office ppt template 029

Upload: zia-khan

Post on 14-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Office Ppt Template 029

    1/53

    NETWORK DIAGRAMMINGTECHINIQUES AND THEIRIMPORTANCE

    PRESENTERS:

    Sadia Nosheen 2k9-che-40

    Zia ullah 2k9-che-64

    Fakhar Abbas 2k9-che-122

    Waqas Ali 2k9-che-149

  • 7/30/2019 Office Ppt Template 029

    2/53

    CONTENTS

    Definition

    Types of network diagramss

    PERT & CPM

    Differences between PERT & CPM

    Terminologies Creating a PERT/CPM diagram

    Importance of network diagramming techinique

  • 7/30/2019 Office Ppt Template 029

    3/53

    Project Time Management

    Project time management involves the processesrequired to ensure timely completion of a project.Processes include:

    Activity definition Activity sequencing

    Activity duration estimating

    Schedule development Schedule control

  • 7/30/2019 Office Ppt Template 029

    4/53

    Schedule development

    Schedule converts action plan intooperating time table

    Basis for monitoring and controlling project

    Scheduling more important in projects thanin production, because unique nature

  • 7/30/2019 Office Ppt Template 029

    5/53

    Project Network Diagrams

    Project network diagrams are the preferredtechnique for showing activity sequencing

    A project network diagram is a schematic displayof the logical relationships among, or sequencing

    of, project activities Graphical portrayal of activities and event

    Shows dependency relationships betweentasks/activities in a project

    Clearly shows tasks that must precede(precedence) or follow (succeeding) other tasks ina logical manner

    Clear representation of plan a powerful tool forplanning and controlling project

  • 7/30/2019 Office Ppt Template 029

    6/53

    Network Diagrams CPM

    PERT

    Bar Charts Milestone Chart

    Gantt Chart

  • 7/30/2019 Office Ppt Template 029

    7/53

    Network Diagrams Developed in the 1950s

    A graphical representation of the tasks necessary

    to

    complete a project

    Clearly visualizes the flow of tasks &relationships

  • 7/30/2019 Office Ppt Template 029

    8/53

    Terminology Activity - A specific task or set of tasks that are

    required by the project, use up resources, andtake time to complete

    Event - The result of completing one or more

    activities. An identifiable end state occurring at aparticular time. Events use no resources.

    Network - The combination of all activities andevents define the project and the activityprecedence relationships

  • 7/30/2019 Office Ppt Template 029

    9/53

    Path - The series of connected activities (orintermediate events) between any two events in anetwork

    Critical - Activities, events, or paths which, ifdelayed, will delay the completion of the project.

    A projects critical path is understood to meanthat sequence of critical activities that connect theprojects start event to its finish event

    Dummy Activity

    Indicates only precedence relationships

    Does not require any time of effort

  • 7/30/2019 Office Ppt Template 029

    10/53

    A dummy activity may be needed:

    to prevent 2 or more activities sharingthe same starting and ending events.

    to maintain network logic i.e. toensure that the network abides by the

    precedence table.

    OK, tellme theworst!!

    Sometimes we have to use

    Dummy activities.

    We use a dashed arrow

    to record these.

  • 7/30/2019 Office Ppt Template 029

    11/53

    Arrows An arrow leads from tail to headdirectionally

    Nodes A node is represented by a circle

    ACTIVITYPRECEEDING SUCCESSOR

    EVENT

  • 7/30/2019 Office Ppt Template 029

    12/53

    Network Diagrams Two classic formats

    AOA: Activity on Arrow

    AON: Activity on Node

    Each activity labeled with

    Identifier (usually a letter/code)

    Duration (in standard unit like days)

  • 7/30/2019 Office Ppt Template 029

    13/53

    Formats

    Activity-on-arrow (AOA)

    Arrows represent activities and nodes are eventsfor points in time, It uses an arrow to depict anactivity.

    The length of arrow shows relative time

    to complete tasks

  • 7/30/2019 Office Ppt Template 029

    14/53

    Activity-on-node (AON)

    Nodes represent activities, and arrows showprecedence

    relationships, It uses a node to depict anactivity.

