onagawa nps dose reduction

21
ONAGAWA NPS ONAGAWA NPS Dose Reduction Dose Reduction October 12, 2006 TOHOKU Electric Power Co.,Inc.

Upload: ogden

Post on 13-Jan-2016

31 views

Category:

Documents


1 download

DESCRIPTION

ONAGAWA NPS Dose Reduction. October 12, 2006 TOHOKU Electric Power Co.,Inc. Miyagi Prefecture. Location. Onagawa NPS. Specifications. Annual Average Dose. Average of BWRs in Japan. Unit2 Operation started. Unit3 Operation started. Unit 1 Operation started. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ONAGAWA NPS  Dose Reduction

ONAGAWA NPS ONAGAWA NPS Dose ReductionDose Reduction

October 12, 2006 TOHOKU Electric Power Co.,Inc.

Page 2: ONAGAWA NPS  Dose Reduction

Location Miyagi Prefecture

Onagawa NPS

Page 3: ONAGAWA NPS  Dose Reduction

SpecificationsOnagawa NPS Unit 1 Unit 2 Unit 3

Commercial Operation start 1984

Jun.

1995Jul.

2002

Jan.

Reactor type BWR4 BWR5 BWR5

Electric Power(MWe) 524 825 825

Condensate Treatment CFD & CD CF & CD

RWCU(% of Feed Water) 2.8 3.0 3.0

Page 4: ONAGAWA NPS  Dose Reduction

Annual Average Dose

0.0

0.5

1.0

1.5

2.0

2.5

3.0

Year

mSv/Y

Unit 1

Operation started

Unit2

Operation started

Unit3

Operation started

Average of

BWRs in Japan

Page 5: ONAGAWA NPS  Dose Reduction

Annual Collective Dose

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

Year

person

Sv/Y

Unit 1

Operation started

Unit2

Operation started

     Unit3

Operation started

Page 6: ONAGAWA NPS  Dose Reduction

Onagawa NPS Outage Dose

0.01.02.03.04.05.0

#1 #2 #3 #4 #5 #6 #7 #8 #9 #10 #11 #12 #13 #14 #15 #16

person

Sv

0.01.02.03.04.05.0

#1 #2 #3 #4 #5 #6 #7 - - - - - - - - -

person

Sv

0.01.02.03.04.05.0

#1 #2 #3 - - - - - - - - - - - - -

person

Sv

Unit 1

Unit 2

Unit 3

Page 7: ONAGAWA NPS  Dose Reduction

Our Dose Reduction Strategy

1. Measures on the design stage

2. Clean-Plant operations on the construction stage and the test run operation stage

3. Continuous Dose Reduction

Page 8: ONAGAWA NPS  Dose Reduction

Dose  Reduction

Reducing Radiation

Shortening exposure time

CRUD  reduction

Improvement of Working environment

Improvement of equipment Automation/Remote operation

Use of Low-Co materials

1.Dose Reduction Measures on the design stage

CRUD Generation Control

Shielding Optimization

Improvement of Water Treatment Capability

Page 9: ONAGAWA NPS  Dose Reduction

  2.Clean-Plant operations on the construction

stage and the test run operation stage

 ・  Keep Work area clean

 ・  Use wrapping against construction dust

 ・  Introduce Water chemistry technologies

Page 10: ONAGAWA NPS  Dose Reduction

  3. Continuous Dose Reduction

3-1. Management of Workers’ Dose Data

3-2. Monitoring of Dust & Radiation

3-3. Water Chemistry Technologies

3-4. Dose Reduction at Outages

Page 11: ONAGAWA NPS  Dose Reduction

3-1.Management of Workers’ Dose Data

Alarm Personnel Dosimeter

Work Code Input Device

Work Code

Work Code Work Code & Dose data & Dose data

Controlled area

Work Code and Dose data

Page 12: ONAGAWA NPS  Dose Reduction

3-2.Monitoring of Dust & Radiation

Page 13: ONAGAWA NPS  Dose Reduction

3-3 . Water chemistry

Dose rate of PLR piping of our plants are remarkably low compared to other plants.

0

1

2

3

0 2 4 6 8 10 12 14 16 18Annual Outage

Dos

e R

ate

at R

ecir

cula

tion

Pip

ing

(mSv

/hr)

Unit-1Unit-2Unit-3

Typical Japanese BWRs

Page 14: ONAGAWA NPS  Dose Reduction

3-4. Dose Reduction at Outages

•  Education program for foremen during Outage

•  Holding “HP work Schedule meetings” periodically

•  HP Patrol during Outage frequently

•  Posting up the Detailed Radiation Map of D/W area

Page 15: ONAGAWA NPS  Dose Reduction

Special issue in 2005

We performed special activities for

1.  Unit 3 Fuel Leakage …Our first experience

2.  Earth Quake on Aug.16,2005

Page 16: ONAGAWA NPS  Dose Reduction

1 . Unit 3 Fuel Leakage

On Jul.2,2005 We first experienced fuel leakage at Unit 3 resulted in the increasing value of OG monitor .

Main measures we took were as follows :

Surveillance of OG

Prevention from intake of I-131

Page 17: ONAGAWA NPS  Dose Reduction

2 . Earth Quake (Aug.16,2005)

Seismic Center

Magnitude : 7.2

Depth : 42Km approx.

All Units in Operation were shut down automatically .

SCRAM triggers are set to

200 GAL: horizontal earthquake movement,

100 GAL : vertical .

Page 18: ONAGAWA NPS  Dose Reduction

2-1.Influence to electricity in 2005

0

500

1000

38443 38473.41 38503.82 38534.23 38564.64 38595.05 38625.46 38655.87 38686.28 38716.69 38747.1 38777.51 38807.92

0

500

1000

38443 38473.41 38503.82 38534.23 38564.64 38595.05 38625.46 38655.87 38686.28 38716.69 38747.1 38777.51 38807.92

0

500

1000

38443 38473.4 38503.8 38534.2 38564.6 38595 38625.4 38655.8 38686.2 38716.6 38747 38777.4 38807.8

Apr. May Jun. Jul. Aug. Sept. Oct. Nov. Dec. Jan. Feb. Mar.

Apr. May Jun. Jul. Aug. Sept. Oct. Nov. Dec. Jan. Feb. Mar.

Apr. May Jun. Jul. Aug. Sept. Oct. Nov. Dec. Jan. Feb. Mar.

Unit 1

Unit 2

Unit 3

MW

eM

We

MW

e

Earth Quake Aug.16

Earth Quake Aug.16

Earth Quake Aug.16

#3

#17

#7

Page 19: ONAGAWA NPS  Dose Reduction

2-2.Comparison of Outage Dose of Unit 3 before / after the Earth Quake

0.0

0.1

0.2

0.3

0.4

0.5

#2 #3

ma

n ・S

v

MSIV

RPV

PLR

SRV

CRD

ISIothers

Before After

Jun.10/2004

      ~ Oct.5/2004

Sep.27/2005

      ~ Apr.18/2006

Page 20: ONAGAWA NPS  Dose Reduction

Recent Annual Average Dose

0.0

0.5

1.0

1.5

2.0

2.5

3.0

2001 2002 2003 2004 2005

Year

mSv/Y Average of

BWRs in Japan

Unit3

Operation started

Page 21: ONAGAWA NPS  Dose Reduction

We keep going to make efforts for ALARA!