Oil & Gas Drainage Task Force Meeting02/28/2020
![Page 2: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/2.jpg)
Drainage Calculation Process1. Site Information/Basin Delineation
2. Rainfall
3. Runoff Calculations
4. Detention
5. Culverts/Open Channels
![Page 3: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/3.jpg)
Weld County Preferred Formulas and Calculations• Runoffo Rational Methodo 2007 UD Runoff Coefficientso UD Rational v1.02a
• Detention oModified FAA Methodo UD Detention v2.35
![Page 4: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/4.jpg)
Rainfall Intensity
Source: USDCM 2004 (same as current edition)
![Page 5: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/5.jpg)
Time of Concentration
Source: USDCM 2007 (same as current edition)
![Page 6: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/6.jpg)
Time of Concentration (Overland/Initial)
Source: USDCM 2007 (same as current edition)
• Max length for rural = 500 feet• Max length for urban = 300 feet
![Page 7: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/7.jpg)
Time of Concentration (Channelized)
Source: USDCM 2007 (same as current edition)
![Page 8: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/8.jpg)
Time of Concentration (Channelized)
Source: USDCM 2018 (same as 2007 edition)
![Page 9: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/9.jpg)
Time of Concentration (Urban Check)
Source: USDCM 2007
Only to be used in urbanized growth areas or urban areas
![Page 10: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/10.jpg)
Runoff Coefficients, C
Source: USDCM 2007
![Page 11: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/11.jpg)
Runoff Coefficients, C
Source: USDCM 2007
![Page 12: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/12.jpg)
Runoff Coefficients, C
Source: USDCM 2007
![Page 13: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/13.jpg)
Runoff Coefficients, C
Source: USDCM 2007
![Page 14: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/14.jpg)
Runoff Coefficients, C
Source: USDCM 2007
![Page 15: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/15.jpg)
Detention
Source: USDCM 2011
![Page 16: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/16.jpg)
Detention
Source: USDCM 2011
![Page 17: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/17.jpg)
Detention
Source: USDCM 2011
![Page 18: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/18.jpg)
Detention
Source: USDCM 2011
![Page 19: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/19.jpg)
Culverts and Open Channels• Culverts
o HY‐8o Culvert Master
• Open Channels o Flowmastero AutoCAD
![Page 20: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/20.jpg)
Calculations
![Page 21: Oil Gas Drainage Task Force Meeting - weldgov.com](https://reader031.vdocuments.us/reader031/viewer/2022022712/621a2e2f4fd5b8409d50425e/html5/thumbnails/21.jpg)
Code Change Recommendations• Allow detention pond area to be calculated at 2% imperviousness (Policy Change)
• Allow alterative materials for the emergency spillway cutoff wall (Chapter 21)
• Allow retention ponds without a variance only for the construction phase (Chapter 21)
• Consider less than 1 foot of freeboard only for the construction phase (Chapter 21)
• Allow secondary containment areas to be subtracted from site imperviousness calculations (Chapter 21)
• NEW: Define the construction phase for oil and gas developments (Chapter 21)
• NEW: Allow a 5 cfs release rate only during the construction phase, production phase is still held to Chapter 8 requirements (Chapter 21)