the block in their respective
conical holes.
32
3. JACK & PUMP FOR STRESSING.
Stronghold Pakistan jacks and pumps shall be used for stressing the cable. The jacks have three
separate cylinders -cylinder for applying the prestressing force, cylinder for seating the wedges
forcibly and a cylinder which returns piston to the closed position and releases the internal wedges
in the jack.
Before the jack is threaded, a bearing ring on
which the jack would rest and a lock off plate,
which forcibly seats the wedges are threaded
on to the cable at the jacking end. Following
this the Stronghold jack is threaded into
position for stressing.
As the jacks are heavy they are typically
suspended off from a support frame.
However sometimes where it is not possible
to use a support frame a crane is used instead.
The jack is activated by a high pressure hydraulic pump with a capacity of pumping oil upto a
pressure of 800 Kg/cm2. This pump has three independent outlets and the appropriate outlet is
connected to the three cylinders in the jack by reinforced high pressure hoses.
33
4. STRESSING PROFORMA AND CALIBRATION OF GAUGES.
Stressing proforma are prepared based on the information provided by the consultants. This
proforma gives the maximum pressure which is to be applied to the cable being stressed and the
theoretically expected extension.
The pressure given on the proforma includes an allowance of 2% for the loss in pressure which
takes place between the gauge on the pump and the pressure which becomes available at the front
end of the jack for the actual application to the cable.
For simply supported girders, stressing is carried out from one end only as there is no technical or
other advantage of stressing such cable from both ends. However, if there are two cable one is
stressed from one end and the second one from the other end, for three cable two are stressed from
one end and the third one from the other end and so on so forth.
It is also not necessary to stress all the cable in one girder before moving to the next. For example,
if 10 girders are to be stressed, cable No. 1 and 3 from the same end, say end A of all 10 girder in
one line can be stressed first and then cable No. 2 can be stressed for all the girders after moving
the equipment to the other end, say end B. This can save time and inconvenience from shifting the
equipment back and forth between the girder ends after each stressing operation.
The gauge on the pump is calibrated when the equipment is sent out for stressing girders at various
sites. A calibration certificate giving the pressures which the gauge on the pump must attain to
apply actual pressures of 100. 200, 300, 400, 500, 600 and 700 Kg/cm2 is sent along with the
equipment.
5. STRESSING OPERATION
As a first step, the jack is activated by the pump with a pressure of upto 100 Kg/cm2 which is
considered as the starting point of the stressing operations. Marks are made on the jack cylinder
and the other end of cable so as to read the extensions at different pressures. The readings are started
at 100 Kg/cm2 to eliminate any slack in the tendon.
Readings are noted at 200, 300, 400 and 500 till the final pressure indicated in the stressing record
sheet is reached. From the first three readings the average extension for 100 Kg/cm2 pressure is
worked out and added to the extensions obtained at the final pressure. This is done to add the
extension which must have taken place when the cable was stressed from 0-100 Kg/cm2 and marks
were put on but readings were assumed to be zero, as shown on the stressing form.
After reaching the final pressure wedges are seated forcibly by injecting oil into the cylinder for
seating wedges, after which the pressure is slowly released and the apparent pull-in is measured.
From this pull-in the elastic recovery is deducted to arrive at the actual pull-in.
The apparent pull-in also includes the elastic recovery of the length of strand beyond the anchor
blocks. The jack grips the strand at a distance of 200 mm from the block, this free length becomes
longer by the amount of extensions obtained at lock off.
34
When the pressure is dropped from final stressing pressure say 600 Kg/cm2 after lock off and
release, the cable moves in due to two actions i.e. the movement of the wedges to grip the strands
and the loss of extension in the free length of strand beyond the anchor block due to its pressure
going down from 600 Kg/cm2 to 0. This later phenomenon is called elastic recovery and has to be
deducted from the apparent pull-in to arrive at the actual pull-in.
6.4. Grouting
After stressing has been satisfactorily completed on a number of girders the cable are prepared for
grouting by cutting the projecting strands leaving only about 20 mm pieces projecting beyond the
anchor blocks. The cable duct is cleared of any muck etc with the help of a compressor or high-
pressure water pump.
Both the ends of the cable are plugged by using concrete ensuring that the holes provided for
injecting the grout at the two ends are not clogged, a pipe for de-airing is left at the end away from
the grouting end.
Alternately specially fabricated steel grout bell caps can be used, which are bolted on to the trumpet
using the threaded holes. This allows grouting to proceed immediately after stressing is
satisfactorily completed.
The neat cement grout is prepared by adding cement gradually in the mixing drum of the grouting
machine, in which the requisite water has already been poured. If the project consultant has
specified any additive like expansive or anti-bleed agents, it shall be added as per its manufacturer’s
recommendation. After the cement is properly mixed and a uniform cement slurry is made, it is
sieved into the lower drum for pumping into the ducts.
It is important that the temperature of the slurry does not exceed 32 degree centigrade . If it does
then iced-water should be used in place of tap water to lower the temperature. It is also
recommended that during summer months grouting shall be done during the mornings when the
girder is relatively cool. If the girder is hot when grouting is done, rapid evaporation of water from
the slurry can take place that can make the grout very thick resulting in clogging.
The cement slurry is injected into the cable duct from one of its
end, say End A. Grout vents that are typically provided in the
trumpet shall be closed-off of the trumpet at the other end of
the duct, say End B once the injected slurry comes out at End
B with the same consistency with which it is pumped at End A.
The flexible pipe sticking out of the grout vent is tied and a
slight pressure (approximately 2 bar) is applied to ensure that
the grout has reached all the empty spaces.
After grouting is completed, the girder should not be moved for
at least 72 hours to allow grout to set properly before it is
disturbed.
Anchorage being sealed
after grouting completed
35
7. END BLOCK RECESS AND CLEARANCES
For the given Stronghold jacks end block recess dimensions are given in Table 7-1. The
tabulation assumes the correct jack as recommended in the relevant data tables in this
catalogue has been used. Where anchorages are borderline the nearest alternative to the
recommended jack may be considered. In all such cases the alternative jack size and stroke
must be considered, and if greater, allowed for by increasing the recess dimensions.
Table 7-1: End Block –
Anchorage Recess Dimensions
Dimension N shall be minimum 20mm.
M and N shall be minimum 20mm. Minimum
values of L and R must be observed to avoid
eccentric stress concentration behind the
anchorage.
Table 7-2: Minimum Clearance Requirements –
Sheath and Trumpet.
36
8. SELECTION TABLES – TENDON, TRUMPET, JACK
AND SHEATH
TABLE 8-1:
0.5Strand (12.7mm).
According to BS 5896.
37
TABLE 8-2:
0.6 Strand (15.24mm).
According to BS 5896.
38
TABLE 8-3:
0.5 Strand (12.7mm).
According to ASTM A-416.
39
TABLE 8-4:
0.6 Strand (15.24mm).
According to ASTM A-416.
40
9. TRUMPET & ANCHOR BLOCK- DESIGN DATA
DIMENSIONS
9.1. Standard Cast Trumpet
41
9.2. Fabricated Trumpet
42
43
9.3. Rib Cast Trumpet
44
10. DEAD ANCHORAGE - DESIGN DATA DIMENSIONS
10.1. Semi-Bonded Dead Anchorage
10.2. X Dead Anchorage
45
11. PRESTRESSING IN BUILDINGS
Post-tensioing in building structures has been
carried out in many countries around the world
since the early years of prestressing in
structural design.
Compare to reinforced concrete prestressing
offers several benefits in many cases. The most
common application of prestressing is in
structures where large span lengths with greater
open spaces are required. Inherently,
prestressed elements are relatively ligther.
Therefore, where prestressed beams and slabs
are utilzied it results in lighter column sections
and thereby lighter foundation for the given
structure. This brings economic benefits in
material savings, formwork and labour cost. In
tall structures thinner slabs translates into
reduction in the overall height of the building.
Conseqently prestressed buildings can offer
more number of stories compare to the regualr
reinforced concrete over the same structure
height.
Typically in slabs prestressing is carried out
using smaller cable sizes with 1 to 5 strands
each of 0.5 or 0.6 diameter. In bonded system
cables are provided in flat sheath and then
stressed using mono-strand jack. Cables are
grouted and the anchor block is sealed-off after
stressing operation is completed for corrotion
protection.
