P05: CD-3a Procurements and DOE O 413.3B documentation
Vaia Papadimitriou, Deputy Project ManagerHL-LHC CMS CD-3a Director’s ReviewFebruary 20, 2020
Biographical sketch Procurement status for the CD-3a scope and
associated documents Status of DOE O 413.3B documentation Additional controlled documents Review of the CD-3a documentation web page Summary
Outline
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 2
This presentation will address charge questions #6 and #9
Senior Scientist at Fermilab since August 2003 (Particle Physics and Accelerator Divisions). U.S. CMS HL-LHC Upgrade Deputy Project Manager since July 2018. LBNE/LBNF Beamline (~$200M) Project Manager for 8.5 years (2009-
2018). Assistant/Associate Division Head of Accelerator Division for 3/8.5 years
(2006-2018). Professor of Physics for 11 years at TTU, followed by 3 years as Adjunct
Professor (1994-2008). PI/co-PI of successful DOE research proposals. 35 years of experience in the design, construction, operation,
data/physics analysis and management of particle physics experiments and of accelerators/beamlines (E731-Kaon, CDF, Fermilab Accelerator Complex, LBNE/LBNF/DUNE, CMS). Previous Apparatus Leadership on Calorimetry and Trigger Electronics. Reviewer of scientific proposals and projects for past 19 years. Certificates from Booth School of Business on management and
leadership training. B. Sc., M. Sc., and PhD in Physics; L. M. Lederman Fellow at FNAL.
Biographical Sketch
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 3
Procurement Status for CD-3a Scope
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 4
Outer Tracker Silicon Sensors $5,442,600 Outer Tracker Module Mechanical Components $ 477,177 MIP Timing Detector LYSO Crystals $ 522,200
BAC
CERN intends to buy Si Sensors from Hamamatsu/HPK for the CMS Outer Tracker (OT), the CMS Endcap Calorimeter (CE) and the ATLAS Outer Tracker. Extensive, two-year long Market Survey (MS-4086/EP) that
started in 2016 and is discussed more later. It was initiated by CERN and was organized in coordination with and significant participation from the U.S. CMS Project Team.
The U.S. Project intends to buy the required Si Sensors from CERN. DOE recommended this to be a procurement action.
Outer Tracker Si Sensor Procurement
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 5
Charge #6
BAC is $5,442,600 ($4,071,695 in direct M&S)
The Market Survey was publicly posted by CERN, and alsosent to 15 known suppliers with the required technical expertise. Eight potential suppliers responded, one from the U.S.
(Tezzaron). The U.S. CMS Project Team participated in two phases of SBIRs
to help enhance Tezzaron’s ability to participate. The U.S. CMS Project Team irradiated several prototype sensors
and test structures at RI Nuclear Science Center and tested them to check prototype quality. Several dozen test structures, ~20 small test sensors, and over
40 full sensors were also extensively tested at Brown and Rochester.
Si Sensor Market Survey Process
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 6
Charge #6
See CMS-doc-13969
Three suppliers (Hamamatsu, Infineon and Tezzaron) passed the first step of qualifications. Hamamatsu and Infineon passed the second step of
qualifications in 2016 (Tezzaron got bought and its foundry no longer available to produce sensors). For third step, each supplier was required to submit samples of
functional sensors for testing (2017). In July 2018 Infineon decided to withdraw from participating in HEP Projects. Hamamatsu’s prototypes met all specifications. An invitation to tender (IT-4504/EP/CMS) for CMS OT Si
Sensors was sent by CERN to Hamamatsu Photonics on April 3, 2019 (similarly for CMS CE). Frame contract between CERN and Hamamatsu signed on
August 23, 2019.
Si Sensor Market Survey Process
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 7
Charge #6
Needed steps and documentation for the acquisition of the sensors from the U.S. side are: Acquisition Plan MOU between CERN and Fermilab to spell the terms and
conditions for the acquisition Request for Proposal (RFP) from Fermilab to CERN Successful Production Readiness Review (PRR) Purchase Order to be issued after CD-3a approval
U.S. Procurement Process – OT Sensors
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 8
Charge #6
The Acquisition Plan (CMS-doc-13962) Although the expected award for OT is close to but less than
$5M, an Acquisition Plan (AP) was prepared by the Project in collaboration with Fermilab Procurement and General Counsel Office. (Process started in January 2019). The reason was that an MOU is required, and another significant
acquisition for CE sensors is following The OT AP was approved by DOE Fermilab Site Office (FSO) on
October 24, 2019.
U.S. Procurement Process – OT Sensors
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 9
Charge #6
The MOU is to cover both the OT and CE Si sensor procurement packages Non-binding MOUs for HL-LHC Accelerator and Detector
upgrades to detail specific scope and responsibilities are contemplated by the existing DOE-CERN international cooperation agreement structure. The AUP MOU was signed in January 2019.
The Fermilab HL-LHC CMS Project Office has been working and continues to work with DOE on finalizing the draft MOU on Si sensor procurement. An extensively reviewed draft of the HL-LHC CMS MOU can be
found in CMS-doc-13968. It is currently at final steps of review by DOE.
