north power corporation electric network project ...documents.worldbank.org/curated/en/...electric...
TRANSCRIPT
NORTH POWER CORPORATION
Electric Network Project Management Board
-------------------------------
ENVIRONMENTAL MANAGEMENT PLAN
(EMP)
SUBPROJECT:
DISTRIBUTION EFFICIENCY PROJECT
PROVING MEDIUM, LOW GRID – LANG SON PROVINCE
PREPARED BY
INVESTMENT ELECTRICAL AND CONSTRUCTION JOINT STOCK COMPANY
Hanoi, 19 April 2012
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
ABBREVIATIONS
CPC Commune People’s Committee
CSC Construction Supervision Consultant
DEP Distribution Efficient Project
DPC District People’s Committee
ECOP Environmental Code of Practice
EIA Environmental Impact Assessment
EMF Electromagnetic Management Framework
EMP Environmental Management Plan
EPC Environmental Protection Commitment
EVN Electricity of Vietnam
HV High voltage
LV Low Voltage
MV Medium Voltage
NPC Northern Power Corporation
PAHs Project Affected Households
PCBs Polychlorinated Biphenyls
PMU Network Project Management Unit (under the NPC)
PPC Provincial People’s Committee
ROW Right of Way
WB World Bank
3
TABLE OF CONTENTS
1. INTRODUCTION ................................................................................................................. 5
2. POLICY, REGULATIONS, AND INSTITUTIONAL FRAMEWORKS ............................ 6
2.1. Vietnam Government Regulations: ................................................................................. 6
2.2. World Bank Environmental Safeguard Policies: ............................................................ 6
3. SUBPROJECT DESCRIPTION ............................................................................................ 7
3.1.Objectives of the subproject............................................................................................. 7
3.2. The subproject location: .................................................................................................. 7
3.3. Subproject management organization: ............................................................................ 7
3.4. Project description .......................................................................................................... 7
3.5. Subproject Implementation Schedule and total investment .......................................... 13
4. SUMMARY OF NATURAL AND ENVIRONMENTAL CONDITIONS OF PROJECT’S
AREA ....................................................................................................................................... 14
4.1. Geographical condition ................................................................................................. 14
4.2. Natural resources .......................................................................................................... 15
4.3. Population, culture, society ........................................................................................... 15
4.4.Traffic ............................................................................................................................ 16
5. IDENTIFICATION OF SUBPROJECT POTENTIAL IMPACTS .................................... 17
6. ENVIRONMENTAL MANAGEMENT PLAN.................................................................. 24
6.1. Mitigation measures ...................................................................................................... 24
6.2. Environmental monitoring plan .................................................................................... 36
7. ARRANGEMENT FOR ENVIROMENTAL MANAGEMENT PLAN
IMPLEMENTATION, IMPROVE CAPACITY ..................................................................... 38
7.1. The responsibilities for implementing Environmental Management Plan (EMP) ........ 38
7.2. Building the EMP implementation capacity ................................................................. 40
7.3. Reporting process: ........................................................................................................ 40
7.4. Estimate cost for the implementation of the EMP ........................................................ 41
8. CONSULTATION AND DISCLOSURE OF INFORMATION ........................................ 42
9. REFERENCES .................................................................................................................... 44
10. ANNEXES ......................................................................................................................... 45
Annex 1: TOR for Construction Supervision Consultant .................................................... 45
Annex 2: Report template for monitoring of EMP implementation (used for report by
supervising consultant to PMU)........................................................................................... 47
Annex 3: Report template for monitoring of EMP implementation (used for reports by
contractor) ............................................................................................................................ 49
Annex 4: The project environment license (The certificate of project environmental
protection commitment) ....................................................................................................... 50
4
Annex 5: The project map and current images of the subproject (attached) ....................... 51
Annex 6: The information of the public consultation and minutes of public consultation
(attached)............................................................................................................................. 53
LIST OF TABLES
Table 3.4.3 (1)- Quantity and substation capacity .................................................................. 9
Table 3.4.3 (2)- The component, position of transformer stations and the distribution line .. 9
Table 3.4.4 – Work volume to be implemented in Lang Son Province ................................ 10
Table 5.1. Environmental impact assessment ....................................................................... 17
Table 6.1. Mitigation measures applied for the Project ........................................................ 24
Table 6.2. Environmental monitoring plan ........................................................................... 36
Table 7.1. The parties involved in the EMP ......................................................................... 39
Table 7.2. Estimated cost to build the EMP implementation capacity ................................. 40
Table 7.3. Responsibilities and frequency of reports on implementation of the EMP ......... 40
Table 7.4. Estimated cost for the implementation of the EMP ............................................. 41
5
1. INTRODUCTION
The subproject: “Improving medium, low voltage grid- Lang Son Province” is one of
subprojects that will be implemented in Phase I of Distribution Efficiency Project (DEP) of
the Viet Nam Electricity. This DEP was funded by the WB.
The activities of subproject include: (i) newly constructing 3.34 km for a medium
voltage transmission line, (ii) new construction of two substations and (iii) rehabilitating and
upgrading of additional 70.157 km of low voltage transmission line in 13 communes of 10
districts in Lang Son Province. These activities as mentioned above may cause negative
impacts on the local environment and local communities during the pre-construction phase,
the construction phase and the operation phase.
To ensure the potential negative impacts are identified and mitigated during the
subproject implementation process and in compliance with the policy on environmental
assessment of the World Bank (OP/BP 4.01), an Environmental Management Plan (EMP) of
the subproject has been prepared in accordance with the guidelines provided in the
Environmental Management Framework (EMF) of DEP. The EMP includes: the subproject
description, the legal framework, applicable regulations and environmental technical
regulations, potential negative impacts and proposed mitigation measures to be carried out
during the pre-construction phase, the construction phase and the operation phase,
arrangements for implementation. The EMP also includes an Environmental Codes of
Practice (ECOP) that will be incorporated into the bidding documents and construction
contracts as well as a scope for environment quality monitoring.
The Government’s regulation on EIA requires submission of an Environmental
Protection Commitment (EPC) for the subproject. An EPC reports has been prepared,
submitted to, and approved by Van Lang District People’s committee on 10 February, 2012.
6
2. POLICY, REGULATIONS, AND INSTITUTIONAL FRAMEWORKS
2.1. Vietnam Government Regulations:
The following laws and regulations are applied for subproject:
Law on Protection of the Environment No. 52/2005/QH11 passed by the National
Assembly, dated 29 November, 2005 regulating the responsibilities of individuals,
organizations regarding environmental protection.
Decree of Vietnamese Government No.80/2006/ND-CP dated 9 August, 2006 on
detail regulations and guidance on the implementation of some Articles of the
Environment Protection Law.
Decree of Vietnamese Government No.29/2011/ND-CP dated 18 April, 2006
regarding regulations on strategic environmental assessment, environmental impact
assessment and environment protection commitments.
Circular No.26/2011/TT-BTNMT dated 18 July, 2011 detailing some articles of
Decree No.29/2011/ND-CP dated 18 April, 2011 regarding regulations on strategic
environmental assessment, environmental impact assessment and environment
protection commitments
Decree of Government No.106/2005/ND-CP dated 17 August, 2005 on detailed
regulations and guidance on implementation of some Articles of the Law on
Electricity related to safe protection of high voltage networks.
Decree of Government No.81/2009/ND-CP dated 12 October, 2009 on revision and
addition of some Articles of Decree 106/2005/ND-CP dated 17th
August 2005 on
detailed regulations and guidance on implementation of some Articles of the Law on
Electricity related to safe protection of high voltage networks.
Circular No.12/2011/TT-BTNMT dated 14 April, 2011 regarding the management of
hazardous wastes.
National Technical Regulations: QCVN01: 2009/BYT- National technical regulations
on quality of drinking water; QCVN02: 2009/BYT- National technical regulations on
quality of domestic water; QCVN08: 2008/BTNMT - National technical regulations
on surface water quality; QCVN09: 2008/BTNMT - National technical regulations on
groundwater quality; QCVN05: 2009/BTNMT – Air quality – Standard for ambient
air quality; QCVN06:2009/BTNMT – Air quality – Maximum allowable
concentration of hazardous substances in the ambient air.
Guidance of EVN No. 2623/CV-EVN - KHCN & MT dated 28 May, 2007 regarding
the management and pollution prevention and exposure to PCBs.
2.2. World Bank Environmental Safeguard Policies:
An environmental screening was undertaken in line with the guidelines provided in the
Environmental Management Framework (EMF) of the DEP project and it showed that the
World Bank’s policies on Environmental Assessment (OP 4.01), Indigenous People (4.10),
and Involuntary Resettlement (OP 4.12) will be triggered for the subproject. In addition, the
Bank’s requirements on public consultation and information disclosure will need to be
followed. The implementation of policies OP 4.10 and OP 4.12 will be addressed in other
social safeguard instruments.