Schematic arangement of anchorage and
cable support shown.
Schematic arrangement of cable shown in a
slab.
46
In an unbonded system, prestressing is carried out using mono-strand cables that come in a protective
sleeve that encloses the given strand with a specialized grease. Typically the choice of system i.e.
bonded or unbonded is recommended by the design consultant based on a number of factors such as
weather, economics, etc.
Installed anchorage-bonded system Cable layout – bonded system
Anchorage – bonded system
Anchorage - unbonded system
47
12. BUILDING PT – ANCHORAGE DATA TABLES
12.1. Bonded System:
Note: 1=Wedge, 2=Anchor Block, 3=Trumpet, 4=Minimum Spiral Reinforcement, 5=Flat Sheath, 6=Strand
48
12.2. Unbonded System:
49
13. GROUND ANCHOR
Application for ground
anchors are widespread as
means of tying down a great
variety of structures. A
geotechnical study is first
required to determine the
degree of anchoring and
method of fixing the
structure according to
ground stability. Certain
application for ground
anchors are shown
diagrammatically on this
page.
Ground anchors may be
either permeant or
temporary, and a suitable
method of recovery in the
latter case must be studied
once their function is fulfilled. Anchorages may be bonded or
unbonded i.e. cement-grouted or greased. Any decision favoring
grouted tendons must first consider appropriate ways of grouting
by injecting through suitably placed ducting.
Bond Length
The construction of an
efficient ground anchor
needs adequate bond length
at the tendon base and this
can be ensured by grouting
that part of the bore from
which the tendon derives its
stability. Cable length is
determined by the quality of
the soil and can be
calculated from the shear
transmitted by the grout
cylinder injected at the
initial stage. Cables
composed of strands
develop high friction with
the surrounding grout and
only slight deviation in
alignment between
component strands is
required to produce a good
anchor. Sleeve Type Anchor
50
14. REHABILITATION – HEAVY LIFTING
Stronghold provides heavy lifting services
on rehabilitation projects for bridges
particularly specializing on projects where
bearing pad replacements are required.
Our history with lifting decks dates back to
1990’s when we completed our first lifting
project with the two bridges on the
Islamabad-Muree Highway.
Lifting operation was executed under the
supervision of NESAK Lahore. At each
end, the span was lifted using 8 jacks under
the diaphragm, all activated by one high
pressure pump. The bridge was clamped to
avoid its displacement in the longitudinal as
well as in the transverse direction during
jacking.
Deflectometers capable of measuring uplift
of 1/100th of a mm were attached to each
one of the four girders of the bridge. The
maximum difference of uplift between
adjacent girders was kept within ±2 mm as
required by the project consultant. The
actual operation from start to end at each end
of the girder took less than an hour.
Set-up before lifting – Jacks, deflectometer,
shims and bearing pad under girder visible
Bridge lifted, bearing removed and laitance
being chiseled before placing new pad.
Bridge on Islamabad-Muree highway being jacked for bearing pad replacement.
51
15. LIFTING EQUIPMENT
Stronghold has special flat jacks ranging from 40 ton lifting capacity to 200 ton lifting capacity
and of different over-all heights. We are in a position to undertake lifting jobs independent of
any foreign assistance both technically and equipment wise. We have available with us over 100
jacks of different capacity at present.
The tallest jack has an overall height of 325mm
with a lifting capacity of 200 tons. These are
typically utilized when adequate space is
available for jacking.
Where available space is limited our smaller
jacks e.g. 40 tons jacks with overall height as
little as 30 mm are utilized.
52
16. PROJECTS – REHABILITATION
Stronghold has lifted a large number of bridge superstructures and successfully replaced
hundreds of bearings in rehabilitation projects across the country. Details on some of these
projects are as follows.
Khushab Bridge: In this 14 span bridge over river Jhelum, the available gap between girder
soffit and top of transom for placing lifting jacks was hardly 40 mm. Stronghold locally
developed flat jacks with over all height of only 30 mm and successfully lifted all 14 spans of
the bridge. The diaphragms of this bridge were in bad condition and could not be used for jacking.
The project was challenging as the 30 mm thin jacks had a very limited lift, about 8mm. Given
the limitation during transfer of load from jacks to shims during each lifting cycle i.e. closing of
the jacks putting the shims underneath and lifting the bridge again, it was noticed that almost all
of the lift was getting lost in each cycle. Stronghold developed a special technique for transferring
the load on to the shims, and with this method at least a net uplift of 5 mm was ensured for every
load transfer cycle which finally ensured the success of the project.
Lifting jacks, shims underneath the girder and dial gauge for measuring up lift
Talibwala II Bridge: Stronghold undertook the lifting of eighteen span of this bridge with each
span weighing about 1,800 tons. Deck supported on temporary supports which had been provided
under the twelve girders of the bridge framing into the end-diaphragm was lifted while temporary
supports being removed and deck reseated on the three high load carrying capacity pot bearings
also supplied by Stronghold in each of the eighteen spans. Under internal girders 8 hydraulic
jacks were placed and activated by one pump while 4 jacks under external girders were placed
and activated by another pump. The uplift and the lowering operations were monitored by
sophisticated measuring devices capable of measuring 1/100th mm of movement. It was ensured
that the differential uplift/lowering of adjacent beams did not exceed 2 mm to avoid damage to
concrete due to the stiffness offered by the diaphragm & deck slab.
53
Ghazi Ghat Bridge: Stronghold teamed up with M/S Kingcrete Builders who were the main contractors for the rehabilitation of this bridge over River Indus near D.G Khan.
In this bridge adequate space was not available to place the lifting jacks and shims underneath
the girders, therefore lifting had to be executed through the diaphragm where larger clearances
were available. However, the condition of diaphragms particularly at the girder-diaphragm
connections were very poor and porous, and it was feared that many girders would shear off
from the diaphragms during the lifting operation.
Stronghold prepared a proposal to get around
this challenge by carrying out temporary
external post-tensioning of the diaphragm to
strengthen it. The proposal was accepted and
external post-tensioning along with bridge
deck lifting was successfully executed by
Stronghold. This strengthening of the
diaphragm turned out to be an important factor
in the success of the project.
Moulds, lifting jacks and shims used in the project.
The bridge used to be closed to traffic from
6 PM to 6 AM on alternate days to allow
replacement of the bearing pads. With proper
planning and sufficient number of jacks,
pumps and other special equipment,
Stronghold was able to adhere to the tight
schedule and completed lifting of all the
spans within the scheduled time to allow M/S
Kingcrete Builders to do the necessary
operations for the rehabilitation of this
bridge.
During lifting operation-Ghazi Ghat
Bridge
S.M Textile Factory Building- SITE: Another interesting project handled by Stronghold in this
field involved releasing the loads from the columns and foundation of a single-story building in
SITE area Karachi. The aim was to enable the contractor to strengthen the foundation as
additional two stories were planned to be constructed on top of the existing structure. Stronghold
worked with the project consultants M/S Alliance Consultants and successfully executed the
lifting operations for this building. We utilized our 75 ton capacity jacks to release the slab load
off the columns. Temporary supports were constructed for the lifting jacks. Once the column
and foundation strengthening was completed by the contractor the slab load was retransferred
back to the existing columns. It was the first project of its kind in Pakistan where without
any demolition such a task was successfully undertaken.
54
A snapshot of some of our lifting projects:
1. Salt Range Bridge (BD 12C5) on Lahore Islamabad Motorway Project
Lifting of the bridge superstructure.
Span length =30 M
Maximum lifting height =150 mm
Sets of Flat Jacks with lifting capacity of 80 Tons were placed under one end of each of
six girders that were then lifted to different heights as per the directions of consultant.
2. Salt Range Bridge (BD12C5).
The project required lifting of the transom as well after lifting the girders.
Total weight lifted = 600 tons
Maximum lifting height = 110 mm
Two hydraulic jacks each 300 Tons capacity were used to lift the transom to the desired height
and its weight transferred from the defective piles which were cut and removed to alternate
foundations.
3. Two Bridges on Islamabad Muree highway
Span lengths = 15 M
Total weight of each span lifted = 200 tons
Lifting height = 20 mm
4. Talibwala Bridge II
Span length = 52 M
Total weight lifted = 1800 Tons
In total 12 girders with 52m span lifted using hydraulic jacks with capacity of 200 tons
placed under each end of the girders.
