ver the past 12 months, the Primary Care team hasbeen actively involved in the delivery of 12 new
primary care schemes on site. Of these, six havebeen completed, totalling 9,685m2 of space with a totalconstruction cost of £17.35 million.
A further 6 projects totalling 7696m2, with a totalconstruction cost of £17.32 million are currently on siteand are due to be completed this calendar year.
A brief synopsis of each project is included below.
❖ Completed projects ❖ Manchester Square Health Centre, Milford Haven
Project details: Manchester Square Health Centre,Milford Haven
Client: Hywel Dda Health Board,Barlow House Surgery &Robert Street Practice
Third Party Developer: LSP Developments Ltd &Assura Medical Centre Ltd
Floor area: 2067m2 GIACost (TOTAL): £2.8mArchitects: West Hart Partnership LtdBuilding Contractor: Opco LtdProject Managers: Carl Dean Associates LtdM & E Engineers: Chapman Bathurst LtdStart on Site: 29 September 2011Completion date: 22 October 2012
❖ Gelligaer Health Centre, Rhymney Valley
Project details: New Gelligaer Health CentreClient: Aneurin Bevan Health Board &
Gelligaer and Gilfach SurgeryThird Party Developer: LSP Developments Ltd &
Assura Medical Centre LtdFloor area: 891m2 GIACost (TOTAL): £1.7mArchitects: West Hart Partnership LtdBuilding Contractor: Opco LtdProject Managers: Carl Dean Associates LtdM & E Engineers: Waterman Building Services LtdStart on Site: 18 July 2011Completion date: 11 June 2012
❖ Grangetown Medical Centre, Cardiff
Project details: Grange Medical Centre,Grangetown, Cardiff
Client: Cardiff and Vale Health Boardand Dr Lush & Partners
Third Party Developer: MedicX Floor area: 1,248m2 GIACost (TOTAL): £3.5mArchitects: Powell Dobson Building Contractor: Vinci Construction LtdProject Managers: Riley ConsultingM & E Engineers: MLMStart on Site: September 2011Opened to patients: October 2012
Primary Care Estate News
O
Courtesy of John Evans Photography
Courtesy of John Evans Photography
Courtesy of Cardiff and Vale UHB, MedicX and Vinci Construction Ltd
Internet: www.wales.nhs.uk/whe12
NHS Issue 14 4/16/13 8:32 pm Page 14
![Page 2: NHS Issue 14](https://reader034.vdocuments.us/reader034/viewer/2022051510/627e9fc1b9064f359e46b739/html5/thumbnails/2.jpg)
❖ Hirwaun Medical Centre, Cynon Valley
Project details: Hirwaun Medical Centre Client: Cwm Taf Health Board and
Dr George & PartnersThird Party Developer: MedicX Floor area: 1,324m2 GIACost (TOTAL): £2.8mArchitects: West Hart Partnership Building Contractor: Dawnus Construction LtdProject Managers: Davis LangdonM & E Engineers: MLMStart on Site: September 2011Opened to patients: July 2012
❖ The Wye Valley Surgery, Trellech, Monmouthshire
Project details: The Wye Valley Surgery, Trellech Client: Wye Valley Practice &
Aneurin Bevan Health BoardThird Party Developer: Ashley House Plc Floor area: 473m2 GIACost (TOTAL): £1.1mArchitects: Ashley House Plc, In-house
architects Building Contractor: Cowlin Construction LtdProject Managers: Ashley House PlcCivil and Structural Eng.: Such Salinger Peters
(Design Stage)M & E Engineers: Design & Build sub-contractorStart on Site: 30 August 2011Opened to patients: 30 April 2012
❖ Aberystwth Primary Care Centre
Project details: Aberystwyth Primary Care CentreClient: Padarn Surgery & University
of WalesThird Party Developer: Gaufron Healthcare Limited Floor area: 3,682m2 GIACost (TOTAL): £5.45mArchitects: Austin Smith Lord Building Contractor: Par Homes LimitedProject Managers: Austin Smith LordM & E Engineers: Unitec Webber LenihanStart on Site: December 2010Completion date: March 2012
Courtesy of Cwm Taf HB, MedicX and Dawnus Construction Ltd
Courtesy of David Stewart