7
3. SUBPROJECT DESCRIPTION
3.1.Objectives of the subproject
The objectives of the proposed Distribution Efficiency Project-Lang Son Province are
to:
- Prevent overload of the local power grid for the subproject communes;
- Reduce power losses, improve electricity quality; and provide stable power supply for
living, production and business activities;
- Meet the power supply demand of the subproject local communes for socio-economic
development;
- Contribute to Government poverty reduction programs in rural areas by providing
basic infrastructures, particularly electricity;
- Contributes to improve material and spiritual life of people in remote areas of
northern provinces.
3.2. The subproject location:
- New construction of 3.34 km for a medium voltage transmission line in Hoang Van
Thu commune-Tien Lang District, Dong Tien commune-Huu Lung District.
- Three substations are hang-on types to minimize the acquired land area in Hoang Van
Thu commune-Tien Lang District and Dong Tien commune-Huu Lung District.
- The new construction and the rehabilitation of the low voltage transmission line are 70
km long. The low voltage transmission line will cross over 13 communes, including: Binh Xa
commune-Dinh Lap District, Hung Vu commune and Bac Son-Bac Son district, Lang Nang
commune-Van Quan district, Hoang Viet commune and Hoang Van Thu commune-Van Lang
district, Dong Quang commune and Dong Buc commune- Loc Binh district, Tri Phuong
commune-Trang Dinh district, Hoang Van Thu commune-Trang Dinh district, Hoang Van
Thu commune-Binh Gia district, Hoa Cu commune-Cao Loc district, Dong Tien commune-
Huu Lung district, Mai Sao commune-Chi Lang district.
3.3. Subproject management organization:
- The Subproject Owner: North Power Corporation
- Technical Design Consulting Unit: INECO.JSC
- The subproject Management Unit: North Grid PMU-North Power Corporation
3.4. Project description
The activities of subproject include: (i) newly constructing 3.34 km for a medium
voltage transmission line, (ii) new construction of two substations and (iii) rehabilitating and
upgrading of additional 70.157 km of low voltage transmission line in 13 communes of 10
districts in Lang Son Province, including: Binh Xa commune-Dinh Lap District, Hung Vu
commune and Bac Son-Bac Son district, Lang Nang commune-Van Quan district, Hoang
Viet commune and Hoang Van Thu commune-Van Lang district, Dong Quang commune and
Dong Buc commune- Loc Binh district, Tri Phuong commune-Trang Dinh district, Hoang
Van Thu commune-Trang Dinh district, Hoang Van Thu commune-Binh Gia district, Hoa Cu
commune-Cao Loc district, Dong Tien commune-Huu Lung district, Mai Sao commune-Chi
Lang district.
8
3.4.1. The medium voltage transmission line supplying electricity to the rebuilt-
substations
a) Hoang Van Thu commune-Van Lang district
- The medium voltage transmission line will go across the inter-hamlet road, going
across Na Pan stream, then going across through a stream to the substation. The line would
not affect the residential, public infrastructures as well as plants of the local people.
- Length of route: 1,499m
- Na Pan substation will be located on public land along Na Pan rural road.
b) Dong Tien commune-Huu Lung district:
- The line will passes through inter-commune road, then going across the inter-hamlet
road to the substation. This line would not affect the residential, public infrastructures and
facilities.
- Length of route: 1,841m
- Dong Tien 3 substation will be located on the land along the inter-hamlet road
between Lang Ca hamlet and Lien Phuong hamlet.
- New construction of the low voltage transmission line: Most of the line sections will
follow the removed lines on the old routes. Some lines sections will newly be constructed
along village lands or village roads to connect to the new lines. Because the occupied land are
of pole foundation is small so the low voltage transmission line does not affect local resident
house. However, trees with heights that exceed safety limit stipulated in power grid safety
regulation will be cut down and the affected households will be adequately compensated.
3.4.2. The low voltage transmission line
- The rehabilitation of the low voltage transmission line: Rehabilitation of the line will
take place along the old route, and including replacement of wires, beams, insulator or pole
that do not have good quality. The recovered materials of this line will be transferred to
warehouse of Tuyen Quang Electricity Company for use in other electricity works. These
works are invested with social objectives such as the addition of the lines supplying
electricity to households that do not have electricity in communes of the outlying areas.
These communes are not invested by DEP.
- New construction of the low voltage transmission line: Most of the line sections will
follow the removed lines on the old routes. Some lines sections will newly be constructed
along village lands or village roads to connect to the new lines. Because the occupied land are
of pole foundation is small so the low voltage transmission line does not affect local resident
house. However, trees with heights that exceed safety limit stipulated in power grid safety
regulation will be cut down and the affected households will be adequately compensated.
3.4.3. Project components
a. Medium voltage transmission line:
Newly constructing total 3.34 km medium voltage transmission line.
In which:
- Transmission line 35kV: 1.499 km
- Transmission line 10kV: 1.841 km
b. Substation:
9
Construct new two substations with total capacity of 200kVA
Table 3.4.3 (1)- Quantity and substation capacity
No Voltage and capacity Unit Quantity
1 35/0,4kV substation:
Capacity: 100kVA Unit 1
2 10/0,4kV substation:
Capacity: 100kVA Unit 1
c. Low voltage transmission line:
Newly constructing total number of 70.157 km low voltage transmission line, In which:
- Rehabilitation: 31.704 km, in which:
7.515 km 1- phase line and 24.189km 3- phase line
- New construction low voltage line: 38.453km, in which:
11.272km 1-phase line and 27.181km 3-phase line
Table 3.4.3 (2)- The component, position of transformer stations and the
distribution line
No Commune/district
name
Length of
medium
voltage line
(km)
Quantity
of
Substation
Length of
rehabilitated
low voltage
line (km)
Length of
new
construction
low voltage
line (km)
1 Length of medium
voltage line, low
voltage line and the
quantity of
transformer station
3.344 2 29.281 37.611
2 Commune name
Dinh Lap
Binh Xa 3.437 1,678
Bac Son
10
No Commune/district
name
Length of
medium
voltage line
(km)
Quantity
of
Substation
Length of
rehabilitated
low voltage
line (km)
Length of
new
construction
low voltage
line (km)
Hung Vu 3.177 2.467
Bac Son 2.096 2.875
Van Quan
Luong Nang 3.414 2.649
Van Lang
Hoang Viet 4.151 1.620
Hoang Van Thu 1.499 1 1.607 313
Loc Binh
Dong Quan - 5.599
Dong Buc 441 5.190
Trang Dinh
Tri Phuong 2.421 3.180
Binh Gia
Hoang Van Thu 1.049 4.762
Cao Loc
Hoa Cu 4.297 1.917
Chi Lang
Mai Sao 3.191 2.719
Huu Lung
Dong Tien 1.841 1 - 2.692
3 Line corridor 3m 6m2 2m 2m
3.4.4. The main work volume of the subproject
Table 3.4.4 – Work volume to be implemented in Lang Son Province
11
No Construction and installation Unit Quantity Method
01 Steel core aluminium wire AC50/8 m 10,641 Manual
02 Lay out of AL/XLPE 4x70 cable m 19,120 Manual
03 Lay out of AL/XLPE 4x50 cable m 37,952 Manual
04 Lay out of AL/XLPE 2x35 cable m 14,008 Manual
05 Set-up of 12m concrete pole piece 16 Manual
06 Set-up of 14m concrete pole piece 14 Manual
07 Set-up of H-8.5m concrete pole piece 8 Manual
08 Set-up of H-7.5m concrete pole piece 1,501 Manual
09 Set-up of H-6.5m concrete pole piece 317 Manual
10 Foundation for concrete poles of all
types piece 43 Manual
11 Foundation for concrete poles of all
types piece 1,576 Manual
12 Accessories of all types set 1,727 Manual
13 Grounding installations set 257 Manual
14 Excavation (pole foundation and
grounding) m3 2,156 Manual
15 Refilling and finishing m3 1,048 Manual
3.4.5. Main activities before and during construction
a. Compensation and site clearance
- The site clearance will be undertaken by local site clearance compensation council
base on consulting agency hands over the route.
- The site clearance will be implemented during construction and installation bidding
process to ensure progress.
- The site clearance works are completely complied by Decree of Government on safety
corridor for high voltage grid.
Besides, the site clearance compensation will be implemented in accordance with the
RP report and policy framework of resettlement compensation.
b. Arranging construction worker force and constructing site
12
- Location of construction site in project’s communes: the specific locations are selected
by construction and installation contractors and be approved by the local authorities.
