1MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
“Partnered for Success”Major Compressor Cylinder Replacement
Electric Power Conference and Exhibition – May 2011
New Harquahala Generating Company, LLC
![Page 2: New harquahala electric power presentation](https://reader035.vdocuments.us/reader035/viewer/2022070301/546d6fa5af795976298b536b/html5/thumbnails/2.jpg)
2MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
Success
“The secret of achievement is to hold a picture of a successful outcome in the mind.”
- Henry David Thoreau
![Page 3: New harquahala electric power presentation](https://reader035.vdocuments.us/reader035/viewer/2022070301/546d6fa5af795976298b536b/html5/thumbnails/3.jpg)
3MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
Facility Overview
![Page 4: New harquahala electric power presentation](https://reader035.vdocuments.us/reader035/viewer/2022070301/546d6fa5af795976298b536b/html5/thumbnails/4.jpg)
4MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
Partnered for Success
![Page 5: New harquahala electric power presentation](https://reader035.vdocuments.us/reader035/viewer/2022070301/546d6fa5af795976298b536b/html5/thumbnails/5.jpg)
5MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
Unit 2 MCCR Highlights
New Harquahala Generating Company and Siemens partnered in the installation of a newly designed
compressor on Unit 2 in January 2010, the second such modification in the 501G Fleet.
Benefits of the installation
Improved reliability
Reduction in unplanned maintenance intervals for diaphragm hook fit repairs
Predictable planned outage intervals
Long term reduction in maintenance expense
Proven design (V Machine)
![Page 6: New harquahala electric power presentation](https://reader035.vdocuments.us/reader035/viewer/2022070301/546d6fa5af795976298b536b/html5/thumbnails/6.jpg)
6MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
Outage Measurable Statistics
Zero Recordable or Lost Time Accidents
Completed under projected timeline (38 days)
Completed on budget
Conducted in parallel to significant BOP and ST work
Measured Performance
Pre and Post performance data indicated no change in performance
Measured Success
![Page 7: New harquahala electric power presentation](https://reader035.vdocuments.us/reader035/viewer/2022070301/546d6fa5af795976298b536b/html5/thumbnails/7.jpg)
7MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
Metronor Alignment
Support Tooling
MCCR Technology / Customized Tooling
![Page 8: New harquahala electric power presentation](https://reader035.vdocuments.us/reader035/viewer/2022070301/546d6fa5af795976298b536b/html5/thumbnails/8.jpg)
8MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
New Robust Hook Fit Design
Keys to Success
Planning, planning, planning Lessons Learned from Millennium Power
Shared resources Risk Assessment
Begun 120 days before implementation Identified key areas that could have diminished results
TMS Process Communication Proper Documentation
Photographic Written
Quality Assurance Protocol Project Management Tools
Gantt Charts Coast Tracking Technical Engineering Correspondence, PCM’s,
OutFar’s, etc.
![Page 9: New harquahala electric power presentation](https://reader035.vdocuments.us/reader035/viewer/2022070301/546d6fa5af795976298b536b/html5/thumbnails/9.jpg)
9MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
Compared three Units at Harquahala to 501 G Fleet (24 Units)
Note: data sample is for CT only (Econopac)
Three Basic Metrics
Availability Factor, which looks at both Scheduled and Forced Outages
Reliability Factor, focus is on Forced Outages only
Starting Reliability Factor
Period Analyzed
12 Month Rolling Average starting from January 2008 through December 2010;
for example, January 2008 data point represents data from February 2007 to
January 2008
Data Sources: Siemens
Availability & Reliability Trending
![Page 10: New harquahala electric power presentation](https://reader035.vdocuments.us/reader035/viewer/2022070301/546d6fa5af795976298b536b/html5/thumbnails/10.jpg)
10MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
Starting Reliability Factor % 12 Month Rolling Average
![Page 11: New harquahala electric power presentation](https://reader035.vdocuments.us/reader035/viewer/2022070301/546d6fa5af795976298b536b/html5/thumbnails/11.jpg)
11MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
Availability Factor % (CT Only) 12 Month Rolling Average
![Page 12: New harquahala electric power presentation](https://reader035.vdocuments.us/reader035/viewer/2022070301/546d6fa5af795976298b536b/html5/thumbnails/12.jpg)
12MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
Reliability Factor % (CT Only) 12 Month Rolling Average
![Page 13: New harquahala electric power presentation](https://reader035.vdocuments.us/reader035/viewer/2022070301/546d6fa5af795976298b536b/html5/thumbnails/13.jpg)
13MAY 10-12, 2011 * Rosemont, Illinois * Donald E. Stephens Convention Center
Partnership Success!
Thank you!