omgt 312 – six sigma part ii - weeblyjyearportfolio.weebly.com/uploads/4/2/4/1/42411199/... ·...
TRANSCRIPT
RUNNING HEAD: FINAL PROJECT 1
Final Project:
The Referral Process
Jason Yearwood
OMGT 312 – Six Sigma Part II
August 16, 2014
Mr. Bruce A. Stephen
Southwestern College Professional Studies
Jason Yearwood Six Sigma Green Belt II Final Project 2
Six Sigma Overview
“The term Six Sigma is a reference to a particular goal of reducing defects to near zero.
Sigma is the Greek letter statisticians use to represent the “standard deviation of a population.”
The sigma, or standard deviation, tells you how much variability there is within a group of items.
In statistical terms,, therefore, the purposes of Six Sigma is to reduce variation to reduce
variation to achieve very small standard variations so that almost all of your products or services
meet or exceed customer expectations” (Pande, Neuman & Cavanaugh, 2002, p. 4).
“One virtue of Six Sigma is that it translates the messiness of variation of variation into a
clear black or white measure of success: either a product or service meets customer requirements
or it doesn’t. Anything that does not meet customer requirements is called a defect. [One]
approach to determining a sigma level is to calculate how many defects occur per opportunities
for things to go wrong. The outcome of this calculation is called Defects per Million”
Opportunities (DPMO) (Pande, Neuman & Cavanaugh, 2002, p. 6). “Six Sigma has three basic
parts, which are process improvement, process design/redesign, process management. These
parts are important because these three parts affect your organization and the process that were
established and are in use on a daily basis. Six Sigma teams when the project is focused on
process improvement finds the critical Xs (causes) that create the unwanted Ys (defects)
produced by the process” (Pande, Neuman & Cavanaugh, 2002, pp. 13-14).
Six Sigma teams use the five step DMAIC method to eliminate or reduce variation in
processes. Define the problem and what customer require, measure the defects and process
operation, Analyze the data and discover the problem, Improve the process to remove causes of
defects, and Control the process to make sure defects don’t recur. I would also add that the new
process must be monitored to ensure there is no variation in what was implemented (Pande,
Jason Yearwood Six Sigma Green Belt II Final Project 3
Neuman & Cavanaugh, 2002, p. 14). In this project, I will use the DMAIC method to eliminate
variation in the Referral Process.
Executive Summary
Introduction
The referral process is designed that when a repair part is requested, the requisition should not
leave Ft. Riley until all warehouses on post have been checked for parts availability. If the part
cannot be requisitioned on post, then and only then the requisition should go to the wholesale
level. We are finding some parts requisitions are leaving the post when we have the parts stocked
in our local warehouse. The results of the parts requisitions not filled at the local level are the
increased wait time and the waste of funds to ship a part from another location.
Analysis
The VoC interview revealed that on average 1-7 parts requisitions per week are being sent to the
wholesale level when there are parts available at the local level to fill the requisitions. The parts
that were requested and sent to wholesale are adding an additional wait time of 13-27 days on the
part to ship and arrive to the post. Once maintenance supervisors realize the part is on post, they
are tempted to walk the part thru and cancel the part that is in route to the post. Canceling the
part is not good supply discipline and maintenance supervisors get frustrated when their request
for walk-thru is denied.
Conclusion
The research shows that the referral process needs to be fixed in order for parts that is in the
warehouses on post would fill the parts requisition instead of the parts request going to
wholesale. Customer units should not have to wait 13-27 days for a part to be shipped and
received in order to fix non-mission capable equipment and vehicles.
Jason Yearwood Six Sigma Green Belt II Final Project 4
Recommendations
Recommend that parameter be set in the SARSS system to check the availability of parts more than once per the required 72 hrs.
Recommend that if the part is zero balance on hand that the SARSS system checks to see if any parts are due in to the warehouse to fill the requisition. If there is a part that is due in and the arrival date is shorter than the date wholesale can get the part to this location, assign part request against the part that is inbound.
Recommend that warning and signs are set in the SARSS system to give clerks inputting the data information to acquire the part in the shortest amount of time.
Recommend that all supervisors and clerks are trained on the new process.