- To ensure the maintenance of equipments, materials and housing for workers, the
temporary buildings may be built, including:
+ Indoor warehouse for preserving cement, equipments, electricity materials and
accessories: 1 warehouse/30m2 /per commune
+ Opening warehouse with protecting fence for transformer, medium voltage wires,
constructing tools, cranes and anchor wires: 1 warehouse/40m2
/per commune.
+ Temporary camps for workers: 1 house/20m2
/per commune
+ Indoor warehouse and temporary house are made of bamboo frame and surrounded by
bamboo mats, their roofs are covered by bamboo mats and oil papers. During implementation
process, domestic water, rain water and leftover water are gathered and released into local
drainage network through temporary drain system. All wastes are collected and disposed in
the right places to ensure the hygiene and the beauty of construction site.
- To streamline local construction apparatus, local workers will be hired to do manual
works that are not required technical.
- Construction labor force includes 1 construction team/commune. The construction
time: 4 months
One construction team includes:
+ Direct employee: 10 persons
+ Indirect employee: 02 persons
+ Site commander: 01 person
c. Transportation
Material and equipment supply
Material and equipment supply will be determined in detail in the later phase,
depending on the State budget disbursement and the subproject bidding method. Two sources
are expected:
- Equipment and material are supplied by investment owner
- Equipment and material are supplied by the contractor
Long distance transportation
For equipment and material supplied by the investor:
+ Long distance transportation of the such material and equipment will be undertaken
suing specialized truck. Such truck will be selected in accordance with the requirements
provided in the contract.
+ Long trasportation form the subproject owner warehouse to the site will be
undertaken using 5-7.5 ton trucks and loading will be done using 5-ton cranes.
For material and equipment supplied by the contractor:
+ Electric poles will be transported using Kawaz trucks, using 5-ton cranes for loading
and unloading.
+ Beam frames, accessories are transported using 5-ton trucks with manual unloading
13
+ Cement, steel will be transported using 5-ton trucks with manual loading and
unloading
+ Stone, sand…will be transported using 5- ton dump trucks.
For material and equipment supplied by the owner such as beam frames, accessories
and poles which be bought in Ha Noi city, will be transported with average distance of 180
km from Ha Noi city. The entire material will be bought in the local and be transported to the
contractor warehouses with average distance of 30-40 km.
Transportation activities of the contractor will be done through residential areas,
hospitals, schools along National Roads, Provincial Roads, the inter-district roads, the inter-
village. So, during transportation, the contractor must execute regulations on traffic safety
and minimize the impacts by the mitigation methods as stipulated in Part VI.
Intermediate transportation
Material and equipment must be stored at the site such as cables, insulators, accessories,
breakers, capacitors, power meters, meter boxes and cement will be transported to the
construction site suing non-motorized vehicles and manual handling.
Manual handling
All of the materials will be transported to the construction site manually. The distance
will be determined case by case, generally from 30 ÷1,000m
3.5. Subproject Implementation Schedule and total investment
3.5.1. Subproject Implementation Schedule
Based on power supply requirements of power supply and capacity of the subproject
owner, the subproject timeline is scheduled as follows:
Investment Preparation December 2011- June 2012
Construction Preparation July 2012- August 2012
Tendering equipment August 2012-September 2012
Tendering construction and installation September 2012- October 2012
Implementation December 2012- May 2013
Completion June 2013
3.5.2. Total investment of the subproject:
Total investment of the project are expected as follows:
Unit: VND
Civil construction cost 17,503,512,205
Procurement cost 457,063,485
Subproject management cost 431,411,199
14
Compensation cost 390,000,000
Consultant cost 3,304,240,112
Other cost 601,929,842
Contingency 2,268,815,684
Total investment 24,956,972,528
4. SUMMARY OF NATURAL AND ENVIRONMENTAL CONDITIONS OF
PROJECT’S AREA
4.1. Geographical condition
4.1.1. Geographical position:
Lang Son is a mountainous province of the Northeast. The Highway 1A, 1B, 4A, 4B,
279 go along this province. This is the important economic intersection:
+ The west borders Cao Bang province, Thai Nguyen province, Bac Kan province,
+ The east borders Bac Giang province, Bac Ninh province, Ha Noi capital,
+ The north borders China with two international border gates, two national border
gates and seven pairs of border markets.
With international railway, giving the province good conditions to economic, scientific
and technological exchanges with the South provinces and China. By these exchanges, this
province could exchange with Central Asia areas, Europe and other countries also.
4.1.2. Topography-geomorphology
The subproject communes are mainly located on hills, low mountains with average
height of 252 meters above sea level, the lowest is 20 meters, the highest is Phia Me peak of
Mau Son mountain with height 1,541 meters. The terrain is divided into three sub-regions:
the northern mountain area (including land mountains and rocky mountains which are
separated complicatedly, creating more mountain slopes above 350), karts (the bow of Bac
Son-Van Quan-Chi Lang-Huu Lung that have a lot of caves, steep slopes and peaks over
550m height, hill areas) and low mountains and hills in the South and Southeast that include
low mountains be interspersed by bowl up form hill with the average slope is 10-250.
4.1.3. Soil
Soil consists 3 main types: feralit soil in hilly areas and low mountains (below 700m),
representing over 90% natural area, alpine humus feralit soil (700-1,500m) and alluvial soil.
4.1.4. Weather
Thermal background is not too high and this is the characteristic of Lang Son climate.
Relatively long winter and quite cold with average annual rainfall 1,400-1,500mm, with the
number of rainy days are 135 days/per year.
Average terrain background is 251m, although the province located in tropical monsoon
climate, but Lang Son climate has specified characteristic of subtropical climate. Its humidity
is high (over 82%) and distribute evenly in the year.
15
4.2. Natural resources
4.2.1. Soil resources
- The total land area of the province is 830,521 hectare, including:
+ Feralit soil in hills and low mountains (below 700), accounting for 90% natural area,
+ Alpine humus feralit soil (700-1,500m),
+ Alluvial soil (9,530 hectare), peat land, agricultural land, specialty crops, medicinal
plants, forest trees.
- Using agricultural land area is 68,958 hectare, accounting for 8.3% of natural land in
which rice cultivation is 38,876 ha.
4.2.2. Forest Resources
The area of afforested land is 277,394 hectare, accounting for 33.4% of natural
land area, in which 185,456 hectare are natural forest, 91,937 hectare are planted
forest. 467,366 hectare unused land, rivers, streams, mountains, rocks, accounting for 43.02%
of natural land. Thus, this is a great potential for agro – forestry manufacturing development
especially agricultural development in the coming years ….
4.2.3. Mineral Resources
According to geological survey data, mineral resources in the province of Lang Son are
not many and the mine reserves is small, but they are quite rich, representing different types
such as Na Yang brown coal (Loc Binh); peat in Binh Gia, phosphoric in Huu
Lung, bauxite in Van Lang, Cao Loc, gold in Tan Van, Van Mich (Binh Gia); placer gold in
Ban Trai, Dao Vien (Trang Dinh), limestone, sand , pebbles, gravels have large reserves in
most places of the province and are being exploited for the production of building materials,
quartz in the Mau Son (Loc Binh), iron ores in Chi Lang and some other such as manganese,
copper, lead, zinc, mercury, tin, ... have not been investigated and evaluated reserves.
4.2.4. Plant Resources
The special characteristic of the tropical climate has allowed Lang Son to able to
develop many crop plants of temperate, subtropical, and tropical. Especially, long-term
crops such as anise trees, filling trees, tangerine trees, persimmon trees, peach trees, pear
trees, pine tree, coffee trees, tea trees, and timber trees...
4.3. Population, culture, society
- The population of subproject area: 416,720 people, mostly local residents are the
Nung and the Tay, the Kinh have a tiny percentage of 15%.
- The economy of subproject district is mainly agricultural and tends to increase the
density of industrial production and services ...
- Culture and society: Lang Son is a civilized land, there are many
cultural relics, historical sites. According to statistics, the province has nearly 600 places , the
relics were divided into 4 categories: archaeological monuments, attraction places, cultural
relics – art relics – religious beliefs relics, revolutionary history relics.
In the subproject’s area , culture and society issues are always interested by the local
government, all people have access to clean water, electricity lighting. The subproject will
directly and indirectly contribute to improve the lives of local people by
providing electricity for production, local economic development and lighting of public
works ...
16
The project is not located in areas which have historic relics, cultural –social
facilities as well as security and defense agents.
4.4.Traffic
Huu Nghi highway 1A (Lang Son) - Hanoi (170 km) includes 2 lanes and this is the
operating first-grade road; The government is implementing the construction of Hanoi-Huu
Nghi highway (Lang Son) with the scale of 6 lanes.
