odot's design build program "overview and update"

15
ODOT’s Design Build Program ODOT’s Design Build Program “OVERVIEW AND UPDATE” What is Design Build Reasons to use DB ODOT’s DB History DB Stakeholder Committee DB Changes ODOT’s Design Build Future Bob Pappe, PE, PLS ODOT Design Build Manager [email protected] 503-986-3477

Upload: mike97

Post on 13-Jun-2015

570 views

Category:

Business


0 download

TRANSCRIPT

Page 1: ODOT's Design Build Program "OVERVIEW AND UPDATE"

ODOT’s Design Build ProgramODOT’s Design Build Program

“OVERVIEW AND UPDATE”

• What is Design Build • Reasons to use DB• ODOT’s DB History• DB Stakeholder Committee• DB Changes• ODOT’s Design Build Future

Bob Pappe, PE, PLSODOT Design Build [email protected] 503-986-3477

Page 2: ODOT's Design Build Program "OVERVIEW AND UPDATE"

Design BuildDesign Build

What is Design Build?

• A contract with a single entity for both design and Construction

• Design Build can look different depending on size of project

• Design Build can look different depending on needs of owner

• ODOT’s Currently defines the Work (OTIA-sized DB) as: – Design, Construction, and Quality Management

Page 3: ODOT's Design Build Program "OVERVIEW AND UPDATE"

Reasons for Design BuildReasons for Design Build• Schedule (Velocity)

– Award Contract earlier in Project life, before Design– Shorten on-site work period, concurrent design and construction– Velocity of delivery, project or program

• Funding– Obligate fed funds at RFP release, not PS&E– Total cost known at award (earlier, fixed cost)

• Cost– Minimize project cost (lump sum for design and construct)– Maximize project budget (competitive bid design + construct, efficiency

of contractor and designer working together)– Complete on budget (assure project cost by fixed price)

• Quality– Screen proposers with RFQ process, only short-listed teams propose– Select ‘Best’ Project Team and proposal / ‘Best’ Team = high quality

• Innovation– Opportunity for innovative thinking– Means and Methods / Outside Agency Design Standards– Agency can test new ideas easier with performance specifications

• Risk and Opportunity for both agency and DB

Page 4: ODOT's Design Build Program "OVERVIEW AND UPDATE"

Understanding Design-Build and its Benefits

Design-Bid-Build

Planning &Program’g

PreliminaryEngineering

Final Engineering Contractor selection

Construction

Minimal Contractor Input Possible Contractor Input

Design-Build

Planning &Program’g

PreliminaryEngineering

Design-BuilderSelections

Final Engineering Construction DB Time Savings

Minimal Contractor Input Extensive Contractor Input

Award of Contract acceleration

DB DBB

Page 5: ODOT's Design Build Program "OVERVIEW AND UPDATE"

I -84 Lower Perry Bridges• 9 Months – Kick-off to Contract• $8.2M (100% OTIA); 2- Interstate Br Replacements • 2 Years Const. –(Contractor completed early)• No Claims

I-84 Quarry Bridges• 8 Months – Kick-off to Contract• $19M (62% OTIA, 38% Fed); 4- Interstate Br Replacements • 3 Years Const. – Incentives reduced to 2• Eliminated Load restrictions – 2nd season• One Claim – UPRR coordination ($35K)

US20 Central Oregon Highway Bridges

• 12 Months – Kick-off to Contract

• $26M (15% OTIA, 85% Fed); 16 –Highway Br Replacements • ½ mile re-alignment- Jonesburo• 2 Years Construction-(No early incentives)• Eliminated Load restrictions – early 2nd season• No Claims

Page 6: ODOT's Design Build Program "OVERVIEW AND UPDATE"

Current DB Projects List

Project Award Value Status1. Coast Fork May 02 $5.7m Complete2. Lower Perry May 02 $8.2m Complete3. Quarry Bridges Jan 03 $18.7m Complete4. COHB Mar 04 $25.6m Complete5. MHC Apr 04 $30.6m Complete6. SRS Nov 04 $37.7m Near Complete7. CBT Mar 05 $34.8m In Const.8. PME Jul 05 $129.9m In Const.9. WHI Apr 06 $23 m In Const.10. MRG May 06 $59.7m In Const.11. I-5 Weaver Oct 06 $51.3m In Const.

12. Elk-Hardscrab. Dec 06 $45 m In Const.

Total to date: $470 Million

Page 7: ODOT's Design Build Program "OVERVIEW AND UPDATE"

HistoryHistoryDesign Build as Part of total Construction Design Build as Part of total Construction

ProgramProgramContract award amounts by year

_________________________________________________________________

Awards 2002 2003 2004 2005 2006 (approximate)

_______________________________________________________________________________________

Total $304m $366m $485m $486m ($600)ODOTAwards________________________________________________________________________________________________

DB $13.8 $18.7 $93.8 $163.7 ($178.7)ProjectAwards________________________________________________________________________________________________

DB 4.6% 5.1% 19.4% 33.7% (29.8%)AwardPercent________________________________________________________________________________________________

Page 8: ODOT's Design Build Program "OVERVIEW AND UPDATE"

Design BuildDesign Build

Design Build Stakeholders Group

• Started November 2004• Core group – AGC, ACEC, ODOT, other Agency’s

Purpose Statement: “The purpose of the Design Build StakeholderCommittee is to assist in the development of a state ofthe art Design Build program that meets ODOT’s needsand allows for industry success.”