Jason Yearwood Six Sigma Green Belt II Final Project 5
Table of Contents
Six Sigma Overview……………………………………………………………………2
Executive Summary…………………………………………………………………….3
Introduction (Define)….………………………………………………………………..6
Measurement and Analysis……………………………………………………………..8
Conclusion……………………………………………………………………………..10
Recommendations (Implementation)…………………………………………………..10
Works Cited –Appendices.……………………………………………………………..11
VoC Interview…………………………………………………………………..12
Data Analysis…………………………………………………………………...13
Introduction
Jason Yearwood Six Sigma Green Belt II Final Project 6
In the Army class IX parts are your repair parts for either ground vehicles or aircrafts. I
work as the Maintenance Management NCO for an Aviation Brigade and we are having some
issues with our class IX parts requisitions process.
The referral process has restrictions/interruptions in the system and customer requisitions
instead of being filled from a local warehouse, parts request are going to the whole sale market
nationally. This leads to costs unknown (this DMAIC Project will give us the costs) and an
average customer wait time that should be 3-5 days turns out to be 13-27 days. Customers are
complaining about parts that are stocked in our local warehouse that are not released to their
request, instead, the request is sent to other warehouses off of Ft. Riley on to the national level in
order for the requisition to be filled.
The requisition process has two sides to filling a parts request; the first part is as follows.
Units will order a part, the Standard Army Retail Supply System (SARSS) searches warehouses
on Ft. Riley to see if any of the five warehouses on post could fill this requisition. If there is a
warehouse on post that has the part, then the requisition is filled from the part that is at that
particular warehouse. A Material Request Order (MRO) is produced in the supplying
warehouse’s system and they release and ship by ground the part to requesting warehouse. This
process cost the Army the cost of the part and zero dollars because the fuel to transport the parts
has already been paid for by a separate account.
The second part is as follows; the request would go out to the warehouses on post and if
the part is zero balance at all of the warehouses, then the part is sent to the wholesale level for
the requisition to be filled. The system only checks the warehouse one time within the 72 hrs
process and it moves on to the wholesale level. If there is a warehouse that has this particular
part inbound after the system checks, the system only recognizes that the warehouse is zero
Jason Yearwood Six Sigma Green Belt II Final Project 7
balance. Some warehouses are getting the parts somewhere between 4-7 days after the system
checks. The maintenance managers while checking their parts status realize that the warehouse is
stocked with the part they need and the part that is coming from wholesale is still on its way to
their location. Some maintenance managers attempt to use the walk-thru process to acquire the
part that is in the warehouse and attempt to cancel the part that is in route.
As the approver of such requests, we deny them immediately and inform them to wait for
their part that is ordered to arrive. We normally approve the parts request with mission essential
considerations and the number of days the equipment or vehicle has been non-mission capable.
Another issue is while the unit has their part and has fixed the vehicle, there is still a requisition
in the supply system that is processing a part to send to the unit. What that means is the unit will
end up paying for that part twice and that is not good supply discipline or maintenance
management.
This project was selected to complete at this time because four of the five customer units
have experienced a delay in parts, complained numerous times and numerous times we have
failed to gain a thorough understanding of why this problem exists. Completing this DMAIC
project will give units a better understanding of the parts requisition process and give us options
as maintainers; especially when we are in a deployed environment and units are spread
throughout theatre. This project will need six members of the logistical management team and
will cost the Army nothing because we are all doing this while at work. The time frame to
complete this DMAIC project will be five weeks, a week for each phase of the DMAIC project.
The goal is to reduce the number of referrals that go wholesale and improve customer
wait time for parts. Conduct a DMAIC project to figure out why requisitions are not being filled
with parts from warehouses at Ft. Riley and are leaving the post for the orders to be filled by
Jason Yearwood Six Sigma Green Belt II Final Project 8
other warehouses at the national level. The reduction of these wait time will also improve our
overall readiness rate.
Measurement and Analysis
After several complaints from customer units about the referral process, the logistics
management team decided to interview the customer unit’s maintenance managers about their
pains with the referral process. The interview lasted about one hour and the interviewees were
the maintenance managers for each of our five customer units. The interview revealed that the
referral process has been failing every customer unit over the past year and most recently 80% of
the customer units have been frustrated about the referral process; because of the increased
customer wait time and the availability of parts at the local warehouse.