-Lang Son Highway 4B- Mui Chua port, Quang Ninh province (114 km),
-Lang Son Highway 1B- Thai Nguyen province (160 km)
-Highway Lang Son 4A - Cao Bang province (148 km)
-The international railway from Hanoi - Lang Son - Dong Dang to China is operating
effectively. Government is expected to upgrade and modernize the railway after the year of
2010.
- The provincial roads, district roads lead to 100% village centers.
In the subproject area, traffic conditions are relatively favorable, because the power line
goes along the roads so that it should not need to build further temporary roads for serving for
construction.
17
5. IDENTIFICATION OF SUBPROJECT POTENTIAL IMPACTS
The subproject will play an important role in the electrification program and the implementation of the policy of poverty alleviation of 13
communes of 10 districts. It will also speed up the national industrialization and modernization which is a step towards promoting rural
development and poverty reduction.
When the transmission lines are constructed, the local residents will tend to move to live close to electricity access. The local authorities
will need to plan for this by opening new roads, new residential areas and industrial and agriculture development. All the subproject districts and
the city will have to work in this direction.
The subproject will bring about significant socioeconomic benefit. This has been documented in detail in the description of feasibility
report. Apart from such benefits, the subproject may also result in environmental and socioeconomic impacts which are adverse to the local
conditions.
By using Environmental Screening Data Checklist and Environmental baseline Checklist as guided in Framework for Environment
Safeguards that be applied Rural Energy II Project, the potential impacts of the Project are described as follows:
Table 5.1. Environmental impact assessment
Questions Yes No Description of impact
1. Project's sitting:
Is the Project site adjacent to or within any of the following
environmental sensitive areas?
Cultural heritage site X The line and transformer station will not pass through
areas with cultural and historic value
The conservation areas X
Wetlands X
Forest X
18
Questions Yes No Description of impact
Estuarine X
Buffer zone of protected areas X
Nature Reserves: bird yards, mangrove forest.ect. X
Rivers and reservoirs X The medium voltage transmission line goes across Na Pan
stream, the line will supply electricity for Na Pa substation
in Hoang Van Thu commune-Van Lang district. However,
the line only goes along, the position of pole is separated
the stream by 50m. Therefore, the impact is insignificant
Canal and irrigation system X
2. The potential impacts, by project?
Encroachment on historical/cultural areas X
Encroachment on critical ecosystem (e.g. sensitive or
protected area, national park, nature reserve etc....)
X
Disfiguration of landscape and increase waste generation X - Because of ROW clearance, there would be small
changes of the landscape and increase wastes but these
changes are considered as small and the appropriate
mitigation measures would be taken.
Removal of vegetation cover or cut down of trees resulted
from clearance at the sub-station and along ROW?
X Along the ROW, the high trees will be cut off whereas the
low vegetations such as the vegetation and low trees are
remained unchanged (the vegetation is only affected at the
positions that are used to construct pole foundations but
19
Questions Yes No Description of impact
the affected area is insignificant). The substations are
hang-on types so the acquired land area is small and these
located in barren lands along the roads.
Change of surface water quality or water flows X
Increase water turbidity due to run- off and erosion X - During construction period, if construction work is
carried in the rainy season and no protection methods for
pole foundation and substation (the underground) be
applied, the erosion can occur and affect to the local flow.
Waste water from camping sites is directly
discharged to the surface water resources or not?
X - The contractor will rent local houses for workers, and
thus, wastewater will be collected into household waste
treatment facilities. In case of building temporary tents for
workers, drainage and garbage collection must be
complied with the regulations.
Construction waste is directly discharged to the
surface water or not?
X
Increase the dust level? X - During transportation, sands, rocks are transported by
trucks so dust will be generated. But this is considered to
be insignificant because material will be covered up during
transportation to prevent scattering of material along the
way
Increase noise and/or vibration? X - Noise and vibration are generated by operation of
transportation means so this is considered to be
insignificant
20
Questions Yes No Description of impact
Permanent land acquisition X Permanently acquired land area is 1,110 m2,
in which, field
land: 270m2, public land along the roads: 840m
2. The
permanently acquired land is very small in comparison
with the total used area of PAHs (accounting for 0.003%)
so that the production of the local people is not affected.
Temporary land acquisition X The temporarily acquired land:1,517m2. Land will be used
for ROW including agricultural land, wasteland and forest
land. these kind of land are unacquired.
Resettlement of households? If yes, how many households? X
Would the resettlement site is environmentally and/or
culturally sensitive
X
Is there any risk of disease dissemination from construction
workers to the local peoples (and vice versa)?
X - Construction force includes one construction team/per
commune, each team will have about 13 workers. The
total number of workers on the site at the peak time is
about 169 people but they are in many places of the route,
not gathering in one place. Therefore, the spread of
disease will also be limited.
Is there any potential for conflict between construction
workers and local peoples (and vice versa)?
X - Social conflict can occur due to difference in income,
culture and behavior so that the minor contradictions
should be occurred but will be limited.
Are explosive and hazardous chemicals used within the
Project?
X
In the past, there was any accident incurred due to landmines X - The subproject area was identified that it does not have
21
Questions Yes No Description of impact
or explosive materials remaining from the war? landmines remaining from the war.
Will Project's construction cause disturbance to the
transportation in the Project's site?
X - Because rural traffic is sparse, time for unloading
materials and equipment would be short (about 1 hour). In
addition, unloading of construction materials (e.g. sand,
soil, stone…) is automatic by trucks. Therefore, impacts on
traffic such as traffic congestion would not be significant.
Project's construction will cause any damage to the existing
local roads, bidges or other rural infrastructures?
X - All materials, equipment are classified for transportation
in accordance with the load of the road. The national
roads and provincial roads here are asphalted roads; the
village roads are scatted stones, other inter-commune
roads are land roads. The contractor will be return the
original conditions of the road if the transportation of the
contractor cause damage to these roads
Will soil excavation during Project's construction cause soil
erosion?
X - The construction time of pole foundation is short (about
1/2 day) and the construction would not be implemented in
the rainy season. Each items will be done completely
before the construction of another item, and thus erosion is
expected to be small
Will Project need to open new access roads? X Since the transmission lines and substation would be
located along roads. Existing roads will be used.
Will Project cause fragmentation of habitat of flora and
fauna?
X Since the transmission lines and substation would be
located along roads. Therefore, the subproject will not
cause fragmentation of habitat of flora and fauna
Will Project cause impact on air quality? X The level of impact on the environment by emission and
dust from transportation vehicles would be small because
22
Questions Yes No Description of impact
the will be covered during the transportation of
construction materials. Emissions from traffic vehicles
spreading into the environment. This impact will be
mitigated by the measures detailed in Section IV.
Will Project cause accident risks for workers and community
during construction phase?
X Accident risks include:
- Construction activities are carried out on steep terrain,
the materials can be slip away, this will be dangerous to
workers and communities.
- Workers who work at height, may have fallen if they do
not have enough the knowledge of safe and adequate labor
protection equipment.
- Ensure safety for workers during construction when they
work with many charged objects/conductor.
- Transporting bulky materials up steep slopes (such as
poles, steel beams, steel for constructing pole foundation,
cables) can cause accidents.
Will Project generate hazardous wastes including PCBs from
the replacement of transformers?
X Currently, the use of PCB was banned in Vietnam because
it cause adverse effects to human health and the
environment.
EVN has circular No. 2623/CV-EVN-KHCN&MT dated on
28 May2007 regarding the management and pollution
prevention and exposure to PCBs.
2 new substations with the transformers that would not
contain PCBs will be installed under DEP project in Lang
Son province. No substation will be removed. Therefore,
23
Questions Yes No Description of impact
the impact of PCBs is insignificant.
Will Project cause risk to safety and human health (electric
and magnetic fields, electric shock etc.)?
X If the lines and substation will not be designed and
constructed in accordance with the standard on rural
power grid DNT44-2006, human health might be affected.
Or if the harmful effects of electromagnetic fields and
standards are not be calculated to ensure electrical safety,
operation safety as prescribed, these can cause harm to
human health as well.
Therefore, the design activities will comply with the
regulations of the Ministry of Industry and Trade (DNT44-
2006) absolutely.
24
6. ENVIRONMENTAL MANAGEMENT PLAN
6.1. Mitigation measures
Table 6.1. Mitigation measures applied for the Project
Environmental-social
issues
Mitigation measures applied Responsible bodies
A. Preparation phase
1. Permanent and
temporary land
acquisition will impact
affected households
and agriculture
production
- Careful site survey, consult with local people and local authority for optimum route
selection which minimize land demand.
