overcoming the challenges derived from the transition of...
TRANSCRIPT
Overcoming the challenges
derived from the transition of traditional
Power Plants to Energy Storage
Barbara Rossi - Business Development
Antonio Zingales – SalesManager
Introduction to SAET
Energy Storage as a new technology for grid needs:
SAET experiences in power & energy projects for
distribution & transmission grid
Future overview & conclusions
From traditional generators to renewables: SAET & the
evolution of Italian electric system
OVERVIEW
Lessons learnt: role & challenges of a system integrator
in Energy storage projects
Introduction to SAET
SAET SpA, founded in 1956, is an engineering company
working as EPC in Energy projects
SAET spa
Via A. Moravia, 8
35030 Selvazzano D.
PADOVA ITALY
Located in Padova, North East Italian region
50 employees (over 20 engineers)
Turnover of 20-30M€
Introduction to SAET
With technical expertise in:
Electrical Systems
( HV substations, MV-LV
switchboards, Protection &
control systems, Electric Scada)
Handling & Dosing Systems
( Bulk Material Handling, Belt
feeders, Belt scales, Dosing of raw
materials)
Automation
(PLC /DCS control systems with
SCADA supervision)
SAET acts as EPC
in different fields
Design &
Engineering
Service
Supply &
Commissioning
POWER PROCESS
TRANSMISSION
DISTRIBUTION
PRODUCTION
Italian electrical system before years 2000 was clearly divided into three
different subsystems Production, Transmission, Distribution
Distribution lines with primary and secondary
substations 145-20-0.4 kV
Transmission with lines and substations 420-245-170-145
kV (+ 72kV)
Several concentrated power plants (mainly Thermo and
Hydro) connected to 420 kV and 145 kV
with POWER FLOW IN ONE DIRECTION
2000 2010 < 2000
Evolution of Italian electric system
Evolution of Italian electric system
2000 2010 < 2000
Saet provided Protection & Control for generators bays …
Protection and control system for 800 MW power plant in Simeri Crichi (CZ)
3 HV GIS generator bays
1 GIS Line bay
3 Generator Bays
MV protection (105)
LV protection (95)
+ HMI system, with SGE redundancy and Protection
+ double ring Lan with distributed switches
Evolution of Italian electric system
… & started to play as turn key supplier for grid substations integrating
power, protection & control
400 kV Substation annexed to a 470 MW combined cycle in S. Severo (FG)
400kV Substation
Single AIS Bay
20kV-480MVA Generator syncronous
complete with
Protection and Supervision
System SCADA
2000 2010 < 2000
2007 2008 2009 2010 2011 2012
87 432 1142
2800
12500
16350
MW
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
664 780 874 1131 1639
1908
2714
3538
4898
5850 6600
8208
MW
Wind 8,2 GW-13,2 TWh/y
Evolution of Italian electric system
2000 2010 < 2000
After year 2000 Wind and PV generation capacity connected to the grid
had a great increase
Solar 16,6 GW-18,8 TWh/y
From traditional generators to renewables:
2000 2010 < 2000
Starting to deeply modify grid assets
Before RES
With RES
Per visitare SAET
Turn key supply of
4,8MW rooftop PV
plant in Giammoro,
Pace del Mela (ME)
Producer SS & TERNA
SSE for 48MW PV plant
in Canaro (RO)
Primary cabin, deliver
and producer SS for wind
farm in San Gregorio
Magno (SA)
Evolution of Italian electric system
2000 2010 < 2000
Renewables lead SAET to play a major role as EPC
Evolution of Italian electric system
2000 2010 < 2000
The growth of random and non-predicatble RES production brought to:
Frequency
Loads Production
• Unbalance issues in grid management
• Increase of power flow on critical
sections of transmission grid
• Regulation issues
◦higher frequency variation due to lower
system inertia
◦reduction of regulating capacity
• Issues in reactive power regulation
Requiring new solutions to manage the grid
Smart grid: new concept of the grid with structures and procedures to:
Energy storage to:
Optimize RES production
Support grid balance
Decrease congestions (possibility to
defer production and consumptions)
Guarantee continuous and high quality
energy supply
2000 2010 < 2000
increase grid safety and reliability;
improve RES management and load control;
increase energy efficiency
Evolution of Italian electric system
Evolution of Italian electric system
SAET mission: turn grid and electrical systems skills into
competitive solutions for the next challenges of energy market
SAET works
here
(HW & grid
communication)
as SYSTEM
INTEGRATOR
POI project promotes the improvement of distribution grid in Southern Italy regions
with high RES penetration providing the possibility to test Energy Storage Systems in
primary substations to:
SAET experiences in Energy storage
1) ENEL POI project: ESS in MV substation of distribution grid
reduce the variability of power flow due
to wind gusts or the passage of clouds
make the exchange of energy profiles
between HV/MV substations and
National grid more predictable
SAET role
SAET experiences in Energy storage
BMS
P, Q, … setpoint
Storage feedback
SAET
SAET
BATTERY
Start, stop &
feedback
P, Q, …
setpoint
EESS
feedback
SUPERVISION
&
CONTROL
SYSTEM
GRID
PCS
transformer +
switchgears &
controls
Nr 3 40 ft containers
batteries +
PCS
Commissioning
March 2014
Turn key supply 2MW/1MWh for Campi Salentina (LE) primary cabin
SAET experiences in Energy storage
Battery technology: lithium ion (NCA)
Nr cycles: 2000
Round trip efficiency: 85%
Installation area: 220 m2
Project schedule: Q4 2012-Q1 2014
Campi Salentina ESS functions:
Main target: RES integration with predictable profile
Time shift + peak shaving
Power balancing (mitigation of RES random production)
Power quality (compensation of voltage gap and unbalance,
harmonic compensation)
Frequency and voltage regulation
Power factor correction
Black start
SAET experiences in Energy storage
Nr inverter:
8 …
BMS BMS BMS BMS BMS BMS BMS BMS
Nr battery strings
4
For each inverter:
20 kV
400 V
250 kVA 700 V
39,5
kWh
250 kVA
39,5
kWh … … 39,5
kWh
39,5
kWh … …
SAET experiences in Energy storage
ESS details
19 module
14 cells (7S2P)
string (ESSU) 29 modules
4 ESSU
cell
Energy Storage System Unit characteristics
BoL Energy 39.5 kWh
Nominal voltage 730 V
Max Discharge power, continuous @ 100% SOC, 25°C 142 kW
Max discharge current 180 A
Weight 750 kg
SAET experiences in Energy storage
ESS details
SAET experiences in Energy storage
Supervision & control system
PC SCADA (+ HMI) for data
storage & management of «slow»
events and alarms
PLC for ESS control monitoring
system status and managing
commands and control logics
Modbus TCP protocol for
diagnostics and data storage
CAN OPEN protocol for fast
feedback (from BMS & PCS) &
command set
IEC 61850 for ENEL remote control
plant solutions
components and
technical solutions
SW and control
competences
SAET experience from Campi Salentina ESS
SAET experiences in Energy storage
NEW
SAET experiences in Energy storage
Per visitare SAET
Fonte: ES
POI
Development plan
Energy
Defense plan
Power
UB reduction
1°
2°
3°
Offgrid & microgrid
projects
Generation Transmission Distribution User
HV GRID
HV/MV
AUXILIARIES
LV dedicated
power supply
Diesel
generator
Energy
Intensive
Power
Intensive
2) Power & Energy projects for transmission grid
SAET experiences in Energy storage
Casuzze ?
Applications: electrical system safety on Italian major islands
Reserve and frequecy/power regulation (support to low system
inertia coming from traditional generators)
Voltage regulation
Power quality
Integration with TSO grid management systems
Defense plan 2012 – 40MW SdA Power Intensive
Technical details:
Storage technology: lithium ion and NaNiCl2
Low energy/power ratio (<5)
Fast response time
1° PHASE: Storage Lab – 16MW
7 ESS:
5 lithium
2 sodium
Codrongianos
1MW/1MWh lithium
turn key supply
1 MW/2MWh sodium
plant integration
SAET
SAET experiences in Energy storage
battery
container
MV + PCS +
scada container
Details: turn key supply Storage technology: LiFePO4
Nr cycles: 4000
Round trip efficiency: ~ 85%
Delivery date: Summer 2014
15kV
800V
Nr 2
40 ft containers
BATTERY STRING DETAILS
Nominal Voltage(V) 793
Voltage range (V) 694-892
Nominal capacity (kWh) 147
Max discharge current (A) 200
SAET experiences in Energy storage
Battery technology: lithium ion (LiFePO4)
Nr cycles: 4000
Round trip efficiency: 85%
Installation area: 300 m2
Project schedule: Q3 2013-Q3 2014
Turn key supply 1MW/1MWh lithium for Codrongianos (SS) substation
Nr inverter:
1
Nr battery
strings
8
cell
module 4 cells (4S)
string 62 modules
SAET experiences in Energy storage
Turn key supply 1MW/1MWh lithium for Codrongianos (SS) substation
PC SCADA (+ HMI) for data
storage & management of
«slow» events and alarms
PLC for ESS control
monitoring system status and
managing commands and
control logics
Modbus TCP protocol for
diagnostics and data storage
CAN OPEN protocol for fast
feedback (from BMS & PCS)
& command set
IEC 61850 for TERNA
remote control
SAET experiences in Energy storage
Battery technology: NaNiCl2
Nr cycles: 4500
Round trip efficiency: ~75-80 %
Installation area: 400 m2
Project schedule: Q3 2013-Q3 2014
Plant integration for 1MW/2MWh sodium for Codrongianos (SS) substation
27
battery
container
MV
container
Control
system
PCS
container
Complex plant layout
Specific container solutions
Auxiliaries feeding
!
