overview of recent commissioning results of kstar … · 22nd iaea fusion energy conference , oct...
TRANSCRIPT
22nd IAEA Fusion Energy Conference , Oct 13, 2008, Geneva, Switzerland
Presented by Joo Shik BakNational Fusion Research Institute
Daejeon, Republic of Korea
Overview of Recent CommissioningResults of KSTAR
2
Basic R&D, Conceptual Design (95.12 – 98. 8)
Engineering Design (98. 9 - 02. 5)
Machine Construction & Assembly(02. 6 - 07. 8)
1st plasma Achievement (08. 6-7)
Integrated Machine Commissioning
(07. 9 – 08. 5 )
Brief History
Why we need commissioning
1. To verify the performance of integrated systems
2. To identify any defect preventing machine operation
3. To verify the scenario for each commissioning step
4. To prepare the basis for full-dress operation
3
Must-check Item Step Item
1. 1Vacuum Base pressure, He leak rate, Baking, Gas puffing, Discharge cleaning
2. Cryogenic Cool-down
Tube cleanness, Cold leak, Temperature control, Structural displacement, Operational stabilityFlow balance, Thermo-hydraulic analysis
3. BasicSCM Test
Electrical insulation, Current directionSuperconducting transition, Joint resistance
Single SCM Test
TF∙PF current charging and dischargingTF∙PF quench, PF blip operationField measurement, Power supply controllability
IntegratedSCM Test
Coupling effect among coils, Loop voltageField measurement, Change of basic environment
4. Plasma Start-up
Operational scenario, Field null controlTiming, ECH pre-ionization, Diagnostics
4
55
Step Item Target
VacuumBase pressure of VV & CR (Pa)Total leak rate (Pa·m3/s)
5.0x10-5 , 1.0x10-2
1.0x10-6
CryogenicCool-down
Inlet temperature of TFC & PFC (K)Inlet temperature of CTS & VVTS (K)Temperature control (K)
< 5< 60< 50
SCM Test
Electrical insulation (MΩ)Joint Resistance (nΩ)TF current charging (kA)PF current charging (kA)Blip rate (kA/s)BTF(T)
100 5
154
10-100 1.5
Plasma Start-up
Loop voltage (V)ECH power & pulse lengthPlasma current (kA)Plasma duration (ms)
3.5-4 400 kW, 300 ms
100100
Target Parameters
Phase Action ItemStartDate
FinishDate
April May June July August
Vacuum&
Cool-down
Evacuation & Leak Test - 04-02
Cool-down 1st Stage (300K~80K)
04-03 04-20
Cool-down 2nd Stage(80K ~ 20K)
04-21 04-24
Cool-down 3rd Stage (20K~4.5K)
04-25 05-02
SC Magnet& MPS Test
Joint Resistance &Insulation Test
04-30 05-05
TF Coil Test 05-06 05-14
PF Coil Test 05-15 05-27
Integrated Test(TF, PF, ECH, ICRH, Fueling Test)
05-28 06-06
Plasma Experiment
Field Null Measurement 06-01 06-02
Plasma Startup Experiment 06-03 06-13
Plasma Control Optimization 06-14 07-15
Engineering Test& Warm-up
Engineering Test 07-16 07-19
Warm-up (4.5K~250K) 07-20 08-01
Vacuum Commissioning (04-02)
Cool-down (5 K) (04-26)
1st Plasma (06-13)
TF Coil 15 kA, 8 hours (05-12)
Milestones6
Vacuum Pumping: 161 daysCryogenic State: 122 daysSuperconducting State: 84 daysPlasma Operation: 48 days
7
Primary Vacuum History
8
Secondary Vacuum History
9
Temperature History
10
Cold Leak Monitoring
Stress History of TF9 Structure11
Preload Change of CS Structure12
Superconducting Transition13
18.2 K(PF1)
17.9 K (TF) 10 K (PF7U)
10 K(PF7L)
Rcoil (300K) : 957 mΩRcoil (18K) : 4.4 mΩRRR ~ 217
Stainless steel body
Copper block
Cable
(96.5Sn3.0Ag0.5Cu) + (0.12 Sb)
63Sn36.65Pb0.35Sb
E-beam welding
Piston
Coil Lap JointsTotal R
[nΩ]
Average R
[nΩ /joint]
Design
Value
TF 6 11.11 1.85
< 5 nΩ
PF1 7 15.58 2.23
PF2 7 11.09 1.58
PF3 12 20.29 1.69
PF4 12 17.42 1.45
PF5 12 25.15 2.09
PF6 14 11.20 0.80
PF7 8 4.11 0.51
[The KSTAR lap joint of the SC bus-line]
PF CLB TF CLB
Vacuum Isolator
OCB Joints
ICB Joints
Current Leads
PF Bus-lines TF Bus-lines
Joint Resistance14
TF Magnet Charging15
PF Magnet Blip Test16
AC Losses17
Measurement Method Shot No. dI/dt[kA/s] Qtot [J] Qhys [mJ/cc] Ntau [ms]
Trapezoidal Pulse
(Calorimetric)
May325 0.5 [0.5-0.5] 867
178.2 < ( 1.3T)
D eff < 13.5 mm
62.5
279 1.0 [1.0-0.5] 1039 62.5
July
1183 0.5 [0.5-0.5] 840 52.6
1184 1.0 [1.0-1.0] 1218 47.2
1185 2.0 [2.0-2.0] 1888 49.1