- Select optimum design on the span between towers and the tower height,etc… to
mitigate the impacts on Project affected households.
- Constructing after crops and shortening construction period.
- Proper compensate for the affected households and individuals according to the
Resettlement Policy Framework of the DEP project and Resettlement Plan of the
subproject.
- The PMU
- Contractor
2. Impacts on vegetation
cover as a result of site
clearance (ROW)
- Work with project affected households to crop rises and others before clearing and
using land.
- Clearing trees by manual if possible, restrict the use of motorized tools.
- Not allow to burn cut trees and its stump.
- Not allow cutting trees outside the scope of regulation.
- Leave out cut trees at prescribed places. Recycle cut trees as fuel (firewood) or
fertilizer.
- PMU + the contractor
3. Explosive materials
left from war
- Contract with related army unit to clear the site from unexploded ordnances left
from war.
- PMU + the contractor
- Resources and
25
Environmental-social
issues
Mitigation measures applied Responsible bodies
- Return the ground after the clearance. Environmental
Department of Lang
Son province will
supervise
B. Construction phase
1. Dust generation - The contractor is responsible for implementing the state applicable regulations
related to air quality.
- The contractor will ensure minum dust generation and no impact on local residents
and take proper measures to control dust generation (e.g. water spray vehicles,
covering of material stockpiles, etc.).
- Material will be covered up during. transportation to prevent scattering of material
along the way.
- Material dump site and storage yards will be covered up and isolated from winds
and located away from schools and residential areas.
- Dust masks should be used where dust levels are excessive
- The contractor
- Construction
Supervision consultant
2. Air pollution - All vehicles must comply with Vietnamese regulations controlling allowable
emission limits of exhaust gases.
- Vehicles in Vietnam must undergo a regular emissions check and get certified
named: “Certificate of conformity from inspection of quality, technical safety and
environmental protection” following Decision No. 35/2005/QD-BGTVT.
- Do not use any type of vehicles, whether in traffic or not, there is excessive
noise oremissions or overloading or speeding. Emissions of vehicles must comply
with standards TCVN 6438-2001: Road Vehicles - The limit of emissions
- The contractor
- Construction
Supervision consultant
26
Environmental-social
issues
Mitigation measures applied Responsible bodies
- There should be no burning of waste or construction materials or cleared
vegetation on site.
3. Impacts of noise and
vibration
- The contractor will be responsible for complying with applicable regulations
related to permitted noise and vibration levels.
- All transportation vehicles need to show certificate of quality, technical safety and
environmental friendliness according to the Decision No.35/2005/QD-BGTVT; to
prevent excessive noise level from machinery that is not properly maintained, proper
noise reduction measures are taken, including noise reducers or arrangement of noisy
machinery in a specific noise proof area.
- To prevent or reduce traffic in residential area as well as processing of material in
residential areas (concrete mixing)
- The contractor
- Construction
Supervision consultant
4. Waste water pollution - The contractor will be responsible for complying with applicable regulations related
to waste water treatment and discharge
- In case, the contractor have to build camps for the workers, the contractor must
provide mobile toilets or construct proper toilets for workers at the site. Toilet
waste water and kitchens will be treated before discharging into the outside
environment.
- When construction is completed, toilets have to be properly destroyed and/or
removed
- The contractor
- Construction
Supervision consultant
5. Drainage and
sedimentation control
- The contractor will comply with the water drainage system design to prevent rain
drop from causing local inundation, soil erosion in high risk areas.
- To ensure proper operation of the drainage system.
- To sustain those areas not impacted by construction activities.
- The contractor
- Construction
Supervision consultant
27
Environmental-social
issues
Mitigation measures applied Responsible bodies
- The excavation work needs to be done in compliance with applicable technical
construction regulations, including measures such as sewer installation and using
plants to cover.
- To prevent the spreading of mud into surrounding environment, take proper
measures to control sedimentation in high risk areas.
- When there is a need to dry construction site (foundation concrete pouring), the
pumped water containing sand will be controlled with regards to sedimentation
before discharging it into outside water bodies.
- Use diversion techniques at construction to prevent deposit from being stirred up in
water bodies.
5. Management of
stockpiles, quarries
- Material storage yards will be predetermined in the approved engineering design.
- Material supplied by local suppliers need to have operation licenses for particular
material type.
- To rehabilitate material storage yard after construction is completed.
- The contractor
- Construction
Supervision consultant
6. Waste and hazardous
waste
- Prior to construction, the contractor needs to prepare a procedure for controlling
waste (storage, use of recycle bins, site decommissioning, etc.) and strictly
complying during construction phase.
- Prior to construction, all necessary licenses have to be obtained related to waste
management.
- Proper measures are taken to ensure good practices in waste management and
treatment. The contractor will provide recycle bins, containers and other means to
collect waste from necessary areas.
- Waste can be stored temporarily at the site when it is approved by the Construction
Monitoring Consultant, local authorities before collection and treatment. If in the
- The contractor
- Construction
Supervision consultant
28
Environmental-social
issues
Mitigation measures applied Responsible bodies
absence of such authorities, normal domestic waste can be land filled.
- Recycle bins or containers storing waste have to be covered up from weather
impacts and intrusion by scavengers. Do not burn waste.
- Recyclable waste such as wood form, waste steel and packing material will be
collected and separated at the site from other waste sources for reuse, refilling or sale
to an external company.
- If it is impossible to carry away from the site, solid waste can be land filled at a
certain place approved by the construction supervising consultant provide in the
waste management plan. Under any circumstance, the contractor has to treat all
construction waste within the site.
- Waste lubricants will be taken out from the site by an authorized recycling
company.
- Waste lubricants and cleaning solutions will be collected into covered containers
and carried away by a contracted external company that is permitted to treat
hazardous waste
7. Impacts on vegetative
cover
- The contractor will prepare a plan on site clearance and vegetation recovery
according to applicable regulations for the construction supervising consultant to
approve. The contractor will strictly comply with this plan.
- Do not use chemicals in clearing vegetation.
- Do not cut down any trees when it is not provided in the vegetation clearance plan.
- If necessary, set up temporary fence to protect valuable trees prior to starting any
construction activities.
- The contractor
- Construction
Supervision consultant
8. Traffic management - Prior to construction, conduct consultation with local authorities and traffic police.
- Impacts on traffic flow needs to be considered in the construction plan before
- The contractor
- Construction
29
Environmental-social
issues
Mitigation measures applied Responsible bodies
approval. Traffic routes, particularly those with heavy duty vehicles need to consider
high risk area such as schools, hospitals or markets.
- It is necessary to provide sufficient lighting system for night time to ensure proper
traffic conditions.
- Arrange indication signs at the construction site to inform public people, provide
instructions to different components and instructions and safety directions
- Take proper traffic safety measures including sign posts and flags to indicate
danger
- Avoid transporting construction materials during peak hours.
- Space spared for walkers and vehicles at the site need to be separate from the site
and can be easily accessible. Provide proper sing posts where necessary.
- When pulling cables through the roads, school gates, residential areas in daylight, it
is necessary to put up scaffoldings, trees to prop cables
Supervision consultant
9. Interruption of utility
services
- Planned and unplanned interruptions to power, internet services: the Contractor
must undertake prior consultation and contingency planning with local authorities
about the consequences of a particular service failure or disconnection.
- During the laying out of cables crossing over telecommunications cable, mitigation
measures have to be taken (What are the measures?)
- Notify affected households of construction schedule as well as expected
interruptions (at least 5 days in advance)
- Interruptions to water supply for agriculture production need to be avoided.
- The contractor will ensure alternative water supply for affected residents in case it
is more than one day.
- Any damage to the existing service cables will be notified to the local authorities
- The contractor
- Construction
Supervision consultant
30
Environmental-social
issues
Mitigation measures applied Responsible bodies
for timely repair.
10. Restoration of
affected areas
- Clearance areas such as soil or rock quarries, waste treatment areas, worker houses,
warehouse and wood forms and any other temporary areas during construction
phase will be rehabilitated with regards to the landscape and vegetation cover.
- Compensate the vegetation cover at the soonest. Use proper vegetation for such
rehabilitation.
- Do not use exotic or banned vegetation for such rehabilitation
- Excavated hillsides and waste yard need to be planted with grass to prevent soil
erosion and landslide;
- All the affected areas will be compensated with proper landscape and there should
be no delay in doing so, including any necessary repair or construction of green
space and other affected areas.
- Soil contaminated with chemicals or hazardous waste will be carried away and land
filled in a proper hazardous dump site
- Rehabilitate all affected roads and bridges due to the project construction
- The contractor
- Construction
Supervision consultant
11. The impacts of
workers in local areas
- The contractor shall perform the registration of temporary residence for his workers
with the local government; and the contractor may collaborate with local authorities
to manage and closely monitor workers’ activities.
