nfm&t - r1.45 proactive pm - managing beyond the obvious ...managing beyond the obvious session...
TRANSCRIPT
![Page 1: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/1.jpg)
2/26/2016
1
Proactive Project Management:Managing Beyond the Obvious
Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345
Presented by
David S. Slick, PE
Joseph D. Rogers, PE
Keith B. Nelson, PE (CA)
Simpson Gumpertz & Heger Inc.
Proactive project management in the design and constructionenvironment includes diligent control of such basics as scheduleand budget. Successful project managers also keep close tabs oninternal employee activities, as well as the progress of externalteam members, while managing the expectations of the Owner.This presentation is an informative study that reviews the basictenets of project management as applied to several projects,then delves deeper into the less obvious factors that cancomplicate or even derail project completion. The presenterswill discuss their implementation of proactive projectmanagement techniques during the design and constructionprocess, will cite specific examples from several challengingprojects, and will augment this presentation by intertwiningvisually interesting subject matter into the discussion.
Abstract
At the end of this presentation, participants will be able to:
1. Understand the importance of managing projectschedule and budget.
2. Recognize the less obvious factors that cancomplicate or even derail project completion.
3. Identify management techniques to unify teamcollaboration.
4. Show that there is no substitute for persistence anddetermination to meet challenging project intricacieswhile never losing site of the project goal.
Learning Objectives
![Page 2: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/2.jpg)
2/26/2016
2
What’s the point ?
• Many construction claim$ result from:
– Conflicting expectations• Client goals and objectives
• Contract documents
– Poor communication• Forum for open dialog
• Accuracy
– Lack of leadership• Responsibility
• Responsiveness
• The Proactive Project Manager
• Monitor Construction Progress – Schedule vs. Budget
• Construction Phase Services – A Few Highlights
• Case Study – Towson United Methodist Church TowerRehabilitation
Presentation Outline
Proactive Project Management
• The Project Manager– Leadership
• Authority and responsibility
• Liaison
• Supervisor
• Mentor
• Resolve conflicts
• Negotiator
– Management• Style
– Positive personality
– Can-do attitude
– Organized
• Risk allocation
• Allocate resources
• Communications– Monitor project information
– Disseminate project information
– Clarity
– Accuracy
![Page 3: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/3.jpg)
2/26/2016
3
You’ve Heard Some of the Clichés
Nike: “Just do it”
Don Beall: “Get it done!”
• The Project Manager– Leadership
• Authority and responsibility
• Liaison
• Supervisor
• Mentor
• Resolve conflicts
• Negotiator
– Management• Style
– Positive personality
– Can-do attitude
– Organized
• Risk allocation
• Allocate resources
• Communications– Monitor project information
– Disseminate project information
– Clarity
– Accuracy
Proactive Project Management
“Stand in Front”
Gus Hochrein
and the
Roper Diving Cart
Story
![Page 4: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/4.jpg)
2/26/2016
4
• The Project Manager– Leadership
• Authority and responsibility
• Liaison
• Supervisor
• Mentor
• Resolve conflicts
• Negotiator
– Management• Style
– Positive personality
– Can-do attitude
– Organized
• Risk allocation
• Allocate resources
• Communications– Monitor project information
– Disseminate project information
– Clarity
– Accuracy
Proactive Project Management
The Owner’s Nightmare
The Engineer
versus
The Contractor
![Page 5: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/5.jpg)
2/26/2016
5
• The Project Manager– Leadership
• Authority and responsibility
• Liaison
• Supervisor
• Mentor
• Resolve conflicts
• Negotiator
– Management• Style
– Positive personality
– Can-do attitude
– Organized
• Risk allocation
• Allocate resources
• Communications– Monitor project information
– Disseminate project information
– Clarity
– Accuracy
Proactive Project Management
Be Positive
• Your personality will be the mood of the job
• Frank Bell: “Management by 2x4 doesn’t work”
• Turn criticism into assistance
– “I need it now!” vs. “When will it be complete?”
