Open Compute Project (OCP)Architectures, Systems & Products evolution
Confidential Property of Schneider Electric |
Brice Martinot-LagardeGlobal Solution Architect, Cloud & Service Providers segmentSept 2018
Page 2Confidential Property of Schneider Electric |
Schneider Electric in OCP
OCP design impact
Rack, Power Supply & Battery
Electrical Architecture evolution
DCIM to Cloud : DMaaSData center Management as a Service
Page 2Confidential Property of Schneider Electric |
Schneider Electric in OCP
Some members…
OCP is 9+ technical areas
Page 5Confidential Property of Schneider Electric | Source OCP
Security
Schneider Electric contribution
Page 6Confidential Property of Schneider Electric |
• Engage with the community and customers whom are serious about deploying OCP
• Track the trends, better understand solution needs, leverage our data center expertise
• Leverage our experience with China Internet Giants (BAT) and duplicate the model for OCP
• Evaluate market momentum and implications to portfolio and coverage
• Develop and promote solutions within the community, including IGs
• PowerSupply (PSU), BatteryBack-up (BBU), Open Rack, HyperPod
• Leverage high market interest in OCP
• White Papers, TradeOff Tools and Reference Designs will help establish our expertise
Schneider’s ObjectivesOpen Compute Project
Confidential Property of Schneider Electric
Open solutions is an ITD growth initiative
We are developing OCP components• Gemini 15kW 12VDC PSU OCP Inspired• Schneider V2 rack submitted as OCP Inspired• HyperPod facilitates integrated OCP rack deployments• Liang Zhang and his team are leading development efforts
Schneider is an OCP Platinum member• We have been a member since 2014• Schneider is “Incubation Committee” representative for the Data Center
Facility Project
We are educating the market on the implications of the OCP architecture
• 56MW reference design, Trade-off Tool, 2 White papers, blog posts
We are developing relationships with ODM (Original Design Manufacturer) and IT integrators
Confidential Property of Schneider Electric
Resources> Contacts:
• Liang Zhang: [email protected] (Open Rack Solutions initiative owner)
• Rob Bunger: [email protected] (OCP Organization POC)
> Open Compute Landing Web Page
> WP228: Analysis of Data Center Architectures Supporting Open Compute Project (OCP) Designs
> WP232: Open Compute Project PSUs vs. Traditional PSUs: a Quantitative Analysis
> TradeOff Tool 18: Traditional vs. OCP Power Architecture Capex Comparison
> Reference Design 101: 56 MW (IEC), OCP-compatible, indirect aircooling, 55000 m2
> Open Compute Project home page• http://www.opencompute.org/
> Latest Open Rack designs• http://www.opencompute.org/wiki/Open_Rack/SpecsAndDesigns
> Schneider submits Operations Model• http://www.datacenterknowledge.com/archives/2015/03/11/schneider-submits-data-center-operations-model-to-ocp/
> Background article on Open Compute Project (June 2015)• http://www.businessinsider.com/facebook-open-compute-project-history-2015-6
Page 9Confidential Property of Schneider Electric |
OCP design impact
SVR
SVR
SVR
SVR
SVR
SVR
SVR
SVR
PSU PSU
PSU PSU
PSU PSU
PSU PSU
PSU PSU
PSU PSU
PSU PSU
PSU PSU
PSU w/ LI
PSU w/ LI
OCP Svrs
OCP Svrs
OCP Svrs
OCP Svrs
OCP Svrs
OCP Svrs
Standard RackWith Servers
Open Compute Project (OCP) V2
PDU
400/2305 wire
UPS Sys
LV UPS System Rack PDU Standard IT Rack
Rack with 12 or 48VDC bus
Rack PDU
Rack level UPS with 12/48VDC
output////////
Consolidated server power supplies with local energy
storage
3 Phase PDU
(RPP)
OCP Architecture (with rack level batteries)Animated Slide
• IT / OT manufacturers are converging to specify a real “end-to end” solution
• Give logical choice on design from grid to rack in AC and inside rack removing silos
• Reduce AC/DC conversion
• Solve questions of centralized vs. distributed UPS and also the technology choice
• Rack/server integration (drawers) and connectivity (bus) , in operation (safety, fast to replace), better efficiency on cooling
Open Compute Project Benefits
Efficiency
Availability
Time To MarketHigh Scalability‘Pay as you Grow’
Return Of InvestmentTotal Cost
Life Cycle Services
Servers &
fans
Servers &
fans
Switch
PSU
Servers
Servers
Servers
Servers
servers and fans
servers and fans
PSU
front
switch
rear fan wall
China: Scorpio v2
front no rear fan wall
PSU
OCP v2
PSU & Switch
Other specs
front rear fan wall
OCP impact Cooling design
Rack, Power Supply & Battery Back-up
Page 13Confidential Property of Schneider Electric |
Confidential Property of Schneider Electric
PSU & BusbarN+1 PSU1 pair Copper BusbarHot plug Server ClipsDC 12v Output450A MAX.