The analysis revealed range for part prices fall between $1000.00 and $7,000.00, the
average ship price is given according to the supplier, location of shipper and number of days
required for part (i.e. high-priority part). The price range to ship parts falls between $400.00 and
$7,000.00 to ship from anywhere in the United States. If part has to travel from an overseas
location, the costs are substantially higher. The warehouse is 5 minutes down the road and if the
clerk drives in a military vehicle to pick up the parts, the government is only charged the cost of
the part, the fuel and shipping is free. Out of 354 parts that were ordered in a month’s time, 52
parts went to national was it was later discovered that only 32 of those parts should have went to
national. The total cost the unit incurred for those parts going to national were $35,019.58. The
average customer wait time was 13-27 days for the parts to ship and arrive at this location. (See
Table 1)
Jason Yearwood Six Sigma Green Belt II Final Project 9
The final issue for the maintenance managers is when they fall below the Army standard
of 90% of operational readiness. The added wait time and the number of equipment and vehicles
that are non-mission capable affect the operational level. The equipment and vehicle could be
collecting down time for two reasons, the first one is for maintenance, meaning the vehicle is in
the shop and being repaired because the parts have arrived and the mechanics are available to
work on the job. The second reasons for collecting down time is due to supply time, meaning
how long it takes for the parts to be processed and shipped to a certain destination. Both times
are reviewed monthly and at the higher headquarters level and while you can explain the
maintenance wait time, you could only voice your frustration with the supply wait time because
that is the way the referral system is currently set up.
Table-1 Data for 20 Parts Sent to Wholesale
# of parts per location
Army Depot Location Cost of Parts Cost of Shipping
Average Customer Wait
Time2 Sierra Army Depot, CA $7,968.50 $3,097.40 133 Red River Army Depot, TX $1,865.37 $567.01 267 Anniston Army Depot, AL $5,982.11 $7,234.94 144 Sierra Army Depot, CA $2,245.08 $1,765.43 153 Red River Army Depot, TX $1,007.63 $1,581.55 171 Letterkenney Army Depot, PA $1,276.54 $428.11 27
Totals: 20 parts 6 Army Depots $20,345.23 $14,674.35 13-27 Days
In the age of rapid deployment and units mandated to remain in a state of operational
readiness, units need predictability as part of their planning process. The referral system hinders
the planning when it comes to equipment available to conduct missions worldwide. When a unit
is not able to conduct its war time mission or support the war fighting exercises, there could be
significant consequences for unit commanders. This referral process affect not only readiness, it
is not practicing good supply discipline, sound maintenance practices, and the additional costs of
acquiring and shipping parts from different locations.
Jason Yearwood Six Sigma Green Belt II Final Project 10
Conclusion
The analysis clearly reveals that the referral system needs to be revamped. The unit is incurring
additional shipping costs; it affects unit readiness, and additional customer wait time. In this
technological age, we should be able to locate parts and resource warehouse that are local instead
of sending parts request to the whole sale level. This project is fully supported by the higher
headquarters and they expect a change in the system that is more aligned with the support the
unit is expected to support to ground troops. The changes made to this system would eliminate
the need to explain the frustrations with waiting for parts to arrive that are already stocked in
local warehouses; it would give unit leaders predictability in planning mission support and
alleviate additional shipping costs.
Recommendations
Set parameters in SARSS to check part availability more than once in the prescribed 72 hrs. (Warehouses might have received the parts after the first checks)
If parts are zero balance, check due-ins and if there are due-ins that is not dedicated to another job, dedicate the part to this parts request.
Set parameters in order for the SARSS to compare shipping times based on location of parts on the wholesale level to the shipping time of due-ins to the local warehouse. If the ship and delivery date is greater for the part dedicated to the local warehouse, then assign parts request to warehouse on the wholesale level and vice versa.
Develop status boxes to identify when parts requests are going to be filled at the wholesale level and give an estimated ship and delivery date.
Recommend that unit maintenance managers, supervisors, and clerks be trained on the new parameters and processes with the SARSS.
Monitor and pull unit data quarterly to ensure the system parameters are working. The SARSS system along with the processes will be inspected semi-annually as part of the Command Discipline Supply Program.
Jason Yearwood Six Sigma Green Belt II Final Project 11
Works Cited – Appendices
The tools used in this project were VoC interview and statistical data analysis. SARSS computer, the SARSS end-users manual, interview with Mr. Hornbaker, supply warehouse manager, interview with maintenance managers, CSDP guidance checklist, SAMS1-E computer and end-users manual, SAMS2-E computer and end users manual.
