Navajo Generating StationOwners Initial Proposal
Timeline DiscussionGlen D. Reeves
February 4, 2011
2-04-11 1NGS Owners Initial Proposal - GDReeves
EPA Rulings Expected
Key Challenges
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Co-Tenancy ExpiresLADWP Withdraws
Lease Expires323 Grants Expire
Coal Contract ExpiresTransmission Contracts Expire
LADWP Seeks Withdrawal
Environmental
Critical Agreements
Ownership
Equipment Installation
Requirement Expected
Water Service Contract Expires
2-04-11 2NGS Owners Initial Proposal - GDReeves
2011
Timeline for Proposed Activities Surrounding NGS Efforts for Meeting the
Goal of the Regional Haze Rule
• Regional Haze Rule•Effective 2005•Natural Background Visibility by 2064•Class 1 Areas
(National Parks, Wilderness Areas)
2064
2-04-11 3NGS Owners Initial Proposal - GDReeves
53 Years
2011 2064
Timeline for Proposed Activities
“Goal is to achieve natural background levels by 2064 (i.e., no manmade visibility impairment)”
53 Years
Every 10 years beginning in 2018 the previous SIP/FIP must be updated to account for current visibility and progress made toward the 2064 goal
2-04-11 4NGS Owners Initial Proposal - GDReeves
2011 2064
Timeline for Proposed Activities
“Goal is to achieve natural background levels by 2064 (i.e., no manmade visibility impairment)”
2018 2028 2038 2048 2058
Every 10 years beginning in 2018 the previous SIP/FIP must be updated to account for current visibility and progress made toward the 2064 goal
2nd SIP/FIP update for RHR is
due in 2018
2-04-11 5NGS Owners Initial Proposal - GDReeves
2011 2064
Timeline for Proposed Activities
2018 2028 2038 2048 2058
2nd SIP/FIP update for RHR is
due in 2018
NGS Site Lease Termination(12/23/19)
2-04-11 6NGS Owners Initial Proposal - GDReeves
Key Durations
• Lease Negotiation and Navajo Nation Approval– Assume End of 2011
• NEPA Process – (EIS required)– Current average 5.9 years– Assume 6 years
• DOI Approval of all Grants and Leases– Assume 6 months
2-04-11 7NGS Owners Initial Proposal - GDReeves
Key Durations
• Legal Challenges - Assume 2 years • Design, Procurement and Installation of SCR
– 43 months for 1st unit– 67 months for all 3 units
• Scheduled Unit Outages– Major Outages
• 2009, 2010, 2011• 2015, 2016, 2017• 2021, 2022, 2023• 2027, 2028, 2029
2-04-11 8NGS Owners Initial Proposal - GDReeves
Key Owner Requirements
• No Major Capital Expenditures Until Lease is Approved, Grants are Issued, Ownership Resolved
• Tie-In Outages Occur Simultaneous with Planned Major Outages.– 2 Months Required for Tie-in Outages – 2 Months Required for Major Outages
2-04-11 9NGS Owners Initial Proposal - GDReeves
2011
Key Dates
NGS Site LeaseTermination(12/23/19)
3 3 32 2 21 1 1
2-04-11 10NGS Owners Initial Proposal - GDReeves
2011
Key Dates
NGS Site LeaseTermination(12/23/19)
3 3 32 2 21 1 1
Lease Negotiations and Approvals
(12/31/11)2-04-11 11NGS Owners Initial Proposal - GDReeves
2011
Key Dates
NGS Site LeaseTermination(12/23/19)
3 3 32 2 21 1 1
Lease Negotiations and Approvals
(12/31/11)
NEPA Process(Comp - 12/31/17)
2-04-11 12NGS Owners Initial Proposal - GDReeves
2011
Key Dates
NGS Site LeaseTermination(12/23/19)
3 3 32 2 21 1 1
Lease Negotiations and Approvals
(12/31/11)
NEPA Process(Comp - 12/31/17)
2-04-11 13NGS Owners Initial Proposal - GDReeves
2011
Key Dates
NGS Site LeaseTermination(12/23/19)
3 3 32 2 21 1 1
Lease Negotiations and Approvals
(12/31/11)
NEPA Process(Comp - 12/31/17)
Legal Challenges(2 years ?)
2-04-11 14NGS Owners Initial Proposal - GDReeves
2011
Key Dates
NGS Site LeaseTermination(12/23/19)
3 3 32 2 21 1 1
Lease Negotiations and Approvals
(12/31/11)
NEPA Process(Comp - 12/31/17)
2nd SIP/FIP update for RHR is
due in 2018 Legal Challenges(2 years ?)
2-04-11 15NGS Owners Initial Proposal - GDReeves
2011
Proposed SCR Installation Period
NGS Site LeaseTermination(12/23/19)
3 3 32 2 21 1 1
Lease Negotiations and Approvals
(12/31/11)
NEPA Process(Comp - 12/31/17)
2nd SIP/FIP update for RHR is
due in 2018
SCR Design and installation
Duration
Legal Challenges(2 years ?)
2-04-11 16NGS Owners Initial Proposal - GDReeves
2011
Installation Period Required if SCR is required in this BART
NGS Site LeaseTermination(12/23/19)
3 3 32 2 21 1 1
Lease Negotiations and Approvals
(12/31/11)
NEPA Process(Comp - 12/31/17)
2nd SIP/FIP update for RHR is
due in 2018
SCR Design and installation
Duration
Legal Challenges(2 years ?)
2-04-11 17NGS Owners Initial Proposal - GDReeves
2011
IF Owners don’t take Risk of installing SCR without knowing NEPA outcome
NGS Site LeaseTermination(12/23/19)
3 3 32 2 21 1 1
Lease Negotiations and Approvals
(12/31/11)
NEPA Process(Comp - 12/31/17)
2nd SIP/FIP update for RHR is
due in 2018
SCR Design and installation
Duration
Legal Challenges(2 years ?)
2-04-11 18NGS Owners Initial Proposal - GDReeves
2011
Proposed SCR Installation Period
NGS Site LeaseTermination(12/23/19)
3 3 32 2 21 1 1
Lease Negotiations and Approvals
(12/31/11)
NEPA Process(Comp - 12/31/17)
2nd SIP/FIP update for RHR is
due in 2018
SCR Design and installation
Duration
Legal Challenges(2 years ?)
2-04-11 19NGS Owners Initial Proposal - GDReeves