Outlook• Production of the 12 DPs (220m Stations) • Installation of the DPs in the LHC Tunnel• Status of the RP Systems/Services• Resources • Production of DPs for the 147m Stations
TOTEM Roman Pots Detectors
G. Ruggiero (PH/TOT) LHCC minireview – 21 September 2009
Production up to Detector Package 12
The production for other pots is ongoing…
The RP Stations at 220m sect 56 (April 09) and 45 (August 09) are fully installed.
Production schedule presented in the previous meeting strictly respected !!!
Production completed end of June !!!
Detector Packages Installation (July 2009)• All the pots formerly installed have been extracted for final inspection
together with the last produced pots.• The insertion of all the 12 Detector Packages has been completed beginning
August.
3Sector 45, RP Station 220mUnit Far
Sector 45, RP Station 220mUnit Near
Safe limit before glow discharge in the pot
Maximum allowed distortion for the thin
window in the pot (POT also moved out)
Vacuum SystemFinal layout of the vacuum system installed on both
sectors at the 220m RP Stations
5
OK
Ong
oing
All pots evacuated as of the insertion of the DPs
PUMP
Bourdon (2 set points)
electrovalve
10 mbar
100 mbar
It includes a local setup constraining the vacuum in the pots in a working range
Cooling System
6
For the stations at 220m:
Pressurisation to 15.2bar of the cooling lines
Pressurisation to 10 bars (long term)
Leak detection and leak fixing
Evacuation of all the lines
Circulation of cooling liquid
Se
cto
r 4
5
Se
cto
r 5
6
Plant operational and running on internal mode since long time
Environmental Sensors
Sensors• Cables installed and tested• Final R/O box for temp and pressure installed and tested• Final R/O box for RadMon installed and tested
TOTEM-DCS-02
<PCname>
DAQ
PSX - XDAQ
1
TOTEM-DCS-02
744
PSS II
sysWORXX
ELMB OPCserver
PVSS II
Detector
OPC client
ELMB
C1
8
E CMS TN
S2B02
PSX - XDAQ
OF
48
WienerVME crate
DCU
RP Station Patch Panel
Tun
nel
Rom
an P
ots
Cou
ntin
g R
oom
(U
SC
55)
DCU Environment monitors(T and currents)
Environment monitors(RadMon, pt 100, pt 1000, pressure)
8
High Voltage and Low Voltage
QYC02
S4F10
S2B03
E CMS TN1 shared
Detector Electronics
Wiener remotemaraton
240
HV
LV
CAEN OPCserver
PVSS IIOPC client
S2B03
Wiener OPCserver
PVSS IIOPC client
44
Distributor
24
HV
SY1527A1520P
8
Wienercontrol unit
4
TOTEM DCS – Hardware overview diagrams
Low voltageHigh voltage
AC/DCpower rectifier
S4F10
cardsA B C D
2 in RR532 in RR57
4
1 shared2 cards
Tun
nel
Rom
an P
ots
TOTEM-DCS-02 TOTEM-DCS-02
4
1
1 crate4 cards
E CMS TN
two sides
OK OK
RP Station Patch Panel
Cou
ntin
g R
oom
(U
SC
55)
High Voltage•All Power Supplies installed and tested •All cables tested•Distributor Box (240 to 24) installed and tested
Low Voltage•All the chain installed •All cables tested •“2.5 V” tested at the Pots in 56
•Overcurrent still to be regulated
Roman Pot Motorisation
See Mario
’s talk
in
previous r
eview
• Calibration of all the motors for the 12 pots is being completed (laser tracker)
• PXI and FESA (soft.) completely tested and running in the lab
• PXI and FESA (soft.) installed in IP5• Interlock box ready by end of Sept.• Final Overall Test with CCC foreseen first two
weeks in October
Hybrid Motherboard
Counting Room Detector Package
DAQ CRATE
Control, Trigger and DAQ
Connection of control cables and fibers in the tunnel Control loop power-up and test
Access to the CCUs and DOHs registersPower-up and calibration of the LV
Fibers connection in the CR Hardware probing
Power-up of HVVFATs Calibration
Sec
tor
56
Sec
tor
45DOHM
fibersfanouts
Available resources, available time…PH-TOT (+Collab.)G. AntchevI. AttannasovV. AvatiM. DaileF. Lucas Rodrig.J. Kopal E. RadermacherE. RadicioniF. RavottiG.RuggieroV. Vaceck +1
PH-DTE. DavidA. De OliveiraC. JoramL. KottelatJ. NoelX. PonsS. Rangod S. RavatH. Sabba
PH-ESEJ. MorantW. Snoeys
OTHER DEPTsO. Crespo-LopezM. DutourM. DupontP. FeraudetA. Perrot
11
• All efforts concentrated on the stations at 220m• Most of the work limited by access to the tunnel (these
activities almost completed).
• Unforeseen two weeks of no cooling has affected the advancement of the commissioning of the RPs
People (physicists, engineers, technicians, students…) helping in this phase of the project.
Not all 100%!!!
New DPs for the stations at 147m
12
Available at:http://spreadsheets.google.com/pub?key=pzsoquTCfFRtXs_kHZq7FFg&gid=0
(Table updated continuously)
The production for the pots at 147m is continuing. Nevertheless, at this stage is hard to produce a reliable planning for these items
51 hybrids at different stages of
their assembly