U.S. Procurement Process – OT Sensors
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 10
Charge #6
Draft MOU between CERN and Fermilab
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 11
Charge #6
CMS-doc-13968
Fermilab Procurement shared a draft RFP for the OT sensors with CERN for their comments on January 21. We are discussing with DOE possible MOU modifications so that
certain RFP provisions can be merged within the current draft MOU.
DOE is also working with CERN Legal Service on proposed edits and comments to finalize the MOU. The MOU will be then routed through DOE, including the Offices of HEP, Science, General Counsel and International Affairs, to obtain the necessary authorizations for the Fermilab Director to sign together with the CERN Director for Research and Computing.
U.S. Procurement Process – OT Sensors
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 12
Charge #6
U.S. Procurement Process – OT Sensors
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 13
PRR took place at CERN on January 30, 2020 Green light given to move forward with the
production/procurement process
The U.S. CMS Project Team will participate in the Quality Control of the sensors (QC centers at the University of Rochester and at Brown University – see P02).
Charge #6
OT Module Mechanical Component Procurement Process
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 14
Carbon fiber 20% of the material is in the CD-3a scope. U.S. CMS will buy the
material and lay up panels for the entire HL-LHC CMS upgrade. The procurement will take place through Purdue University. The supplier is expected to be Toray, CA/U.S. - Sole Source. Layups will take place at Fermilab and Purdue University.
Aluminum carbon fiber 20% of the material is in the CD-3a scope. U.S. CMS will buy the
material only for the U.S. part of the HL-LHC CMS upgrade. The procurement will take place through Brown University. Potential suppliers for the material are Parker/U.S. and
Novapack/Europe. PRR for both items to take place at CERN on March 11,
2020
Charge #6
BAC is $477,177 ($424,422 in direct M&S)
MTD LYSO Crystal Procurement Process
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 15
Charge #6
Barrel Timing Layer (BTL) LYSO crystals specifications ready to initiate procurement Crystal R&D completed on schedule and final report available at
CMS-doc-13957. No changes in the design of other BTL elements impacts the choice of
the LYSO crystals Several potential vendors available:
• Crystal Photonics Inc., U.S.A• EPIC Crystal, China• Hypercrystal, Taiwan• JT Crystal Technology, China• Shanghai Institute of Ceramics, China• Simcrystals Technology, China• SIPAT, China• Tianle Photonics, China• Zecotek, Singapore
All nine vendors satisfy the BTL requirements on: Dimensions and tolerances Density Light output
Five of the nine vendors satisfy all BTL requirements
Two vendors require adjustment of the reflective material used in the array
BAC is $522,200 ($500,000 in direct M&S)
MTD LYSO Crystal Procurement Process
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 16
Charge #6
Test results so far provide input for the start of a formal three-step Market Survey through CERN (MS-4588/EP/ CMS) expected to lead to an invitation to tender in Q4 of 2020 (see CMS-doc-13976). PRR took place at CERN on February 13, 2020. Purchase of crystals to take place through CERN, with Italy,
Switzerland and U.S. expected to provide the funding. INFN Rome is expected to perform the quality control for
the crystals (see P04).
Status of DOE O 413.3B documentation
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 17
Checklist from 413.3B for CD-1 approval
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 18
Charge #9
CD-1 documents updated as appropriate after the October 2019 CD-1 Review
Checklist from 413.3B for CD-3a approval
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 19
Charge #9
CD-1 documents updated as appropriate
Owned by DOE(CMS-doc-13092)
Approved at ESAAB ofDecember 19, 2019
Checklist from 413.3B for CD-3a approval
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 20
Charge #9
CD-1 documents updated as appropriate
Owned by DOE
(CMS-doc-13517)
Approved at ESAAB ofDecember 19, 2019
Checklist from 413.3B for CD-3a approval
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 21
Charge #9
PRR for Outer Tracker Si sensors on January 30, 2020 Green light given; report pending
PRR for MTD LYSO crystals on February 13, 2020 Green light given; report pending
PRR for Outer Tracker module mechanics on March 11, 2020
Checklist from 413.3B for CD-3a approval
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 22
Charge #9
Technical Design Report: CMS-doc-13965
An 85-page document covering the CD-3a DOE scope of the Project
Checklist from 413.3B for CD-3a approval
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 23
Charge #9
We have started exercising a certified EVMS as per the FRA contract and have statused the Project through January 2020 (see P01).
Checklist from 413.3B for CD-3a approval
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 24
Charge #9
CMS-doc-13093, approved
CMS-doc-13394, approved
Additional controlled documents
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 25
Charge #9
Document Type CMS Document # Status
Project Management Plan CMS-doc-13104 approved
Procurement Management Plan
CMS-doc-13267 approved
Key Assumptions CMS-doc-12919 approved
Configuration Management Plan
CMS-doc-12907 approved
Codes and Standards CMS-doc-13717 approved
Review of the CD-3a documentation Web page
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 26
Project Documentation Index
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 27
Charge #9
Project Documentation Index
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 28
Charge #9
The procurement process for the CD-3a scope items is well advanced and the relevant documentation is in good order and properly reviewed. All required project documents for CD-3a are in place, and
at the appropriate level for this stage of the Project.We are ready to proceed to CD-3a.
Summary
2/20/20 Vaia Papadimitriou HL-LHC CD-3a Director's Review 402.1 - Project Management 29