Server ShelvesFor server LxWxH: 550mmx539mmx2OU50kg MAX. loading
All-in-One RackAssemble Servers + PSUs + Busbar + Cabling in factory.Connect Only Power cord and Network in Datacenter.Deploy 100+ Racks (= 4000+ Servers) in 1 day.
Frame structureHeight: 2220mmWidth: 600mmDepth: 1067mm1500kg transport weightDynamic load: 1400Kg
Open Computer Rack (OCP V2.0 specs)
UL, Facebook OCPNo back door fans
As of 2017, there are 3 main server and rack designs in OCP
Open Rack V2• This is the most well-known OCP design.• Rack has 21” mounting rails and bigger “U” spacing.• Centralized rack level PSU and option for rack level Li-ion batteries (currently, only
Facebook and Google deploy rack batteries).• 12VDC (Facebook & others) or 48VDC (Google) backplane options.
Project Olympus• Developed by Microsoft• Servers fit standard 19” rack• Servers have internal redundant 3-phase PSUs and are fed by a specialized universal
rPDU. No batteries in the server or rack.
CG-OpenRack-19 (Carrier Grade)• Developed by Radisys within the Telco Project.• Similar to Open Rack V2 but in 19” rack.• Limited deployments at Verizon as of 2018.
OCP impact to data center electrical designNot all OCP designs have batteries in the rack
CG-OpenRack-19
Project Olympus
Open Rack V2
Confidential Property of Schneider Electric
Scorpio System
OCP System(*Details in Backup slide)
19” HD Systems
Rack OCP Li-on BatteryOCP Power
Product Category
Total Solution for Hyperscale White Space
Confidential Property of Schneider Electric
Meeting more complex demands with a partnership
Offerings
Priorities Solutions
• Mitigate risk
• Optimise & Lower operating costs
• Reduce & preserve capital
• Increase speed to market
• Improve customer satisfaction
• Gain a competitive edge
• Custom Engineering
• Combined IT & Infrastructure offers
• “Open” Innovation from plant to processor
• Global Supply Standardisation
• Pre-integrated modular solutions from container to rack to U
• Operational and lifecycle services
Adaptable
Innovation & Evaluation
Open Efficient
Technology and Engineering focused on profitable partnerships
Page 18Confidential Property of Schneider Electric |
HyperPod successfully addresses the growing trend of IT equipment being deployed rack-by-rack, rather than server-by-server.
� Fast � Speeds up deployment and integrates fully configured racks
� Flexible � Compatible with many power/cooling/rack configurations
� Simple � Standardize design and deployment by scaling at pod level
� Cost Effective � Lower overall deployment cost
Software defined power improving efficiency at the PSU
� Programmable � power sharing improving efficiency at the PSU
� Dynamic � PSU module redundancy depending on load condition.