– “How can I help you do your job better?”
– “What tools do you need to do your job better?”
• The Project Manager– Leadership
• Authority and responsibility
• Liaison
• Supervisor
• Mentor
• Resolve conflicts
• Negotiator
– Management• Style
– Positive personality
– Can-do attitude
– Organized
• Risk allocation
• Allocate resources
• Communications– Monitor project information
– Disseminate project information
– Clarity
– Accuracy
Proactive Project Management
![Page 6: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/6.jpg)
2/26/2016
6
Calvert vs. Ronald Reagan
The
Indiana Limestone
Story
![Page 7: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/7.jpg)
2/26/2016
7
![Page 8: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/8.jpg)
2/26/2016
8
![Page 9: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/9.jpg)
2/26/2016
9
![Page 10: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/10.jpg)
2/26/2016
10
![Page 11: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/11.jpg)
2/26/2016
11
• The Project Manager– Leadership
• Authority and responsibility
• Liaison
• Supervisor
• Mentor
• Resolve conflicts
• Negotiator
– Management• Style
– Positive personality
– Can-do attitude
– Organized
• Risk allocation
• Allocate resources
• Communications– Monitor project information
– Disseminate project information
– Clarity
– Accuracy
Proactive Project Management
Be Organized
• Contract
• Change orders
• Requests for information
• Correspondence
• Meeting minutes
• Schedule
• Field notes/trip reports
• Photos
• Payment requisitions
• Budget
• The Project Manager– Leadership
• Authority and responsibility
• Liaison
• Supervisor
• Mentor
• Resolve conflicts
• Negotiator
– Management• Style
– Positive personality
– Can-do attitude
– Organized
• Risk allocation
• Allocate resources
• Communications– Monitor project information
– Disseminate project information
– Clarity
– Accuracy
Proactive Project Management
![Page 12: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/12.jpg)
2/26/2016
12
Deal With It Now !
Joe Russell:
“Manage the downside risk”
• The Project Manager– Leadership
• Authority and responsibility
• Liaison
• Supervisor
• Mentor
• Resolve conflicts
• Negotiator
– Management• Style
– Positive personality
– Can-do attitude
– Organized
• Risk allocation
• Allocate resources
• Communications– Monitor project information
– Disseminate project information
– Clarity
– Accuracy
Proactive Project Management
Be Clear When Communicating
“We discussed the orientation of the jamb flashingat punched window openings. A flashing is desiredat the jambs to provide a back-up waterproofingsystem behind the exterior sealant joint. Aftermuch discussion, we decided on the jamb flashingdetail.”
VERSUS
“We decided on the orientation of the punchedwindow jamb flashing. The flashing at sill/jambintersections is discontinuous, because the sillflashing extends to the back of the window, and thejamb flashing stops at the window attachmentangle.”
![Page 13: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/13.jpg)
2/26/2016
13
“The vapor barrier has been laid out in theareas of the mock-up where pours will takeplace tomorrow, and in a few of the officeareas.”
VERSUS
“The vapor barrier was installed in the mock-up area at the east side of the warehouse, andin some of the office areas. The mock-upconcrete pour is scheduled for tomorrow.”
Be Clear When Communicating
• The Project Manager– Leadership
• Authority and responsibility
• Liaison
• Supervisor
• Mentor
• Resolve conflicts
• Negotiator
– Management• Style
– Positive personality
– Can-do attitude
– Organized
• Risk allocation
• Allocate resources
• Communications– Monitor project information
– Disseminate project information
– Clarity
– Accuracy
Proactive Project Management
Be Accurate !You May Have to Defend Yourself
• What occurred:Control joints were cut in a concrete slab several hours after it was poured. Some of
the edges of the control joints raveled during the cutting process (were not perfectlysquare).
• What was asked:“Do the contract specifications address raveling?”
