O’Hare Noise Compatibility Commission Illinois Route 490 Tollway Project Update January 11, 2019

Upload: others

Post on 11-Dec-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: O’Hare Noise Compatibility Commission

O’Hare Noise Compatibility Commission

Illinois Route 490 Tollway Project Update

January 11, 2019

Page 2: O’Hare Noise Compatibility Commission

Part of a dynamic transportation network • Connects to regional transit 

network• Supports three international 

airports• Part of one of the nation’s largest 

interstate systems

Five roadways294‐mile system across 12 countiesServes more than 1.6 million vehicles a day

About The Tollway

2January 11, 2019

Page 3: O’Hare Noise Compatibility Commission

Move Illinois Program 15‐year, $14 billion capital program  

3

Taking care of existing system ‐ $4 billion• Repair roads, bridges and interchanges  

Illinois Route 390, I‐490 Tollway ‐ $3.4 billion• Provide access to O’Hare International Airport

Central Tri‐State Tollway (I‐294) ‐ $4 billion• Reconstruct 22 miles at heart of the system 

Jane Addams Memorial Tollway (I‐90) –$2.5 billion

• Rebuild and widen 62 miles with transit options

I‐294/I‐57 Interchange ‐ $719 million• Connect two major interstates 

January 11, 2019

Page 4: O’Hare Noise Compatibility Commission

I‐490 Interchange – Enhanced Western Access

January 11, 2019 4

Page 5: O’Hare Noise Compatibility Commission

I‐490 Interchange/Western Access Construction

January 11, 2019 5

33 I‐490 Interchange – Western access ramp constructionScheduled: 2019 ‐ 2023

I‐490 Interchange – Illinois Route 83 to York Road construction Scheduled: 2019 – 2020 

11

O’Hare Airport perimeter fence and road relocation Completed: June 2018

33

221122

Page 6: O’Hare Noise Compatibility Commission

I‐490 Tollway North Segment Construction

January 11, 2019 6

11 I‐490/I‐90 Interchange bridgesScheduled: 2018 – 2019

22 I‐490/I‐90 Interchange bridges and fuel station removal Scheduled: 2018 – 2020

33 Touhy Avenue Reconstruction Project – Cook CountyScheduled: 2019 – 2021

11

2233

Page 7: O’Hare Noise Compatibility Commission

January 11, 2019 7

I‐490/I‐90 Interchange

Page 8: O’Hare Noise Compatibility Commission

January 11, 2019 8

I‐490/I‐294 Interchange

Page 9: O’Hare Noise Compatibility Commission

THANK YOU

January 11, 2019 9