p09029: robotic hand improvement

19
Casey Dill (ME): Lead/Mechanics Arthur Connors (EE): Control System Andrew Torkelson (ISE): Test Development Dr. Kathleen Lamkin-Kennard: Guide/Sponsor P09029: Robotic Hand Improvement

Upload: amos

Post on 08-Feb-2016

21 views

Category:

Documents


0 download

DESCRIPTION

P09029: Robotic Hand Improvement. Casey Dill (ME): Lead/Mechanics Arthur Connors (EE): Control System Andrew Torkelson (ISE): Test Development Dr. Kathleen Lamkin-Kennard: Guide/Sponsor. Customer Needs. Engineering Specifications. Concept Description and Rationale. Electrical Concepts - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: P09029: Robotic Hand Improvement

Casey Dill (ME): Lead/MechanicsArthur Connors (EE): Control System

Andrew Torkelson (ISE): Test DevelopmentDr. Kathleen Lamkin-Kennard: Guide/Sponsor

P09029: Robotic Hand Improvement

Page 2: P09029: Robotic Hand Improvement
Page 3: P09029: Robotic Hand Improvement
Page 4: P09029: Robotic Hand Improvement

Customer Needs

Page 5: P09029: Robotic Hand Improvement

Engineering Specifications

Page 6: P09029: Robotic Hand Improvement

Electrical ConceptsLabVIEW

Control System DevelopmentOutputs to SolidWorks ModelOutputs to Physical Prototype

Control SystemMovement Accuracy – Position and SpeedFeedback Considerations – Accommodating for

DelayOutputs to Both SolidWorks and Prototype Using

Same VIComponent Familiarization

Relay Boards, Relays, and Data Acquisitioners (DAQs)

Concept Description and Rationale

Page 7: P09029: Robotic Hand Improvement

Control System Overview

Page 8: P09029: Robotic Hand Improvement

Control System Feedback Loop

Page 9: P09029: Robotic Hand Improvement

Concept Description and Rationale

Page 10: P09029: Robotic Hand Improvement

Concept Description and Rationale

Page 11: P09029: Robotic Hand Improvement

Concept Description and Rationale

Page 12: P09029: Robotic Hand Improvement

System Architecture

Page 13: P09029: Robotic Hand Improvement

Med-High Risk Assessment

Page 14: P09029: Robotic Hand Improvement

All software has been installed on a computerEli* from NI. His latest email indicates

academic license may be an issue. Limit at getting SolidWorks and Labview

working together set to 2 weeks, or switch to a different software package.

*Eli SeidnerApplications Engineer, National [email protected] | (512) 683-0971

Current State of Design

Page 15: P09029: Robotic Hand Improvement
Page 16: P09029: Robotic Hand Improvement

Milestone ScheduleWeek Plan Contingency

1Start building test stand  

Work on getting simulation workingIf simulation isn't working by Friday, look for alternatives

2Get simulation working If simulation isn't working by

Friday, use a different programMake a few air muscles

Buy controls stuff  

3

Make a control system to test muscles  

Test relaysIf parts haven't arrived, refine model

Run through demosIf a alternative simulation program is being used, attempt demo 

4Make list of joints to test  Complete test plan  Work on simulation  

5Demonstrate simulation with displacement If not done, work on simulationWorking air muscles for 1 joint Debug controls

Page 17: P09029: Robotic Hand Improvement

Milestone Schedule

6Get forces working for simulation (I)  Characterize more air muscles (I)  

7

Get forces working for simulation (II)  Find math models  Find how to apply math  

8Develop math more  Characterize more air muscles (II)  

9Apply math model to simulation If model is too complicated, use a

simplerapproximation 

10 Calibrate forces in simulation  

11

Demonstrate working simulation of air muscles  Show test stand  Prove math model  

Page 18: P09029: Robotic Hand Improvement

Primary DeliverablesComputer simulation of common joints.Prototype that demonstrate accuracy of the

simulation.Sub Deliverables

Week 2: A test stand.Week 3: A working simulation software.Week 5: A simulated joint without accurate

forces.Week 7: Simulated forces in simulation.Week 10: Working, accurate computer model.

Milestone Schedule

Page 19: P09029: Robotic Hand Improvement

For the next two weeks:Continue emailing and calling Eli S. (Casey and

A.J.)Design the test stand (Casey and Andrew)Create a preliminary control system for the test

stand (A.J.)

Milestone Schedule