• The answer that was given:“Control joint raveling is addressed by the application of flexible joint sealer in the
control joints prior to the installation of the floor coating system.”
• What was reported in the meeting minutes:“The control joints will have to be repaired prior to the installation of the floor coating.”
![Page 14: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/14.jpg)
2/26/2016
14
Monitor Construction Progress
• Construction Schedule– Identifies logical sequence of work
– Identifies responsibilities and client requirements
– Identifies critical activities
– Provides means to coordinate subcontractors
– Tracks project progress
– Provides means to track payments vs. resources
– Provides means to manage cash flow
– Provides means to manage and allocate risk
– Documents delays• Compensable (Time, Cost, Time and cost)
• Non-compensable
– Demonstrates impact
– General contractor’s schedule vs. project schedule
• Project Budget
– Estimate to complete
• Assigns a value to risk
• Three aspects
– Actual to date (ATD)
– Estimate to complete (ETC)
– Estimate at completion (EAC)
Monitor Construction Progress
![Page 15: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/15.jpg)
2/26/2016
15
The Pat Knapp Story
Patrick Knapp:
Former Head Coach
of
Georgetown University’s
Women’s Basketball Team
• Mock-ups– Product selection validation
– Performance testing
– Allows Contractor the opportunity perform the work
– Gives manufacturers opportunity to assist Contractor
– Allows Engineer/Architect to assess work performance
– Allows Owner to assess visual impact of work
Construction Phase Services
![Page 16: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/16.jpg)
2/26/2016
16
• Observation of the work– Familiarity with contract documents
– Thoroughness
– Correction of work
– Safety
Construction Phase Services
Check and Check Again !
The
Baltimore Metro
Portal Invert Rebar
Story
![Page 17: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/17.jpg)
2/26/2016
17
Construction Phase Services
• Progress meetings– Attendees
– Review prior meeting minutes
– Record of activities and discussions
– Occupant communication• Notification of work locations
• Occupant issues and feedback
• Public relations– Project information
– Progress
– Review updated schedule
– Identify items with potential budget implications
Progress Meeting Rule #1
Frank Bell:
“You’re invited until you’re un-invited;
lack of attendance is no excuse
for not being aware of something”
4 March 2013 51
Case Study – Towson United MethodistChurch Tower Rehabilitation
![Page 18: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/18.jpg)
2/26/2016
18
• Introduction
• Background and Investigation
• Rehabilitation
• Summary
52
Case Study – Towson United MethodistChurch Tower Rehabilitation
• Needs:– Stop the Leaks
• Primary Options– Option 1 – Reroof; Coat and Seal
• High Risk of Continued Leakage
• Maintenance Nightmare
– Option 2 – Convert to Cavity Wall
• Long Term Fix
• Expensive
53
Case Study – Towson United MethodistChurch Tower Rehabilitation
• Shortcomings:– Mass Masonry; No redundancy
– Reliant on mortar/sealant joints
• Leakage at deteriorated precast andfailed metal roofing joints
• Lack of functional watermanagement
• Little to no maintenance performed
54
Case Study – Towson United MethodistChurch Tower Rehabilitation
![Page 19: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/19.jpg)
2/26/2016
19
• Owner’s Priorities1. “50 year” solution
2. Low maintenance
3. Low tolerance forleakage
4. Long-term investment
55
Case Study – Towson United MethodistChurch Tower Rehabilitation
• Value– Redundancy
56
Tower Remediation
Case Study – Towson United MethodistChurch Tower Rehabilitation
• Takeaways– Investigation Findings
Determined Needs/Wants/ValueOptions
– Tolerance for leakage droveapproach
– Interior redundant roof
57
Case Study – Towson United MethodistChurch Tower Rehabilitation
![Page 20: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/20.jpg)
2/26/2016
20
• Introduction
• Background and Investigation
• Rehabilitation
• Summary
58