� Efficient � Continuously tracks load vs efficiency and compare the data to the
efficiency profile of the power module
80
85
90
95
10 20 30 40 50 60 70 80 90 100
Efficiency %
Power Load %
Open Architectures ongoing investment in technical evaluation and product development
� Open Compute Project � V2 Rack, powershelf and Lion Battery pack development
� Open 19 � Rack & Cage, Ready Product, powershelf in development
� SCORPIO � No 1 in Scorpio Rack (>90% share) Full Power Solution, leading in Li-on BBU Offers
Page 7Confidential Property of Schneider Electric |
Electrical Architecture impact & evolution
Page 20Confidential Property of Schneider Electric |
2 Different Electrical Architectures
“OCP” typical Design
MV Gear
MV Gear
MV Gear
BBU
IT Enclosure
LV Gear
Busway
PSU
Optimized Traditional 2N Design
IT Enclosure
LV Gear
Busway
G
MV Gear MV Gear
G G G G
MV Gear
UPS
UPS
UPS
LV Gear
RPDU RPDU
LV Gear
Busway
UPS
UPS
UPS
LV Gear
Utility connectivity
Medium Voltage
Low Voltage& Critical power
Racks & IT space
Back-upgeneration
Traditional 2N vs. Open Compute Specific 1N
Page 21Confidential Property of Schneider Electric |
0,87
0,22 0,150,34 1,53
0,03
2,77
Open Compute
Specific 1N
Power supplies
BatteriesUPSRack system
RedundancyTraditional 2N
$ / w
att
45% capex savings
Critical questions arise about what is upstream of the rack…
?How can I mix SLAs*?
How do I support Traditional and Open Compute racks?
What does my power architecture looks like?
Page 22Confidential Property of Schneider Electric |
LV distribution
~
kWh
Utility Network
MVdistribution
Utility
Data Center
If I adopt Open Compute…
*Service Level Agreement
Page 23Confidential Property of Schneider Electric |
Hybrid Electrical Architecture all 2N
MV Gear MV Gear
G G G G
MV Gear
LV Gear
Busway
UPS
UPS
UPS
LV GearTraditionnal LV/UPS power train
for existing or legacy2N
OCP power trains for OCP Rack
2N / dual attached
MV Gear MV Gear
G
LV Gear
Busway
UPS
UPS
UPS
LV Gear
LV Gear
Busway
LV Gear
Busway
………..
Page 24Confidential Property of Schneider Electric |
Hybrid Electrical Architecture 2N and N with dedicated power train
MV Gear MV Gear
G G G G
MV Gear
LV Gear
Busway
UPS
UPS
UPS
LV Gear
Low Voltage& Critical power
Racks & IT space
MV Gear MV Gear
G
LV Gear
Busway
UPS
UPS
UPS
LV Gear
Busway
LV Gear
Busway
Busway
LV Gear
Busway
LV Gear
Busway
LV Gear
Busway
……………….
…
LV Gear
Busway
LV Gear
Busway
Traditional vs. OCP-based designs
$2.77/watt
$1.53/watt
$2.08/watt
Traditional2N
Open Compute 1N Open Compute 2N
We think most will want to maintain
2N (Tier 3) redundancy
25% savings
1N on LV distribution45% savings
A design that accommodates both types of loads
$2,77
$1,53
$2,08$2,150 to 0.23
Traditional2N
Open ComputeSpecific 1N
Open ComputeSpecific 2N
Simplified 2N
Premium for traditional power supplies (PSUs) depends on mix of loadsAssumes $0.46 traditional PSU cost per watt of IT load
$ / w
att
DCIM to Cloud : DMaaS(Data center Management as a Service)
Digital TRAFFIC
Page 3Confidential Property of Schneider Electric |
IoT and major IT trends
Source: Cisco Cloud Index Report 2015
Internet of THINGS
Source: Gartner, 2016
3xgrowth of global data center IP traffic over the next 5 years
20.8 Bconnected things by 2020
DataPRIVACY
Source: EU Data Protection Reform
Up to 4%total annual turnover fine for failing to comply with the EU’s GDPR by 2018
EdgeCOMPUTING
Source: IDC WW IoT Predictions, 2015
40% of IoT data will be stored, processed, analyzed and acted upon at the edge
Offer PositioningShift to cloud opens up a range of new possibilities
EcoStruxure Data Lake
Visibility
Val
ue
What happened?
Descriptive Analytics
Why did it happen?
Diagnostic Analytics
What will happen?