  • 7/30/2019 Office Ppt Template 029

    15/53

    Project Network Rules

    Networks typically flow from left toright.

    An activity can not begin until all of itspreceding activities are complete.

    Arrows indicate precedence and cancross over each other.

    Are there any rules tofollow when drawingnetwork diagrams?

  • 7/30/2019 Office Ppt Template 029

    16/53

    Identify each activity with a uniqueidentifier, this identifier must increment(1.2.3, A,B,C etc) as the network proceeds.

    Looping is not allowed.

    Conditional statements are not allowed.

    Use the start and stop nodes

  • 7/30/2019 Office Ppt Template 029

    17/53

    Time-Related Task

    Properties

  • 7/30/2019 Office Ppt Template 029

    18/53

    Situations in network

    diagram

    A

    B

    C

    A must finish before either Bor C can start

    A

    B

    C both A and B must finish

    before C can start

  • 7/30/2019 Office Ppt Template 029

    19/53

    D

    C

    B

    A

    both A and C must

    finish before either ofB or D can start

    A

    C

    B

    D

    DummyA must finish beforeB can start

    both A and C mustfinish before D canstart

  • 7/30/2019 Office Ppt Template 029

    20/53

    Example

    Develop the network for a project with followingactivities and immediate predecessors:

    Activity Immediatepredecessors

    A -

    B -

    C B

    D A, C

    E C

    F C

    G D,E,F

    Try to do for the first five (A,B,C,D,E) activities

  • 7/30/2019 Office Ppt Template 029

    21/53

    Network of first five activities

    1 3 4

    2

    5

    We need tointroduce a

    dummy activity

  • 7/30/2019 Office Ppt Template 029

    22/53

    Network Diagrams

    NETWORK TECHNIQUESNETWORK TECHNIQUES

    PERT

    -Program Evaluation andReview Technique

    - developed by the USNavy with BoozHamilton Lockheed

    - on the PolarisMissile/Submarineprogram 1958

    CPM

    Critical Path Method

    Developed by ElDupont for ChemicalPlant ShutdownProject- about

    same time as PERT

    Both use same calculations, almost similarMain difference is probabilistic and deterministic in time

    estimationGantt Chart also used in scheduling

  • 7/30/2019 Office Ppt Template 029

    23/53

    Critical Path Method (CPM)

    The Critical Path Method (CPM) is one of severalrelated techniques for doing project planning.CPM is for projects that are made up of a number

    of individual "activities." If some of the activitiesrequire other activities to finish before they canstart, then the project becomes a complex web ofactivities.

    It is used for one time estimations.

  • 7/30/2019 Office Ppt Template 029

    24/53

    CPM can help to figure out :

    1. how long the complex project will take tocomplete

    2. which activities are "critical," meaning that theyhave to be done on time or else the whole project

    will take longer

    WOW

  • 7/30/2019 Office Ppt Template 029

    25/53

    If you put in information about the cost ofeach activity, and how much it costs to

    speed up each activity, CPM can help tofigure out:

    1. whether you should try to speed up the project,

    and, if so, 2. what is the least costly way to speed up the

    project.

  • 7/30/2019 Office Ppt Template 029

    26/53

    Example

    Right, nowwell solve

    an exampleof CPM

  • 7/30/2019 Office Ppt Template 029

    27/53

    Doingwell!!!

  • 7/30/2019 Office Ppt Template 029

    28/53

    Keep going!!

    Find the total path and the critical path

  • 7/30/2019 Office Ppt Template 029

    29/53

    Critical path

  • 7/30/2019 Office Ppt Template 029

    30/53

    A Critical Path is a specific set of sequential tasks upon

    which the project completion date depends

    Tasks on the critical path cannot be delayed without

    delaying the project completion day If a task on the critical path is delayed by 1 day, then

    the project completion date is delayed (at least) by 1

    day

    All projects have at least one Critical PathCritical Paths are the paths with duration = total project

    duration

    CPM Ad t d

  • 7/30/2019 Office Ppt Template 029

    31/53

    CPM: Advantages and

    Disadvantages

    Advantages Show precedence well

    Reveal interdependencies not shown in other

    techniques Ability to calculate critical path

    Ability to perform what if exercises

  • 7/30/2019 Office Ppt Template 029

    32/53

    Disadvantages

    Default model assumes resources are unlimited You need to incorporate this yourself (Resource

    Dependencies) when determining the real CriticalPath

    Difficult to follow on large projects

  • 7/30/2019 Office Ppt Template 029

    33/53

  • 7/30/2019 Office Ppt Template 029

    34/53

    Purpose

    To simplify the planning and scheduling of largeand complex projects.