Nov 04 to Aug 05 – 8 meetingsDeveloped List of Issues to improve on

Page 9: ODOT's Design Build Program "OVERVIEW AND UPDATE"

Design BuildDesign Build

Design Build Stakeholders GroupIssues:• Selection and evaluation process• Stipend amount• Shortlist to RFP time• Reduce Proposal effort• Consistency issues in ODOT documents• Project goals clearly defined in RFP?

• Project specific information in one location in RFP

• Roles, Responsibilities, Risks• Standard Documents • Proposal deficiencies- scoring vs non-responsiveness• Independent Quality Firm• …………• …………

Page 10: ODOT's Design Build Program "OVERVIEW AND UPDATE"

Design BuildDesign BuildDesign Build Changes• Selection and evaluation

– PD Team at core of scoring, - Oral Presentations

• Shortlist to RFP time – link RFQ to RFP readiness• Reduce Proposal effort

– Limit number of pages, - narrative to check the box– eliminate duplication, - reduce project schedule size,– Move to DB Standards and DB Specials (Project specific)

• Concept Design - 4 major risks (R/W, Enviro., Utilities, RR)• Project specific information in one location in RFP• Base Documents on Web for comment• www.oregon.gov/ODOT/HWY/OPD/DB_Home.shtml Then click "Base Document" link

Stakeholder Subcommittees• Quality Management• Design Review• Progress Payments• Innovation• Design Build “Lite”

Page 11: ODOT's Design Build Program "OVERVIEW AND UPDATE"

Original DB Projects ListProject Award Value Status1. Coast Fork May 02 $5.7m Complete2. Lower Perry May 02 $8.2m Complete3. Quarry Bridges Jan 03 $18.7m Complete4. COHB Mar 04 $25.6m Complete5. MHC Apr 04 $30.6m Complete6. SRS Nov 04 $37.7m Near Complete7. CBT Mar 05 $34.8m In Const.8. PME Jul 05 $129.9m In Const.9. WHI Apr 06 $23 m In Const.10. MRG May 06 $59.7m In Const.11. I-5 Weaver Oct 06 $51.3m In Const.

12. Elk-Hardscrab. Dec 06 $45 m In Const.13. I-5 Comstock (Nov 07) $34m future Change to DBB14. US30 –B415 (Jun 08) $17m future Change to

DBB15. OR126-B508 (Dec 08) $23m future16. US395-B414 (May 09) $25m future17. OR6-B507 (Nov 09) $34m future

Page 12: ODOT's Design Build Program "OVERVIEW AND UPDATE"

ODOT’s Design Build Future 1. I-5 Cmstk-B309 (Nov 07) $34m future change- DBB2. US30 –B415 (Jun 08) $17m future change-

DBB3. OR126-B508 (Dec 08) $23m future4. US395-B414 (May 09) $25m future5. OR6-B507 (Nov 09) $34m future

Possible Changes to Schedule – move B414 forward to replace B309YEAR: ’07 ’08 ’09 ’10 ’11NTP: 3-08 12-08 11-09Bundle: B414 B508 B507

Future – need to: • Maintain ODOT’s ability to efficiently run DB procurement and

manage contract execution?• Maintain industry’s interest and ability to assemble teams, submit

proposals, and manage contract execution with DB mentality?

• Continue mainstreaming the DB method, - ODOT Culture, Industry culture, don’t lose what we’ve learned.

Page 13: ODOT's Design Build Program "OVERVIEW AND UPDATE"

ODOT’s Design Build Future:

Stay Ready for Future Funding requiring quick start!

Look for larger STIP projects (OTIA- Sized) • OTIA sized DB, proportional procurement/execution efforts

Develop a DB-Lite for STIP sized projects• Develop desired attributes

– Velocity to award of contract– Reduce procurement time and effort (agency and industry)– Maintain concurrent design and construction (shortened on-site)– Augment ODOT resources (part of out-sourcing strategy)– Lower Design Builder’s risks– Attractive to industry (lots of DBB work, why take this?)– Eases new-comers to DB (agency and industry)– Does not sacrifice quality

• Develop optional processes to obtain attributes– Design – Conceptual Plans vs DAP– Procurement – 2-step best value vs minimum threshold then low bid– Quality Management after contract execution – DB or ODOT or mix

Page 14: ODOT's Design Build Program "OVERVIEW AND UPDATE"

ODOT’s Design Build Future:Look for larger Region STIP projects (OTIA- Sized) • OTIA sized DB, proportional procurement/execution efforts

Develop a DB-Lite for STIP sized projects• Develop desired attributes

Velocity to award of contractReduce procurement time and effort (agency and industry)Maintain concurrent design and construction (shortened on-site)Augment ODOT resources (part of out-sourcing strategy)Lower Design Builder’s risksAttractive to industry (lots of DBB work, why take this?)Eases new-comers to DB (agency and industry)Does not sacrifice quality

• Develop optional processes to obtain attributes

Design – Conceptual Plans vs DAP

Procurement – 2-step best value vs minimum threshold then low bidQuality Management after contract execution – DB or ODOT or mix

Stay ready for future funding that requires quick start!

Page 15: ODOT's Design Build Program "OVERVIEW AND UPDATE"

Understanding Design-Build and its Benefits

Design-Bid-Build

Planning &Program’g

PreliminaryEngineering

Final Engineering Contractor selection

Construction

Minimal Contractor Input Possible Contractor Input

Design-Build

Planning &Program’g

PreliminaryEngineering

Design-BuilderSelections

Final Engineering Construction DB Time Savings

Minimal Contractor Input Extensive Contractor Input

Award of Contract acceleration

DB DBB