Predictive Analytics
What are the options?
Prescriptive Analytics
Hindsight ForesightInsight
Evolution of DCIM analytical capabilities
Source: Adapted from Gartner, Modern data and analytics, 2017
Main Goals
Improved Architecture• Web-based browser• Disaster Recovery Support• Scalability
Improved Monitoring Capabilities• Incidents vs. Alarms• Anomaly Detection• Root Cause Analysis
Predictive Analytics• Health Planning• Proactive Lifecycle Management• Recommendations for Optimization
An open, interoperable IoT-enabled architecture for actionable business insights
Connected Products
Edge Control
Apps, Analytics & Services
End
to E
nd
Cyb
erse
curit
yC
loud
and
/or
On
Pre
mis
e
InfrastructureBuilding Data Center Industry
EcoStruxureArchitecture
EcoStruxure TM
GridEcoStruxure TM
ITEcoStruxure TM
PlantEcoStruxure TM
MachineEcoStruxure TM
BuildingEcoStruxureTM
Power
Schneider Electric Connectivity & Digital Services platform
Page 30Confidential Property of Schneider Electric | https://www.youtube.com/watch?v=ZGrch1-Wm9A
Cloud-based
EcoStruxure Asset AdvisorRemote Monitoring Service
EcoStruxure IT AdvisorPlanning & ModelingQ4 2018EcoStruxure IT
App
EcoStruxure IT ExpertMonitoringQ3 2018
On-premises
StruxureWare Data Center ExpertMonitoring
StruxureWare Data Center OperationPlanning & Modeling
EcoStruxure IT Software & Services
MARKETPRIMARY SECONDARY
Data Centers
Data CentersEdge
Data Centers
Edge
Data Centers
Edge
Page 9Confidential Property of Schneider Electric |
Page 32Confidential Property of Schneider Electric |
Operational challengesEcoStruxure IT cloud enabled DCIM is designed to meet these challenges
Visibility
Supply Chain Value
Scalability
Availability
Customer Satisfaction
Capital Budget and Resource Efficiency
Capacity Management
Availability
For the End-user For the Service Provider
Page 33Confidential Property of Schneider Electric |
EcoStruxure IT ExpertComponents
+ +EcoStruxure Gateway
Discovers devices Transmits data to our cloud
Web ApplicationLive data & alarms
Asset dataInventory
Sensor valuesBenchmarking
Smartphone AppLive data & alarms
Asset dataInventory
Sensor valuesTwo factor authentication
EcoStruxure IT software and services
Page 25Confidential Property of Schneider Electric |
Page 35Confidential Property of Schneider Electric |
CyberSecurity
• Standards & regulationIEC 62443 / 270x / GDPR…• IT & OT convergence• From R&D in products• SE engagementrules & trainings• Includes Systems& Architecures• People certifications & Services capabilities• Partnerships• Portal & White papers
Page 36Confidential Property of Schneider Electric |
Deploying the future
THE CUSTOMERWAY
SCHNEIDER ELECTRIC SERVICE BUREAU
Peace of mind
24/7 extra pair of eyes
Incident resolution
Expert recommendations
YOUR PREFERRED PARTNER
Actionable insights
Customer reports
Ticketing interface
PSA/RMM integration EOL
recommendations
Customer health
Assessments
Partner interface
EcoStruxure IT
customized to the end-user specific needs
DIY
SaaS
Mobility
Monitoring
AnalyticsEcoStruxure IT ExpertEcoStruxure IT Advisor
EcoStruxure Asset Advisor
EcoStruxure IT for Partners
FACILITY OPERATIONS
Expert support
“The biggest challenge is keeping everything good (normal operating status) because it’s not just monitoring the alarm, the alerts, etc., it’s resolving them.”Customer - 451 Research, 2017
The power of the cloud for centralized Data Center and Regional EdgeKey benefits when connecting to EcoStruxure IT
Easy to get started
Access from anywhere, at anytime
Vendor Neutral Data Analytics
Up-to-date cyber security
Automatic software updates
and backup
Page 20Confidential Property of Schneider Electric |