5. Soan Bridge near Rawalpindi - Lifting of 1 span to relocate the pad which
shifted out of position.
Span length = 44.4 M
Total weight of span lifted = 900 tons
Jacks used for lifting = 70 ton capacity
55
6. Bridge Over River Jehlum at Khushab.
Span length = 47 M
No. of spans = 14
No. of lifting operations = 28
Total weight per span = 1,000 tons
No of pads replaced with new ones = 112 All 4 beams at one end of a span were lifted simultaneously by using sets of 70 M. Tons
capacity jacks, 40 mm clearance was available between beam soffit and transom and these
very specially designed jacks were placed in that 35 mm (11/2-) clearance. We also imported
bearing pads for this project.
7. Ghazi Ghat Bridge near D.G Khan.
Span length = 44.24 M
No. of spans = 22
Total weight per span = 1000 tons
No. of pads replaced = 176
On this project jacks ranging in capacities from 60, 150 &200 tons were used. We imported
bearing pads for this project to replace the existing old ones.
8. Chiniot Bridge
Span length = 39.4 M
No. of spans = 06
Total weight per span = 1,200 tons
No. of pads replaced with new ones = 72
All 6 girders of a span were lifted simultaneously on one transom by using 200 & 75
tons capacity jacks.
9. Lifting of 2 spans of Balleli Bridge Quetta on N-25
We have successfully carried out lifting and lowering operation of this old steel bridge in
Quetta. The piers of this bridge were to be re-constructed for which temporary supports
were provided under all beams. Our work was to lower these beams on newly constructed
piers. We used our 70 ton jacks for this purpose and both spans of bridge were lifted from
temporary supports and lowered to new piers.
56
10. Lifting of bridge over river Sutlej at Bahawalpur for replacing old bearing pads with
new ones.
Span length = 48.77 M
No. of spans = 12
Total weight per span = 1,200 tons
No of pads replaced with new ones = 96
All 4 beams of each span were lifted simultaneously on one transom by using 75 tons
capacity jacks.
11. Lifting of Silyaza Nullah Bridge at KM 322+363.605 on Zhob Mughalkot Section
Span length = 30 M
No. of spans = 03
Total weight per span = 650 tons
No. of pads replaced with new ones = 24 nos.
The lifting was carried out for removing and replacing bearing pads. Jacks of 70 ton
capacity were placed underneath diaphragms to carry out the lifting.
12. Lifting 12 spans of Simtua Nullah Bridge on Zhob-Mughal kot Section
Span length = 25 M
No. of spans = 12
Total weight per span = 500 tons
No. of pads replaced with new ones = 96 nos.
On each transom 8 beams were lifted simultaneously by using 70 tons capacity jacks.
Old bearings were replaced with new ones.
13. Testing on U-TUB Girder at Orange Line Lahore
Length of girder = 30 M
Width of girder = 5.7 M
Contractors = Maqbool - Calsons J.V.
Test was carried out under the supervision of NESPAK Lahore & Dr. Ali (UET Peshawar).
Used 20 jacks of 70 ton capacity. All jacks were activated with one pump. Girder was
monitored for deflection and cracking.
57
17. PROJECTS – BEARING REPLACEMENT
The following is a list of some selective projects in which bearing pad supply and replacement
has been carried out by Stronghold.
58
59
DESIGN NOTES
In the design of prestressed concrete members consideration is normally given to three sets of conditions or limit states namely:
1. Conditions at transfer, when the prestress is applied to the concrete
2. Conditions at working load (serviceability limit state) 3. Conditions at ultimate load (ultimate limit state).
Of these the third usually determines the dimensions of the section: the second establishes the magnitude of the prestressing force: and the first gives the tendon profiles and the details of the end block.
Calculation of losses The prestressing force applied to the end of a tendon at transfer is larger than that which acts at mid-span at transfer and under service conditions. Some of the losses of prestress occur at the time of prestressing while others take place over a period of months. Some vary with the distance along the member while others are constant throughout the length. The methods of calculation presented in the following are approximate and fairly simple. More complex methods are available, but they usually demand a disproportionate amount of time for their employment and produce only a spurious accuracy, since the assumptions made are of doubtful validity. As a general rule it is better to make simple calculations and to provide some leeway to allow the prestressing force to be varied if necessary to suit the actual job conditions. A few spare tones of stressing capacity on site is more valuable than a file of unduly detailed calculations in the office.
Losses at transfer (i) Loss due to friction
At any point distant x from the jacking end of a post-tensioned tendon the prestressing force is reduced, from Po at the jack to:
Px = Po e - (µα+kx) Px = Prestressing force at distance X from jack Po = Prestressing force at jack e = Base of natural logarithms µ = Coefficient of friction for curved portions of tendons α = Total angular deviation of tendon (in all planes) throughout distance x, in radians k = Wobble coefficient per unit length of tendon (to allow for friction due to inaccuracies in placing) The loss of prestress due to friction is therefore equal to
ΔP1 = Po [1 – e- (µα+kx)] Values of µ and k taken from BSCP 110 (1972), are given in Table I.
TABLE I: Data for tendon friction
Condition
µ
K (per meter)
For normally supported ducts Strong ducts with close supports
33 x 10-4 17 x 10-4
Circular construction: Steel moving on steel bearing attached to concrete Steel moving on smooth concrete Steel moving on steel rollers
0.25 0.45 0.10
Linear construction: Steel Moving on steel Steel moving on concrete Steel moving on lead Lubricated tendons
0.30 0.55 0.25 <0.10*
*Values for lubricated tendons depend to some extent on the tendon geometry.
Reduction of frictional loss by temporary overstressing The tendon force should not exceed 70% of its strength after it is anchored; but a temporary stress of up to 80% can be applied prior to anchoring. This not only reduces the frictional loss; it also provides a useful proof test load on both the concrete and the tendons, and the practice is to be recommended. When the overstress is removed reverse frictions occurs in the tendon, over a length near stressing end or ends (see upper curve in Fig. I). Complete reduction of the overstress is not necessary, since a part of the reduction is obtained by pull-in of the anchor wedges (see next section). If the tendon is curved near the jacking end, the length over which this reduction takes place is significantly shorter than for a straight tendon. (ii) Loss due to pull-in of wedges
In order to fully anchor the wedges at the jacking end of a tendon some movement of the tendon itself is needed. For the STRONGHOLD systems, the movements are typically 7mm. The movement produces a reverse fictions effect similar to that obtained by reducing the temporary overstress. It extends over the length w of the tendon given with sufficient accuracy by the expression
W = √ΔI .Es. As
ΔP
Where: ΔI is the pull-in (mm) Es is the elastic modulus of the prestressing steel, As is the cross-sectional area of the prestressing steel (mm2): ΔP is the rate of loss of force (kN/mm). This in turn is given by
60
Po - Px max.
x max.
for straight tendons. For tendons curved at the jacking end
ΔP = Po - Px
x
in which x, is the length to the end of the curved section and Px, is the prestressing force at that point. Once W is known the corresponding loss of prestressing force can be calculated as:
ΔP2 = 2 ΔP.W
EFFECT OF PULL IN
(iii) Losses due to elastic compression of the concrete
When tendons are tensioned successively, the stressing of each tendon causes some loss of prestressing force into those already stressed and anchored. The magnitude of the loss is given by the expression
ΔP3 = n-1
2n fcs As
Es
Ecj
Where; n: is the number of tendons that are tensioned successively fcs: is the stress in concrete adjacent to tendons [KN/mm2] As: is the cross-sectional area of the prestressing steel [mm2] Es: is the elastic modulus of the prestressing steel Ecj: is the elastic modulus of the concrete at the time of
prestressing
Delayed losses
The anchored prestress is reduced over a period of up to
two years by time – dependent movement of the steel and
concrete.