Case Study – Towson United MethodistChurch Tower Rehabilitation
Background
• Completed in 1956
• Precast concretepanels and brick /CMU masonry infillover structural steelat Tower
59
• Series of stepped metalroofs and precast panel walls
– Precast panels arecladding and roof decksover steel framing
• Large wood windows
• Interior roof (“Redundancy”)
60
Background
![Page 21: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/21.jpg)
2/26/2016
21
Background
61
• Deterioration of finishes atoffice below Tower
Background
62
• Staining at Tower Room
Background
63
• Staining at interior of Tower
![Page 22: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/22.jpg)
2/26/2016
22
Background
4 March 2013 64
• Leaks at classroom east ofTower
• Staining/Deteriorated roofdeck in attic south of Tower
• Staining on stair ceiling on eastside of Tower
Investigation – Construction
65
Investigation – Construction
66
![Page 23: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/23.jpg)
2/26/2016
23
Investigation –Survey of Metal Roofing
67
Investigation –Survey of Precast Panels
68
69
Investigation –Survey of Precast Panels
![Page 24: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/24.jpg)
2/26/2016
24
Investigation –Survey of Wood-Framed Windows
70
Investigation –Tower Base to Roof
71
Investigation –Water Testing
72
![Page 25: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/25.jpg)
2/26/2016
25
73
Investigation –Water Testing
74
Investigation –Water Testing
75
Investigation –Water Testing
![Page 26: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/26.jpg)
2/26/2016
26
Investigation - Summary
• Everything Leaks
• Leakage is deteriorating interior finishes, cast stonepanels and anchorages, and structural steel
• Maintenance and Repairs Necessary:– Painting of windows, repointing of cast stones,
replacement of sealants, and maintenance of metal roofing
– Likely large energy losses through Tower (Chimney Effect)
• Significant work must be done to address leakage
76
• Introduction
• Background and Investigation
• Rehabilitation
• Summary
77
Case Study – Towson United MethodistChurch Tower Rehabilitation
Rehabilitation
78
![Page 27: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/27.jpg)
2/26/2016
27
Rehabilitation
79
Rehabilitation
80
Rehabilitation
81
![Page 28: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/28.jpg)
2/26/2016
28
Rehabilitation
82
Rehabilitation
83
Rehabilitation
84
![Page 29: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/29.jpg)
2/26/2016
29
Rehabilitation –Cell Phone Antennas
85
Rehabilitation
86
• Introduction
• Background and Investigation
• Rehabilitation
• Summary
87
Case Study – Towson United MethodistChurch Tower Rehabilitation
![Page 30: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/30.jpg)
2/26/2016
30
Summary
• Think outside the box
• Bring new technology tosustain vs. replace
• Keep your eyes open
88
Proactive Project Management
• Conclusion– Rewarding
– Sense of accomplishment
– Be in control
– Guaranteed business success
1. Proactively managing project schedule and budget areimportant in order to successfully meet overall projectdelivery expectations. True False
2. Even the most apparently minor factor can have adramatic negative effect on project delivery if notproactively managed. True False
3. Team collaboration and communication is a good practice,but should be minimized in order to maximize projectprofitability. True False
4. Proactive coordination of challenging project intricacies isimportant to achieve the project goal. True False
Learning Assessment Questions
![Page 31: NFM&T - R1.45 Proactive PM - Managing Beyond the Obvious ...Managing Beyond the Obvious Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345 Presented by David S](https://reader033.vdocuments.us/reader033/viewer/2022053023/605220f1adb9410cdd3ea265/html5/thumbnails/31.jpg)
2/26/2016
31
Proactive Project Management:Managing Beyond the Obvious
Session R1.45 – Thursday, 24 March 2016, 9:00 am to 9:50 am, Room 345
Presented by
David S. Slick, PE
Joseph D. Rogers, PE
Keith B. Nelson, PE (CA)
Simpson Gumpertz & Heger Inc.