onagawa nps dose reduction
DESCRIPTION
ONAGAWA NPS Dose Reduction. October 12, 2006 TOHOKU Electric Power Co.,Inc. Miyagi Prefecture. Location. Onagawa NPS. Specifications. Annual Average Dose. Average of BWRs in Japan. Unit2 Operation started. Unit3 Operation started. Unit 1 Operation started. - PowerPoint PPT PresentationTRANSCRIPT
ONAGAWA NPS ONAGAWA NPS Dose ReductionDose Reduction
October 12, 2006 TOHOKU Electric Power Co.,Inc.
Location Miyagi Prefecture
Onagawa NPS
SpecificationsOnagawa NPS Unit 1 Unit 2 Unit 3
Commercial Operation start 1984
Jun.
1995Jul.
2002
Jan.
Reactor type BWR4 BWR5 BWR5
Electric Power(MWe) 524 825 825
Condensate Treatment CFD & CD CF & CD
RWCU(% of Feed Water) 2.8 3.0 3.0
Annual Average Dose
0.0
0.5
1.0
1.5
2.0
2.5
3.0
Year
mSv/Y
Unit 1
Operation started
Unit2
Operation started
Unit3
Operation started
Average of
BWRs in Japan
Annual Collective Dose
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
Year
person
Sv/Y
・
Unit 1
Operation started
Unit2
Operation started
Unit3
Operation started
Onagawa NPS Outage Dose
0.01.02.03.04.05.0
#1 #2 #3 #4 #5 #6 #7 #8 #9 #10 #11 #12 #13 #14 #15 #16
person
Sv
・
0.01.02.03.04.05.0
#1 #2 #3 #4 #5 #6 #7 - - - - - - - - -
person
Sv
・
0.01.02.03.04.05.0
#1 #2 #3 - - - - - - - - - - - - -
person
Sv
・
Unit 1
Unit 2
Unit 3
Our Dose Reduction Strategy
1. Measures on the design stage
2. Clean-Plant operations on the construction stage and the test run operation stage
3. Continuous Dose Reduction
Dose Reduction
Reducing Radiation
Shortening exposure time
CRUD reduction
Improvement of Working environment
Improvement of equipment Automation/Remote operation
Use of Low-Co materials
1.Dose Reduction Measures on the design stage
CRUD Generation Control
Shielding Optimization
Improvement of Water Treatment Capability
2.Clean-Plant operations on the construction
stage and the test run operation stage
・ Keep Work area clean
・ Use wrapping against construction dust
・ Introduce Water chemistry technologies
3. Continuous Dose Reduction
3-1. Management of Workers’ Dose Data
3-2. Monitoring of Dust & Radiation
3-3. Water Chemistry Technologies
3-4. Dose Reduction at Outages
3-1.Management of Workers’ Dose Data
Alarm Personnel Dosimeter
Work Code Input Device
Work Code
Work Code Work Code & Dose data & Dose data
Controlled area
Work Code and Dose data
3-2.Monitoring of Dust & Radiation
3-3 . Water chemistry
Dose rate of PLR piping of our plants are remarkably low compared to other plants.
0
1
2
3
0 2 4 6 8 10 12 14 16 18Annual Outage
Dos
e R
ate
at R
ecir
cula
tion
Pip
ing
(mSv
/hr)
Unit-1Unit-2Unit-3
Typical Japanese BWRs
3-4. Dose Reduction at Outages
• Education program for foremen during Outage
• Holding “HP work Schedule meetings” periodically
• HP Patrol during Outage frequently
• Posting up the Detailed Radiation Map of D/W area
Special issue in 2005
We performed special activities for
1. Unit 3 Fuel Leakage …Our first experience
2. Earth Quake on Aug.16,2005
1 . Unit 3 Fuel Leakage
On Jul.2,2005 We first experienced fuel leakage at Unit 3 resulted in the increasing value of OG monitor .
Main measures we took were as follows :
Surveillance of OG
Prevention from intake of I-131
2 . Earth Quake (Aug.16,2005)
Seismic Center
Magnitude : 7.2
Depth : 42Km approx.
All Units in Operation were shut down automatically .
SCRAM triggers are set to
200 GAL: horizontal earthquake movement,
100 GAL : vertical .
2-1.Influence to electricity in 2005
0
500
1000
38443 38473.41 38503.82 38534.23 38564.64 38595.05 38625.46 38655.87 38686.28 38716.69 38747.1 38777.51 38807.92
0
500
1000
38443 38473.41 38503.82 38534.23 38564.64 38595.05 38625.46 38655.87 38686.28 38716.69 38747.1 38777.51 38807.92
0
500
1000
38443 38473.4 38503.8 38534.2 38564.6 38595 38625.4 38655.8 38686.2 38716.6 38747 38777.4 38807.8
Apr. May Jun. Jul. Aug. Sept. Oct. Nov. Dec. Jan. Feb. Mar.
Apr. May Jun. Jul. Aug. Sept. Oct. Nov. Dec. Jan. Feb. Mar.
Apr. May Jun. Jul. Aug. Sept. Oct. Nov. Dec. Jan. Feb. Mar.
Unit 1
Unit 2
Unit 3
MW
eM
We
MW
e
Earth Quake Aug.16
Earth Quake Aug.16
Earth Quake Aug.16
#3
#17
#7
2-2.Comparison of Outage Dose of Unit 3 before / after the Earth Quake
0.0
0.1
0.2
0.3
0.4
0.5
#2 #3
ma
n ・S
v
MSIV
RPV
PLR
SRV
CRD
ISIothers
Before After
Jun.10/2004
~ Oct.5/2004
Sep.27/2005
~ Apr.18/2006
Recent Annual Average Dose
0.0
0.5
1.0
1.5
2.0
2.5
3.0
2001 2002 2003 2004 2005
Year
mSv/Y Average of
BWRs in Japan
Unit3
Operation started
We keep going to make efforts for ALARA!