(I) Loss due to relaxation of tensioned steel
Relaxation is analogous to creep: it is a loss of force which
takes place in tensioned steel when the length of the
tendon is kept constant. The magnitude of the loss
depends mainly on the stress in the tendon and on the
service temperature. Low relaxation steels are available, at
a slight cost premium, for normal temperature, BSCP 110
recommends a maximum relation loss of 8% of the
prestressing force, when the anchored force is 0.7 Pu,
reducing linearly to zero when the anchored force is s 0.5
Pu
(II) Loss due to shrinkage
Values due to shrinkage in BSCP 110 to allow an approximate assessment of shrinkage to be made. Typical values for concrete stressed between 7 and 14 days after casting are: 70 x 10-6 (humid exposure) 200 x 10-6 (normal exposure at 70% relative humidity) Therefore the loss of prestressing force due to shrinkage is: ΔP5 = 200 x 10-6 x Es x As (normal exposure at 70% relative humidity)
ΔP6=70 x10-6x Es x As (humid exposure) In which Es and As are the elastic modulus and the cross-sectional area of the prestressing steel. (III) Loss due to creep The creep of concrete is proportional to the stress applied to it. Its magnitude may be taken as:
36 x 10-6 x 40 x fcs
fci
Where; fcs: is the stress in the concrete adjacent to the steel fci: is the cube strength at transfer Then the loss of prestressing force is:
ΔP6 = 36 x 10-6 x 40 x fcs
fci
. Es . As Where; A is the cross-sectional area of the prestressing steel. When fci exceeds 40 N/mm2 the expression reduces to:
ΔP6= 36 x 10-6 x fci x Es x As
61
END BLOCK REINFORCEMENT
(I) Bursting forces
A simplified version of a design method originally proposed by Guyon is given in BSCP 110. Each anchor is assumed to be symmetrically placed within a small individual end block, and the bursting force is then obtained from Table II in this, YO is half the side of the individual end block Ypo is half the side of the loaded area Fbst is the tensile bursting force Pk is the load in the tendon. This is assumed to equal the
maximum jacking load; for non – bonded tendons the greater of the maximum jacking load or the tendon force at ultimate load should be used.
TABLE II BURSTING FORCES IN END BLOCK
Ypo/Yo 0.3 0.4 0.5 0.6 0.7
Fbst/Pk 0.23 0.20 0.17 0.14 0.11
(II) End bending
Within the beam, the prestress is distributed linearly from top to bottom. At the ends it is concentrated at the anchors which therefore act as the reactions to the distributed prestress. When the anchors are not themselves distributed over the whole of the end block, reinforcement may be needed to resist the tensile beam-bending stresses between upper and lower anchors. The effective overall depth of this vertical end-beam can be taken as half the actual depth of the beam itself.
(III) Calculation example
Bursting reinforcement For the block shown in Fig. III the relevant data are: Face size of Stronghold CS-13 anchor: 180 mm Square Prestressing force at each anchor: 900 kN Reinforcement yield stress: 410 N/mm2 Hence; Yo = 125; Ypo = 90; Ypo/Yo = 90/125 = 0.72 From Table II: Fbst/Fk = 0.11; Pk = 900 kN; Hence, Fbst = 0.11 x 900 = 99 kN Stress in reinforcement = 0.87x410=357 N/mm2, so that area of reinforcement per anchor = 99000/357=277 mm2 in each direction. Provide 4 no. 10 mm hooked bars (314 mm2) in each direction. [Fig IV].
62
63
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
01.
TALIBWALA CHENAB 45 18 12/0.5”
04/0.5” 21.
GUDDU FEEDER RD: 367 28 2 12/0.5”
02.
KUNDIANI BRIDGE
45
2
11/0.5”
22.
RURKAN BRIDGE 27 2 09/0.5”
12/0.5”
03.
DATA NAGAR
39 1 11/0.5” 23.
RICE CANAL RD: 223 26.8 4 12/0.5”
04.
SEHWAN ARALWAH
37.5 1 12/0.5” 24.
ROHRI CANAL RD: 278 26.2 3 12/0.5”
05.
MIRWAH CANAL
33.5 1 11/0.5”
25.
NAWABSHAH BRDIGE – MAIN BR.
26
4
06/0.5”
06.
MIRWAHA CANAL
23 1 12/0.5” 26.
N.W. CANAL RD: 40
25.9 3 12/0.5”
07.
KATCHA KHU MULTAN
33 2 10/0.5”
12/0.5” 27.
JAMRAO CANAL RD: 265
25.9 2 12/0.5”
08.
ZARDDRLU
BALOCHISTAN
32 4 12/0.5” 28.
ROAD RAIL OVERPASS H.B.P
25 3
12/0.5”
10/0.5”
09.
QANDEEL BRIDGE
31 1 11/0.5” 29.
MALIR RIVER SEC. 1 24.7 13 12/0.5”
10.
MACH BRIDGE
31 6 12/0.5” 30.
LAHERWALI NADI
24.7 2 10/0.5”
11.
SAROTA NALA
3.05 1 12/0.5” 31.
MANGLA MOWER STATION GIRDERS 24.5 17 12/0.5”
12.
SHINKARI BRIDGE
30.5 1 11/0.5” 32.
STEEL MILL I/C.
24.4 2 12/0.5”
13.
SAIFUL MINOR
30.5 1 33.
QUAD CANAL RD: 358
24.4 3 10/0.5”
14.
ASTOL I
30 1 09/0.5” 34.
SATHIO WAH RD: 45 24.3 1 11/0.5”
15.
BIBI NANI BRIDGE
30 8 10/0.5” 35.
NARA CANAL RD: 465
24.3 5 12/0.5”
16.
ASTOL II
30 1 09/0.5” 36.
PHULRA – N.W.F.P
24 1 12/0.5”
17.
TARBAH
30 1 11/0.5” 37.
NARA CANAL RD: 255
24 5 12/0.5”
18.
B.S. FEEDER SUKKUR
29 1 12/0.5” 38.
LYARI RIVER O MILE
24 6 08/0.5”
19.
DUBI MINOR
28.8 1 12/0.5” 39.
SARGODHA OVERHEAD BRIDGE
23.9 33 08/0.5”
20.
MURAD TALPUR BRIDGE.
28 1 12/0.5” 40.
RANIPUR SINDH
23.4 5 12/0.5”
64
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
41.
NUSRAT CANAL RD: 34
23.3 2 11/0.5” 61.
KHIPRO RD: 156
21 1 12/0.5”
42.
KINGRI BRIDGE
23 3 11/0.5” 62.
HAJNA SHAH
20.6 2 12/0.5”
43.
NARA CANAL RD: 68
23 4 09/0.5” 63.
ROHRI CANAL RD: 63
20.3 6 10/0.5”
44.
PISHEN LORA (QUETTA) 23 3
10/0.5”
11/0.5”
64.
SULEMAN SHAH RD.
15 5&1
04/0.5”
05/0.5”
45.
NARA CANAL RD: 96
23 4 09/0.5” 65.
NAWABSHAH BRIDGE – DISTT.
RD:
20 17
11/0.5”
10/0.5”
08/0.5”
46.
ROHRI CANAL RD: 834
23 3 12/0.5” 66.
KALRI BAGAR CANAL H.B.P
20 7 10/0.5”
47.
NARA CANAL RD: 97 23 3 09/0.5” 67.
NARA CANAL RD: 227 20 7 10/0.5”
48.
PHULLELI RD: 22
22.9
3
12/0.5”
68.
GHOTKI FEEDER 20 1 11/0.5”
49.
SCHEME 33 SUPER HIGHWAY
22.9 2 12/0.5” 69.
PHULLELI CANAL I H.B.P. 20 9 10/0.5”
50.
SCHEME 33 SUPER HIGHWAY
22.9 2 12/0.5” 70.
NEW LAL MIRWA 19.8 2 09/0.5”
08/0.5"
51.
DADU CANAL RD: 39.83
22.6 2 12/0.5”
71.
NARA CANAL RD: 269
19.8
2
12/0.5”
52.
GARHI YASEEN SINDH 22.5 3
12/0.5”
11/0.5” 72.
CHAKORA NALLAH RD: 2 + 500
19.5 2 12/0.5”
53.
ROHRI CANAL RD: 786
22 3 09/0.5”
73.
FAIZ GANJ RD: 265
19 2 12/0.5”
54.
CIRCULAR RAILWAY
21.6 2 12/0.5” 74.
GHOREWAH RD: 32
19 1 12/0.5”
55.
MUSKIN II 21.5 1 07/0.5” 75.
CHAKORA NALLAH RD: 0 + 300 18.4 2 12/0.5”
56.
NAWABSHAH BRIDGE –
SANGHAR RD
21.5 15 11/0.5” 76.
ALI BAHAR WAHRD: 10
18.4 1
09/0.5”
08/0.5”
57.
LUSHKHUM BALA
21.5 1 07/0.5” 77.
