• Construction Days Elapsed: 233• Construction Days Remaining: 487• Percent of Contract Days Elapsed:
32%
Construction Schedule: 720 days
• Notice to Proceed: 8/1/11• Original Completion Date: 7/20/13• Percent of Construction Completed:
30%
Projected Completion
Date: 7/20/2013