Measurement Method Shot No. Frequency[Hz] Q/cycle [J/cycle] Qhys [mJ/cc] Ntau [ms]
DC biased Sinusoidal
(Enthalpy)July
1187 0.1 86.5164.6 < ( 0.65T)
D eff < 9 mm
32.0
1190 0.14 98.55 32.4
1188 0.2 119.97 35.8
Trapezoidal current waveformTraditional temperature overshoot by PF coil current pulse
Cryogenic circuit of PF 1 UL coil
• KSTAR design value
- Qhys < 250 mJ/cm3 per 3T
- n < 60 ms
Sinusoidal current waveform
Magnetic Configuration18
Conventional mode- Favorable for initial breakdown due to larger field null- Flux contributions mainly from PF1~4, weakly from PF5~7
Dipole mode - Higher flux for current ramp-up and feedback control- Considerable flux contributions from PF 5 ~7
0.5 1 1.5 2 2.5 3 3.5 4-2
-1.5
-1
-0.5
0
0.5
1
1.5
2
R [m]
Z [
m]
KSTAR Initial Magnetization Flux, o = 0.82497 Vs
1
1
2
2
2
5
5
510
10
1020
20
20
30
30
30
50
50
50
100
100
100
10
0
100
Coil I (kA)1 1.7202 2.1223 2.9294 2.9575 0.8026 0.7357 -0.413
0.5 1 1.5 2 2.5 3 3.5 4-2
-1.5
-1
-0.5
0
0.5
1
1.5
2
R [m]
Z [
m]
KSTAR Initial Magnetization Flux, o = 0.949 Vs
2
2
2
5
10
10
20
20
20
30
30
30
50
50
50
10
0
100
100
Coil I (kA)1 1.9132 3.0773 2.5524 2.0485 1.0006 1.4147 -1.100
Shot 858 Shot 977
Initial flux: 0.825 WbMax. Vloop @ vacuum: 4.4 VNull size (<10 G): 1m (dia.)Bz/dt: -0.1 T/s
Initial flux: 0.949 WbMax. Vloop @ vacuum: 5.1 VNull size (<10 G): 0.5 (dia.)Bz/dt: -0.12 T/s
Shot no. 794
ECH power: ~ 350 kW with perpendicular launch
ECH power on time: t = -30 ms
H2 pre-fill gas pressure: ~ 4.5 x 10-5 mbar
ECH Pre-ionizationR ~ 1.8 m
2nd
harmonic
resonance
position
(Bt = 1.5 T)
R ~ 1.7 m
(a) Shot 794
(b) Shot 977
(c) Shot 1057
• Shot no. 794Conventional modePerpendicular launchEC beam target:Z=0m, R=~1.8 m
•Shot no. 1057Dipole-like modeOblique launch(tor. angle=-10)EC beam target:Z= -0.1m, R=~1.7 m
• Shot no. 977Dipole-like modePerpendicular launchEC beam target:Z= -0.1m, R=~1.7 m
ECH Pre-ionization19
Observation of 2nd Harmonic ECH Pre-ionization
-0.04 -0.03 -0.02 -0.01 0.00 0.01 0.020.0
0.1
0.2
0.3
0.4
-0.04 -0.03 -0.02 -0.01 0.00 0.01 0.02
0
1
2
3
4
5
PE
CH (
MW
)
ECH power
H(
a.u
.)
Time (s)
ha03 ha05
ha07 ha09
ha11 ha12
ha13 ha14
ha15 ha16
Toroidal H signals
Ch#11
Pre-ionized plasma at t=-10ms before the onset
of the toroidal electric field for shot no. 977
R = ~1.7 m
2nd
harmonic
resonance
•Line of sight of toroidal H channel no. 11 is near
the 2nd harm. EC resonance at R ~ 1.7 m
Evidence of 2nd harmonic ECH pre-ionization
Ch #11
EC beam
ECH antenna
20
Plasma Shot Log 21
First Plasma(#794, ‘08. 6. 13) 22
PF Coil Current
Pressure
ECH Power
H-alpha
ECE
Line Density
Plasma Current
Loop Voltage
BTF : 1.5 Tesla
R=1.8 m, a=0.3m
PECH : 350 kW
Line Density : 1x10 19/m2(peak)
Peak loop voltage : 1.93 V @ inboard mid-plane
Plasma Current : 107 kA (peak)
Pulse length : 210 ms
23
(a) #1058, 200 ms
(b) #1058, 372 ms
(c) #1058, 586 ms
ECH turned off at 300 ms
>380 ms with >100kA
Vertical Instability Onset
(a) (b) (c)
±3cm
Ip Feedback Control
Representative Shots 24
Target Results
ECH Pre-ionization Plasma Current > 100 kA Pulse Length > 100 ms
Reliable Pre-ionization by 2nd Harmonic ECH at 84 GHz Max. Plasma Current : 133 kA (shot 976) Max. Pulse Length : 862 ms (shot 1127)
25
Failure Analysis
Total Fault Events: 330 Total Interrupt Time: 164 hr
Summary
1. KSTAR was successfully passed the engineering/plasma commissioning on the first trial. So, the first Nb3Sn technology-based fully superconducting tokamak is newly registered in operating machine entry.
2. KSTAR has achieved the first plasma on June 13 (Fri).After more than 600 breakdown shots, plasma current was ramped up to 133kA with rate of 0.8 MA/s, and well-controlled with duration up to 862 ms.
3. Success keys to overcome from poor technological base and unexperienced man-power are even pain-taking, exhaustive preparation and ceaseless confirmation.
4. KSTAR now plans to upgrade its power supply, plasma facing components, diagnostics and heating devices as quickly and feasibly as possible.
26