References
Pande, P., S., Neuman R., P., & Cavanaugh, R., R. (2002). The Six Sigma Way Team Field Book. New York, NY: McGraw Hill
Jason Yearwood Six Sigma Green Belt II Final Project 12
Voice of the Customer Interview:
The team will be conducting face-to-face interviews with personnel from the affected units. The results from the face-to-face interviews conducted are as follows (each person was asked the same set of questions):
1. What problems have you encountered with the referral system?a. All five unit representative expressed disgust with the referral system. The system is
supposed to fill the requisitions at the local level in order for customer units to get the parts in a shorter time frame, thus reducing non-mission capable time. The Army conducts and evaluation every month that evaluates the different reasons equipment are non-mission capable. One of the areas that are evaluated is how long the non-mission capable equipment is affected by the supply process or by maintenance procedures (i.e. days in the shop after part is received). The system recognizes that local warehouses are stocked with basic parts according to the fleet at that location and parts are readily available. Instead the customer units have encountered wait times anywhere between 13-27 days depending on the location of the supplier and shipper.
b. How many parts per week are referred to wholesale when the part is sitting in a local warehouse?
a. On average 7-10 parts of different prices are referred to the wholesale level per customer units. (35-50 parts per month for all units combined)c. What is the average wait time as a result of the requisition being filled at the
wholesale level?a. The average wait time increase goes from a normal 3-5 days if filled locally to 13-27
days if filled at the wholesale level.d. How does this affect your maintenance readiness program?
a. The maintenance program is affected because our readiness rate reflects that we have critical equipment down for a period of time. When your readiness rate is < 90% then you have to answer to the higher headquarters. Usually when the parts arrive the mechanics have to work later than usual to get the equipment fully mission capable because the supply side of the maintenance process took up most of the allotted time for the part to arrive. e. What have you done to rectify the problem?f. The units have brought this issue to the attention of the maintenance manager, the
warehouse manager, and also the regional materials manager. g. What were the results of your inquiry?
a. None of these individuals could explain why the requisition process is not working like it should.h. How would fixing the problem reduce or eliminate your pain?
a. Fixing the problem would ensure the referral process is working and parts request are filled at the local level instead of being filled at the wholesale level. It would also help the readiness rate and reduce down time of critical equipment of the units affected and mechanics would not have to work later than usual in order to get the equipment fully mission capable. There could also be some predictability in the maintenance and supply process. It would also save the Army some money on shipping costs of the parts.
Jason Yearwood Six Sigma Green Belt II Final Project 13
The Define Phase Questions
1. What is the name of the process?a. Referral Process
2. What is the aim of the process?a. To fix referral process and shorten wait time for parts.
3. What is the business case (economic rationale) for the project?a. To save money for shipping cost of parts.
4. Why conduct the Referral project at all?a. The Army is spending extra money to ship parts on the wholesale level when the
parts are at one of several local warehouses. 5. Why conduct the Referral project now?
a. The Army tracks how many parts are referred to wholesale and it is part of the Command Supply Discipline Program (CSDP). The unit received a failing grade in this area of the annual inspection. In this fiscal age of downsizing and limited budget, fixing the referral process would save substantial funds for the Army.
6. What business objectives are supported by the Referral project?a. The Referral project is most strongly related to “saving shipping cost” and “reduce
customer wait time” business objectives.7. What are the consequences of not doing the project?
a. The consequences of not doing the project are wasted funds, long wait time for parts, referral system not fixed, and customer complaints.
8. What projects have higher or equal priority?a. This project has the highest priority.
9. What is the problem statement? What is the pain?a. The referral system is broken and long customer wait time for parts.
10. What is the goal (desired state) for this project?a. The goal is to fix the referral system and shorten customer wait time for parts.
11. What is the project scope?a. The following questions will answer this question:
12. What are the process boundaries?a. The starting point is when the clerk enters the data into the SAMS1E box. The
stopping point is when the part status is updated and allocated from a warehouse.13. What are the process boundaries?
a. The project team cannot contact the dedicated warehouse for part information.14. What resources are available for the project?
a. There are six team members, one Standard Army Maintenance System-Enhanced (SAMS1-E) computer, one Standard Army Retail Supply System (SARSS) computer, maintenance worksheets, logistical parts tracking website Logistics Information Warehouse (LIW), and one Standard Army Maintenance System-Enhanced SAMS2-E computer.