Courtesy of Janet Baxter Photography - Aberystwyth
Intranet: howis.wales.nhs.uk/whe 13
NHS Issue 14 4/16/13 8:32 pm Page 15
![Page 3: NHS Issue 14](https://reader034.vdocuments.us/reader034/viewer/2022051510/627e9fc1b9064f359e46b739/html5/thumbnails/3.jpg)
❖ Beacon Development, SA1, Swansea
Project details: Beacon Development, SA1,Swansea
Client: Tawe Medical Centre, Port TennantPractice, ABMU Health Board,Eastside Dental Centre,University of Swansea College ofMedicine and Coop Pharmacy
Third Party Developer: Apollo Capital Projects Floor area: 3,100m2 GIACost (TOTAL): £7.25m total development costArchitects: B3 Architects Building Contractor: Dawnus ConstructionProject Managers: RPA LtdM & E Engineers: McCann & PartnersStart on Site: October 2011Practical Completion date: 26 April 2013Opened to patients: 13 May 2013
❖ Cloughmore Surgery, Cardiff
Project details: Cloughmore Surgery, Cardiff Client: Cloughmore Surgery – Dr Foy &
PartnersThird Party Developer: Apollo Capital Projects Floor area: 1,050m2 GIACost (TOTAL): £2.5mArchitects: Boyes Rees Architects Building Contractor: Dawnus ConstructionProject Managers: RPA LtdM & E Engineers: McCann & PartnersStart on Site: August 2012Practical Completion date: 2 August 2013Opened to public: 19 August 2013
❖ North Caerphilly Integrated Resource Centre
Project details: Integrated Health & Social CareResource Centre, Rhymney,North Caerphilly
Client: Aneurin Bevan Health Board,Caerphilly County BoroughCouncil, Dr Evans and Dr Potts
Third Party Developer: MedicX Floor area: 3,718m2 GIACost (TOTAL): £7.7mArchitects: Powell Dobson Building Contractor: Dawnus Construction LimitedProject Managers: E C HarrisM & E Engineers: Hicks TitleyStart on Site: 30 April 2012Estimated completion
date: 26 July 2013
❖ On site projects
Courtesy of Apollo Capital Projects Developments Ltd
Courtesy of Apollo Capital Projects Developments Ltd
Courtesy of Aneurin Bevan HB, MedicX and Dawnus Construction Ltd
Internet: www.wales.nhs.uk/whe14
NHS Issue 14 4/16/13 8:32 pm Page 16
![Page 4: NHS Issue 14](https://reader034.vdocuments.us/reader034/viewer/2022051510/627e9fc1b9064f359e46b739/html5/thumbnails/4.jpg)
❖ Rumney Primary Care Centre, Cardiff
Project details: Rumney Primary Care Centre Client: Rumney Medical Centre,
Cardiff & Vale University HealthBoard and GS Bhogal Pharmacy
Third Party Developer: Apollo Capital Projects Floor area: 2,386m2 GIACost (TOTAL): £6mArchitects: Boyes Rees ArchitectsBuilding Contractor: Vinci ConstructionProject Managers: RPA LtdM & E Engineers: McCann & PartnersStart on Site: August 2012Practical Completion date: 13 September 2013Opened to public: 30 September 2013
❖ Felinheli Primary Care Centre, Gwynedd
Project details: Felinheli Primary Care Centre Client: Betsi Cadwaladr University
Health Board andFelinheli Surgery
Third Party Developer: Amcen Floor area: 880m2 GIACost (TOTAL): £1.9mArchitects: W M DesignBuilding Contractor: Watkin Jones & SonProject Managers: Adeiladol CyfM & E Engineers: Carpenter Davies PartnershipStart on Site: 10 September 2012Estimated completion
date: 30 July 2013
❖ Crymych Extra Care Housing and Health Scheme,Pembrokeshire
Project details: Crymych Extra Care Housing andHealth Scheme
Client: Hywel Dda LHBThird Party Developer: Family Housing Association
(Wales) Ltd Floor area: 712m2 GIACost (TOTAL): £1.715mArchitects: B3 Architects Building Contractor: Cowlin ConstructionProject Managers: Ivor Russell and PartnersM & E Engineers: SABA Consult Start on Site: 23 July 2012Estimated completion
date: 2 May 2014
Acknowledgements
NWSSP – FS is grateful for the information and imagesprovided by each of the individual developers to enablepublication of this feature.