Applications: reduction of congestions on HV grid portions with high wind penetration
Energy storage capabilities for enough hours to avoid 150kV lines congestion
Support to primary regulation
Increase of tertiary reserve
Voltage regulation
Technical details:
Storage technology: NaS
(provided by TERNA)
High energy/power ratio (>7)
Fonte: TERNA
TERNA Development plan 2011 – 35MW SdA Energy Intensive
3 projects:
Nr 2 12 MW/ 90
MWh installations
Nr 1 10.8 MW/ 81
MWh installation
10.8 MW / 81 MWh
turn key plant in
SCAMPITELLA (AV)
SAET experiences in Energy storage
SANC frame contract - first phase
29
• assembly of 9 NAS battery container
• n. 9 PCS container
• MV containers
• MV/LV transformers
• LV container
• diesel supply
• containerized station control system
• MV connection between SANC and
national grid connection point
• batteries-PCS control system
• auxiliaries and cables up to MV level
• civil works
Turn key supply 10.8MW/81MWh NAS plant in Scampitella (AV)
Total timing: 240 days
Area: 8200 m2
HV GRID
HV/MV
LV dedicated
power supply
Diesel
AUXILIARIES
SAET experiences in Energy storage
SAET experiences in Energy storage
SAET Energy storage projects: technology overview
DISTRIBUTION TRANSMISSION
2MW/1MWh 1MW/1MWh 1MW/2MWh 10,8MW/81MWh
Lithium (NCA) Lithium (LiFePO4) NaNiCl2 NaS
2000 cycles 4000 cycles 4000 cycles 4500 cycles
ή = 95% (Battery) ή = 95% (Battery) ή = 85% (Battery) ή = 75% (Battery)
Energy/Power: 0,5-2 Energy/Power: 0,5-2 Energy/Power: 2-5 Energy/Power: 6-8
450 kg
20 kWh
25 kg
2,5 kWh 3000 kg
225 kWh
18,5 kg
1,5 kWh
12x2,4x2,8 m 9x4x4 m
3MWh 9MWh
12x2,4x2,8 m
1MWh
Role & challenges of a ES system integrator
What’s the role of a system integrator?
It’s not simply
building a
box… Or laying wires…
It’s tailoring the right system
for each application
and make it properly work…
A system integrator…
Has a full overview of applications and technologies …
Time shift
Back up
Arbitrage
Regulation & Load
following
Power quality
Frequency control
Spinning reserve
Peak shaving
Lead acid Lithium
NaNiCl2 NAS
> 1000 cycles
ή < 75%
Energy/Power = 10
4000 cycles
ή = 85%
Energy/Power = 4
4500 cycles
ή = 75%
Energy/Power = 6-8
> 4000 cycles
ή = 95%
Energy/Power = 1
?
Role & challenges of a ES system integrator
Is able to propose the best
plant architectures…
Single line
diagram for
power
applications
Single line
diagram for
power /energy
applications
Single line
diagram for big
energy
applications
Role & challenges of a ES system integrator
can manage components and technical solutions…
Role & challenges of a ES system integrator
Plays a key role for
control and
supervision strategy…
REMOTE CONTROL
CENTRAL
PLC
Field data GRID
Role & challenges of a ES system integrator
Microgrid (on grid & offgrid) : distribution grid with loads, generation and storage
connected to the upper distibution grid on a single node or isolated
36
SAET & the future in Energy storage
Electrical system
knowledge
EPC for RES
System integrator for
Energy Storage
Turn key Energy storage projects for distribution, transmission & generation
Microgrid projects
Energy
efficiency
RES increasing penetration lead to strong issues in the management of the
Italian electric grid requiring new solutions and technologies and energy storage
is one of them
Italian DSO & TSO on going projects are providing the possibility to test the
capabilities of different storage solutions & technologies
System integrators like SAET can play a key role in the development of energy
storage system turning consolidated electrical system skills into new
competences and supporting both partners (battery & PCS producers) &
customers in tailoring the best solution for each application
37
Conclusions
38
Thank you for the attention