ROHRI CANAL RD: 806 18.3 4 09/0.5”
58.
NUSRAT CANAL RD: 156
21.4 2 12/0.5” 78.
MALIR RIVER - KARACHI
18
&
20
13
12/0.5”
11/0.5”
10/0.5”
07/0.5”
59.
KARO KHAU
21.4 4
12/0.5”
10/0.5”
79.
NARA CANAL RD: 447
18.3
2
09/0.5”
60.
RICE CANAL RD: 40 21.3 5
12/0.5”
10/0.5” 80.
PHULLELI RD: 24 18.3 4 09/0.5”
65
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
81.
SINDH CANAL RD: 22
18 1 09/0.5”
08/0.5” 101.
HARO RIVER BRIDGE
30.4 5 10/0.5”
82.
WARA CANAL RD: 280
18 2 09/0.5” 102.
ARSHAD NALLAH 28 1 12/0.5”
83.
DEFENCE SQUASH COMPLEX
– SINGLE T
17.6 41 05/0.5” 103.
HANA NALLAH
28 4 12/0.5”
84.
NARA CANAL RD: 101
15.8 2 10/0.5” 104.
K.W.F. CANAL MAIN KHA 25.9 1 12/0.5”
85.
KECH – KAUR MAIN BR.
15.1 26 10/0.5” 105.
M.N.V. DRAIN
25.3 3 12/0.5”
86.
KECH – KAUR SEC BR.
15.1 4 10/0.5” 106.
VRD ON MNV 25 1 11/0.5”
87.
LUBANO SUKKUR 14.7 1 07/0.5” 107.
DRB ON MNV
25 2 12/0.5”
88.
MEVA SHAH BRIDGE
14.7
13
07/0.5” 108.
M.N.V. DRAIN RD: 66
24.3 1 11/0.5”
89.
NARA CANAL RD: 99
14.4
2
08/0.5”
109.
M.N.V. DRAIN RD: 900
24.3 1 11/0.5”
90.
BUND MINOR
13 1
09/0.5”
110.
MATLI BY PASS.
24 3 11/0.5”
91.
VEEHO WAH RD: 96
12 1 09/0.5” 111.
DHOULA NALLAH:
23.9 4 10/0.5”
92.
JAIL CHOWK BR. EXT.
9 1 12/0.5” 112.
MNV DRAIN RD: 8.5
23.4 2 12/0.5”
93.
CHENAB RIVER N-5 46 16 12/0.5” 113.
NATIONAL HIGHWAY I/C 23 2 12/0.5”
04/0.5”
94.
PHULKU NALLAH N-5 40&35 4
11/0.5”
114.
EXTENSION B. S. F. 21.5 1 07/0.5”
95.
BULANGAH NALAH
50 1 12/0.5”
115.
BR. AT MINCHINABAD
20.7
2
12/0.5”
96.
AKBARI BRDIGE
37 3 12/0.5”
04/0.5” 116.
BR. AT MINCHINABAD
20 2 08/0.5”
97.
K.W.F. CANAL BRIDGE 33.5 1 12/0.5” 117.
BRIDGE OVER MIRWAH 18.3 2 11/0.5”
10/0.5"
98.
K.W.F. KOTPUR
32 1 12/0.5”
118.
BRIDGE OVER RICE CANAL
15.3
6
10/0.5”
99.
DINGA SEC. 7B N-5
31 3 10/0.5” 119.
CANAL LARKANA BY PASS
BRIDGE AT RAHIM YAR KHAN
15 2 10/0.5”
100.
K.W.F. CANAL HADIL SHAH
30.5 1 12/0.5”
120.
SARIAB LORA
26.6 3 07/0.5”
66
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
121.
ROHRI CANAL RD: 951
20 12/0.5”
141.
MNV DRAIN RD: 233 25
1
12/0.5”
122.
GUNIWAH 18 2 12/0.5” 142.
ARTHAR CANAL RD: 7
17 2 12/0.5”
123.
MALOT BRDIGE
31 9
12/0.5”
04/0.5”
143.
WARAH CANAL RD: 109
30
1
12/0.5”
124.
CHAKORE NALLAH 19 3 09/0.5” 144.
MNV DRAIN RD: 53 24 2 12/0.5”
125.
SORANGE RAOD
19
7 11/0.5”
10/0.5” 145.
ARTHAR CANAL RD: 53
23 3 12/0.5”
126.
SQUASH CLUB DEFENCE
SINGLE T
18
41
07/0.5”
04/0.5”
146.
WARAH CANAL RD: 109
19 2 12/0.5”
127.
GHAR CANAL RD: 4 26 2 12/0.5” 147.
HADIARA DRAIN
22&23 4 08/0.5”
128.
KHIPRO CANAL RD: 248
18 2 11/0.5”
148.
DADU CANAL 20 3 10/0.5”
129.
MAHIWAH RD: 86
31 1 12/0.5”
149.
CHICHANA N-55 30.6 3 10/0.5”
130.
GHAR CANAL RD: 20
24 2 11/0.5”
150.
NAZIMABAD WIDENING
17.7 3 12/0.5”
131.
LORA NADI
17 2 08/0.5”
151.
LYARI DHOBI GHAT 15.3 13 06/0.5”
132.
RICE CANAL RD: 299
24 1 12/0.5”
152.
KARIMABAD WIDENING
10 3
06/0.5”
&
04/0.5”
133.
NARA CANAL RD: 76
22 2 09/0.5”
153.
MOCH GOTH BRIDGE 23 4 10/0.5”
09/0.5”
134.
COMSER NALLA 40 1 12/0.5”
04/0.5”
154.
AKRAM WAH CANAL
17.3 2 10/0.5”
135.
WIRHAB BRIDGE
29
5 12/0.5”
155.
NARA CANAL RD: 85
21.3 4 10/0.5”
136.
MNV DRAIN RD: 0
24 1 11/0.5”
156.
NARA CANALRD: 96
11.5 2 10/0.5”
137.
MNV DRAIN RD: 16 24 1
11/0.5”
157.
BOLAN BRIDGE
30 1 09/0.5”
138.
MNV DRAIN RD: 47
24 1 11/0.5”
158.
KOTRI INTERCHANGE
28.5 2 12/0.5”
04/0.5”
139.
RICE CANAL RD: 80
26
3
12/0.5”
159.
LASSAN NAWAB N.W.F.P. 24 1 12/0.5”
140.
DADU CANAL RD: 0/4.5. 20 3 12/0.5”
160.
TUR MURGHA BRIDGE 18.3 8 12/0.5”
67
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
161.
INDUS RIVER BRIDGE
(H.B.P) 45 18 12/0.5”
04/0.5” 181.
BRIDGE OVER SAIF-UL-LAH CANAL
36.27
1 12/0.5”
162.
SHAHEED E MILLAT
FLYOVER 14 & 16 80
09/0.5”
to 12/0.5”
182.
2ND OVER HEAD BRIDGE AT
SAHIWAL
39.92
16.81
25
11/0.5” 10/0.5”
163.
SHIKARPUR BRIDGE 31&16 2 12/0.5” 183.
OVER HEAD BRIDGE AT SARGODHA 23.92
13.71
11
04/0.5”
08/0.5”
164.
GAWADAR NALLANT RD.
31
1
12/0.5”
11/0.5”
184.
KUNRI CANAL BRIDGE 18.21 1 12/0.5”
165.
MARIAM ZAI
25 3 11/0.5” 185.
GHOTKI FEEDER RD: 78 26.36 3 12/0.5”
166.
WAZIRABAD OVERHEAD
BRIDGE
19 &21
2
09/0.5”
04/0.5”
186.
GHOTKI FEEDER RD: 110 21.94
3
09/0.5”
167.
RAHMANI BRIDGE
37 3 12/0.5” 187.
WIDENING OF LAT NALLAH BRDIGE 16.43 5 12/0.5”
168.
CHASHMA ACHO ZAI 15 6 11/0.5” 188.
OVERPASS AT FAISLABAD
11.8
to
20
17 12/0.5”
04/0.5”
169.
HONEY DAN BRIDGE
24 10 12/0.5” 189.
KOSHAK BRIDGE 25 1 12/0.5”
170.
KUMBRI RIVER BRIDGE 31 3 11/0.5” 190.
BRIDGE ON KB FEEDER KOTRI 12.72 2 12/0.5”
171.