For further information contact:Nicola Powell on 029 2031 5509 ore-mail: [email protected]
SOLAR SHADING BRISE SOLEIL TO SAME DEPTH AS THE SLATEWALL FEATURE PANELS. TO COMPRISE TIMBER LOUVRES ONSAE 316 MARINE GRADE STAINLESS STEEL FRAME
WG - 01WG - 02WG - 18WG - 19
WF - 27 WF - 26 WF - 25 WF - 24 WF - 23 WF - 22 WF - 21
WG - 13WG - 14WG - 15WG - 16WG - 17
ALUMINIUM/TIMBER COMPOSITEWINDOW SYSTEM, NATURAL TIMBERFINISH INTERNALLY AND LIGHT GREYEXTERNALLY AS L10/35A
LINDAB GALVANISED STEEL GUTTERINGAND DOWNPIPES
MOVEMENT JOINT INMASONRY AND RENDER
MOVEMENT JOINT INMASONRY AND RENDER
ASHLAR SLATE WALLING, RANDOMCOURSED BLOCKS AND SIZES
WESTERN RED CEDER CLADDING
SPECIALIST DESIGN GLASSCANOPY OVER MAIN ENTRANCESUPPORTED OFF MARINE GRADESTAINLESS STEEL.
NATURAL SLATE ROOF OFUNIFORM COLOUR AND TEXTURE22.5 DEGREE PITCH AND 100MMMINIMUM HEADLAP
ASHLAR SLATE WALLING, RANDOMCOURSED BLOCKS AND SIZES
100X25MM SQUARE EDGEWESTERN ReD CEDaR AT 150MMVERTICAL CTS ACTING AS SOLARSHADING.
WG - 04WG - 05WG - 03 WG - 20
ED - 02 ED - 01 S - 02
WF - 28
2,1
00
ALUMINIUM/TIMBER COMPOSITEWINDOW SYSTEM, NATURAL TIMBERFINISH INTERNALLY AND LIGHT GREYEXTERNALLY AS L10/35A
IBSTOCK HOLBROOK SANDFACED DARKFACE BRICKWORK BELOW DPC LEVEL
NDAB GALVANISED STEEL GUTTERINGND DOWNPIPES
LINDAB GALVANISED STEELGUTTERING AND DOWNPIPES
FROSTED GLASS TO EXTERNALFIRE ESCAPE DOORS.
MOVEMENT JOINT IN MASONRYAND RENDER
MOVEMENT JOINTIN MASONRYALONG LINE OFSTONE FACING
EXTERNAL LETTERBOX MODEL 6362V BYMAILBOXES GB. SIZE 362X322X104MMMOUNTED AT 850MM TO LETTER SLOTABOVE EXTERNAL GROUND LEVEL
Felinheli HealthCentre
CanolfanIechyd
Prif FynedfaMain Entrance
NORTH EAST ELEVATION 1:100
SOUTH EAST ELEVATION 1:100
Courtesy of Apollo Capital Projects Developments Ltd
Courtesy of W M Design & Architecture LTD
Courtesy of B3 Architects
Intranet: howis.wales.nhs.uk/whe 15
NHS Issue 14 page 17 5/14/13 3:50 pm Page 4