    Pack production planning & Material Transfers procedure

    Steps;

    1. Sale order creation

    2. Order BOM creation (assign of RM component)

    3. Sale Order Planning

    4. Conversion of planned order to Production Order

    5. Checking of Pur Req no for subcontracting with Offset

    6. Creation of Sub contracting PO with PR reference

    7. Transfer posting of stock to subcontractor(offset)8. Creation of sub contracting challan with Transfer posting Mat Doc

    9. Goods receipt for Subcontracting PO

    10. Reconcile the challan

    11. Closing of challan

    12. Production Confirmation of FPS-200 (Flat printed sheet from offset)

    production order

    13. Production Confirmation of final product

    14. Checking of sales order stock in stock overview

  • 8/8/2019 Pack Production Planning

    2/39

    1. Ensure sales order is complete with out any incompletion logs, check the

    details of configuration also

    2. Order BOM creation (assign of RM component

    Go to transaction code: CU51

    And input: sales order no and item no

    Now press enter to display the following screen

  • 8/8/2019 Pack Production Planning

    3/39

    Now click on printed sheet tab to view the entered configuration details in sales

    order

  • 8/8/2019 Pack Production Planning

    4/39

    Now click on result icon

    Now select any FPS-200 component which is inconsistent (Red X mark)

  • 8/8/2019 Pack Production Planning

    5/39

    Now click on find object button to view the following screen

    Now click on find object tab

  • 8/8/2019 Pack Production Planning

    6/39

    Select the required characteristics values to search for the material

    Now click on find in initial class button to display all the materials having these

    Characteristics values

  • 8/8/2019 Pack Production Planning

    7/39

    Now select the required material and click on Stock display to check the stock

    inventory

    now come back to the earlier screen and select the material by clicking on the

    Green tick mark

  • 8/8/2019 Pack Production Planning

    8/39

    Now the chosen material is assigned for the production in Order BOM

    Now save the Order BOM

  • 8/8/2019 Pack Production Planning

    9/39

    Sale Order Planning

    Go to transaction MD50

    And input the following

    1. Sales order no

    2. Sales ord item no

    3. Select planning mode as 3

    4. Select the control parameters

  • 8/8/2019 Pack Production Planning

    10/39

    Now press enter to Start the Planning run

    Now again press enter

    Planning is carried out for Main product

  • 8/8/2019 Pack Production Planning

    11/39

    Now click on Save

    Planning for the next subordinate component is started

    Press continue

  • 8/8/2019 Pack Production Planning

    12/39

    Planning for the subordinate component is carried out

    Again click on save

    Displayed screen indicates END of planning run

  • 8/8/2019 Pack Production Planning

    13/39

    Conversion of planned order to Production Order

    Go to transaction MD04

    Input the following

    Material (finished product)

    Plant:

    Now press enter

  • 8/8/2019 Pack Production Planning

    14/39

    In the displayed screen check the planned order listed out against the respective

    sales order

    Now double click on the planned order to view the pop up window

    Click on ->Prod.Ord if Full qty is to be produced orClick on -> PartConvProdOrder if part production is scheduled so that

    remaining qty is in planned stage only

  • 8/8/2019 Pack Production Planning

    15/39

    On clicking -> Prod.Ord

    Creation of production orders has begun

    Now double click on Final product Production order to check operations

    Now click on operations overview icon to view the operations sequence

  • 8/8/2019 Pack Production Planning

    16/39

    Any operations to be deleted select the operation and click on delete

    Now come back to the initial screen

    Now click on Release

  • 8/8/2019 Pack Production Planning

    17/39

    Release carried out message is displayed

    Now click on save to view the order no created

  • 8/8/2019 Pack Production Planning

    18/39

    Display of Production order and Pur Req no for Flat printed sheet

    Go to transaction CO03

    Input the Production order generated

    And press enter to view the COLLECTIVE ORDERS

    Now double click on FPS-200 Order to view the following Production Order

    Header screen

  • 8/8/2019 Pack Production Planning

    19/39

    Now click on Operations overview icon to display operations list

  • 8/8/2019 Pack Production Planning

    20/39

    Now double click on operation no 10 to view details of the operation

    Select Ext,processing Tab to view the Purchase requisition number generated

    for the subcontracting job

    NOTE THE PURCHASE REQUISITION NUMBER

  • 8/8/2019 Pack Production Planning

    21/39

    Conversion of Subcontracting Purchase order with reference to Pur Req no

    Go to Transaction ME21n

    Input:

    Subcon PO-packdocument type

    Purchasing orgPur Grp

    Company code

    In the Purchase requisition filed enter the PR no to be used

    Now press enter to view the following screen

  • 8/8/2019 Pack Production Planning

    22/39

    In the net price field enter the subcontracting price and select tax code in invoice

    tab also

  • 8/8/2019 Pack Production Planning

    23/39

    Now click on check to view any messages

    Now save the Purchase order

    Purchase order is now created

  • 8/8/2019 Pack Production Planning

    24/39

    Transfer posting of stock to subcontractor(offset)

    Go to transaction : MB1B

    Input Mov type, Plant, storage location and click on To Purchase order

    Input Pur Ord no and item no and click on adopt+ details

  • 8/8/2019 Pack Production Planning

    25/39

    Check the details and click on save to complete transfer posting of stock

    Note down the Mat Doc no Created.

  • 8/8/2019 Pack Production Planning

    26/39

    Creation of sub contracting challan with Transfer posting Mat Doc

    Go to transaction: J1IF01

    Input: Mat doc no, Mat Doc year, Excise grp, Series Grp

    Check details of qty in Qty overview tab

    Now click on save to generate Challan number

  • 8/8/2019 Pack Production Planning

    27/39

    Goods receipt for Subcontracting PO

    Go to transaction MIGO

    Input: Goods receipt, Purchase order, Purchase order no and press enter

  • 8/8/2019 Pack Production Planning

    28/39

    Now select Item O.K and click on Check

    Message Pop up is displayed

    Close the pop up

    Now you can see the excise invoice Tab generated

    Click on excise invoice tab

  • 8/8/2019 Pack Production Planning

    29/39

    Select Refer subcontracting challan

    Now click on more data icon

  • 8/8/2019 Pack Production Planning

    30/39

    In the excise invoice data screen enter

    Challan number and year and click on continue

  • 8/8/2019 Pack Production Planning

    31/39

    Now again click on check

    Document is now O.K .

    Now save the document

    Material document for Goods Receipt is generated, Note down this number

  • 8/8/2019 Pack Production Planning

    32/39

    Reconcile the challan

    Go to Transaction : J1IFQ

    Input: Mat Doc, Mat doc Year, Challan no, item no and click on reconcile

    In the assigned qty field input the qty to be reconciled and save

  • 8/8/2019 Pack Production Planning

    33/39

    Now the reconciling of challan is completed

    Closing of challan

    Go to Transaction : J1IF13

    Input : Challan no and year and press enter

  • 8/8/2019 Pack Production Planning

    34/39

    View the quantity overview details and save

    Challan is closed.

  • 8/8/2019 Pack Production Planning

    35/39

    Production Confirmation of FPS-200 (Flat printed sheet from offset) production

    order

    Go to Transaction : CO15

    Input the FPS-200 production order no( Subordinate order)

    And press enter

  • 8/8/2019 Pack Production Planning

    36/39

    In the confirmation data screen enter the yield qty(actual production qty)

    And select whether it is part confirmation or Final confirmation

    Now click on save to Confirm the production

  • 8/8/2019 Pack Production Planning

    37/39

    Production Confirmation of final product

    Go to Transaction : CO15

    Input the final product Production order no and press enter

    In the confirmation data screen enter the yield qty(actual production qty)

    And select whether it is part confirmation or Final confirmation

  • 8/8/2019 Pack Production Planning

    38/39

    Now click on save to confirm the Production Qty

    Now the final product confirmation is saved.

    Checking of sales order stock in stock overview

    Go to transaction : MMBE

    Input: Mat code, Plant, storage location and click on execute

  • 8/8/2019 Pack Production Planning

    39/39

    Double click on sales order qty to view the individual sales order stock qtys

    For our respective sales order reference corresponding stock produced is

    available for delivery