NETWORK DIAGRAM, CRITICAL PATH METHOD AND GANTT CHARTLESSON 4
![Page 2: Network Diagram, CPM and Gantt Chart](https://reader036.vdocuments.us/reader036/viewer/2022082414/5695d0bb1a28ab9b0293a408/html5/thumbnails/2.jpg)
Activity
Description Precedent Activity
Time Estimat
es
A Project Team Planning NONE 2
B Consultation with Barangay Officials
A 1
C Reservation of Guest Speakers
A 2
D Estimation of Materials and Equipment Expenses
B 1
E Fund Raising C, D 3
F Canvassing and Procurement of Materials
E 1
G Renting of Sound Equipment E 1
H Printing of Certificates and Programme
F 1
I Information Dissemination G, H 3EXAMPLE Activity table
![Page 3: Network Diagram, CPM and Gantt Chart](https://reader036.vdocuments.us/reader036/viewer/2022082414/5695d0bb1a28ab9b0293a408/html5/thumbnails/3.jpg)
A
B
C
D
E
F
G
H
I
2 DAYS
1 DAY
2 DAYS
1 DAY
3 DAYS
1 DAY 1 DAY
1 DAY
3 DAYS
Network Diagram
Paths:1. A-B-D-E-F-H-I = 11 days2. A-B-D-E-G-I = 10 days3. A-C-E-F-H-I = 11 days4. A-C-E-G-I = 10 days
Critical path method
Critical Path: A-B-D-E-F-H-I and A-C-E-F-H-I with 11 days duration
![Page 4: Network Diagram, CPM and Gantt Chart](https://reader036.vdocuments.us/reader036/viewer/2022082414/5695d0bb1a28ab9b0293a408/html5/thumbnails/4.jpg)
Gantt Chart – discovered by Henry Gantt
ACTIVITY
11 12 14 15 16 17 18 21 22 23 24
A
B
C
D
E
F
G
H
I
STARTING DECEMBER 11, 2015 EXCLUSIVE OF WEEKENDS
![Page 5: Network Diagram, CPM and Gantt Chart](https://reader036.vdocuments.us/reader036/viewer/2022082414/5695d0bb1a28ab9b0293a408/html5/thumbnails/5.jpg)
Activity
DescriptionRequired Predecess
or
Duration (months)
A Product design (None) 5
B Market research (None) 1
CProduction analysis
A 2
D Product model A 3
E Sales brochure A 2
F Cost analysis C 3
G Product testing D 4
H Sales training B, E 2
I Pricing H 1
J Project report F, G, I 1ASSIGNMENT
![Page 6: Network Diagram, CPM and Gantt Chart](https://reader036.vdocuments.us/reader036/viewer/2022082414/5695d0bb1a28ab9b0293a408/html5/thumbnails/6.jpg)
MAKE THE FOLLOWING:1. DRAW THE NETWORK
DIAGRAM2. INDENTIFY CRITICAL
PATH/S3. MAKE A GANTT
CHART – starting December 14, 2015 exclusive of Sundays only