- To organize training courses for the workers on health, safety and the way to prevent
infectious diseases
- Dissemination of preliminary customs of local people for construction workers.
-
31
Environmental-social
issues
Mitigation measures applied Responsible bodies
12. Worker and public
safety
- The contractor will comply with all applicable regulations related to labor safety.
- Prepare and implement action plan in response to risk and emergency cases.
- Prepare emergency services right at the site.
- Provide training for workers on labor safety requirements.
- Ensure to provide protective devices for workers, including noise protection at high
risk places
- In destroying existing structures, workers and community need to be protected from
falling objects by taking proper protection measures
- Provide protective fences and warnings of danger at the construction site to indicate
danger to local resident.
- The contractor will provide safety measures such as installation of fences, provision of
warning signs at high risk areas, including pole foundation under construction to prevent
traffic accidents as well as other risk to local residents.
- Only allow trained workers to install, maintain or repair electrical equipment.
- Cut off and do correct earthling for the existing power line prior to construction work.
- Comply with labor safety procedures when working at height and with electrical
equipment
- The contractor
- Construction
Supervision consultant
13. Communication with
local communities
- Sustain communications to local authorities and community; the contractor will
work with local authorities to agree on construction schedule for sites near sensitive
areas or at sensitive time (regional festivals).
- Enhance relationship with local community in order to obtain necessary
information about the project activities in the region, progress and performance;
- Keep track of the community concerns and information required such as project
- The contractor
- Construction
Supervision consultant
32
Environmental-social
issues
Mitigation measures applied Responsible bodies
progress;
- Respond to community concerns via telephones and documents in a timely manner;
- Notify local residents of construction schedule, work schedule, potential
interruptions to services and detour roads and temporary buses, any destruction or
mine explosion schedule;
- Provide technical data and drawings for community, particularly a scheme on
construction sites and EMP;
- Provide notice boards at all sites to provide information about the site manager,
environmental officer, medical and safety officer, with concrete contact details and
other information so that affected people will be able to raise their voice and
concerns.
14. Chance find
procedures
During construction phase if the contractor finds any cultural and historical sites,
including commentary or tombs, the contractor will:
- Stop construction activities in the particular area;
- Protect the area from any damage or loss to the sites. In case the historical objects
can be removed or sensitive objects assign a person to protect it until local
authorities come to confirm and take over the issue;
- Notify the construction supervising consultant, who will be responsible for
informing local authorities or the state agencies of such cultural or historical sites
(within 24 hours or less);
- Local authorities or state agencies will be responsible for protecting and isolating
such area before any further processing.
- Decide how to process such issues is the responsibility of the local authorities,
including change, (in case a cultural or historical site is found and cannot be
- The contractor
- Construction
Supervision consultant
- NPMU
33
Environmental-social
issues
Mitigation measures applied Responsible bodies
removed), reservation, isolation, rehabilitation and rescue;
- If the cultural or historical site are of high value and the reservation is
recommended by relevant agencies the project owner will have to change project
design accordingly for the component in that particular area;
- Decisions related to the management of found sites will be notified in writing to
relevant authorities;
- Construction work will continue only after relevant authorities come and take
responsibility of potential sites..
C. Operation phase
1. Health and safety with
for workers and local
residents
1. Disseminate the information on electricity safety regulations to the users.
2. Comply Decree No. 106/2005/ND-CP dated 17 August 2005 of Goverment
on protecting grid; Decree No. 81/2009/ND-CP dated 12 October 2009 of
Goverment on protecting hight voltage grid
3. Regular training for local technicians and people on safety issues.
4. Use warning signs, barriers (locks, gates, iron barriers...) around substation
or tower to prevent people reach danger equipment;
Putting warning signs, barriers on the ground close to electricity wire to prevent electric
shock electric shock
North Power
Cooperation , Lang Son
Power Company (the
project operating units)
collaborating with local
government
2. Fire and explosion - Periodically inspect fire prevention and fighting facilities.
- Organize training on fire prevention and fighting for operation workers
3. Transmisison line -
Mitigation measures
- Only allow workers who have been trained and obtained certificates on installation,
maintenance and repair of electrical equipment
- The contractor
34
Environmental-social
issues
Mitigation measures applied Responsible bodies
related to transmission
lines
- Cut off power and provide safe earthling before construction on the power line or
where it is near power line
- Ensure operations related to power line will be undertaken by trained workers with
strict compliance with safety regulations. Qualified or trained workers to operate
power lines need to able to:
Distinguish between online and offline power lines from other parts of the
distribution system
Determine voltage of online power lines
Understand safety distance for each cable types
Ensure correct and sufficient use of safety devices and other safety procedures or
other online parts of the distribution system
- Even when being trained, workers will not contact any online parts unless:
Workers have been safely isolated from online parts via gloves or other insulation
devices
Online parts have been safely isolated from workers and other parts or
Workers have been isolated and safely insulated from online objects
- When operations and maintenance request minimum distance, provide trainings on
safety measures and safety devices for individuals and other preventive measures
identified in the health and safety compliance plan. (Below is the recommended
safety distance for workers:
o 2-15 kV: 0.6 m
o 15.1-35kV: 0.71 m
o 72.6-121 kV: 1.01 m
- CSC
- NPMU
Lang Son Power
Company (the project
operating units)
collaborating with local
government
35
Environmental-social
issues
Mitigation measures applied Responsible bodies
4. 4.Safety measures
when working at
height
Preventive and control measures include:
- Check the firmness of structures before starting work
- Take anti-fall measures including climbing skills, use of supporting devices and first
aid toolkit
- Install supporting and anti-fall devices
- Safety bands will not be smaller than 16 mm, two layers, and durable strength.
Safety bands will be replaced before any defect or crack is detected or if is too old
- When working with tools at height, workers will need an additional safely band
(backup).
- Sign posts and other obstacles need to be removed before starting work
- Use standard tool bag to carry tools and materials to the height when working on
pillars
5. 5. Electric and
Magnetic Filed
impacts
Prevent or minimize exposure to EMF in the working environment by developing and
implementing a EMF safety program with the following components:
- Determination of potential exposure level
- Trainings for workers on how to identify their exposure to EMF and its impacts
- Determination of safe areas in order to differentiate those areas with higher EMF
impacts than the others where EMF impacts are small enough not to be provided
with mitigations and minimize exposure to high EMF impact areas
- The exposure detector for individuals will be installed to give warning when
exposure is below the safety limit (for example, 50%). Action plans for mitigating
impacts includes taking turn to work in high risk areas, and if necessary being
provided with protective devices..
36
6.2. Environmental monitoring plan
Table 6.2. Environmental monitoring plan
Impacts Monitored
Parameter
Monitored
Point
Monitoring
equipment/
methods
The
timing/freque
ncy of
monitoring
Costs Responsibili
ty
Construction phase
I. Vegetation
cover
clearance or
cutting down
trees
Clearance
technique
- Disposal
of cut-
down trees
- Along
the
transmissi
on line
- In a
centralize
d place for
processing
- Observing - Everyday, -
From
beginning to
the last
moment.
- The
contractor –
Construction
supervising
consultant
II. Rural
roads in the
project region
- All heavy
tonnage
vehicles on
the local
roads
- Along
the roads
Observation
and
consultation
with local
residents.
- Every
month, when
materials,
machinery are
transported to
the region.
- Four
months.
-Contractor,
-
Construction
supervising
consultant
III. Surface
water quality,
sedimentation
and erosion
- Not
excavate
while it is
raining
- Not clear
plants
completely
- Surface
water near
the site
-
Observation
- During and
after heavy
rain
- The
contractors –
Construction
supervising
consultant
IV. Dust, air
pollution
- Dust
concentrati
on in
material
storage
area
- Cover for
material
during
transportat
ion process
- Areas
with
excavation
foils and
material
storage
Observing -In presence
of strong
winds
- The
contractors –
Construction
supervising
consultant
37
Impacts Monitored
Parameter
Monitored
Point
Monitoring
equipment/
methods
The
timing/freque
ncy of
monitoring
Costs Responsibili
ty
V. Noise
level
- Noise
level
- People’s
reaction to
noise
emanating
from
constructio
n activities
- The line
section
running
over
residental
area
Consultation
with local
residents
-During
activities that
may result in
high noise
level;
Complaints
by local
residents
- The
contractors –
Construction
supervising
consultant
VI. The
culture and
history
monuments
The effects
of noise
At the
constructi
on places
close to
culture
and
history
monument
s
Observing
the local
residents
During
construction,
the activities
emanate noise
- The
contractors –
The
construction
monitoring
consultant
VII.
