oasis plcs tc telecon 4 january 2007 trine hansen – dnv
DESCRIPTION
OASIS PLCS TC Telecon 4 January 2007 Trine Hansen – DNV. Estimated budget – Phase I (As presented in face-to-face mtg in Huntsville 31 Oct 06). Contributions to the OASIS project. * Direct costs not included. **Includes more development activities than originally estimated. Way Forward. - PowerPoint PPT PresentationTRANSCRIPT
OASIS PLCS TC Telecon
4 January 2007
Trine Hansen – DNV
2PLCS Inc. (c) 2002
Estimated budget – Phase I(As presented in face-to-face mtg in Huntsville 31 Oct 06)
# Activity Budget [Hours]
1 Project Management 500
2 Kick-off workshop 200
3 Establish TOG support management 100
4 DEXLib infrastructure 2310
5 DEXLib Help section 300
6 Develop Core capabilities 1860
7 Decide which DEXs to be standardized 10
8 Develop capabilities for completion of 2 sets of DEXs 460
9 Review and update capabilities for completion of 2 sets of DEXs 40
10 Develop 2 sets of DEXs 560
11 Reference data content 300
12 Review 2 sets of DEXs 120
13 Preparations for establishing Implementers Forum 100
14 Direct Costs -
SUM 6860
3PLCS Inc. (c) 2002
Contributions to the OASIS project
Contributors Hours
UK MOD 2614 **
FMV 1327
NDLO 3510
US DoD including US Army
DNV 500
Eurostep
Saab
BAESystem
Locheed Martin
Mantech
BOEING
LSC
Rolls-Royce
EPM Technology
Sum contributions 7451
**Includes more development activities than originally estimated
Estimates Hours
Total budget 6860 *
Contingency 2000
Total 8860
* Direct costs not included
4PLCS Inc. (c) 2002
Way Forward
Deadline for contribution to the project: Friday 12 January 07
Establish a Steering Committee by 19 January Detailed planning week 3 and 4 (15 – 26 January) Presentation of detailed plan for the Steering
Committee week 5 (29 Jan – 2 Feb) If accept for detailed plan:
Kick-off meeting for the Core Team 7 – 8 February
5PLCS Inc. (c) 2002
Detailed planning
Questions to be sorted out: Are all identified activities covered through the
contributions? (such as harmonization activities) Are direct costs included in the contributions (e.g. travel
expenses)? Time frame limitations in on-going projects Named resources to be identified and allocated Etc.
Detailed plan to be worked out by the PM. Assisted by Rob Bodington and Leif Gyllström
Identify budget for Contingency
6PLCS Inc. (c) 2002
Working method
Identify a Core Team Use Net meetings as far as possible Face-to-face meetings when necessary – primarily for
Core Team members Assume procedures and quality requirements from the
Quality Group, such as Requirements for checklists, documentation of methods
etc. Procedures for how to handle disagreements …..