Environmental Monitoring Report Annual Report Loan 2540-PAK February 2014–January 2015
Pakistan: National Highway Development Sector
Investment Program–Tranche 2
Qillah Saifullah–Zhob Road Project, ICB–3B (N–50)
Prepared by the Environment, Afforestation, Land and Social (EALS) Unit, National Highway
Authority (NHA) for the Asian Development Bank.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
Contents
1.0 Introduction .......................................................................................................................... 4
2.0 Activities of the project. ......................................................................................................... 4
3.0 Environmental Monitoring ..................................................................................................... 5
3.1 Environmental Monitoring Summary ................................................................................. 5
3.2 Noise ................................................................................................................................ 5
3.3 Drinking Water Quality. ..................................................................................................... 5
3.4 Air Quality. ........................................................................................................................ 5
3.5 Flora and Fauna. .............................................................................................................. 5
3.6 Borrow Areas .................................................................................................................... 6
3.7 Safety Provision ................................................................................................................ 6
4.0 Conclusion ........................................................................................................................... 6
Annexure
Annexure 1 Pictorial Profile of Project’s Operational Phase
Annexure 2 Environmental Monitoring Test Reports
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
KARACHI
Uthal
Bela
Khuzdar
Ratodero
Sukkur
Sibbi
DalbandinNok Kundi
Taftan
LakpassSariab Chowk
QUETTA
Chaman QilaSaifullah
LoralaiKuchlak
D.G.Khan
D.I.Khan
Awaran
Turbat
GWADAR
IRAN
AFGHANISTAN
KPK
PUNJAB
SINDH
Jiwani
Hub
Ormara
Pasni
Wad
Sorab
Kalat
Gabd
Dhan
asar
ZhobMughalkot
Dera Allah Yar
Basima
Nag
Panjgur
Hoshab
Kakkar
136
80
72
18
LOCATION MAP
91
N-50
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
4
1.0 Introduction The Qillah Saifullah - Zhob road project ICB-38, section N-50 is located at the main artery from
Kuchlack to D.I. Khan and within the administrative jurisdiction of district Qillah Saifullah and Zhob.
This Annual Environmental Monitoring Report (February 2014 – January 2015) presents the
findings for operational phase of the project.
The project involved the improvement and widening of the road ICB-3B (N-50) from Qillah Saifullah
to Zhob (150 Km) carriageway from the existing 3.65 meters to 7.30 meters (within the existing
right of way). The project was funded by the Asian Development Bank Loan No 2540-PAK National
Highway Development Sector Investment Program. With the improvement of this section of the
national highway N-50, trade activities have been enhanced and the general public has been
facilitated through considerable amount of savings against vehicular operating cost including lower
vehicle maintenance costs.
The main objective of this project was to facilitate people and goods transportation and promotion
of business activities like the establishment of real estate, small hotels, warehouses, cattle farms
and businesses on adjacent lands along the road alignment.
The area traversed by the project road comprises is agricultural. Wheat and vegetables are the
major crops cultivated here as well as fruits including grapes, apple and almond. The main source
of pollution in the project area is vehicular emissions due to heavy traffic movement, and
Suspended Particulate Matters (PM10) due to vehicular movement. Currently there is no major
industrial area, mineral processing unit or industrial mining unit operating in the project area, which
could enhance air and noise pollution. However during the operation period, necessary mitigating
measures have been adopted to minimize the emissions so that they comply with the National
Environmental Quality Standards (NEQS) limits through the implementation of Environmental
Management and Monitoring Plan.
2.0 Activities of the project.
Activities were carried out in an environmentally sound and sustainable manner. Specific Traffic
Management Plans (TMP) were developed and implemented as per requirement of EMP, for the
protection and safety of public and road users.
For registering any complaints from the local community or any complaint from the local
Government agencies regarding environmental pollution/land etc., a complaint register is made
available in NHA’s Qila Saifullah office.
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
5
3.0 Environmental Monitoring
3.1 Environmental Monitoring Summary
Environmental monitoring was carried out as per EMP compliance requirement during the
operation phase. Comprehensive monitoring of noise, air quality, soil and water was conducted
through an authorized laboratory as per EMP testing requirement frequency.
3.2 Noise
Noise monitoring was carried out as per requirements. On 20-06-2014 comprehensive monitoring
of the project was undertaken by PERAC labs Karachi, including measurement of noise level along
the road alignment. The noise levels were recorded between 75 to 80 dB, which conform to the
NEQS.
3.3 Drinking Water Quality.
Drinking water parameters were analyzed during the comprehensive monitoring on 29-04-2014
and were found conforming to WHO-guide lines and Pakistan Standards for Drinking Water
Quality. No adverse impact was noted on the quality of drinking water used by the community
living along the road alignment.
Table 1: Drinking Water Sampling Results of the camps side and urban areas.
CODE DESCRIPTION F.E. Coli Count/ml 1430 D/W1-Main Camp side
(215+500) NIL
1431 DW2- Sub Camp side (243+100 )
NIL
1432 DW3 –community drinking water (250+700)
NIL
1433 DW4-Urban area 255 R/S, community drinking water.
NIL
1434 Dw5-Urban area (263 +100), community drinking water
NIL
3.4 Air Quality.
The parameters of air emission were checked as per EMP testing frequency/ requirements. These
included particulate matter (PM10), SO2, NO2 and CO2 concentrations. These were compared with
NEQS. The recommended value of PM10 as per NEQ for 24 houres is 250 ug/m3.The Test reports
is attached as Annexure-2. The evolving of very fine dust particulate matters is mainly due to
heavy traffic volume or wrong side overtaking of public transport.
3.5 Flora and Fauna.
Safety sign boards depicting the speed limit and to alert drivers at wildlife crossing points have
been installed at various locations. No mortality of wild animals has yet been reported in the
operation phase of the project. Tree plantation is under process as per schedule.
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
6
3.6 Borrow Areas
All borrow areas have been closed. The last operative borrow was closed on 31st Oct, 2013, after
leveling of land. The Borrow Area Management Plan prepared for the project was followed during
excavation of materials from various borrows areas.
3.7 Safety Provision
Road markers, sign boards and cat’s eyes have been installed throughout the length of the project.
4.0 Conclusion
The agricultural land along the project alignment has not been damaged due to project activities.
The water courses crossing the road site at different locations have been protected from pollution
and contamination during the construction phase. Parameters like noise, air and liquid emissions
have been controlled to NEQS limits with continual efforts. Appropriate safety measures were
adopted for the safety of work force during marking and installation of traffic/safety sign boards. No
complaints regarding the environment have been received from the local community. Road
accident rate was minimal and no mortality was reported during the entire operation phase
reporting period.
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
7
ANNEXURE - 1
Pictorial Profile of Project’s Operational Phase
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
8
Project was inaugurated on 30 January 2014 by Honorable Prime Minister of Pakistan; Mian Mohammad Nawaz Sharif
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
9
Start point of N-50 project
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
10
Bridge picture
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
11
Safety Signboard
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
12
Safety Signboard
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
13
ANNEXURE – 2
Environmental Monitoring Test Reports
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
14
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
15
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
16
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
17
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
18
NATIONAL HIGHWAY DEVELOPMENT SECTOR INVESTMENT PROGRAM QILLAH SAIFULLAH – ZHOB (ICB‐3B) N‐50_______________________________________________________________
19