Sanitation
situation at
the
construction
site,
including the
hygiene of
workers’
tents
- Garbage,
waste
water at
the
constructio
n site and
workers’
tents
- If he
tents have
been
supplied
clean
water and
had
sanitary
latrines
At the
tents
Observing Every week,
when official
acceptance of
work
- The
contractors –
The
construction
monitoring
consultant
VII. Safety of
workers and
local
residents
Accidents
happen
At the
sites, local
areas
- Consult,
Record the
construction
log of the
contractor
- The
contractors –
The
construction
monitoring
consultant
38
Impacts Monitored
Parameter
Monitored
Point
Monitoring
equipment/
methods
The
timing/freque
ncy of
monitoring
Costs Responsibili
ty
Operation phase
I. Maintain
and protect
the ROW
The height
of plants
along the
ROW
- Along
the ROW,
houses
and trees
- Prune trees
and ensure a
safe distance
for the ROW
One
month/time
- North High
Voltage grid
Company
II. Danger
due to danger
The intact
situation of
poles,
insulators,
protecting
devices of
the station
At the
pole of
the line
route, the
position
of the
station
Observing
and
assessing
3 months/time - North high
voltage grid
Company
7. ARRANGEMENT FOR ENVIROMENTAL MANAGEMENT PLAN
IMPLEMENTATION, IMPROVE CAPACITY
7.1. The responsibilities for implementing Environmental Management Plan (EMP)
7.1.1. During Detailed Design and Preparation of Bidding Contract Documents
During the detailed design and bidding invitation preparation, the project management
unit will be responsible for incorporate the EMP (mitigation measures, responsibilities of the
contractor) into the attached annexes in the bidding invitation and contract signed with the
contractor. Engineers taking charge of the detailed design will also refer to findings in the
EIA and EMP to ensure environmental issues will be looked at in the final design.
During the bidding invitation preparation and the contract, it is necessary to ensure the
contractor is fully informed of its responsibilities in implementing environmental mitigation
measures and its commitment to compliance.
7.1.2. During Construction Phase
PPMU will assign the Construction Supervising Consultant (CSC) and/or field engineer
to be responsible for supervision of safeguard performance of contractor on a daily basis. A
generic Terms of Reference (TOR) is provided in Annex 1. CSC and/or field engineers will
carry out, but not limited to, the following tasks:
- Before the commencement of the construction, confirm that all compensation for land
and facilities are provided and relocation and/or land acquisition/donation has been
completed.
- Closely supervise the implementation of safeguard measures throughout the
construction period.
39
- Confirm the compliance with the EMP and inspect for any damages caused by the
contractor. If necessary, prepare a minutes to ask the contractor to compensate or rehabilitate
as provisions of the contract. Contractor safeguard performance will be included in the
subproject progress report.
Role and responsibilities of parties in implementing EMP are summarized in the below
table:
Table 7.1. The parties involved in the EMP
Role Responsibilities Organization
Project Owner - Ultimately responsible for overall project
management, including environmental
management.
North Power
Corporation
Environmental
Officer
- Specific responsibility and point of
contact for environmental issues.
Environmental
Officer
Project
Implementation
and
management
Agency
- Responsible for coordination and
management of overall project
implementation, including guiding and
supervising implementation of the EMP.
- Planning and implementation of
environmental management activities
during construction
- Coordinating with other parties in
relation to environmental
management activities.
- Carrying out internal monitoring and
supervising
- Supervising and providing budget for
monitoring activities.
- Reporting on environmental information to
concerned parties
PMU
Project Operator - Responsible for operation of the project
including operation stage environmental
management and monitoring activities.
North High
voltage Grid
Company
Consultant - Responsible for preparation of EMP
documentation.
Construction
Monitoring
consultant
agency hired by
PMU
Construction
Supervision
- Responsible for supervision of civil works
contractors during construction, including
implementation of environmental
The contractor
selected by the
PMU
40
Role Responsibilities Organization
consultant management activities under the EMP
7.2. Building the EMP implementation capacity
- Planning: (i) training on environmental management in which there are the EMP
implementation part and other training contents for NPC officials, if required ,
ii)environmental and EMP training for construction staffs of the contractor (done by the
contractors or by the construction monitoring consultant, or done by PMU)
- Estimated Cost
Table 7.2. Estimated cost to build the EMP implementation capacity
No Training contents Participants Unit Amount
1 Annual training of
EVN for all parties
3 persons from the
PMU of NPC,
participating in
2days
5,000,000 VND 30,000,000 VND
2 Experience sharing
workshops on the
EIA preparation and
the EMP
implementation
2 persons from the
PMU of NPC,
participating in
2days
5,000,000 VND 20,000,000 VND
3 Training on the EMP
implementation
2 persons from Lang
Son Power
Company,
participating in 2
days
5,000,000 VND 20,000,000 VND
4 Training on the EMP
enforcement for local
officers
1 person/commune x
13 communes
1 person/district x 10
districts,
participating in 1 day
500,000 VND 11,500,000 VND
5 Training for site
commanders
01 person/commune
x 13 communes
500,000 VND 7,500,000 VND
Total 89,000,000 VND
7.3. Reporting process:
Reporting responsibilities and frequency for the EMP implementation described in the
table below:
Table 7.3. Responsibilities and frequency of reports on implementation of the EMP
41
No. Report by Submitted to Frequency of
reporting
1 The contractor PMU Once prior to
starting construction
afterwards every one
month.
2 Construction supervisor (cum
environmental monitor)
PMU Monthly
3 Community supervisor (if any) MPU If any complaint
4 PMU EVN Quarterly
5 EVN WB Biannually
7.4. Estimate cost for the implementation of the EMP
Funds for implementation cost: Estimating cost for (i) the implementation of mitigation
measures (ii) training activities
Table 7.4. Estimated cost for the implementation of the EMP
No. Description Construction phase Operation phase
01 Mitigation measures. Under the contract with
the contractor
Under the
production cost of
province electricity
02 Environmental monitoring
during construction phase
(incorporated into the cost of
construction supervising
consultant).
Under the cost for PMU
operation (Supervising
consultant will exercise
independent monitoring)
Under the cost of
the project owner
operation
03 Training on environmental
management by project
investor for local officers,
contractor and supervising
consultant.
89,000,000 VND Capacity building
need assessment
(trainings,
workshops and
study tours)
TOTAL COST: 89,000,000 VND
* The cost for mitigation measures during the construction phase and
environmental monitoring by the supervising consultant will be included in the
construction supervising contract.
42
8. CONSULTATION AND DISCLOSURE OF INFORMATION
In the subproject preparation phase (the year of 2011), the following five activities
were carried out:
Activity 1: Surveying the site, working with the local authorities to discuss the route
and the substation locations.
Activity 2: Surveying the site and preparing the EMP reports.
Activity 3: Conducting public consultation on the subproject.
From August 10, 2011 to September 15, 2011, a meeting with local residents in 13
communes was organized in order to consult public on the EMP, the representatives of the
Project Owner also involved the following contents:
- Describing the subproject, the route, the substation locations, and the necessity for the
subproject;
- The potential impacts on the environment and communities;
- The measures to mitigate environmental impacts.
Participants: Participants of the Commune People Committee, Farmer Association,
Women Association , and other public organizations, hamlet chiefs, representatives of
project’s affected households, and consulting agency.
Summary of comments from the participants:
Most of opinions of the local authorities and people were supportive of the subproject.
And there are some suggestions for implementing the projects as follows:
- Agree with the alignment selected by consulting agency;
- The design of the pole position is required to consider carefully to avoid building
poles in the garden, near houses, in the building land areas.
- The investor must notify the acquisition land area and the affected people;
- Compensation must be fair and have a thorough implementation
- The constructing contractors must have a plan to work in the shortest possible time to
avoid affecting the agricultural production.
- To implement measures to limit pollution such as dust, spillage of construction
materials during transportation and construction
- In the phase of laying foundations, the contractors must implement quickly and
always having people around the foundation position or covering the hole to avoid cattle,
poultry or people, especially children fall to the hole.
- It is necessary to place the signs at site locations in order to create favorable
conditions for traffic and have warning measures to avoid the unfortunate accident occurred.
- During project construction phase, the local government and people will work in
partnership with building contractors, consultancy agencies and investors to monitor the
project implementation to ensure a project implementation way that be fast, compact, safe
and guaranteed under the provisions of the state of construction.
The public consultation minutes is included in Appendix 6.
43
All the involved issues as well as suggestion of the local people that recognized by the
consultant and the investor, will be considered in the sub-project design and in the EMP
implementation phase.