NARI RIVER BRIDGE
31
3 11/0.5” 191.
BRIDGE OVER RICE CANAL 22.85
30.47
4
10/0.5”
172.
TARKHA BRIDGE
27
4 11/0.5” 192.
PINYARI CANAL BRIDGE RD: 114 22.85 3 12/0.5”
173.
SHAKARDARA ROAD
BRIDGE
20.75
18.75 9 07/0.5” 193.
DADU CANAL RD: 535 18.21 1 10/0.5”
174.
DINA BRIDGE
33.8 2 12/0.5”
194.
DADU CANAL RD: 546
16.68 1 12/0.5”
175.
KHARIAN BRIDGE
19.5 2 09/0.5”
04/0.5” 195.
MIR WAH BRIDGE RD: 71 26.63 1 12/0.5”
176.
RATIAN BRIDGE
12.9
26.9
2
09/0.5”
10/0.5” 196.
BRIDGE AT FP. BUND RD: 198 26.63 1 12/0.5”
177.
BEGGARI CANAL BRIDGE
23.5 4 10/0.5” 197.
JOHI DADU CANAL 22.78 7 12/0.5”
178.
ARJA BRIDGE
30.4 2 08/0.5”
10/0.5” 198.
BRIDGE OVER WATER WAY &
MANJHAND
26 1 11/0.5”
179.
GUL PUR BRDIGE
33.52 1 12/0.5” 199.
NUSRAT CANAL BRIDGE 19 1 12/0.5”
180.
NIHINGE BRIDGE 18.21 12 09/0.5” 200.
BRIDGE OVER THADO NALOO MALIR 22.85 4 11/0.5”
68
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
201.
CHANNI ALAM SHER
OVERHEAD
20 1 11/0.5” 221.
LAHORE GUJRANWALA 19 7 12/0.5”
202.
BRIDGE ON RICE CANAL
30.4 21 11/0.5” 222.
WAZIRABAD 7-7
12.4 3 10/0.5”
203.
CHOHI BRIDGE 26 2 10/0.5” 223.
AJIGAR NADI SEC - 2
25 3 10/0.5”
204.
SUKKUR OVERHEAD BRIIDGE 27.5
27.9 4 12/0.5” 224..
DINA NALLAH BRIDGE
29.85
27.85 5
10/0.5”
10/0.5”
205.
BRIDGE OVER NUSRAT
WAHCAL RD: 187
20.57 2 12/0.5”
04/0.5” 225.
LEI BRIDGE
43 4 12/0.5”
04/0.5”
206.
BRIDGE OVER NUSRAT
WAHCAL RD: 172
19.04 2 07/0.5” 226.
WIDENING OF LEI BRIDGE
16.43 5 07/0.5”
207.
PHULLELI CANAL BRIDGE 16.36 2 08/0.5” 227.
JARI WAH BRDIGE
14.75 1 11/0.5”
08/0.5”
208.
PESHAWAR OVERHEAD
BRIDGE
30 4 12/0.5” 228.
MASHERO BRIDGE 14.75 1 11/0.5”
08/0.5”
209.
LAHORE BYPASS 25 & 38 2 08/0.5”
to 12/0.5” 229.
KAMAL WAH BRIDGE
14.75
1 11/0.5”
08/0.5”
210.
FAIZ BUX WAH BRIDGE 25 1 12/0.5” 230.
SULHANI WAH BRIDGE
13.75 1 09/0.5”
08/0.5”
211.
BRIDGE ROAD CONNECTING
ZONES OF PORT QASIM
AUTHORITY
26.75 18 08/0.5” 231.
SANGI MINOR BRIDGE 9 1
10/0.5”
08/0.5”
212.
REHEBILTATION OF CONT
NO.2KARACHI-HYDERABAD
FROM KMB 1 TO 78
21.84
1
12/0.5”
232.
JANIB WAH BRIDGE 15.75 1 10/0.5”
08/0.5
213.
BHUMBER NALLA BRIDGE 25.4 11 10/0.5” 233.
GARIKO BRIDGE
15.75 1 09/0.5”
08/0.5”
214.
THADO NADI. SEC – 1. 25 5
10/0.5” 234.
KORAI WAH BRIDGE 14.75 1 09/0.5”
215.
LAGLEJI SEC – 1. 23.5 6 12/0.5” 235.
PIRWAH BRIDGE 13.75 1
09/0.5”
08/0.5”
216.
JARAMDO BRIDGE 23.5 5 12/0.5” 236.
LILLY ROAD OVERHEAD BRIDGE
KARACHI.
18.28
19.5 20
07/0.5”
12/0.5”
217.
CHENAB RIVER BRIDGE 46 16 12/0.5” 237.
TARIQABAD OVERHEAD BRIDGE AT
DFAISLABAD
13.4
to
26.6
14
07/0.5”
to
12/0.5”
218.
PHULKA NALLAH BRIDGE 40&35 7 11/0.5” 238.
MANGLA BRIDGE AZAD KASHMIR
31.17
6 18 11/0.5”
219.
DINGA SECTION 7-B
31
3 10/0.5” 239.
EXTENTION OF BRIDGE OVER LYARI
RIVER AT RASHID MINHAS ROAD
19.5 2 10/0.5”
12/0.5”
220. UPPER CHENAB BRIDGE
23.6 4 10/0.5” 240. BRIDGE OVER NALA CANAL
23.36 3 10/0.5”
69
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
241.
BRIDGE NO.2 ON WANI
MANDA ZIARATA SANHAWI
ROAD
19.7 3 08/0.5” 258.
ROHRI BY PASS 20.73 6
05/0.5”
06/0.5”
07/0.5”
11/0.5”
242.
B.S.LINK CANAL PATOKI
18.56
4
10/0.5” 259.
LAHORE ISLAMABAD ROAD 22.35 5 10/0.5”
243.
GUJJAR KHAN BRIDGE
27
19.93
1
2
10/0.5”
08/0.5” 260.
NOWSHEARA HASAN ABDAL
CARRIAGE WAY
16
20 16
09/0.5”
12/0.5”
244.
CHINOT BRIDGES:
WEST CHANNEL BRIDGE
39.4 06 12/0.5” 261.
CONTRACT NO. KOTRI MANJHAND N-
55 7
11/0.5”
10/0.5”
245.
EAST CHANNEL BRIDGE
39.4 06 12/0.5” 262.
D.G. KHAN TO TONSA CONTRACT NO.
10 N-55
30
3 10/0.5”
246.
ROAD RAIL OVERPASS
BRIDGE 39.4 04 12/0.5”
263.
CONTRACT NO. 12, KARAK GAMBILA
SECTION, N-55
30
4 10/0.5”
247.
ROAD RAIL OVERPASS
APPROACH SPANS
19.7 04 09/0.5” 264.
CONTRACT 12-B, N-55
30 7 12/0.5”
10/0.5”
248.
JHELUM RIVER BRIDGE AT
KHUSHAB
47 14 11/0.5”
04/0.5” 265.
SOAN BRIDGE 44 3
12/0.5”
04/0.5”
249.
OVERHEAD BRIDGE AT
RAILWAY LARKANA
15.9 44 10/0.5” 266.
KAHUTA BRIDGE 20 3 09/0.5”
250.
BUHAN OVERPASS 25 17 10/0.5” 267.
BRIDGE OVER RIVER INDUS ON
SUKKUR BY PASS
42.75 5 12/0.5”
4/0.5”
251.
BRIDGE OVER 5-L DISTRICT
19 1 11/0.5” 268.
APPROACH VIA DUCT ON SUKKUR BY
PASS
20 4 11/0.5”
252.
MINOR BRIDGE CHALBAT
NOWSHERA SECTION
16
to
40
22
10/0.5”
11/0.5”
12/0.5”
269.
UNDER PASS ON SUKKUR BY PASS 9.9 5 7/0.5”
4/0.5”
253.
KHURRAM RIVER BRIDGE 30 30 11/0.5” 270.
2 LANE BRIDGE OVER RICE CANAL 19.82 1 9/0.5”
254.
BRIDGE OVER 9-L, DISTRICT 31.75 18 12/0.5” 271.
4 LANE BRIDGE OVER RICE CANAL
20
1
9/0.5”
255.
BRIDGE OVER HUDDIYARA
RAIN
26 1 07/0.5” 272.