15. Who can approve expenditures?a. We will not have any expenditure.
16. How much can the team spend beyond the budget?a. We do not have a budget.
Jason Yearwood Six Sigma Green Belt II Final Project 14
17. What are the obstacles and constraints of the project?a. The obstacles might be people conducting work on the systems, time to interview
warehouse personnel, SAMS1E, 2E operators, LIW site is down, and the constraints would be no recordkeeping done by affected units or systems data purged as part of 45 day purging process.
18. What time commitment is expected of team members?a. Team members will work from 9:00 a.m. until 6:00 p.m. There may be times when
we have to work later because of systems failures or processing of data. 19. What will happen to each team member’s regular job while working on the project?
a. Team members will be replaced by other individuals and focus on the project.20. Is there a Gantt chart for the project?
a. Yes.21. What are the benefits of the project?
a. The soft benefits of the project are eliminating customer complaints about long wait times and fix the referral system. The hard benefits of the project are costs savings from shipping parts.
22. What are the roles and responsibilities of the team members? a. The team members are:
LT “C”-Maintenance OfficerSFC “N”-Maintenance SergeantChief “T”-Systems OfficerChief “S”-Warehouse ManagerSFC “H”-Materials Manager/ResearcherChief “Q”-Regional Materials Manager/Research
Jason Yearwood Six Sigma Green Belt II Final Project 15
Critical-to-Quality
This test was conducted to eliminate the hypothesis that the clerks were inputting the data incorrectly and causing the parts request to go straight to wholesale.
Operational Definition for CTQ 1: Accuracy of Data Input.Clerks follow steps for inputting data. Any steps missed could hinder parts ordering process.
Test:1. School trained clerk goes through steps for ordering parts.2. Parts ordering process is verified.
Decision:1. If the steps are performed accurately, process complete.2. If the steps are done incorrectly or are missed, clerk will go through entire process again.
Develop a Baseline for Each CTQ:
Shift Clerk Data AccuracyAM #1 10 parts 95%AM #2 10 parts 90%PM #3 10 parts 100%PM #4 10 parts 85%
Average Clerks 1, 2, 4 6 Parts Ordered Wrong 92.5%
*5% was deducted per missed step
Jason Yearwood Six Sigma Green Belt II Final Project 16
SIPOC Analysis (Current)
Suppliers Input (X) Process Output (Y) CustomersLocal Warehouses
Wholesale Warehouses(National) Data Start
Material Request Order (MRO)
Aviation Units Parts Requisitions
Parts request from customer unit
Customer Supported Units
Data splits and goes into two systems
Parts for Supported
Units
SAMSE and SARSS
SARSS checks local warehouse
If part is on hand, an MRO is issued to fill
requisition
If part not on hand
request goes to wholesale
Referral Process SIPOC Analysis
Jason Yearwood Six Sigma Green Belt II Final Project 17
SIPOC Analysis (New)
Suppliers Input (X) Process Output (Y) CustomersLocal Warehouses
Wholesale Warehouses
(National) Data Start
Material Release Order (MRO
Aviation Units
Parts Requisitions
Parts request from unit
Customer Supported Units
Data splits and goes to SAMSE and
SARSS
Parts for Customer
Units
SARSS checks local warehouse for parts
more than once
If local warehouse is zero balance; check
for due-ins
If due-ins are inbound dedicate part for this
parts request
If no parts are
inbound for local warehouse, send
requisition to wholesale
Referral Process SIPOC Analysis (RED indicates New Process)
Jason Yearwood Six Sigma Green Belt II Final Project 18
Risk Assessment Matrix
Risk Assesment Matrix How to
Risk Priority Monitor Action/ReactionWho
Implements Comments
1-10 (1-Highest)
Input of wrong data 1 Supervision Check data Supervisor Clerk not checking
parts due in 2 Supervision Have clerk verify checks by initialing Supervisor
Clerk not recognizing warning signs 3 Supervision Set parameters that
will not allow order to go through Supervisor
Clerk not assigning
part request with 2 SupervisionSupervisor will
check Supervisor part due in 3 times a day
Jason Yearwood Six Sigma Green Belt II Final Project 19
Referral Process
Table-II Dot Chart
0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 5.50
1
2
3
4
5
6
7
8
Parts Going to Wholesale
Y-Values
*Note in week-3 two days in that week there were 3 parts referred to wholesale.
Weeks
Jason Yearwood Six Sigma Green Belt II Final Project 20
Impact/Effect Matrix