    To incorporate uncertainty in the sense that it waspossible to schedule a project not knowingprecisely the details and duration's of all theactivities.

    Event-oriented technique rather than start- andcompletion-oriented.

    Used more in R&D-type projects where Cost is not

    a major factor but Time is.

  • 7/30/2019 Office Ppt Template 029

    35/53

    Terminologies

    PERT event: is a point that marks the start or completionof one (or more) tasks. It consumes no time, and uses noresources. It marks the completion of one (or more) tasks.It is not reached until all of the activities leading to that

    event have been completed. Predecessor event: an event (or events) that immediately

    precedes some other event without any other eventsintervening. It may be the consequence of more than one

    activity. Successor event: an event (or events) that immediately

    follows some other event without any other eventsintervening. It may be the consequence of more than one

    activity.

  • 7/30/2019 Office Ppt Template 029

    36/53

    PERT activity: is the actual performance of a task. Itconsumes time, it requires resources (such as labor,materials, space, machinery), and it can be understood as

    representing the time, effort, and resources required tomove from one event to another. A PERT activity cannotbe completed until the event preceding it has occurred.

    Optimistic time (O): the minimum possible time requiredto accomplish a task, assuming everything proceeds betterthan is normally expected

    Pessimistic time (P): the maximum possible time requiredto accomplish a task, assuming everything goes wrong(but excluding major catastrophes).

    Most likely time (M): the best estimate of the timerequired to accomplish a task, assuming everythingproceeds as normal.

  • 7/30/2019 Office Ppt Template 029

    37/53

    Expected time (TE): the best estimate of the time

    required to accomplish a task, assumingeverything proceeds as normal (the implicationbeing that the expected time is the average timethe task would require if the task were repeated

    on a number of occasions over an extended periodof time).

  • 7/30/2019 Office Ppt Template 029

    38/53

    Creating a PERT DiagramSTEPS 1:

    Determine the tasks that the project requires andthe order in which they must be completed

    Determine the optimistic, most likely, andpessimistic time of each task

    Compute for the Expected time using the formula

    Te=(O+4M+P)/6

    Determine whether to use AOA or AON diagrams

  • 7/30/2019 Office Ppt Template 029

    39/53

    Activity Predecessor Optimistic(a)

    Normal(m)

    Pessimistic(b)

    Te(a+4m+b)/6

    A --- 2 4 6 4.00B --- 3 5 9 5.33

    C A 4 5 7 5.17

    D A 4 6 10 6.33

    E B, C 4 5 7 5.17

    F D 3 4 8 4.50

    G E 3 5 8 5.17f

    Rightnowwell solveanexample

  • 7/30/2019 Office Ppt Template 029

    40/53

    Start

    F

    C

    GE

    D

    B

    A

    Finish

  • 7/30/2019 Office Ppt Template 029

    41/53

    STEPS 2: Determine the ES & EF of each activity by:

    Start at the beginning moving towards the end

    ES & EF for the start activity is always 0 since they aremilestones

    Use the EF of the predecessor activity as the ES of thecurrent activity

    EF of an activity is computed by adding its ES with itsduration

    For activities with 2 or more predecessor activities, usethe predecessor with the higher EF as the ES of thecurrent activity

  • 7/30/2019 Office Ppt Template 029

    42/53

    Creating a PERT Diagram

    STEPS 3:

    Determine the LS & LF of each activity by:

    Start at the end and work towards the beginning

    Use the LS of the successor activity as the LF of thecurrent activity

    LS of an activity is computed by subtracting its LF withits duration

    For activities with 2 or more successor activities, usethe successor with the lower LS as the LF of the currentactivity