4 LANE BRIDGE OVER DADU CANAL
20 1 9/0.5”
256.
CONT NO. 7016/M-B-R-P 16.75 11 10/0.5” 273.
2 LANE BRIDGE OVER DADU CANAL 19.85 04 09/0.5”
257.
GHOTKI BRIDGE 19.9 5 12/0.5”
274.
4 LANE BRIDGE OVER N.W CANAL 20
05
09/0.5”
70
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
275.
2 LANE BRIDGE OVER N.W
CANAL 19.82 04 09/0.5” 292
BRIDGE ON LARALAI ROAD QILA
SAIFULLAH D.G. KHAN
30 02 10/0.5”
276.
4 LANE BRIDGE OVER OBAL
WAH CANAL
19.82 02 10/0.5”
09/0.5” 293.
SAKHI SARWAR BRIDGE MULTAN 30 02 10/0.5”
277.
2 LANE BRIDGE OVER OBAL
WAH CANAL
20 07 10/0.5”
09/.5
294.
BRIDGE ON RURAL ACCESS ROAD
PANJGUR
20
25
05
11/0.5”
278.
TALIBWALA BRIDGE II 52 18
12/0.5”
04/0.5” 299.
BRIDGES ON CHABLAT NOSHERA
SECTION
25
30 26 12/0.5”
279.
LIAQUATABAD FLY OVER
KARACHI
18
to
30.5
26
12/0.5”
09/0.5”
08/0.5”
300.
BRIDGE LASMO OIL FIELD SEHWAN 40
30 04 12/0.5”
280.
RASHID MINHAS FLY OVER
KARACHI
18
to 35
50X2 12/0.5”
10/0.5” 301.
BRIDGES ON QUETTA SIBBI ROAD
15
to 24
25 12/0.5”
10/0.5”
281.
UNIVERSITY ROAD FLY OVER
KARACHI 26.9 28 12/0.5” 302.
BRIDGES ON KOHAT TUNNEL
PROJECT
30
25
25 12/0.5”
282.
LILY ROAD OVERHEAD BRIDGE
KARACHI
19.5
36 20
07/0.5”
12/0.5” 303.
BRIDGES ON ZERA METER RAWAT
ISLAMABAD HIGHWAY
24
30
to
48
12/0.5”
11/0.5”
283.
BRIDGE OVER RAILWAY
OVERHEAD KHANEWAL
24
40 06
12/0.5”
11/0.5”
10/0.6”
304.
BRIDGE OVER LORA NULLAH AT
SPINNY ROAD QUETTA
30 01 21/0.5”
284.
GARHI SHAHU BRIDGE LAHROE
24
22 16
09/0.5”
07/0.5”
04/0.5”
305.
BRIDGES ON PINDI BHATTIAN
FAISALABAD MOTORWAY (M-3)
47.30
20.25 28
12/0.5”
10/0.5”
285.
CAVAKRY GROUND FLYOVER
LAHROE
30 19 12/0.5” 306.
SHAHFAISAL COLONY FLYOVER
KARACHI
22
20
17
50
12/0.5”
11/0.5”
09/0.5”
286.
FLYOVER AT KATCHERY
CHWOK MULTAN
25 17 09/0.5”
08/0.5” 307.
BRIDGE AT AZAD PATTAN-
RAWALKOT ROAD
33 02 15/0.5”
12/0.5”
287.
SHERPAO BRIDGE LAHROE 30
22 12
11/0.5”
12/0.5” 308.
BRIDGE OVER HALAR RIVER AZAD
KASHMIR 42 01
12/0.5”
04/0.5”
288.
PORT QASIM AUTHORITY
BRIDGES KARACHI
20
to
30
12 12/0.5”
10/0.5” 309.
BRIDGE OVER NALDAT AT KHUZDAR
KHARAN ROAD
24.9 06 11/0.5”
289.
EXTENSION OF LASBELLA
BRIDGE KARAC HI
12
28
12/0.5”
11/0.5”
10/0.5”
310.
BRIDGE OVER RAILWAY CROSSING
TANDO ALLAH YAR
22
02
12/0.5”
290
WANI MANDA BRIDGE AT
ZIARAT
24 03 09/0.5” 311.
BRIDGE OVER AKRAM WAH CANAL
NEAR HYDERABAD
19 02 11/0.5”
291.
FLYOVER AT GT ROAD
PESHAWAR
19.9 06 09/0.5”
71
LAHORE – ISLAMABAD PAKISTAN MOTORWAY (M-2) (TWO BRIDGES AT EACH LOCATION)
SECTION – I
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
S.NO.
NAME OF PROJECT
SPAN
(M)
NO. OF
SPANS
CABLE
USED
312.
SHADHRA DISTRIBUTORY
BRIDGE
20 2 11/0.5” 329
DEGH NULLAH BRIDGE 25 2x6 10/0.5”
313.
JOLA DISTRIBUTORY BRIDGE
25
2
10/0.5”
330
FLOOD WATER WAY BRIDGE
25
2x3
10/0.5”
314.
UPPER CHENAB CANAL BRIDGE
& CHICKOKI MALIAN
DISTRIBUTORY BRIDGE
25 2x6 10/0.5” 331.
FLOOD WATER WAY BRIDGE 25 2x5 10/0.5”
315.
QADIRABAD BALOKI LINK
CANAL
30 2x6 12/0.5”
332.
NIKI DEH BRIDGE
25 2x5 10/0.5”
316.
UPPER GUGERA CANAL
BRIDGE
30 2x3 12/0.5” 333.
SHEIKHUPURA DRAIN
30 2x1 12/0.5”
317.
MANAWALI DISTRIBUTORY
CANAL
25 2 10/0.5” 334.
MANGORI DRAIN 25 2x2 10/0.5”
318.
MIAN ALI BRANCH CANAL
BRIDGE
16 2x2 10/0.5” 335.
WATER DRAN BRIDGE
25 2 10/0.5”
319.
MALLARY DISTRIBUTORY
BRIDGE
20 2 11/0.5” 336.
AJNIANWALA DRAIN BRIDGE 20 2 11/0.5”
320.
RAKH BRANCH & LOWE
CHENAB CANAL BRIDGE
30 2x4 12/0.5” 337.
SALAR DRAIN
16 2x3 10/0.5”
321.
JHANG BRANCH CANAL BRIDGE 25 2x3 10/0.5” 338.
AHMADPUR KOT NIKKA
BRIDGE
20 2x2 11/0.5”
322.
SHAHSDIA SANGLA HILL
OVERHEAD BRIDGE
25 2x3 10/0.5” 339.
FLYOVER, QILLA SATTAR
SHAH MURIDKE RD.
30 2x2 12/0.5”
323.
WAZIRABAD SANGLA HILL
OVERHEAD BRIDGE
16
& 20
3
10/0.5”
11/0.5”
340.
FLYOVER, CHICKOKI LMALIAN
MURIDKE RD.
30 2x2 12/0.5”
324.
LAHORE SHEIKHUPURA ROAD
30 2x2 12/0.5” 341.
FLYOVER, SHEIKUPURA
HAFIZBAD ROAD
30 2x2 12/0.5”
325.
FLOOD WATER WAY BRDIGE 25 2x6 10/0.5” 342.
FLYOVER, FAROOQABAD
GUJRANWALA RD.
30 2x2 12/0.5”
326.
FLOOD WATER WAY BRDIGE 25 2x6 10/0.5” 343.
FLYOVER, HAFIZABAD
CHOWKI SUKHERI
30 2x2 12/0.5”
327.
BHED NULLAH BRIDGE
25
2
10/0.5” 344.
FLYOVER, SUKHEI JALAPUR
BHATIAN
30 2x2 12/0.5”
328.
FLOOD WATER WAY BRDIGE 25 2x6 10/0.5” 345.