Activity 4: Review and correct the EMP in accordance with the comments. Continuing
to receive feedback from the affected households. To collect opinions of the people to
complete the environmental impact mitigation measures in the EMP.
Activity 5: Disclosure of the EMP
The PMU will disclose the EMP, RP in Vietnamese, and the summary of the project for
Lang Son Provincial People Committee, the subproject’s communes and district People
Committees before the appraisal of the DEP project.
The EMP copies in Vietnamese and English will also be sent to the Vietnam
Development Information Center at 63 Ly Thai To street, Hanoi City for information
disclosure.
The EMP copies in English will also be disclosed at the InfoShop of the World Bank in
Washington DC.
44
9. REFERENCES
1 The project’s compensation plan
2 Source book of the World Bank on environmental impact assessment
3 Statistical Yearbook 2010
4 The project investment report
5 Draft of Safety Policy Framework on environmental and distribution efficiency project
45
10. ANNEXES
Annex 1: TOR for Construction Supervision Consultant
General
The Construction Supervision Consultant is to provide professional technical services
(“the Services”) to help ensure effective implementation of the subproject EMP
Scope of services:
The general services to be provided by the CSC are to inspect, monitor the construction
activities to ensure that mitigation measures adopted in the EMP are properly implemented,
and that the negative environmental impacts of the project are minimized.
On behalf of the PMU, the CSC will conduct the following tasks:
- Conduct regular site inspections;
- Review the status of implementation of environmental protection measures against the
EMP and contract documents;
- Review the effectiveness of environmental mitigation measures and project
environmental performance;
- As needed, review the environmental acceptability of the construction methodology
(both temporary and permanent works), relevant design plans and submissions. Where
necessary, the CSC shall seek and recommend the least environmental impact alternative in
consultation with the designer, the Contractor(s), and PMU;
- Verify the investigation results of any non-compliance of the environmental quality
performance and the effectiveness of corrective measures; and
- Provide regular feedback audit results to the contractor’s Chief Engineer according to
the procedures of non-compliance in the EMP;
- Instruct the Contractor(s) to take remedial actions within a specified timeframe, and
carry out additional monitoring, if required, according to the contractual requirements and
procedures in the event of non-compliances or complaints;
- Instruct the Contractor(s) to take actions to reduce impacts and follow the required
EMP procedures in case of non-compliance / discrepancies identified;
- Instruct the Contractor(s) to stop activities which generate adverse impacts, and/or
when the Contractor(s) fails to implement the EMP requirements / remedial actions.
- For contracts that Site Environmental Management Plan (SEMP) are required, the CSC shall provide the final review and recommend clearance of all Site Environmental
plans which may affect the environment. These include, but are not limited to: dredging
areas, borrow pits and disposal sites, worker’s camp plans. The CSC will review and approve
the SEMP presented by the Contractors. Where these plans are found not to comply with the
EMP or RP, the CSC shall work with the PMU and Contractor to establish a suitable solution.
- Addressing Complaints: Complaints will be received by the Contractor’s Site Office
from local residents with regard to environmental infractions such as noise, dust, traffic
safety, etc. The Contractor’s Chief Engineer or his deputy, and the CSC shall be responsible
for processing, addressing or reaching solutions for complaints brought to them. The CSC
shall be provided with a copy of these complaints and shall confirm that they are properly
addressed by the Contractors in the same manner as incidents identified during site
inspections.
- Certification for Monthly Payments: The CSC shall confirm the monthly payments
for environmentally related activities implemented by the Contractor.
- Reporting: the CSC shall prepare the following written reports:
46
o Bi-weekly report of non-compliance issues
o Summary monthly report covering key issues and findings from reviewing and
supervision activities
o At the end of the project the CSC shall prepare a final report summarizing the
key findings from their work, the number of infringements, resolutions, etc. as
well as advice and guidance for how such assignments should be conducted in
the future.
47
Annex 2: Report template for monitoring of EMP implementation (used for report by
supervising consultant to PMU)
Project name:
Project location: Province: District:
Commune/Town:
The construction supervision consultant:…………….(Full name)
Date of report:
No. Parameter
Assessment of
comments by
supervising
consultant and
community
Comment/
Recommenda
tion
Construction phase
1 Water turbidity and soil erosion
2 Noise level at the site and nearby
residential area
3 Dust concentration
4 Solid waste and site cleaning after
construction
5 Conflict between workers and local
residents
6 Disease spreading
7 Hygiene condition and safety for workers
8 Local traffic interruption
9 Road damage
10 Safety measure application
11 Material management
12 Remained soil and rock management
48
No. Parameter
Assessment of
comments by
supervising
consultant and
community
Comment/
Recommenda
tion
13 Evidences about loss to biodiversity (if
any)
14 Evidences about loss to cultural and
historical sites
15 Other environmental issues (if any)
….
Operation phase
16 Transmission line lobby maintenance
17 1. Health and safety for operation
workers and local residents
49
Annex 3: Report template for monitoring of EMP implementation (used for reports by
contractor)
Project name:
Project location:
Construction agency name:
The initial project report or monthly report:
Date of report:
No. Impact Mitigation
measure taken Comment
Construction phase
1 Surface water pollution
2 Noise and vibration level
3 Soil erosion
4 Air pollution
5 Impacts on agriculture land due to
temporary land acquisition
6 Local traffic interruptions
7 Existing road damage
8 Solid waste from excavation
9 Remained soil management
10 Environmental impacts by workers
11 Conflict between workers and local
residents
12 Disease spreading between workers
and local residents
13 Health and safety
14 …..
Name of person prepared this report:
Title:
Address:
Telephone:
50
Annex 4: The project environment license (The certificate of project environmental
protection commitment)
51
Annex 5: The project map and current images of the subproject (attached)
5.1. The project map
52
5.2. Current images of the project location:
Na Pan substation will be built on public
land near Na Pan hamlet road.
Image 1: The location of the Na Pan substation – Hoang Van Thu commute-Van Lang
district
Dong Tien 3 transformer station will built on
the land near the inter-hamlet road between
Lang Ca hamlet and Lien Phuong hamlet
Image 2: The location of Dong Tien 2 substation – Dong Tien commute-Huu Lung
district
53
Annex 6: The information of the public consultation and minutes of public consultation (attached)
No Commute/District The consultation
location Date
Number of
participants
Issues or concerns to be
discussed/raised PMU Feedback
Dinh Lap - Has the subproject been carried
out on time?
- How will the new pole be located
,these affect local land and trees?
- How many acquisition land and
trees will be required?
- How the compensation will be
implemented?
- The construction period is
expected, execution time?
- Measures to minimize dust,
construction waste
- The accidents arising from the
foundation such as cattle, poultry,
people fall to the hole
- The construction activities affect
traffic.
- The local people will work
together to monitor the
implementation of the subproject
-The investors and the consultant
agencies try to implement the
project according to the
schedule
- The consultant will select the
pole position to mitigate the
impacts to local people, the
position of pole will be
determined confirmed by the
local government
- The impacts will be considered
in RP and be sent to the local
people
- Cash compensation at
replacement costs for all affected
- The construction time is
expected to begin in December,
2012, after the winter harvest is
completed
- Mitigation measures will be
applied to limit the impact
- Appoint staffs or the pole be
1 Binh Xa Commute People
Committee Office
12,
August
2011
15
Bac Son
2 Hung Vu Commute People
Committee Office
09,
August
2011
16
3 Bac Son Commute People
Committee Office
8,
August
2011
17
Van Quang
4 Luong Nang Commute People
Committee Office
5,
August
2011
16
Van Lang
5 Hoang Viet Commute People
Committee Office 13,
August 17
54
No Commute/District The consultation
location Date
Number of
participants
Issues or concerns to be
discussed/raised PMU Feedback
2011 position will be covered to avoid
causing accidents, especially
accidents with children
- Place signs warning
instructions and safety
- Desire the local people and
government to join in the project
implementation phase the
project on schedule and
regulations
6 Hoang Van Thu Commute People
Committee Office
14,
August
2011
15
Loc Binh
7 Dong Quan Commute People
Committee Office
3,
August
2011
14
8 Đong Buc Commute People
Committee Office
4,
August
2011
16
Trang Dinh
9 Tri Phuong Commute People
Committee Office
21,
August
2011
15
Binh Gia
10 Hoang Van Thu Commute People
Committee Office
20,
August
2011
18
Cao Loc
55
No Commute/District The consultation
location Date
Number of
participants
Issues or concerns to be
discussed/raised PMU Feedback
11 Hoa Cu Commute People
Committee Office
23,
August
2011
16
Chi Lang
12 Mai Sao Commute People
Committee Office
26,
August
2011
14
Huu Lung
13 Don Tien Commute People
Committee Office
30,
August
2011
18
56