  • 7/30/2019 Office Ppt Template 029

    43/53

    Creating a PERT Diagram

    STEPS 4:

    Compute for the critical path by adding theduration's of various paths for all activities

    Determine if any activities have slack by

    subtracting the activitys LF & EF

  • 7/30/2019 Office Ppt Template 029

    44/53

    PERT & CPM Similarities

    Both follow the same steps and use network

    diagrams Both are used to plan the scheduling of individual

    activities that make up a project

    They can be used to determine the earliest/lateststart and finish times for each activity

  • 7/30/2019 Office Ppt Template 029

    45/53

    PERT & CPM Differences

    PERT is probabilistic whereas CPM is deterministic

    In CPM, estimates of activity duration are basedon historical data

    In PERT, estimates are uncertain and we talk of

    ranges of duration and the probability that anactivity duration will fall into that range

    CPM concentrates on Time/Cost trade off.

    ADVANTAGES:

  • 7/30/2019 Office Ppt Template 029

    46/53

    ADVANTAGES:PERT chart explicitly defines and makes visible

    dependencies (precedence relationships) between the

    work breakdown structure (commonlyWBS) elementsPERT facilitates identification of the critical path and

    makes this visible

    PERT facilitates identification of early start, late start,

    and slack for each activityPERT provides for potentially reduced project duration

    due to better understanding of dependencies leading

    to improved overlapping of activities and tasks where

    feasible.

    The large amount of project data can be organized &

    presented in diagram for use in decision making.

  • 7/30/2019 Office Ppt Template 029

    47/53

    DISADVANTAGES

    There can be potentially hundreds or thousands of activities

    and individual dependency relationshipsPERT is not easily scalable for smaller projectsThe network charts tend to be large and unwieldy requiringseveral pages to print and requiring special size paper

    The lack of a timeframe on most PERT/CPM charts makes itharder to show status although colours can help (e.g.,specific colour for completed nodes)When the PERT/CPM charts become unwieldy, they are nolonger used to manage the project.

    Importance of a Network Diagram

  • 7/30/2019 Office Ppt Template 029

    48/53

    Importance of a Network Diagram

    Visual Imagery:

    It can be quite difficult for non-technical people tounderstand how a particular piece of softwareworks, and why its proper operation is so criticalto the success of the business. The network

    diagram includes pictures that show each step inthe software process, from inputting the data todistributing the resulting reports.

  • 7/30/2019 Office Ppt Template 029

    49/53

    Faster Education:

    Creating a detailed network diagram that shows

    how a particular piece of software interfaces withcompany hardware and other pieces of softwareallows both new hires and existing employers togain a better understanding of the work they need

    to do and how their particular jobs affect theentire organization. The ability to see each step inthe software development and softwaremanagement process in visual form is often

    helpful for workers in the IT field and formembers of the management team.

  • 7/30/2019 Office Ppt Template 029

    50/53

    Better Record Keeping:

    Documentation is a critical, but often overlooked,

    part of any IT organization. Without the properdocumentation in place it can be difficult to trackdown problems in complex systems. By taking thetime to create a detailed network diagram for

    each piece of software used in the company, theIT staff makes it easier for their colleagues to findand resolve problems, even if they have no directexperience with that type of software.

  • 7/30/2019 Office Ppt Template 029

    51/53

    Better Project Planning:

    A detailed network diagram allows project managers andother members of the project team to plan their projects

    more effectively. When everyone on the project team cansee exactly how the software works, and what othersystems it interfaces with, it is much easier for those teammembers to move forward with beneficial changes. A

    good network diagram also allows project teams to avoidcostly mistakes that could have an impact the operation ofthose software packages and the networks on which theyrun. In fact, the Project Management Institute cites theimportance of network diagrams in their trainingmaterials and other literature.

  • 7/30/2019 Office Ppt Template 029

    52/53

    REFERENCES

    www.smartdraw.com/specials/network.asp

    www.edrawsoft.com/Network-Diagram-Tutorials.php

    www.opnet.com/solutions/network_management/netmapper.htm

    www.slideshare.com

  • 7/30/2019 Office Ppt Template 029

    53/53

    Thank You