INTERCHANGE SHEKUPURA
GUJRANWALA
16
25
16
2x1
2x2
2x1
10/0.5”
10/0.5”
10/0.5”
72
SECTION - II SECTION - III
S. NO. NAME OF BRIDGE SPAN (M) NO. OF SPANS
CABLE USED
S. NO. NAME OF BRIDGE SPAN
(M) NO. OF SPANS
CABLE USED
348 KHADER CANAL BRIDGE 20 2x2 11/0.5"
372 JALAPUR CANAL BRIDGE 20 2 12/0.5”
349 LOWER JHELUM CANAL BRIDGE (SOUTH BRIDGE)
16 23 10/0.5"
373 PIND DADAN KHAN KHUSHAB OVERHEAD BRIDGE
16 20 16
2 2 2
10/0.5” 11/0.5” 10/0.5”
350 HUJJAN DISTRIBUTORY BRIDGE
20 2x1 11/0.5"
374 WATER COURSE BRDIGE 20 2 11/0.5"
351 LOWER JHELUM CANAL BRIDGE (NORTH BRIDGE)
20 2x3 11/0.5"
375 WATER COURSE BRDIGE 20 2x3 11/0.5"
352 SHAHPUR BRANCH CANAL BRIDGE
16 2x3 10/0.5” 10/0.5” 10/0.5”
376 WATER COURSE BRDIGE 16 2x3 10/0.5” 10/0.5” 10/0.5”
353 SARGODHA BRIDGE MALKWAL OVERHEAD BRDIGE
16 23 16
2x1 21 2x1
12/0.5”
377 BD - 12C-6 16 23 16
2x1 2x1 2x1
12/0.5”
354 BUDHI NULLAH BRIDGE 30 2x3 12/0.5"
378 BD - 12C-7 30 2x3 12/0.5"
355 SEM NULLAH BRIDGE 2x1 10/0.5”
379 BD - 12C-4 25 27 20/0.5”
356 SEM NULLAH DRAIN BRIDGE
30 2x2 12/0.5”
380 NARWAH KAS BRDIGE 30 2x4 12/0.5”
357 NULLAH BRIDGE 30 2x2 12/0.5”
381 NARWAH KAS BRDIGE 30 2x4 10/0.5”
358 SEM NULLAH BRIDGE 30 22 12/0.5”
382 NIKKA ULLAH BRDIGE 25 2x4 10/0.5”
359 MONA DRAIN BRIDGE 30 2x2 12/0.5”
383 DHARAB RIVER BRIDGE 25 2x5 12/0.5”
360 FLYOVER, THATTI BHELOL KOT BELA
30 2x2 12/0.5”
384 FLYOVER, BAGA SIAYAL AHMADABAD RD
30 2x2 12/0.5”
361 FLYOVER, SIAL CHOWK MINDH RANJHA
30 2x2 12/0.5”
385 FLYOVER, SAIDAN SHAH KALLAR KAHAR
30 2x2 12/0.5”
362 FLYOVER, MIDH RANJHA KOT MOMIN
30 2x2 12/0.5”
386 FLYOVER, KALLAR KAHAR - CHAKWAL RD
30 2x2 12/0.5”
363 FLYOVER, BHARBRAH – KOT MOIN RD
30 2x2 12/0.5”
387 FLYOVER, BALKASSAR MUNDEY RD
30 2x2 12/0.5”
364 FLYOVER, KOT MOMIN – SALAM RD.
30 22 12/0.5”
388 FLYOVER, BHAGWAL BALKASSR RD.
30 2x2 12/0.5”
365 FLYOVER, BHLWAL – GUJRAT RD.
30 2x2 12/0.5”
389 FLYOVER, BALKASSAR – DULLA RD.
30 2x2 12/0.5”
366 FLYOVER, SALAM – BHERA RD
30 2x2 12/0.5”
390 FLYOVER, BHAGWAL DULLA RD.
30 2x2 12/0.5”
367 FLYOVER, SALAM – BHERA RD
30 2x2 12/0.5”
391 INTERCHANGE LILA PIND DADAN KHAN RD.
16 25 16
2x1 2x2 2x1
10/0.5” 10/0.5” 10/0.5”
368 FLYOVER, BHALWAL – BHERA RD
30 2x2 12/0.5”
392 INTERCHANGE BALKASSAR CHAKWAL RD.
16 25 16
2x1 2x2 2x1
10/0.5” 10/0.5” 10/0.5”
369 FLYOVER, BHERA SHAHPUR RD
30 2x2 12/0.5”
370 INTERCHANGE PINDI BHATTIAN – HAFIZABAD RD.
30 2x1 12/0.5”
371 INTERCHANGE KOT MOMIN – SALAM RD.
16 25 16
2x1 2x2 2x1
10/0.5” 10/0.5” 10/0.5”
73
SECTION - IV BRIDGES ON ISLAMABAD-PESHAWAR MOTORWAY PROJECT (M-1)
S. NO. NAME OF BRIDGE SPAN
(M) NO. OF SPANS
CABLE USED
S. NO. NAME OF BRIDGE SPAN
(M) NO. OF SPANS
CABLE USED
393 PALCHARAN KAS BRIDGE
30 2x6 12/0.5"
410 INTERCHANGE CHAKRI RAWALPINDI, RD.
25 16
8 10/0.5"
394 WATER COURSE 25 2x2 10/0.5"
411 RAILWAY BRIDGE AT F. JUNG
16 20
8 11/0.5” 10/0.5”
395 WATER COURSE 25 2x2 10/0.5"
412 BRIDGE AT CHAINAGE 9-040
30 2 12/0.5"
396 WATER COURSE 25 2x2 10/0.5"
413 BRIDGE AT CHAINAGE 9-643
30 4 12/0.5"
397 SID RIVER BRIDGE 30 2x8 12/0.5"
414 FLYOVER AT CHAINAGE 10+956
16 30
8 12/0.5"
398 NIKKI WALA KAS BRIDGE
30 2x4 12/0.5"
415 BRIDGE AT TARAT 30 2 12/0.5” 10/0.5”
399 DRAIN BRIDGE 30 2x3 12/0.5"
416 FLYOVER AT CHAINAGE 15+983
16 25
8 10/0.5"
400 BASLAKAS NULLAH BRIDGE
30 2x4 12/0.5"
417 FLYOVER AT CHAINAGE 17+960
16 30
8 12/0.5” 10/0.5”
401 PATAN KAS BRIDGE 25 2x4 10/0.5"
418 BRIDGE I AT SUKKA 30 2 12/0.5"
402 PATAN KAS DISTRIBUTORY BRIDGE
25 2x2 10/0.5"
419 BRIDGE II AT SUKKA 30 2 12/0.5"
403 FYOVER, DULLAH NILA RD.
30 2x2 12/0.5"
420 FLYOVER AT CHAINAGE 24+617
25 16
8 10/0.5"
404 FLYOVER, NILLAH DULLAH KOWAT RD
30 2x2 12/0.5"
421 BRIDGE AT JABI 30 2 12/0.5"
405 FLYOVER, KATORIAN THALLAIAN RD
30 2x2 12/0.5"
422 BRIDGE AT GADAN 25 2 10/0.5"
406 INTERCHANGE CHAKRI RAWALPINDI, RD.
16 20 16
2x1 2x2 2x1
10/0.5” 10/0.5” 10/0.5”
423 BRIDGE AT DOTAL 20 4 11/0.5”
INCREMENTALLY LAUNCHED BRIDGES
S. NO. NAME OF BRIDGE SPAN
(M)
NO. OF
SPANS
CABLE
USED
407
2 BRIDGES OVER
JHELUM AT BHERA
COMPLETED EXCEPT
SOME 19/0.5" CABLES
30
50
2x2
2x15
12/0.5”
&
19/0.5”
408
2 BRIDGES OVER
SOAN AT CHAKRI
COMPLETED EXCEPT
SOME 19/0.5" CABLES
40
50
2x1
2x7
12/0.5”
&
19/0.5”
409
2 BRIDGES OVER
PANEAD CHAKRI
RAWALPINDI RD.
40
50
2x1
2x6
12/0.5”
&
19/0.5”
424 RAILWAY OVERHEAD
AT BURHAN
30
16 6
12/0.5”
10/0.5”
425 INTERCHANGE AT
BURHAN
20
16 8
11/0.5”
10/0.5”
426 HARD RIVER BRIDGE 30 26 12/0.5"
427 DHAL NULLAH
BRIDGE 25 4 10/0.5"
74
75
Head Office: Plot 7, Block 7 & 8, Maqbool Co-Operative
Housing Society, Shahrah-e-Faisal, Karachi, Pakistan.
Branch Office: Kala Khatai Road, G.T. Road, Shadra Town,
Lahore, Pakistan.
Tel: (+92 21) 3432 2090-91. Fax: (+92 21) 3454 3129
Web: www.stronghdpk.com
Email: [email protected]